CN107254849A - 一种净高受限状态下钢箱梁安装方法 - Google Patents

一种净高受限状态下钢箱梁安装方法 Download PDF

Info

Publication number
CN107254849A
CN107254849A CN201710573869.9A CN201710573869A CN107254849A CN 107254849 A CN107254849 A CN 107254849A CN 201710573869 A CN201710573869 A CN 201710573869A CN 107254849 A CN107254849 A CN 107254849A
Authority
CN
China
Prior art keywords
girder
steel box
track
installation method
method under
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710573869.9A
Other languages
English (en)
Inventor
黄泽
梁艳兵
江伟
凌勇
周克勤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201710573869.9A priority Critical patent/CN107254849A/zh
Publication of CN107254849A publication Critical patent/CN107254849A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种净高受限状态下钢箱梁安装方法,包括以下步骤:S1:在桥梁下安装立柱,在立柱的两侧设置支撑体系、轨道梁和轨道,轨道的至少一端位于桥梁外,轨道上设置滑移小车;S2:将第一件钢箱梁通过吊车吊装至滑移小车上临时固定,用牵引装置将滑移小车滑移到预定位置;S3:将第一件钢箱梁定位好后用临时门式支撑固定,将滑移小车移动至非受限空间处,进行第二件钢箱梁的滑移施工,重复完成后续钢箱梁的滑移施工;S4:全部钢箱梁安装完毕后,进行钢箱梁拼接,并将钢箱梁与立柱连接。本发明在施工的同时能够保证正常的交通,且施工时吊机支腿作业固定在同一处位置,节约了反复支腿、收腿的时间,节约了成本,提高施工效率。

Description

一种净高受限状态下钢箱梁安装方法
技术领域
本发明涉及钢箱梁安装领域,更具体地说,涉及一种净高受限状态下钢箱梁安装方法。
背景技术
某市H匝道及渐变段拓宽改造采用帮宽钢箱梁的形式,为避开地下已建成的地铁隧道,帮宽钢箱梁下方设计为钢箱梁门式桥墩。钢箱梁门式墩顶部距现有高架桥底部仅0.5米,常规的吊装方式仅能安装两侧的钢柱,而无法安装钢柱上方的钢横梁。
以往对此类钢箱梁的施工主要采用搭设满堂脚手架的滑移方式、垂直顶升或水平顶推的方式进行,满堂脚手架滑移、垂直顶升的施工方式除需搭设复杂的支撑体系外,还不能保证施工投影区域下车辆的正常行驶;水平顶推的方式如遇实际无反力构筑物的情况下也无法实施。
综上所述,虽然现有施工方法能够满足施工,但需耗费大量的人工、物资及宝贵的施工时间,且施工工序繁琐,安全隐患多。
发明内容
本发明要解决的技术问题在于,提供一种易于操作、施工简单、效率高的净高受限状态下钢箱梁安装方法。
本发明解决其技术问题所采用的技术方案是:构造一种净高受限状态下钢箱梁安装方法,包括以下步骤:
S1:在桥梁下安装立柱,在立柱的两侧设置支撑体系、轨道梁和轨道,立柱用于支撑钢箱梁,轨道梁固定在支撑体系上方,轨道位于轨道梁上,轨道的至少一端位于桥梁外,轨道上设置滑移小车;
S2:将第一件钢箱梁通过吊车吊装至滑移小车上临时固定,用牵引装置将滑移小车滑移到预定位置;
S3:将第一件钢箱梁定位好后用临时门式支撑固定,将滑移小车移动至非受限空间处,进行第二件钢箱梁的滑移施工,重复完成后续钢箱梁的滑移施工;
S4:全部钢箱梁安装完毕后,进行钢箱梁拼接,并将钢箱梁与立柱连接。
上述方案中,所述滑移小车上设有可拆卸千斤顶。
上述方案中,所述滑移小车上设有定位挡板。
上述方案中,所述立柱左右两侧的轨道梁通过横梁连接。
上述方案中,在步骤S3中,将第二件钢箱梁定位好后用临时门式支撑固定,将滑移小车移动至非受限空间处,用连接梁将滑移小车与附加小车连接成整体,进行第三件钢箱梁的滑移施工。
上述方案中,所述钢箱梁顶部设有吊环。
上述方案中,所述支撑体系包括支架和隅撑,所述隅撑连接支架和轨道梁。
上述方案中,在所述步骤S4之后还包括步骤S5:拆除临时门式支撑、滑移小车、轨道梁、轨道及支撑体系。
上述方案中,所述步骤S2中的牵引装置为手拉葫芦。
上述方案中,所述立柱为钢立柱。
实施本发明的净高受限状态下钢箱梁安装方法,具有以下有益效果:
1、采用本发明方法安装净高受限钢箱梁,弥补了净高受限钢箱梁施工技术上的空白。
2、施工的同时能够保证正常的交通,且施工时吊机支腿作业固定在同一处位置,节约了反复支腿、收腿的时间,节约了大量的机械费、人工费及材料费,提高施工效率。
3、钢箱梁移动到位后,通过临时门式支撑固定,然后拆除可拆卸千斤顶和定位挡板,然后将滑移小车移动至非受限空间处,实现小车的重复利用,简化了施工程序,也减少了小车使用量,节省成本。
附图说明
下面将结合附图及实施例对本发明作进一步说明,附图中:
图1是本发明净高受限状态下钢箱梁安装方法的示意图;
图2是图1的侧视图;
图3是滑移小车的结构示意图;
图4是第一件钢箱梁的安装时的示意图;
图5是第一件钢箱梁的安装到位后的示意图;
图6是三件钢箱梁的拼接示意图。
具体实施方式
为了对本发明的技术特征、目的和效果有更加清楚的理解,现对照附图详细说明本发明的具体实施方式。
如图1-图6所示,本发明净高受限状态下钢箱梁安装方法包括以下步骤:
S1:在既有桥梁12下安装立柱1,本实施中为两根钢立柱,立柱1用于支撑钢箱梁9。在立柱1的两侧设置支撑体系、轨道梁3和轨道,立柱1左右两侧的轨道梁3通过横梁16连接。支撑体系和轨道梁3均为模块化结构,拆装方便。支撑体系包括支架2和隅撑4,隅撑4连接支架2和轨道梁3。轨道梁3固定在支撑体系上方,轨道位于轨道梁3上,轨道5的至少一端位于桥梁外,轨道5上设置滑移小车6。滑移小车6上设有可拆卸千斤顶7和定位挡板8。
S2:将第一件钢箱梁9通过吊车吊装至滑移小车6上临时固定,钢箱梁9顶部设有吊环10,吊环10通过钢丝绳11与吊车连接。通过定位挡板8对第一件钢箱梁9限位,通过可拆卸千斤顶7调整水平度。用手拉葫芦等牵引装置将滑移小车6滑移到预定位置。
S3:将第一件钢箱梁9定位好后用临时门式支撑13固定,拆除可拆卸千斤顶7和定位挡板8,如图5所示,然后将滑移小车6从临时门式支撑13下部钻出移动至非受限空间处,进行第二件钢箱梁9的滑移施工,重复完成后续钢箱梁9的滑移施工。本实施例中,第三件钢箱梁9跨度较大,需要两个小车承托。待第二件钢箱梁9定位好后用临时门式支撑13固定后,将滑移小车6移动至非受限空间处,用连接梁15将滑移小车6与附加小车14连接成整体,进行第三件钢箱梁9的滑移施工。
S4:全部钢箱梁9安装完毕后,进行钢箱梁9拼接,并通过螺栓连接、焊接等方式将钢箱梁9与立柱1连接,然后在上方完成拟拓宽钢箱梁17的安装。
S5:拆除临时门式支撑13、滑移小车6、轨道梁3、轨道5及支撑体系。整个支撑体系的重心均在钢箱梁9之外,拆卸时净高不受影响,可简单完成拆卸工序。
上面结合附图对本发明的实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,而不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可做出很多形式,这些均属于本发明的保护之内。

Claims (10)

1.一种净高受限状态下钢箱梁安装方法,其特征在于,包括以下步骤:
S1:在桥梁下安装立柱,在立柱的两侧设置支撑体系、轨道梁和轨道,立柱用于支撑钢箱梁,轨道梁固定在支撑体系上方,轨道位于轨道梁上,轨道的至少一端位于桥梁外,轨道上设置滑移小车;
S2:将第一件钢箱梁通过吊车吊装至滑移小车上临时固定,用牵引装置将滑移小车滑移到预定位置;
S3:将第一件钢箱梁定位好后用临时门式支撑固定,将滑移小车移动至非受限空间处,进行第二件钢箱梁的滑移施工,重复完成后续钢箱梁的滑移施工;
S4:全部钢箱梁安装完毕后,进行钢箱梁拼接,并将钢箱梁与立柱连接。
2.根据权利要求1所述的净高受限状态下钢箱梁安装方法,其特征在于,所述滑移小车上设有可拆卸千斤顶。
3.根据权利要求1所述的净高受限状态下钢箱梁安装方法,其特征在于,所述滑移小车上设有定位挡板。
4.根据权利要求1所述的净高受限状态下钢箱梁安装方法,其特征在于,所述立柱左右两侧的轨道梁通过横梁连接。
5.根据权利要求1所述的净高受限状态下钢箱梁安装方法,其特征在于,在步骤S3中,将第二件钢箱梁定位好后用临时门式支撑固定,将滑移小车移动至非受限空间处,用连接梁将滑移小车与附加小车连接成整体,进行第三件钢箱梁的滑移施工。
6.根据权利要求1所述的净高受限状态下钢箱梁安装方法,其特征在于,所述钢箱梁顶部设有吊环。
7.根据权利要求1所述的净高受限状态下钢箱梁安装方法,其特征在于,所述支撑体系包括支架和隅撑,所述隅撑连接支架和轨道梁。
8.根据权利要求1所述的净高受限状态下钢箱梁安装方法,其特征在于,在所述步骤S4之后还包括步骤S5:拆除临时门式支撑、滑移小车、轨道梁、轨道及支撑体系。
9.根据权利要求1所述的净高受限状态下钢箱梁安装方法,其特征在于,所述步骤S2中的牵引装置为手拉葫芦。
10.根据权利要求1所述的净高受限状态下钢箱梁安装方法,其特征在于,所述立柱为钢立柱。
CN201710573869.9A 2017-07-14 2017-07-14 一种净高受限状态下钢箱梁安装方法 Pending CN107254849A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710573869.9A CN107254849A (zh) 2017-07-14 2017-07-14 一种净高受限状态下钢箱梁安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710573869.9A CN107254849A (zh) 2017-07-14 2017-07-14 一种净高受限状态下钢箱梁安装方法

Publications (1)

Publication Number Publication Date
CN107254849A true CN107254849A (zh) 2017-10-17

Family

ID=60025517

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710573869.9A Pending CN107254849A (zh) 2017-07-14 2017-07-14 一种净高受限状态下钢箱梁安装方法

Country Status (1)

Country Link
CN (1) CN107254849A (zh)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107761582A (zh) * 2017-10-31 2018-03-06 武汉冶钢结构有限责任公司 受限空间安装钢箱梁的滑移吊装方法及滑移辅助吊装装置
CN109056438A (zh) * 2018-09-06 2018-12-21 上海市机械施工集团有限公司 一种城市高架匝道改造的施工方法
CN109457626A (zh) * 2018-10-18 2019-03-12 广西路桥工程集团有限公司 一种在限高区安装预制梁的方法
CN110374001A (zh) * 2019-06-27 2019-10-25 中国一冶集团有限公司 一种桥底大跨度横梁施工方法
CN110878525A (zh) * 2019-11-06 2020-03-13 武船重型工程股份有限公司 一种双层钢箱梁桥安装方法及安装用组合支架
CN111058046A (zh) * 2019-11-28 2020-04-24 上海二十冶建设有限公司 一种受限空间内活套车的安装方法
CN112010147A (zh) * 2020-07-22 2020-12-01 上海二十冶建设有限公司 一种受限空间内大型机组附属设备的快速安装方法
CN112224642A (zh) * 2020-09-23 2021-01-15 中国五冶集团有限公司 一种钢结构构件调整件安装输送装置及输送方法
CN113026522A (zh) * 2021-03-22 2021-06-25 北京市政建设集团有限责任公司 一种桥梁钢箱梁安装结构及施工工艺
CN113152166A (zh) * 2021-04-15 2021-07-23 中铁三局集团华东建设有限公司 跨座式单轨轨道梁滑移架设工装
CN114211187A (zh) * 2021-12-29 2022-03-22 河南六建重工有限公司 一种用于钢结构桥梁焊接施工的送料装置

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04289303A (ja) * 1991-03-19 1992-10-14 Kawasaki Steel Corp 道路橋の拡幅方法
CN202298467U (zh) * 2011-08-16 2012-07-04 中铁十七局集团第二工程有限公司 横跨既有铁路线的转换平台架梁装置
CN104480846A (zh) * 2014-12-30 2015-04-01 桂林理工大学 一种拼接桥梁及其施工方法
CN106638325A (zh) * 2016-12-31 2017-05-10 中铁十八局集团第五工程有限公司 适用于狭窄空间下钢构件滑移组装的施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04289303A (ja) * 1991-03-19 1992-10-14 Kawasaki Steel Corp 道路橋の拡幅方法
CN202298467U (zh) * 2011-08-16 2012-07-04 中铁十七局集团第二工程有限公司 横跨既有铁路线的转换平台架梁装置
CN104480846A (zh) * 2014-12-30 2015-04-01 桂林理工大学 一种拼接桥梁及其施工方法
CN106638325A (zh) * 2016-12-31 2017-05-10 中铁十八局集团第五工程有限公司 适用于狭窄空间下钢构件滑移组装的施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
ZB: "竹叶山立交匝道改造完工通车 汉口站往武汉大道长江二桥更通畅", 《长江商报》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107761582A (zh) * 2017-10-31 2018-03-06 武汉冶钢结构有限责任公司 受限空间安装钢箱梁的滑移吊装方法及滑移辅助吊装装置
CN109056438B (zh) * 2018-09-06 2021-02-23 上海市机械施工集团有限公司 一种城市高架匝道改造的施工方法
CN109056438A (zh) * 2018-09-06 2018-12-21 上海市机械施工集团有限公司 一种城市高架匝道改造的施工方法
CN109457626A (zh) * 2018-10-18 2019-03-12 广西路桥工程集团有限公司 一种在限高区安装预制梁的方法
CN110374001B (zh) * 2019-06-27 2021-05-18 中国一冶集团有限公司 一种桥底大跨度横梁施工方法
CN110374001A (zh) * 2019-06-27 2019-10-25 中国一冶集团有限公司 一种桥底大跨度横梁施工方法
CN110878525A (zh) * 2019-11-06 2020-03-13 武船重型工程股份有限公司 一种双层钢箱梁桥安装方法及安装用组合支架
CN111058046A (zh) * 2019-11-28 2020-04-24 上海二十冶建设有限公司 一种受限空间内活套车的安装方法
CN112010147A (zh) * 2020-07-22 2020-12-01 上海二十冶建设有限公司 一种受限空间内大型机组附属设备的快速安装方法
CN112224642A (zh) * 2020-09-23 2021-01-15 中国五冶集团有限公司 一种钢结构构件调整件安装输送装置及输送方法
CN113026522A (zh) * 2021-03-22 2021-06-25 北京市政建设集团有限责任公司 一种桥梁钢箱梁安装结构及施工工艺
CN113152166A (zh) * 2021-04-15 2021-07-23 中铁三局集团华东建设有限公司 跨座式单轨轨道梁滑移架设工装
CN114211187A (zh) * 2021-12-29 2022-03-22 河南六建重工有限公司 一种用于钢结构桥梁焊接施工的送料装置
CN114211187B (zh) * 2021-12-29 2024-04-12 河南六建重工有限公司 一种用于钢结构桥梁焊接施工的送料装置

Similar Documents

Publication Publication Date Title
CN107254849A (zh) 一种净高受限状态下钢箱梁安装方法
CN104594918B (zh) 分体整合式地下通道钢模板台车及其施工方法
CN106638687B (zh) 一种预制拼装综合管廊精准快速拼装工艺
CN111852521B (zh) 大断面盾构隧道内部结构施工用口字件拼装台车及同步施工方法
CN103726421B (zh) 地铁施工用高度及跨度可调式轨道铺设机
CN101152949A (zh) 超高超大型大吨位行走井架式吊装机具平移方法及其装置
JP2006265884A (ja) 跨道橋の既設橋脚撤去方法
CN107060823B (zh) 隧道锚段二衬混凝土施工无拆卸台车
CN205591116U (zh) 用于立交桥钢箱梁底部施工的双梁移动小车操作平台
CN104973517A (zh) 一种用于烧结机头部设备安装的电动龙门平台及其使用方法
JP2001146716A (ja) 橋桁の架設方法
CN206245344U (zh) 一种用于预制拼装综合管廊拼装的安装车
KR101234090B1 (ko) 철도 판형교의 거더 교체 방법
CN106192761B (zh) 一种在桥隧狭短过渡段拆解移动模架的方法
CN210049105U (zh) 一种自行式桥梁模板作业台车
CN208203298U (zh) 一种有轨式侧墙大钢模
CN112726442A (zh) 大跨度薄壁混凝土声屏障浇筑台车的施工方法
CN109607384B (zh) 超大直径盾构机刀盘的翻身方法
CN112030777A (zh) 一种下行式移动模架支撑托架跨越式转运施工方法
CN111705682A (zh) 一种跨电气化铁路加宽桥梁上部结构拆除与重建的施工方法及其设备
CN103410104B (zh) 城市高架的支座更换方法与装置
CN107245960A (zh) 一种用于城市高架桥更新的分段式施工***及方法
JP2023074170A (ja) 床版取替方法及びこれに用いる施工機械
CN111139742B (zh) 公路架桥机安装与拆卸方法
CN210140770U (zh) 现浇桥梁模板支架体系装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171017