CN107169672A - System, the method and device of a kind of automatic data collection workshop task - Google Patents
System, the method and device of a kind of automatic data collection workshop task Download PDFInfo
- Publication number
- CN107169672A CN107169672A CN201710431116.4A CN201710431116A CN107169672A CN 107169672 A CN107169672 A CN 107169672A CN 201710431116 A CN201710431116 A CN 201710431116A CN 107169672 A CN107169672 A CN 107169672A
- Authority
- CN
- China
- Prior art keywords
- cloud terminal
- cloud
- acquisition server
- plan
- task
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 29
- 238000013480 data collection Methods 0.000 title claims abstract description 23
- 230000002159 abnormal effect Effects 0.000 claims abstract description 41
- 238000004519 manufacturing process Methods 0.000 claims abstract description 38
- 230000005540 biological transmission Effects 0.000 claims abstract description 11
- 230000001360 synchronised effect Effects 0.000 claims description 18
- 238000012545 processing Methods 0.000 claims description 14
- 230000005856 abnormality Effects 0.000 claims description 9
- 238000012790 confirmation Methods 0.000 claims description 9
- 238000013461 design Methods 0.000 claims description 9
- 239000000463 material Substances 0.000 claims description 9
- 239000002184 metal Substances 0.000 claims description 9
- 238000010586 diagram Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063114—Status monitoring or status determination for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/25—Integrating or interfacing systems involving database management systems
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063116—Schedule adjustment for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063118—Staff planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06315—Needs-based resource requirements planning or analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/04—Manufacturing
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Development Economics (AREA)
- Game Theory and Decision Science (AREA)
- Quality & Reliability (AREA)
- Educational Administration (AREA)
- Operations Research (AREA)
- Databases & Information Systems (AREA)
- Data Mining & Analysis (AREA)
- General Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- General Factory Administration (AREA)
Abstract
The embodiment of the invention discloses a kind of method of automatic data collection workshop task, apparatus and system.Methods described includes:Number evidence is sent in the plan that cloud data acquisition server obtains the transmission of cloud terminal in real time;The cloud terminal receives the task information that the cloud data acquisition server is issued.So as to differ because of each group technique in workshop, nonstandard product, by the way that this scheme can automatic refresh shows that each group sends work information in each group information screen automatically, the progress and target of the clear all producers of guide, while group leader also has the more time to carry out quality in site management and control;Outlet is sent after work exception, and client (group) can be accelerated administrative staff and plan as a whole scheduling with service end (shop office) abnormal information simultaneous display and alarm;Work efficiency rate is sent so as to lift production.
Description
Technical field
The present embodiments relate to the technical field of Workshop Production system, more particularly to a kind of automatic data collection workshop task
System, method and device.
Background technology
In existing, when needing to obtain each group progress and situation in production system, group leader, which needs to login ERP in person, to go to look into
Oneself group is looked for send work progress and information.It is communicated to following set of member again simultaneously, information has will also go to verify at any time after renewal,
The time for constraining group leader's field management quality simultaneously, occurs also reporting that elongation supervisor is coordinated to office in person after exception
Solve, have impact on the efficiency for sending work.
The content of the invention
The purpose of the embodiment of the present invention is system, the method and device for proposing a kind of automatic data collection workshop task, it is intended to
Solve how to improve the efficiency for sending work.
For up to this purpose, the embodiment of the present invention uses following technical scheme:
In a first aspect, a kind of system of automatic data collection workshop task, the system includes:
Cloud data acquisition server and cloud terminal;
The cloud data acquisition server, appoints for obtaining the task information of ERP database and issuing the work
Information of being engaged in is to the cloud terminal;
The cloud terminal, for receiving the task information that the cloud data acquisition server is issued;
Wherein, the ERP database includes production task plan scheduling and sends number evidence.
Alternatively, the system also includes:
If not according to the scheduling scheduled completion time during production in cloud terminal, the cloud terminal closes plan;
If the cloud terminal occurs abnormal design, abnormal material and production and processing tool abnormality in production, the cloud
Terminal carries out abnormal confirmation by the metal keyboard under screen billboard, while the lower section of correspondence group billboard display screen is shown to,
Synchronized transmission is into the database of the ERP.
Alternatively, the system also includes:Send number according to occurring under abnormal conditions in the plan, the cloud terminal will show
Show that warning message is synchronized to the cloud data acquisition server, the cloud terminal acquisition server display alarm and flashing light, remind
Administrative staff make overall arrangements processing.
A kind of second aspect, the method for automatic data collection workshop task, methods described includes:
Number evidence is sent in the plan that cloud data acquisition server obtains the transmission of cloud terminal in real time;
The cloud terminal receives the task information that the cloud data acquisition server is issued.
Alternatively, methods described also includes:
If not according to the scheduling scheduled completion time during production in cloud terminal, the cloud terminal closes plan;
If the cloud terminal occurs abnormal design, abnormal material and production and processing tool abnormality in production, the cloud
Terminal carries out abnormal confirmation by the metal keyboard under screen billboard, while the lower section of correspondence group billboard display screen is shown to,
Synchronized transmission is into the database of the ERP.
Alternatively, methods described also includes:
Send number according to occurring under abnormal conditions in the plan, display alarm information is synchronized to the cloud by the cloud terminal
Data acquisition server, the cloud terminal acquisition server display alarm and flashing light, remind administrative staff to make overall arrangements place
Reason.
A kind of third aspect, the device of automatic data collection workshop task, described device includes:
Acquisition module, number evidence is sent for obtaining the plan that cloud terminal is sent in real time;
Sending module, for receiving the task information that the cloud data acquisition server is issued.
Alternatively, described device also includes:
If not according to the scheduling scheduled completion time during production in cloud terminal, the cloud terminal closes plan;
If the cloud terminal occurs abnormal design, abnormal material and production and processing tool abnormality in production, the cloud
Terminal carries out abnormal confirmation by the metal keyboard under screen billboard, while the lower section of correspondence group billboard display screen is shown to,
Synchronized transmission is into the database of the ERP.
Alternatively, described device also includes:
Send number according to occurring under abnormal conditions in the plan, display alarm information is synchronized to the cloud by the cloud terminal
Data acquisition server, the cloud terminal acquisition server display alarm and flashing light, remind administrative staff to make overall arrangements place
Reason.
A kind of method of automatic data collection workshop task provided in an embodiment of the present invention, apparatus and system, cloud data acquisition clothes
Number evidence is sent in the plan that business device obtains the transmission of cloud terminal in real time;The cloud terminal receives what the cloud data acquisition server was issued
Task information.So as to differ because of each group technique in workshop, nonstandard product can be automatically in each group information by this scheme
Automatic refresh shows that each group sends work information on screen, the progress and target of the clear all producers of guide, while group leader also has more
Many times carry out quality in site management and control;Outlet is sent after work exception, and client (group) can be abnormal with service end (shop office)
Synchronizing information shows and alarmed, and accelerates administrative staff and plans as a whole scheduling;Work efficiency rate is sent so as to lift production.
Brief description of the drawings
Fig. 1 is a kind of structural representation of the system of automatic data collection workshop task provided in an embodiment of the present invention;
Fig. 2 is a kind of schematic flow sheet of the method for automatic data collection workshop task provided in an embodiment of the present invention;
Fig. 3 is a kind of high-level schematic functional block diagram of the device of automatic data collection workshop task provided in an embodiment of the present invention.
Embodiment
The embodiment of the present invention is described in further detail with reference to the accompanying drawings and examples.It is understood that this
The specific embodiment of place description is used only for explaining the embodiment of the present invention, rather than the restriction to the embodiment of the present invention.In addition also
It should be noted that for the ease of description, the part related to the embodiment of the present invention rather than entire infrastructure are illustrate only in accompanying drawing.
With reference to Fig. 1, Fig. 1 is a kind of structural representation of the system of automatic data collection workshop task provided in an embodiment of the present invention
Figure.
As shown in figure 1, the system includes:
Cloud data acquisition server 101 and cloud terminal 102;
The cloud data acquisition server 101, for obtaining the task information of ERP database and issuing the work
Mission bit stream is to the cloud terminal 102;
The cloud terminal 102, for receiving the task information that the cloud data acquisition server 101 is issued;
Wherein, the ERP database includes production task plan scheduling and sends number evidence.
Specifically, the ERP database includes production task group, planned time, job order, process names, ProductName
Title, quantity and standard work force.It is multi-user access server, each one user of cloud terminal distribution and IP address are attached
Cloud data acquisition server, one of cloud terminal is used as service end.
One of cloud terminal is arrived as service end for obtaining the task information of ERP database and issuing task
Other cloud terminals, other cloud terminals receive the task information that service end is issued as client.It is shown to simultaneously corresponding
On billboard information screen.
Alternatively, the system also includes:
If not according to the scheduling scheduled completion time during production in cloud terminal, the cloud terminal closes plan;
If the cloud terminal occurs abnormal design, abnormal material and production and processing tool abnormality in production, the cloud
Terminal carries out abnormal confirmation by the metal keyboard under screen billboard, while the lower section of correspondence group billboard display screen is shown to,
Synchronized transmission is into the database of the ERP.
Alternatively, the system also includes:Send number according to occurring under abnormal conditions in the plan, the cloud terminal will show
Show that warning message is synchronized to the cloud data acquisition server, the cloud terminal acquisition server display alarm and flashing light, remind
Administrative staff make overall arrangements processing.
A kind of system of automatic data collection workshop task provided in an embodiment of the present invention, cloud data acquisition server is obtained in real time
Number evidence is sent in the plan that cloud terminal is sent;The cloud terminal receives the task letter that the cloud data acquisition server is issued
Breath.So as to differ because of each group technique in workshop, nonstandard product can be brushed automatically in each group information screen automatically by this scheme
New display each group sends work information, the progress and target of the clear all producers of guide, while group leader also has more time progress
Quality in site management and control;Outlet is sent after work exception, and client (group) can be synchronously aobvious with service end (shop office) abnormal information
Show and alarm, accelerate administrative staff and plan as a whole scheduling;Work efficiency rate is sent so as to lift production.
With reference to Fig. 2, Fig. 2 is a kind of flow signal of the method for automatic data collection workshop task provided in an embodiment of the present invention
Figure.
As shown in Fig. 2 the method for automatic data collection workshop task includes:
Step 201, cloud data acquisition server obtain in real time cloud terminal transmission plan send number evidence;
Step 202, the cloud terminal receives the task information that the cloud data acquisition server is issued.
Alternatively, methods described also includes:
If not according to the scheduling scheduled completion time during production in cloud terminal, the cloud terminal closes plan;
If the cloud terminal occurs abnormal design, abnormal material and production and processing tool abnormality in production, the cloud
Terminal carries out abnormal confirmation by the metal keyboard under screen billboard, while the lower section of correspondence group billboard display screen is shown to,
Synchronized transmission is into the database of the ERP.
Alternatively, methods described also includes:
Send number according to occurring under abnormal conditions in the plan, display alarm information is synchronized to the cloud by the cloud terminal
Data acquisition server, the cloud terminal acquisition server display alarm and flashing light, remind administrative staff to make overall arrangements place
Reason.
A kind of method of automatic data collection workshop task provided in an embodiment of the present invention, cloud data acquisition server is obtained in real time
Number evidence is sent in the plan that cloud terminal is sent;The cloud terminal receives the task letter that the cloud data acquisition server is issued
Breath.So as to differ because of each group technique in workshop, nonstandard product can be brushed automatically in each group information screen automatically by this scheme
New display each group sends work information, the progress and target of the clear all producers of guide, while group leader also has more time progress
Quality in site management and control;Outlet is sent after work exception, and client (group) can be synchronously aobvious with service end (shop office) abnormal information
Show and alarm, accelerate administrative staff and plan as a whole scheduling;Work efficiency rate is sent so as to lift production.
With reference to Fig. 3, Fig. 3 is that a kind of functional module of the device of automatic data collection workshop task provided in an embodiment of the present invention is shown
It is intended to.
As shown in figure 3, the device of automatic data collection workshop task includes:
Acquisition module 301, number evidence is sent for obtaining the plan that cloud terminal is sent in real time;
Sending module 302, for receiving the task information that the cloud data acquisition server is issued.
Alternatively, described device also includes:
If not according to the scheduling scheduled completion time during production in cloud terminal, the cloud terminal closes plan;
If the cloud terminal occurs abnormal design, abnormal material and production and processing tool abnormality in production, the cloud
Terminal carries out abnormal confirmation by the metal keyboard under screen billboard, while the lower section of correspondence group billboard display screen is shown to,
Synchronized transmission is into the database of the ERP.
Alternatively, described device also includes:
Send number according to occurring under abnormal conditions in the plan, display alarm information is synchronized to the cloud by the cloud terminal
Data acquisition server, the cloud terminal acquisition server display alarm and flashing light, remind administrative staff to make overall arrangements place
Reason.
A kind of device of automatic data collection workshop task provided in an embodiment of the present invention, cloud data acquisition server is obtained in real time
Number evidence is sent in the plan that cloud terminal is sent;The cloud terminal receives the task letter that the cloud data acquisition server is issued
Breath.So as to differ because of each group technique in workshop, nonstandard product can be brushed automatically in each group information screen automatically by this scheme
New display each group sends work information, the progress and target of the clear all producers of guide, while group leader also has more time progress
Quality in site management and control;Outlet is sent after work exception, and client (group) can be synchronously aobvious with service end (shop office) abnormal information
Show and alarm, accelerate administrative staff and plan as a whole scheduling;Work efficiency rate is sent so as to lift production.
The technical principle of the embodiment of the present invention is described above in association with specific embodiment.These descriptions are intended merely to explain this
The principle of inventive embodiments, and the limitation to protection domain of the embodiment of the present invention can not be construed in any way.Based on herein
Explanation, those skilled in the art, which would not require any inventive effort, can associate the other specific of the embodiment of the present invention
Embodiment, these modes are fallen within the protection domain of the embodiment of the present invention.
Claims (9)
1. the system of a kind of automatic data collection workshop task, it is characterised in that the system includes:
Cloud data acquisition server and cloud terminal;
The cloud data acquisition server, for obtaining the task information of ERP database and issuing the task letter
Cease the cloud terminal;
The cloud terminal, for receiving the task information that the cloud data acquisition server is issued;
Wherein, the ERP database includes production task plan scheduling and sends number evidence.
2. system according to claim 1, it is characterised in that the system also includes:
If not according to the scheduling scheduled completion time during production in cloud terminal, the cloud terminal closes plan;
If the cloud terminal occurs abnormal design, abnormal material and production and processing tool abnormality in production, the cloud terminal
Abnormal confirmation is carried out by the metal keyboard under screen billboard, while the lower section of correspondence group billboard display screen is shown to, it is synchronous
In the database for being sent to the ERP.
3. system according to claim 1 or 2, it is characterised in that the system also includes:Number evidence is sent in the plan
Occur under abnormal conditions, display alarm information is synchronized to the cloud data acquisition server, the cloud terminal by the cloud terminal
Acquisition server display alarm and flashing light, remind administrative staff to make overall arrangements processing.
4. the method for a kind of automatic data collection workshop task, it is characterised in that methods described includes:
Number evidence is sent in the plan that cloud data acquisition server obtains the transmission of cloud terminal in real time;
The cloud terminal receives the task information that the cloud data acquisition server is issued.
5. method according to claim 4, it is characterised in that methods described also includes:
If not according to the scheduling scheduled completion time during production in cloud terminal, the cloud terminal closes plan;
If the cloud terminal occurs abnormal design, abnormal material and production and processing tool abnormality in production, the cloud terminal
Abnormal confirmation is carried out by the metal keyboard under screen billboard, while the lower section of correspondence group billboard display screen is shown to, it is synchronous
In the database for being sent to the ERP.
6. the method according to claim 4 or 5, it is characterised in that methods described also includes:
Send number according to occurring under abnormal conditions in the plan, display alarm information is synchronized to the cloud data by the cloud terminal
Acquisition server, the cloud terminal acquisition server display alarm and flashing light, remind administrative staff to make overall arrangements processing.
7. the device of a kind of automatic data collection workshop task, it is characterised in that described device includes:
Acquisition module, number evidence is sent for obtaining the plan that cloud terminal is sent in real time;
Sending module, for receiving the task information that the cloud data acquisition server is issued.
8. device according to claim 7, it is characterised in that described device also includes:
If not according to the scheduling scheduled completion time during production in cloud terminal, the cloud terminal closes plan;
If the cloud terminal occurs abnormal design, abnormal material and production and processing tool abnormality in production, the cloud terminal
Abnormal confirmation is carried out by the metal keyboard under screen billboard, while the lower section of correspondence group billboard display screen is shown to, it is synchronous
In the database for being sent to the ERP.
9. the device according to claim 7 or 8, it is characterised in that described device also includes:
Send number according to occurring under abnormal conditions in the plan, display alarm information is synchronized to the cloud data by the cloud terminal
Acquisition server, the cloud terminal acquisition server display alarm and flashing light, remind administrative staff to make overall arrangements processing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710431116.4A CN107169672A (en) | 2017-06-07 | 2017-06-07 | System, the method and device of a kind of automatic data collection workshop task |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710431116.4A CN107169672A (en) | 2017-06-07 | 2017-06-07 | System, the method and device of a kind of automatic data collection workshop task |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107169672A true CN107169672A (en) | 2017-09-15 |
Family
ID=59824744
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710431116.4A Pending CN107169672A (en) | 2017-06-07 | 2017-06-07 | System, the method and device of a kind of automatic data collection workshop task |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107169672A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107886300A (en) * | 2017-11-07 | 2018-04-06 | 微服云联科技(深圳)有限公司 | Billboard card management method, apparatus, computer equipment and storage medium |
CN109624253A (en) * | 2018-12-28 | 2019-04-16 | 武汉思伟塑业有限公司 | A kind of injection workshop monitoring discharge system |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102385363A (en) * | 2011-09-19 | 2012-03-21 | 浙江理工大学 | ERP-based intelligent intensive control system of continuous dyeing production line |
CN202523104U (en) * | 2012-03-28 | 2012-11-07 | 浙江力太科技有限公司 | Accurate production event notification device based on manufacturing industry |
CN103810576A (en) * | 2014-03-07 | 2014-05-21 | 西安工业大学 | Workshop production management method and system based on Internet of Things |
CN104331767A (en) * | 2014-10-28 | 2015-02-04 | 江苏云道信息技术有限公司 | Multi-system cooperative system and method for production process control of discrete manufacturing enterprises |
CN104463452A (en) * | 2014-11-29 | 2015-03-25 | 中山市铧禧电子科技有限公司 | Management method of production management system |
CN105574647A (en) * | 2015-12-11 | 2016-05-11 | 李庆钗 | Active intelligent in-place equipment management system |
CN106056276A (en) * | 2016-05-23 | 2016-10-26 | 国家电网公司 | Material information management method and application platform |
CN106327072A (en) * | 2016-08-19 | 2017-01-11 | 李广伟 | Budget cost management system for project node controlling |
CN106355358A (en) * | 2016-10-21 | 2017-01-25 | 用友网络科技股份有限公司 | Data manipulation method with double modes in mobile ERP system and ERP system |
CN106779592A (en) * | 2016-12-02 | 2017-05-31 | 林冠良 | A kind of improving production management banner system and application process |
-
2017
- 2017-06-07 CN CN201710431116.4A patent/CN107169672A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102385363A (en) * | 2011-09-19 | 2012-03-21 | 浙江理工大学 | ERP-based intelligent intensive control system of continuous dyeing production line |
CN202523104U (en) * | 2012-03-28 | 2012-11-07 | 浙江力太科技有限公司 | Accurate production event notification device based on manufacturing industry |
CN103810576A (en) * | 2014-03-07 | 2014-05-21 | 西安工业大学 | Workshop production management method and system based on Internet of Things |
CN104331767A (en) * | 2014-10-28 | 2015-02-04 | 江苏云道信息技术有限公司 | Multi-system cooperative system and method for production process control of discrete manufacturing enterprises |
CN104463452A (en) * | 2014-11-29 | 2015-03-25 | 中山市铧禧电子科技有限公司 | Management method of production management system |
CN105574647A (en) * | 2015-12-11 | 2016-05-11 | 李庆钗 | Active intelligent in-place equipment management system |
CN106056276A (en) * | 2016-05-23 | 2016-10-26 | 国家电网公司 | Material information management method and application platform |
CN106327072A (en) * | 2016-08-19 | 2017-01-11 | 李广伟 | Budget cost management system for project node controlling |
CN106355358A (en) * | 2016-10-21 | 2017-01-25 | 用友网络科技股份有限公司 | Data manipulation method with double modes in mobile ERP system and ERP system |
CN106779592A (en) * | 2016-12-02 | 2017-05-31 | 林冠良 | A kind of improving production management banner system and application process |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107886300A (en) * | 2017-11-07 | 2018-04-06 | 微服云联科技(深圳)有限公司 | Billboard card management method, apparatus, computer equipment and storage medium |
CN109624253A (en) * | 2018-12-28 | 2019-04-16 | 武汉思伟塑业有限公司 | A kind of injection workshop monitoring discharge system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101768810B1 (en) | Wind farm supervision monitoring system | |
CN107481349B (en) | Station inspection method and inspection system thereof | |
CN110782370A (en) | Comprehensive operation and maintenance management platform for power dispatching data network | |
CN110428112A (en) | A kind of dual prevention mechanism management system of enterprise based under internet+mode | |
CN102124486B (en) | Apparatus and associated method for tracking aircraft status | |
Martin et al. | The interactional affordances of technology: An ethnography of human-computer interaction in an ambulance control centre | |
CN110599007A (en) | Project progress management system | |
CN107135276A (en) | A kind of full link monitoring methods, devices and systems under micro services framework | |
CN109784508A (en) | A kind of power grid panorama monitoring operation management method and system based on cloud platform | |
CN105894601A (en) | Supervising device and supervising method for maintenance operation on site | |
CN106504361A (en) | A kind of moving 2 D code power station cruising inspection system | |
CN108107851A (en) | A kind of production line intelligent remote pacifies lamp control system | |
CN106156988A (en) | Logistics waybill records folk prescription method automatically | |
CN111178778A (en) | Security activity scheme generation method and system based on machine learning and security activity management system | |
CN112477927A (en) | Rail transit station control information system based on mobile terminal | |
CN107169672A (en) | System, the method and device of a kind of automatic data collection workshop task | |
CN112288903A (en) | Card punching system, method and equipment | |
CN110992492A (en) | Three-dimensional visual production management system and method | |
CN110570125A (en) | Intelligent housekeeper system for safe operation of oil and gas pipeline | |
CN112465163A (en) | IT operation and maintenance emergency cooperation system and method | |
CN102262402A (en) | A method and apparatus for providing industrial plant information | |
CN109117526A (en) | One kind being suitable for mechanical system maintenance of equipment and guides data record and analysis system | |
CN103150682A (en) | Workshop information intelligent interactive system | |
CN109357898A (en) | Spacecraft parts grade normal pressure heat test control system | |
WO2016180083A1 (en) | Airport operation command system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170915 |
|
RJ01 | Rejection of invention patent application after publication |