CN107190983B - A kind of construction method of prefabricated assembled cornice - Google Patents

A kind of construction method of prefabricated assembled cornice Download PDF

Info

Publication number
CN107190983B
CN107190983B CN201710408249.XA CN201710408249A CN107190983B CN 107190983 B CN107190983 B CN 107190983B CN 201710408249 A CN201710408249 A CN 201710408249A CN 107190983 B CN107190983 B CN 107190983B
Authority
CN
China
Prior art keywords
cornice
iron parts
embedded iron
installation
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710408249.XA
Other languages
Chinese (zh)
Other versions
CN107190983A (en
Inventor
周炳高
周波
矫贵峰
江华
何称称
袁一歧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kangboda Construction Technology Group Co ltd
Original Assignee
Kang Boda Energy Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kang Boda Energy Technology Co Ltd filed Critical Kang Boda Energy Technology Co Ltd
Priority to CN201710408249.XA priority Critical patent/CN107190983B/en
Publication of CN107190983A publication Critical patent/CN107190983A/en
Application granted granted Critical
Publication of CN107190983B publication Critical patent/CN107190983B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

The invention discloses a kind of construction methods of prefabricated assembled cornice, specifically comprise the following steps: preceding preparation of constructing, main structure ironware is pre-buried, cornice element precast, it builds operating platform and welds installation cornice, wherein cornice element precast determines the size of each specification component according to the model of preparation, the size of embedded iron parts in component is determined simultaneously, and determine the length and weld seam size of internal embedded bar, corresponding embedded iron parts are prepared according to embedded iron parts size, then fabrication and installation template and brushing release agent, embedded bar and corresponding embedded iron parts are installed in installation template, it pours haydite concrete and vibrates, then smear with plasterer's trowel presses receipts face to ensure that surface reaches hydrophilic effect, then demoulding is numbered after being conserved, and it is stacked according to corresponding specification.

Description

A kind of construction method of prefabricated assembled cornice
Technical field
The present invention relates to the realm of building construction, and in particular to a kind of construction method of prefabricated assembled cornice.
Background technique
With epoch and economic development, the moulding of building is also increasingly complicated.Such as Chinese air elementals a large amount of at present are mixed It is also applied in Xtah Crude Clay structure engineering.Pseudo-classic architecture refer to dedicated for imitate and substitute ancient architecture, traditional religion Buddhist and Taoist temples, Tradition makes scape, historical building, landmark, old countries group, restores the building of historical sites overview.Struggle against arch, and also referred to as paving is made, and is The essential part of Chinese tradition ancient building, and the one of the important signs that of display class of construction height.Join in column and crossbeam Place, the frame structure for leaning out archwise from level to level added from capital is arch, and the square cushion block padded between arch and arch is liter, bottom For portion's supporting block bucket, bucket, arch and liter are collectively referred to as " bucket arch ".
The conventional construction method of pseudo-classic architecture is all to be constructed using cast-in-place method, and the pseudo-classic architecture of construction molding is Cast-in-place concrete structure, the complex component of cornice also uses concrete structure and it synchronizes with main structure and carries out cast-in-place construction, There are complicated construction technique, the construction period is long, construction efficiency is low, security control item is more, quality control on construction difficulty is larger etc. Defect and deficiency.
Therefore a kind of prefabricated assembled cornice construction method is needed, above-mentioned unfavorable factor can be made to obtain radical change, be multiple Miscellaneous moulding building construction technology development, starts the road Chu Yitiaoxin.
Summary of the invention
Goal of the invention: the purpose of the present invention is to provide a kind of construction methods of prefabricated assembled cornice, are built first Primary structure construction is built, it is prefabricated to the progress of whole complex components in conjunction with BIM technology and 3D printing technique, then built completed It builds successively to weld on frame and whole complex components is installed, can simplify complex model construction and dominate process, make complex component Fabrication and installation are not take up total construction period, and quality control level also can be improved, and have feasibility.
Technical solution: a kind of construction method of prefabricated assembled cornice specifically comprises the following steps:
A, prepare before construction:
The construction of roofing complex model is simulated using BIM technology, determine Cast-in-Situ Segment and precast section divide position and Tie point, while threedimensional model is made to cornice bucket or model is prepared by timber, and model scale is 1:1 ~ 1:10, is passed through The location control and job order of welding installation are verified and improved to model;
B, main structure ironware is pre-buried
It checks main structure reinforcing bar and determines the position of embedded iron parts, it is ensured that embedded iron parts are located at frame column and cornice and hang Embedded iron parts are fixed on determining position and formwork, again ensure that embedded iron parts position does not have after formwork by the junction for choosing component There is change, casting concrete makes embedded iron parts be cast in inside, and then demoulding carries out check correction to embedded iron parts position;
C, cornice element precast
The size of each specification component is determined according to the model of preparation, while determining the size of embedded iron parts in component, and The length and weld seam size for determining internal embedded bar, prepare corresponding embedded iron parts according to embedded iron parts size, then make Make installation template and brushing release agent, embedded bar and corresponding embedded iron parts are installed in installation template, pour haydite coagulation Soil simultaneously vibrates, and then smear with plasterer's trowel and receipts face is pressed to ensure that surface reaches hydrophilic effect, demould and carry out after then being conserved Number, and stacked according to corresponding specification;
D, it builds operating platform and welds installation cornice
Operating platform is built around main structure, order when cornice is verified according to model carries out erecting and welding, tool Center line and horizontal line are popped up when body is installed on each prefabricated components, while also popping up center line in main body mechanism corresponding position With absolute altitude control line, determine welding installation site, horizontal ruler used for the horizontal control of component, into component arranged in columns it Between, by first drawing logical line to carry out unified adjustment.
Preferably, the cornice installation order is that first big angle is built in installation, then installs intermediate position, intermediate position is followed Lower layer's sets of brackets on top of the columns is first installed, then upper layer sets of brackets on top of the columns is installed, sets of brackets on top of the columns on the inside of first installation between same layer sets of brackets on top of the columns, then outside sets of brackets on top of the columns is installed.
Preferably, first pacifying a hanging wire component on each big angle after the installation of building big angle and drawing logical line, then intermediate bucket Arch according to line install and checks position, levelness and verticality it is errorless after be fixed welding, welding Shi Xiansi edge point weldering reexamines Whether there is or not displacements, and are adjusted to the component for having displacement, are formally welded after adjusting, and component both sides pair are taken in formal welding The mode of welding is claimed to carry out, last four side weld all around, weld bead height is controlled in 8mm.
Preferably, the embedded iron parts use fashioned iron or steel plate.
The utility model has the advantages that a kind of construction method of disclosed prefabricated assembled cornice, has the following beneficial effects:
On procedure arrangement, first progress the production of complex building frame part and by whole complex components carry out it is prefabricated, with Successively whole complex components are installed in welding on completed complex building frame afterwards, and this form makes construction operation difficulty It is small, intensity is low, process is few, speed is fast.
With traditional cast-in-place concrete construction technics comparing, with short time limit, quality control is simple and easy, need to do safe control The features such as content processed is few, cost is lower.
Specific embodiment
The present invention is further explained in the light of specific embodiments:
A kind of construction method of prefabricated assembled cornice, specifically comprises the following steps:
A, prepare before construction:
The construction of roofing complex model is simulated using BIM technology, determine Cast-in-Situ Segment and precast section divide position and Tie point, while threedimensional model is made to cornice bucket or model is prepared by timber, and model scale is 1:1 ~ 1:10, is passed through The location control and job order of welding installation are verified and improved to model;
B, main structure ironware is pre-buried
It checks main structure reinforcing bar and determines the position of embedded iron parts, it is ensured that embedded iron parts are located at frame column and cornice and hang Embedded iron parts are fixed on determining position and formwork, again ensure that embedded iron parts position does not have after formwork by the junction for choosing component There is change, casting concrete makes embedded iron parts be cast in inside, and then demoulding carries out check correction to embedded iron parts position;
C, cornice element precast
The size of each specification component is determined according to the model of preparation, while determining the size of embedded iron parts in component, and The length and weld seam size for determining internal embedded bar, prepare corresponding embedded iron parts according to embedded iron parts size, then make Make installation template and brushing release agent, embedded bar and corresponding embedded iron parts are installed in installation template, pour haydite coagulation Soil simultaneously vibrates, and then smear with plasterer's trowel and receipts face is pressed to ensure that surface reaches hydrophilic effect, demould and carry out after then being conserved Number, and stacked according to corresponding specification;
D, it builds operating platform and welds installation cornice
Operating platform is built around main structure, order when cornice is verified according to model carries out erecting and welding, tool Center line and horizontal line are popped up when body is installed on each prefabricated components, while also popping up center line in main body mechanism corresponding position With absolute altitude control line, determine welding installation site, horizontal ruler used for the horizontal control of component, into component arranged in columns it Between, by first drawing logical line to carry out unified adjustment.
The cornice installation order is that first big angle is built in installation, then installs intermediate position, and intermediate position follows under first installation Layer sets of brackets on top of the columns, then upper layer sets of brackets on top of the columns is installed, sets of brackets on top of the columns on the inside of first installation between same layer sets of brackets on top of the columns, then outside sets of brackets on top of the columns is installed;Build big angle installation Afterwards, first pacify hanging wire component on each big angle and draw logical line, then intermediate sets of brackets on top of the columns install and check according to line position, levelness and Welding is fixed after verticality is errorless, whether there is or not displacements for welding Shi Xiansi edge point weldering re-inspection, and carry out to the component for having displacement Adjustment, is formally welded after adjusting, formally welds the mode for taking component both sides to be symmetrically welded and carry out, last four side is enclosed Weldering, weld bead height are controlled in 8mm.
Technology contents and technical characteristic of the invention have revealed that as above, however those skilled in the art still may base Make various replacements and modification without departing substantially from spirit of that invention in announcement of the invention, therefore, the scope of the present invention is answered unlimited It in the revealed content of embodiment, and should include various without departing substantially from replacement and modification of the invention, and be present patent application right It is required that being covered.

Claims (2)

1. a kind of construction method of prefabricated assembled cornice, which comprises the following steps:
A, prepare before construction:
The construction of roofing complex model is simulated using BIM technology, determines that Cast-in-Situ Segment and precast section divide position and connection Point, while threedimensional model is made to cornice bucket or model is prepared by timber, and model scale is 1:1~1:10, passes through mould The location control and job order of welding installation are verified and improved to type;
B, main structure ironware is pre-buried
It checks main structure reinforcing bar and determines the position of embedded iron parts, it is ensured that embedded iron parts are located at frame column and cornice and overhanging structure Embedded iron parts are fixed on determining position and formwork, again ensure that embedded iron parts position does not change after formwork by the junction of part Become, casting concrete makes embedded iron parts be cast in inside, and then demoulding carries out check correction to embedded iron parts position;
C, cornice element precast
The size of each specification component is determined according to the model of preparation, while determining the size of embedded iron parts in component, and is determined The length and weld seam size of internal embedded bar, prepare corresponding embedded iron parts according to embedded iron parts size, then production peace Decking and brushing release agent install embedded bar and corresponding embedded iron parts in installation template, pour haydite concrete simultaneously It vibrates, then smear with plasterer's trowel and receipts face is pressed to ensure that surface reaches hydrophilic effect, demoulding is numbered after then being conserved, And it is stacked according to corresponding specification;
D, it builds operating platform and welds installation cornice
Operating platform is built around main structure, order when cornice is verified according to model carries out erecting and welding, specific to pacify Center line and horizontal line are popped up when dress on each prefabricated components, while also popping up center line and mark in main body mechanism corresponding position High control line determines welding installation site, uses horizontal ruler for the horizontal control of component, between component arranged in columns, By first drawing logical line to carry out unified adjustment;
The cornice installation order is that first big angle is built in installation, then installs intermediate position, and intermediate position follows first installation lower layer bucket Arch, then upper layer sets of brackets on top of the columns is installed, sets of brackets on top of the columns on the inside of first installation between same layer sets of brackets on top of the columns, then outside sets of brackets on top of the columns is installed;
After building big angle installation, first pacifies a hanging wire component on each big angle and draw logical line, then intermediate sets of brackets on top of the columns is installed simultaneously according to line Review position, levelness and verticality it is errorless after be fixed welding, welding Shi Xiansi edge point weldering re-inspection is and right whether there is or not displacement There is the component of displacement to be adjusted, formally welded after adjusting, formally welds the mode for taking component both sides to be symmetrically welded It carries out, the weld all around of last four side, weld bead height is controlled in 8mm.
2. a kind of construction method of prefabricated assembled cornice according to claim 1, it is characterised in that: the embedded iron parts Using fashioned iron or steel plate.
CN201710408249.XA 2017-06-02 2017-06-02 A kind of construction method of prefabricated assembled cornice Expired - Fee Related CN107190983B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710408249.XA CN107190983B (en) 2017-06-02 2017-06-02 A kind of construction method of prefabricated assembled cornice

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710408249.XA CN107190983B (en) 2017-06-02 2017-06-02 A kind of construction method of prefabricated assembled cornice

Publications (2)

Publication Number Publication Date
CN107190983A CN107190983A (en) 2017-09-22
CN107190983B true CN107190983B (en) 2019-08-30

Family

ID=59876976

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710408249.XA Expired - Fee Related CN107190983B (en) 2017-06-02 2017-06-02 A kind of construction method of prefabricated assembled cornice

Country Status (1)

Country Link
CN (1) CN107190983B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108532953B (en) * 2018-05-18 2020-03-31 宝业湖北建工集团有限公司 BIM-based cantilever plate construction method and building construction method
CN110761560A (en) * 2019-11-08 2020-02-07 陕西建工第三建设集团有限公司 Mounting and construction method for steel bracket-arch lifting composite structure of pseudo-classic architecture
CN111236554B (en) * 2020-01-20 2022-02-11 湖南宝信云建筑综合服务平台股份有限公司 One-step forming pouring method for cornice
CN111852019A (en) * 2020-06-30 2020-10-30 中铁上海工程局集团有限公司 Construction method of bar counter with special-shaped concrete structure
CN112482779B (en) * 2020-11-11 2022-04-22 重庆中科建设(集团)有限公司 Integral hoisting construction method for cornice bucket arch of antique building

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101417460A (en) * 2008-09-25 2009-04-29 陕西省第三建筑工程公司 Post welding mounting construction method of pseudo-classic architecture element
CN102094494A (en) * 2010-12-31 2011-06-15 中国建筑第四工程局有限公司 Construction process for paving S-shaped tiles on roof with slope of more than 60 degrees
CN103195214A (en) * 2013-04-24 2013-07-10 北京城建亚泰建设集团有限公司 Wood roof cornice decking and concrete composite structure in archaized buildings and construction method thereof
CN103938857A (en) * 2014-04-30 2014-07-23 山东送变电工程公司 Building cornice double-water-drip-line formwork and construction method thereof
CN105332510A (en) * 2015-11-12 2016-02-17 徐仁贵 Construction method of complicated beam column joint core area
CN105908889A (en) * 2016-04-29 2016-08-31 陕西建工第三建设集团有限公司 Construction method for prefabrication and reverse installation of cornice concrete decoration members of archaistic building
CN107832498A (en) * 2017-10-18 2018-03-23 陕西有色建设有限公司 A kind of complicated construction technology based on BIM is told somebody what one's real intentions are method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8407958B2 (en) * 2006-05-15 2013-04-02 Thomas L. Kelly Wind and water resistant back wrap roof edge termination

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101417460A (en) * 2008-09-25 2009-04-29 陕西省第三建筑工程公司 Post welding mounting construction method of pseudo-classic architecture element
CN102094494A (en) * 2010-12-31 2011-06-15 中国建筑第四工程局有限公司 Construction process for paving S-shaped tiles on roof with slope of more than 60 degrees
CN103195214A (en) * 2013-04-24 2013-07-10 北京城建亚泰建设集团有限公司 Wood roof cornice decking and concrete composite structure in archaized buildings and construction method thereof
CN103938857A (en) * 2014-04-30 2014-07-23 山东送变电工程公司 Building cornice double-water-drip-line formwork and construction method thereof
CN105332510A (en) * 2015-11-12 2016-02-17 徐仁贵 Construction method of complicated beam column joint core area
CN105908889A (en) * 2016-04-29 2016-08-31 陕西建工第三建设集团有限公司 Construction method for prefabrication and reverse installation of cornice concrete decoration members of archaistic building
CN107832498A (en) * 2017-10-18 2018-03-23 陕西有色建设有限公司 A kind of complicated construction technology based on BIM is told somebody what one's real intentions are method

Also Published As

Publication number Publication date
CN107190983A (en) 2017-09-22

Similar Documents

Publication Publication Date Title
CN107190983B (en) A kind of construction method of prefabricated assembled cornice
CN100476142C (en) Construction method for combined V-shape steel pipe concrete pile
CN106121236B (en) Floor bar protective layer and structural elevation integrated control method
CN106012851B (en) Steel box-girder and performance of concrete column confined method for synchronously constructing
CN108638324A (en) A kind of construction method of prefabricated case beam
CN106759354A (en) A kind of stratified continuous pouring mode of ultra-long and ultra-thick volume of concrete foundation
CN105568854B (en) Shaped form fish-bellied type cast-in-situ steel reinforced concrete box girder construction method waterborne
CN206015861U (en) The cast-in-place core body of light block wall
CN108590008A (en) Fold shape roof system cast-in-place concrete construction method
CN109176843A (en) A kind of horizontal pier stud bent cap integral preform mold and its construction method
CN108487630A (en) Coagulation earth steps platform prefabrication and assembly construction construction method
CN105839985A (en) Hydropower station rectangular high tower hydraulic climb slip form system and construction method
CN105714966A (en) Inverted laminated slab provided with elevation adjustment devices and construction method
CN107806019A (en) Large-span suspension bridge gate Sarasota construction method
CN105089184B (en) Multi-curved concrete hollow modelling wall construction method and rhombic hollow structure formwork
CN106869493A (en) One kind cheats new formwork system and its construction method in hole
CN101417460B (en) Post welding mounting construction method of pseudo-classic architecture element
CN105064500B (en) Balcony beam slab inner side filling wall body and main body structure integral casting construction method
CN108625531A (en) A kind of construction method pouring constructional column concrete non-dismantling formwork
CN106906747A (en) A kind of column and bent cap splicing structure
CN106049665B (en) The construction method of the cast-in-place core of light block wall
CN106567329A (en) Semi-prefabricated reinforced concrete wall type guardrail
CN106567328A (en) Half-prefabricated reinforced concrete wall-type guardrail construction process
CN209652963U (en) Mold for assembly concrete hypogee sole plate
CN103171052B (en) The disposable prefabricated construction engineering method of twin columns wave-breaking body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 226100 No. 76-1, Xincheng West Road, Yuelai Town, Haimen District, Nantong City, Jiangsu Province

Patentee after: Kangboda Construction Technology Group Co.,Ltd.

Address before: 226000 No. 69, Xincheng West Road, Yuelai Town, Haimen City, Nantong City, Jiangsu Province

Patentee before: KANGBODA ENERGY SAVING TECHNOLOGY Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190830