CN107245998A - A kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base - Google Patents

A kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base Download PDF

Info

Publication number
CN107245998A
CN107245998A CN201710519398.3A CN201710519398A CN107245998A CN 107245998 A CN107245998 A CN 107245998A CN 201710519398 A CN201710519398 A CN 201710519398A CN 107245998 A CN107245998 A CN 107245998A
Authority
CN
China
Prior art keywords
vacuum
cocoanut shell
filling
ditch
sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710519398.3A
Other languages
Chinese (zh)
Other versions
CN107245998B (en
Inventor
高盟
石传志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Rui Hsi Technology Co ltd
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201710519398.3A priority Critical patent/CN107245998B/en
Publication of CN107245998A publication Critical patent/CN107245998A/en
Application granted granted Critical
Publication of CN107245998B publication Critical patent/CN107245998B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention relates to a kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base.This method process includes:1)Cocoanut shell is admixed in storing bin;2)By the mixture hydraulic reclamation of barged-in fill and cocoanut shell to designed elevation;3)One layer of 20cm sand bedding course is laid above and drain bar is set;4)Lay 30cm middle level sand bedding courses and embedded vacuum pipe network;5)Sealing ditch is excavated, diaphragm seal is laid;6)Examination vacuumizes and checks whether gas leakage;7)Continue to be pumped to settlement stability under pumping is stable;8)Benefit is banketed to design altitude.It is an advantage of the current invention that having recycled cocoanut shell as packing material, cocoanut shell has the performances such as intensity highly corrosion resistant, mixes the stability and intensity that soil is added in filling soil, a large amount of that the use of filling soil can be reduced using cocoanut shell, is conducive to cost-effective.

Description

A kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base
Technical field
The present invention relates to a kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base, barged-in fill is primarily adapted for use in The processing of ground, belongs to Soft Ground field.
Background technology
Marine reclamation land refers to original marine site, lake region or riverbank to be changed into land by artificial technology's means.To Yushan Hill More few coastal cities, marine reclamation land is a kind of method that development for the city confined space plays an important role.Holland is certainly Begin to enclose extra large made ground on a large scale from 13rd century, nowadays the artificial sea of filling out of the 20% of Dutch territory is created." hills is all dug Go to fill out sea and go, Fu Laifulan, which is saved, almost creates what is come ", therefore have the title of " God makes sea, Dutchman's epeirogenetic ".Japan is individual Archipelago country, territory is narrow and small, populous.After World War II between more than 50 years, Japanese's reclaiming land around sea reaches 200km2, phase When in the area of 2.6 Hong Kong Islands.China's Perioperative cardiac events activity since last century five, the sixties, to last century Mo, littoral Area's Perioperative cardiac events make ground area up to 1.2 ten thousand km2, the km of Perioperative cardiac events 230 to 240 every year on average2.The many level lands in Hong Kong mountain are few, perfume (or spice) in 1842 The sandstone for building queen main road are promoted sea by port first, and the just continuous marine reclamation land of later Hong Kong over more than 100 years, fills out sea product Up to 67 km2, Hong Kong gross area is accounted for more than 6%.
The primary raw material of sea reclamation is sandstone, and significant wastage consumes substantial contribution, the particularly Nanhai area, sandstone money Source is extremely limited, and the Nanhai area produces a large amount of cocoanut shells every year, and high with intensity, and compressive property is good.The present invention applies coconut palm Sub- shell filling barged-in fill carrys out sea reclamation, not only saves great amount of cost, and cocoanut shell is distributed in filling soil can improve soil Shearing strength.
The content of the invention
Object of the present invention is to provide a kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base, the party Method has low cost, the advantages of constructing simple.
The present invention is realized by the following technical scheme.A kind of cocoanut shell filling combined vacuum prepressing blowing filling soil The method of base, it is characterised in that including procedure below:1)Cocoanut shell is admixed in feeding chamber;2)By the mixed of barged-in fill and cocoanut shell Compound hydraulic reclamation is to designed elevation;3)One layer of 20cm sand bedding course is laid above and drain bar is set;4)Lay 30cm middle levels sand pad Layer and embedded vacuum pipe network;5)Sealing ditch is excavated, diaphragm seal is laid;6)Examination vacuumizes and checks whether gas leakage;7)Pumping is stable Under continue to be pumped to settlement stability;8)Benefit is banketed to design altitude.
The advantage of the invention is that:Construction is simple, saves a large amount of sandstones, meets engineering construction needs, saves construction Cost, while greatly strengthen foundation strength.
Brief description of the drawings
Fig. 1 conveys layout drawing for the cocoanut shell and barged-in fill of the present invention;
Fig. 2 is vacuum pre-press reinforcing layout drawing of the invention;
In figure:1- sand carriers, 2- hydraulic reclamation sandy soil, 3- conveyance conduits, 4- barged-in fill delivery pumps, 5- feeding chambers, 6- hydraulic reclamation soil blocks, 7- Lower floor's sand bedding course, 8- upper stratas sand bedding course, 9- vacuum diaphragms, 10- sealing ditches, 11- vertical drainage plates.
Embodiment
Cocoanut shell is admixed in storing bin.
By the mixture hydraulic reclamation of barged-in fill and cocoanut shell to designed elevation.
Laid above and one layer of 20cm sand bedding course and set drain bar, plastic draining board uses Type B plate, construction depth 20m, Spacing 1.2m, equilateral triangle(It is quincunx)Arrangement.Set perpendicularity deviation control in ± 1.5%, every rewind it is of length no more than 50cm, otherwise should immersed tube plate again, embedment sand bedding course length is not less than 0.3m at the top of plastic strip plate.
30cm middle level sand bedding courses and embedded vacuum pipe network are laid, vacuum tube is selected reinforcement PVC plastic expects pipe, is responsible for as φ 75mm, branch pipe is φ 50mm, it is desirable to which the intensity of PVC can bear 400kPa pressure.It is responsible for spacing 25m or so, filter pipe Array pitch 6m or so, distance of the outermost layer filter pipe away from place side is 2~5m.Led between supervisor and branch chimney filter with reducing tee and four Connect.
Sealing ditch is excavated, diaphragm seal is laid.(1)Diaphragm seal is fixed in advance by manufacturer according to vacuum preloading area size Process, the size of view picture diaphragm seal will ensure that disposable all whole vacuum preloading areas of covering.The size of film during processing Consider the part of embedment sealing ditch, leave enough have more than needed.Diaphragm seal seam is firmly bonded, and flat lap side seam width is met in double heat seals It cannot be less than 15mm.(2)Sand bedding course surface should be smooth before vacuum preloading, and surface is without sharp stone, lump and other sharp debris.Sealing When film is laid, the particle such as the intermembranous sand do not cleaned out, stone, which wears out film, when need to prevent from vacuumizing causes gas leakage.(3)In order to Vacuum diaphragm is protected, one layer of 250g/m is respectively laid up and down in vacuum diaphragm2Acupuncture nonwoven geotextiles.Treat vacuum line, vacuum probe and After other observation instruments have been buried, first layer geotextiles are being laid thereon, laying area is slightly less than diaphragm seal(Receive 2~3m of side), Lay scope and be slightly larger than stabilization zone, 1m is about widened per side.
Examination vacuumizes and checks whether gas leakage.After every vaccum-pumping equipment placement is in place, proceeds by examination and vacuumize.Start The speed of stage control vacuum pressed, to extract the air in sand bedding course out, vacuum pressure increases step by step from 20kPa, with film Vacuum gradually increases and stably on 80kPa in the discharge of air and the raising of soil layer discharging consolidation degree, film.Starting to take out Vacuum stages, with the discharge of air and water, check diaphragm seal comprehensively and seal the sealing state of ditch, if any gas leakage, to gas leakage Part repairing in time and sealing, prevent from influenceing vacuum effectiveness.
Continue to be pumped to settlement stability under pumping is stable.Under conditions of under-membrance vacuum degree is stably maintained at more than 80kPa, After the completion of continuous air extraction, roadbed filling, the continuous 10d average settlements amount of actual measurement surface subsidence speed is less than or equal to 2mm/d, you can Termination of pumping is unloaded.
Benefit is banketed to design altitude.

Claims (5)

1. a kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base, it is characterised in that:Cocoanut shell is mixed in and filled In banketing, the mixture of cocoanut shell and filling soil is fills up to design altitude, and discharging consolidation is carried out with vacuum method, it is led Step is wanted to have:1)Cocoanut shell is admixed in storing bin;2)By the mixture hydraulic reclamation of barged-in fill and cocoanut shell to designed elevation;3) One layer of 20cm sand bedding course is laid above and sets drain bar;4)Lay 30cm middle level sand bedding courses and embedded vacuum pipe network;5)Excavate Ditch is sealed, diaphragm seal is laid;6)Examination vacuumizes and checks whether gas leakage;7)Continue to be pumped to settlement stability under pumping is stable;8) Benefit is banketed to design altitude.
2. a kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base according to claims 1, its feature It is in step 3 that sand bedding course sand material uses medium coarse sand, clay content(Particle diameter is less than 0.075mm fine grained)Less than 5%, infiltration system Number is not less than 2 × 10-2Cm/s, it is ensured that horizontal drainage effect, plastic draining board use Type B plate, construction depth 20m, spacing 1.2m, Equilateral triangle(It is quincunx)Arrangement, sets perpendicularity deviation control in ± 1.5%, every rewinds of length no more than 50cm, otherwise Embedment sand bedding course length at the top of immersed tube plate again, plastic strip plate is answered to be not less than 0.3m.
3. Vacuum Drainage pipe selects reinforcement PVC plastic expects pipe in step 4 according to claim 1, it is responsible for as φ 75mm, branch pipe is φ 50mm, it is desirable to the intensity of PVC can bear non-woven geotextile in 400kPa pressure, step 5, the thickness of diaphragm seal, thoroughly Gas performance, tensile strength, species, specification and performance should meet in design requirement, step 5 seal ditch have to comply with epiphragma hold one's breath will Ask, excavated using hand fit's excavator, 0.8~1.0m of ditch bottom width or so, ditch depth 1.5m~2.0m, with digging with paving with filling out, with Long 20m of ditch or so be a work section promote successively, slope collapse is prevented during excavation, the mound dug out during plastic film mulch in outside just On road, it must not pile up on sand bedding course, it is to avoid sand grains is slipped into ditch, the clay backfilled in ditch wants closely knit and is not mingled with sandstone, if Bottom of trench or both sides are sealed with the presence of the interlayer of the good penetrabilities such as rubble or layer of sand, the interlayer are excavated totally, and backfill weak soil.
4. step 5 respectively lays one layer of 250g/m up and down in order to protect vacuum diaphragm in vacuum diaphragm according to claim 12Acupuncture without Geotextiles are spun, after vacuum line, vacuum probe and other observation instruments have been buried, first layer geotextiles, paving are being laid thereon If area is slightly less than diaphragm seal(Receive 2~3m of side), laying scope is slightly larger than stabilization zone, 1m is about widened per side, according to place situation, Geotextiles are deployed in certain direction and lay smooth, geotextiles overlapping part is carried out with portable sewing machine using sewing up processing Sew up, lap width is no less than 30mm when sewing up.
5. carry out examination in step 6 according to claim 1 to vacuumize, incipient stage control vacuum pressed speed, to extract sand out Air in bed course, vacuum pressure increases step by step from 20kPa, with carrying for the discharge of air under film and soil layer discharging consolidation degree Vacuum gradually increases and stably on 80kPa in height, film, is starting vacuumizing phase, with the discharge of air and water, entirely Face checks diaphragm seal and seals the sealing state of ditch, if any gas leakage, to the repairing in time of gas leakage part and sealing, prevents from influenceing vacuum In effect, step 7 under conditions of under-membrance vacuum degree is stably maintained at more than 80kPa, continuous air extraction, after the completion of roadbed filling, Survey the continuous 10d average settlements amount of surface subsidence speed and be less than or equal to 2mm/d, you can termination of pumping is unloaded.
CN201710519398.3A 2017-06-30 2017-06-30 A kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base Active CN107245998B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710519398.3A CN107245998B (en) 2017-06-30 2017-06-30 A kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710519398.3A CN107245998B (en) 2017-06-30 2017-06-30 A kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base

Publications (2)

Publication Number Publication Date
CN107245998A true CN107245998A (en) 2017-10-13
CN107245998B CN107245998B (en) 2019-10-18

Family

ID=60014683

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710519398.3A Active CN107245998B (en) 2017-06-30 2017-06-30 A kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base

Country Status (1)

Country Link
CN (1) CN107245998B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102776877A (en) * 2012-08-22 2012-11-14 吉林大学 Stepped vacuum drainage consolidation method for ultra-soft soil foundation
CN103388330A (en) * 2013-07-31 2013-11-13 河海大学 Pump drainage type vacuum preloading soft foundation strengthening method
CN103643672A (en) * 2013-11-12 2014-03-19 浙江江南春建设集团有限公司 Vacuum preloading foundation treatment construction method
CN104047281A (en) * 2014-06-30 2014-09-17 洛阳广鑫建设集团有限公司 Construction method for vacuum combined preloading consolidated foundation
CN106048886A (en) * 2016-07-19 2016-10-26 广东浚丰华科技有限公司 Plant-fiber ecological felt and preparation method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102776877A (en) * 2012-08-22 2012-11-14 吉林大学 Stepped vacuum drainage consolidation method for ultra-soft soil foundation
CN103388330A (en) * 2013-07-31 2013-11-13 河海大学 Pump drainage type vacuum preloading soft foundation strengthening method
CN103643672A (en) * 2013-11-12 2014-03-19 浙江江南春建设集团有限公司 Vacuum preloading foundation treatment construction method
CN104047281A (en) * 2014-06-30 2014-09-17 洛阳广鑫建设集团有限公司 Construction method for vacuum combined preloading consolidated foundation
CN106048886A (en) * 2016-07-19 2016-10-26 广东浚丰华科技有限公司 Plant-fiber ecological felt and preparation method thereof

Also Published As

Publication number Publication date
CN107245998B (en) 2019-10-18

Similar Documents

Publication Publication Date Title
CN104120710B (en) A kind of highway on soft ground method of vacuum pre-pressed joint serous fluid of dredger fill
CN100549304C (en) A kind of nothing sealing fast vacuum prepressing method
CN103628468B (en) A kind of water penetration pile combined vacuum prepressing ground foundation treatment method
CN110306616A (en) A kind of construction method of sewage conduct
CN101265701A (en) Soft soil foundation reinforcing means
CN104088208B (en) A kind of wet and soft earth foundation processing method
CN101220598A (en) Vacuum preloading method for non-water discharge sand cushion
CN103233454A (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN108166518B (en) Structure for synchronous treatment of underground pipeline foundation pit and soft soil foundation and reinforcing method thereof
CN105780754A (en) Sand-bed-free vacuum preloading and water bag heaped loading combined reinforcing device and method for soft soil foundation
CN203755293U (en) Vacuum preloading combined stacking system
CN106400776A (en) Drainage system of dredger fill of depressions and bottom vacuumizing and pre-pressing method
CN104120711A (en) Structure and method for conducting reinforcing processing on soft foundation by combining surcharge preloading and vacuum preloading
CN209039896U (en) The soft soil roadbed three-dimensional reinforced structure of convolution is knitted in a kind of stake-
CN112411518A (en) Soft foundation section vacuum combined surcharge preloading construction method
CN105200973A (en) Comprehensive treatment method of soft foundation
CN111733792A (en) Foundation treatment method and system for soft soil foundation vacuum preloading and power consolidation drainage
CN102704458A (en) Sand-free cushion layer vacuum-surcharge preloading reinforcement device and method for soft ground
CN101591906A (en) The method for processing foundation of intubate, multipass vacuum well-point dewatering dynamic consolidation
CN105804045A (en) Equipment for strengthening deep soft soil foundation by vacuum preloading of filter well and method
CN105484229B (en) Vacuum preloading method is sealed suitable for the overlying mud layer of the soft base in waters
CN104746506A (en) Soft soil combined preloading structure and construction method
CN209412838U (en) A kind of Cut Slopes of Expansive Soil structure
CN103276717A (en) Method for treating soft soil foundations with composite geotechnical synthetic material reinforced cushions
CN107245998A (en) A kind of method of cocoanut shell filling combined vacuum prepressing blowing filling soil base

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20240103

Address after: 251200 east of Yingbin Avenue, national high tech Industrial Development Zone, Dezhou City (Yucheng), Shandong Province

Patentee after: Shandong Rui HSI Technology Co.,Ltd.

Address before: 266590 No. 579, Qian Wan Gang Road, Qingdao economic and Technological Development Zone, Shandong

Patentee before: SHANDONG University OF SCIENCE AND TECHNOLOGY

TR01 Transfer of patent right