CN107152147A - A kind of concrete abrasion-resistant terrace construction technique - Google Patents
A kind of concrete abrasion-resistant terrace construction technique Download PDFInfo
- Publication number
- CN107152147A CN107152147A CN201710466662.1A CN201710466662A CN107152147A CN 107152147 A CN107152147 A CN 107152147A CN 201710466662 A CN201710466662 A CN 201710466662A CN 107152147 A CN107152147 A CN 107152147A
- Authority
- CN
- China
- Prior art keywords
- concrete
- construction technique
- terrace
- carried out
- abrasion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/12—Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Curing Cements, Concrete, And Artificial Stone (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
A kind of terrace construction technique belongs to floor construction technical field, relates generally to a kind of concrete abrasion-resistant terrace construction technique;The present invention produces that crack, poor toughness, anti-fatigue ability are low to solve terrace, and tensile strength is low, shock resistance fragmentation, and later maintenance maintenance cost is high, the problem of terrace service life is short;Comprise the following steps:Base treatment:Template is laid:Template laying is carried out according to concrete point bin location;Concreting:Constructed using sequence placing mode;Leveling, is constructed using being flattened from periphery to center centralized system, concrete surface flatness is met construction requirement;Wearing layer, the spreading of three progress high-abrasive materials of part are laid, and is carried out levelling;Maintenance:Sealing compound is sprayed, cracking is prevented;The slot cementation of fissures is constructed;The present invention solve concrete ground criticize the cracking occurred, hollowing, flake, the flatness quality problems such as not enough, reduce cost, and reduce the maintenance cost in later stage and the service life of extension terrace.
Description
Technical field
A kind of terrace construction technique belongs to floor construction technical field, relates generally to a kind of concrete abrasion-resistant floor construction work
Skill.
Background technology
The service range of terrace is modern industrial enterprises terrace, business terrace, big-and-middle-sized parking lot terrace, garage parking
Level ground, commercial square, station terminal, school's sports ground, logistics warehouse terrace, hospital's terrace, office's terrace, swimming pool terrace,
Tourist attraction terrace, various recreation centers terrace, various research and development fields terrace, in a word, as long as using the ground of concrete
Level ground face can make terrace, and terrace has that anti-pressure ability is strong, wear-resistant Chengdu is high, dust-proof, grease proofing, impermeabilisation, easy to clean etc.
Premium properties, in actual applications using more and more extensively, however, terrace is urgently to be resolved hurrily in the presence of some in work progress
The problem of, for example terrace generation crack, poor toughness, anti-fatigue ability are low, and tensile strength is low, shock resistance fragmentation, later maintenance dimension
Accomplish this height, terrace service life is short.
The content of the invention
In order to solve the above problems, the invention discloses a kind of concrete abrasion-resistant terrace construction technique, terrace is enhanced
Toughness, crack resistance are strong, anti-fatigue ability is high, extend the service life of terrace.
The object of the present invention is achieved like this:
A kind of concrete abrasion-resistant terrace construction technique, comprises the following steps:
Step one:Base treatment:Basic unit is cleared up, absolute altitude is carried out and compacting is constructed;
Step 2:Template is laid:Template laying is carried out according to concrete point bin location;
Step 3:Concreting:Constructed using sequence placing mode;
Step 4:Leveling, is constructed using being flattened from periphery to center centralized system, and concrete surface flatness is met construction will
Ask;
Step 5:Wearing layer, the spreading of three progress high-abrasive materials of part are laid, and is carried out levelling.
Step 6:Maintenance:Sealing compound is sprayed, cracking is prevented;
Step 7:The slot cementation of fissures is constructed.
The detailed process of base treatment described in step one includes:Base cleaning is clean;Bottom element soil is compacted;Paving
If broken sandstone simultaneously and is conserved.
The plain soil compaction coefficient is 0.95, and flatness scope is 0-3mm.
Step 3 specifically includes procedure below:The double-deck polypropylene isolated film of laying;The preparation of concrete;Poured using a point storehouse
The method of building is poured;Progress is vibrated levelling.
The preparation method of the concrete includes:Steel fibre, sand and rubble are stirred;Once add in stirring thing
Add water mud, flyash, zeolite powder, silicon ash water and auxiliary agent is stirred.
The slump of the concrete is less than 5cm,.
Step 5 is specifically included:When concrete initial set is to 50%-60%, one layer of quartz sand particle is dispensed;Carry out floating carry
Slurry, it is 0-3mm to make its flatness;Second of quartz sand particle spreading is carried out, floating warehouse, flatness reaches 0-3mm;Carry out the
Three times quartz sand particle is dispensed, and floating warehouse, flatness reaches 0-2mm.
The ratio between consumption of three spreadings quartz sand particle is 4:1:1.
Step 7 is specifically included:After concreting 30h-60h, lancing operation is carried out, deep and concrete thickness ratio is stitched
For between 1/3-3/5.
The slit width is 3-5mm.
The present invention compared with prior art, has the advantages that steel fibre is abundant and is uniformly filled in coagulation
Each place of soil, is improved terrace toughness, using the terrace high mechanical properties of construction technology of the present invention, solves coagulation
Soil criticize occur cracking, hollowing, flake, flatness not enough etc. quality problems, reduce cost, and reduce the later stage
The service life of maintenance cost and extension terrace, without assembling reinforcement, in casting and compacting of concrete, it is not necessary to pump, improves and pours
Speed, easy construction, without large-scale construction equipment, low cost, speed of application is fast, short time limit, with better economy effect
Benefit;Rolled steel dosage reduction power consumption is reduced, low-carbon environment-friendly economizes on resources.
Embodiment
The specific embodiment of the invention is described in further detail below.
A kind of concrete abrasion-resistant terrace construction technique of the present embodiment, comprises the following steps:
Step one:Base treatment:Base cleaning is clean;Bottom element soil is compacted, the plain soil compaction coefficient is
0.95, flatness scope is 0-3mm;The broken sandstone of 15mm-30mm specifications is laid, laying depth is 20mm, and coefficient of loose laying is
1.2, it is compacted using 20t road rollers, compacting factor is more than in 0.95, compacting process according to actual needs, is moistened on a small quantity
It is wet;0-15mm year sandstone is laid, thickness is 40mm, compacting is entered using road roller, carry out gap filling and levelling, laying is completed
Conserved afterwards, the broken sandstone is the crushed-gravel that sand content is 3%,
Step 2:Template is laid:Template laying is carried out according to concrete point bin location, using the side form of channel-section steel seat concrete, and
Fixed using triangular reinforced bar support;During formwork, the upper flat absolute altitude of template is consistent with bottom surface absolute altitude;
Step 3:Concreting:Constructed, specifically included using sequence placing mode:Lay the thick polypropylene of bilayer 0.15mm
Provided with the epoxy glue layer that 0.1mm is thick between film, two layers of polypropylene film;Using double-deck isolated film as an entirety,
Prevent occurring misplacing in work progress and breakage, meanwhile, epoxy glue layer has good insulation and toughness, to the later stage
Concrete pour with good basic effect;
Transmission rod is installed, sets up straight by spacing of the power transmission between dry and transmission rod on locating template, locating template in template both sides
Footpath is drilled, and transmission rod one end is fixed for one section, the transmission rod is uniformly arranged in transmission rod through drilling by spot welding with support
At terrace plate thickness 1/2;The transmission rod is vertical with locating template, and the outside of transmission rod brushes pitch and carries out colligation again in advance
On support,
The preparation of concrete:Steel fibre, sand and rubble are stirred;Cement, flyash, boiling are once added in stirring thing
Stone flour, silicon ash water and auxiliary agent are stirred, and the content of the steel fibre is 20kg/m3;The slump of the concrete is less than
5cm, the intensity of concrete is that grade is C30.
Poured using sequence placing method, using catching up with slurry processes to be promoted, during concreting, virtual resurfacing thickness is than actual
Thickness is higher by 5mm or so, is vibrated using vibrating spear, after completion is vibrated, is rolled repeatedly using steel pipe roller, until surface goes out
Existing bleeding state;For the diamond-shaped area of building on the peripheries such as cylinder, diamond-shaped area pours one week after or so first, carries out secondary
Pour, it is to avoid surrounding terrace stress, which is concentrated, produces crack;
Step 4:Leveling, is constructed using being flattened from periphery to center centralized system, and concrete surface flatness is met construction will
Ask;
Step 5:When concrete initial set is to 50%-60%, one layer of quartz sand particle is dispensed;Carried out at least twice using trowel ray machine
Polishing, is allowed to be combined with concrete, carries out floating warehouse, and it is 0-3mm to make its flatness;Second of quartz sand particle is carried out to spread
Cloth, carries out trowel ray machine operation at least twice, and operation is crisscross to be carried out, and floating warehouse, flatness reaches 0-3mm;Carry out the 3rd
Secondary quartz sand particle is dispensed, and is carried out at least three times and is not installed the trowel ray machine operation of disk additional, while coordinate craft to be polished, it is floating
Warehouse, flatness reaches 0-2mm.
The ratio between consumption of three spreadings quartz sand particle is 4:1:1.
Step 6:Maintenance:Sprinkling sealing compound is conserved after abrasion-proof terrace construction 10h, and consumption is 0.2L/m2, prevent out
Split, curing time is no less than 7d;
Step 7:The slot cementation of fissures is constructed.After concreting 30h-60h, lancing operation is carried out, deep and concrete thickness ratio is stitched
For 2/3, slit width is 5mm;The debris such as microlith, cement mortar in the progress cementation of fissures, thorough cleaning slot, with air compressor machine or crack-cleaning machine
Dust on seam bottom, latasuture is blown clean, and keeps drying;It is 3 that contracting, which seams closure material breadth depth ratio,:5, minimum crack pouring width is
6mm-8mm;The joint seal material breadth depth ratio on expansion joint (E.J.) material top is 3:2.
Terrace surface is handled.
The compression strength of the present embodiment concrete improves 15% compared with the normal concrete compression strength of ad eundem;From
By expansion and contraction compared with normal concrete, 30% is reduced.
Claims (10)
1. a kind of concrete abrasion-resistant terrace construction technique, it is characterised in that:Comprise the following steps:
Step one:Base treatment:Basic unit is cleared up, absolute altitude is carried out and compacting is constructed;
Step 2:Template is laid:Template laying is carried out according to concrete point bin location;
Step 3:Concreting:Constructed using sequence placing mode;
Step 4:Leveling, is constructed using being flattened from periphery to center centralized system, and concrete surface flatness is met construction will
Ask;
Step 5:Wearing layer, the spreading of three progress high-abrasive materials of part are laid, and is carried out levelling;
Step 6:Maintenance:Sealing compound is sprayed, cracking is prevented;
Step 7:The slot cementation of fissures is constructed.
2. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:Described in step one at basic unit
The detailed process of reason includes:Base cleaning is clean;Bottom element soil is compacted;Lay broken sandstone and and conserved.
3. a kind of concrete abrasion-resistant terrace construction technique according to claim 2, it is characterised in that:The plain soil compaction system
Number is 0.95, and flatness scope is 0-3mm.
4. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:Step 3 specifically include with
Lower process:The double-deck polypropylene isolated film of laying;The preparation of concrete;Poured using sequence placing method;Progress, which is vibrated, looks for
It is flat.
5. a kind of concrete abrasion-resistant terrace construction technique according to claim 4, it is characterised in that:The preparation of the concrete
Method includes:Steel fibre, sand and rubble are stirred;Cement, flyash, zeolite powder, silicon ash are once added in stirring thing
Water and auxiliary agent are stirred.
6. a kind of concrete abrasion-resistant terrace construction technique according to claim 4, it is characterised in that:The slump of the concrete
Degree is less than 5cm.
7. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:Step 5 is specifically included:
When concrete initial set is to 50%-60%, one layer of quartz sand particle is dispensed;Floating warehouse is carried out, it is 0-3mm to make its flatness;Enter
Second of quartz sand particle of row is dispensed, and floating warehouse, flatness reaches 0-3mm;Third time quartz sand particle spreading is carried out, it is floating
Warehouse, flatness reaches 0-2mm.
8. a kind of concrete abrasion-resistant terrace construction technique according to claim 7, it is characterised in that:Three spreadings quartz
The ratio between consumption of sand particle is 4:1:1.
9. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:Step 7 is specifically included:
After concreting 30h-60h, lancing operation is carried out, seam depth and concrete thickness ratio is between 1/3-3/5.
10. a kind of concrete abrasion-resistant terrace construction technique according to claim 1, it is characterised in that:The slit width is 3-
5mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710466662.1A CN107152147A (en) | 2017-06-20 | 2017-06-20 | A kind of concrete abrasion-resistant terrace construction technique |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710466662.1A CN107152147A (en) | 2017-06-20 | 2017-06-20 | A kind of concrete abrasion-resistant terrace construction technique |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107152147A true CN107152147A (en) | 2017-09-12 |
Family
ID=59796389
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710466662.1A Pending CN107152147A (en) | 2017-06-20 | 2017-06-20 | A kind of concrete abrasion-resistant terrace construction technique |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107152147A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110835997A (en) * | 2019-11-29 | 2020-02-25 | 上海宝冶集团有限公司 | One-step construction molding construction process for wear-resistant terrace and structural plate |
CN111620662A (en) * | 2020-06-16 | 2020-09-04 | 湘潭大学 | Concrete doped with modified zeolite |
CN111962349A (en) * | 2020-07-18 | 2020-11-20 | 北京住总第一开发建设有限公司 | Wear-resistant concrete ground construction process |
CN112282294A (en) * | 2020-10-23 | 2021-01-29 | 安徽四建控股集团有限公司 | Construction method of steel fiber wear-resistant terrace |
CN112942764A (en) * | 2021-01-29 | 2021-06-11 | 武汉固立达建筑科技有限公司 | Terrace integrated structure and construction method thereof |
CN114135077A (en) * | 2021-11-08 | 2022-03-04 | 中建四局第六建设有限公司 | Concrete super-building reset cutting floor construction method free of warehouse dividing strip structure |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS54127130A (en) * | 1978-03-25 | 1979-10-02 | Kanebo Ltd | Method of executing floor foundation material |
US20030091793A1 (en) * | 2001-11-09 | 2003-05-15 | Morton Steven E. | Wear-resistant reinforcing coating |
CN102691401A (en) * | 2012-06-15 | 2012-09-26 | 北京城建建设工程有限公司 | Construction method for large-area concrete weighbridge |
CN104108911A (en) * | 2013-04-17 | 2014-10-22 | 北京江达雷博建筑装饰品有限公司 | Production formula and construction technology of ultra-wear-resistant ground |
CN104314289A (en) * | 2014-11-07 | 2015-01-28 | 广西壮族自治区冶金建设公司 | Wear-resisting concrete terrace overall molding construction method |
CN106401144A (en) * | 2016-06-23 | 2017-02-15 | 青岛海川建设集团有限公司 | Construction technology for addition type wear resisting concrete ground |
CN105587102B (en) * | 2016-03-01 | 2018-08-17 | 黑龙江泽林科技有限公司 | A kind of wet construction method to the wet type high abrasion terrace that paves |
-
2017
- 2017-06-20 CN CN201710466662.1A patent/CN107152147A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS54127130A (en) * | 1978-03-25 | 1979-10-02 | Kanebo Ltd | Method of executing floor foundation material |
US20030091793A1 (en) * | 2001-11-09 | 2003-05-15 | Morton Steven E. | Wear-resistant reinforcing coating |
CN102691401A (en) * | 2012-06-15 | 2012-09-26 | 北京城建建设工程有限公司 | Construction method for large-area concrete weighbridge |
CN104108911A (en) * | 2013-04-17 | 2014-10-22 | 北京江达雷博建筑装饰品有限公司 | Production formula and construction technology of ultra-wear-resistant ground |
CN104314289A (en) * | 2014-11-07 | 2015-01-28 | 广西壮族自治区冶金建设公司 | Wear-resisting concrete terrace overall molding construction method |
CN105587102B (en) * | 2016-03-01 | 2018-08-17 | 黑龙江泽林科技有限公司 | A kind of wet construction method to the wet type high abrasion terrace that paves |
CN106401144A (en) * | 2016-06-23 | 2017-02-15 | 青岛海川建设集团有限公司 | Construction technology for addition type wear resisting concrete ground |
Non-Patent Citations (1)
Title |
---|
吕俊冕: "钢纤维混凝土配合比设计耐磨地坪施工技术的探讨", 《广东建材》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110835997A (en) * | 2019-11-29 | 2020-02-25 | 上海宝冶集团有限公司 | One-step construction molding construction process for wear-resistant terrace and structural plate |
CN111620662A (en) * | 2020-06-16 | 2020-09-04 | 湘潭大学 | Concrete doped with modified zeolite |
CN111962349A (en) * | 2020-07-18 | 2020-11-20 | 北京住总第一开发建设有限公司 | Wear-resistant concrete ground construction process |
CN112282294A (en) * | 2020-10-23 | 2021-01-29 | 安徽四建控股集团有限公司 | Construction method of steel fiber wear-resistant terrace |
CN112942764A (en) * | 2021-01-29 | 2021-06-11 | 武汉固立达建筑科技有限公司 | Terrace integrated structure and construction method thereof |
CN114135077A (en) * | 2021-11-08 | 2022-03-04 | 中建四局第六建设有限公司 | Concrete super-building reset cutting floor construction method free of warehouse dividing strip structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107152147A (en) | A kind of concrete abrasion-resistant terrace construction technique | |
CN102535296B (en) | Construction method of superheavy-load reinforcement-free large-area seamless epoxy self-leveling terrace | |
CN105587102B (en) | A kind of wet construction method to the wet type high abrasion terrace that paves | |
CN107143111A (en) | A kind of construction method of abrasion-proof terrace | |
CN106401144A (en) | Construction technology for addition type wear resisting concrete ground | |
CN105040554A (en) | Garden path structure and paving construction technology thereof | |
CN207228171U (en) | Concrete floor waterproofing node is worn under a kind of steel column | |
CN104929365B (en) | Refuse of refuse burning generating plant discharging platform combined type surface construction technology | |
CN109457728A (en) | A kind of steel reinforced concrete pipe gallery quickly builds construction method | |
JP4537938B2 (en) | Block pavement construction method | |
CN103790168A (en) | Application method of soil nailing wall in deep foundation pit supporting | |
JP2017133344A (en) | Construction method using inorganic material | |
JP5974346B1 (en) | Inorganic material construction method | |
CN104529322A (en) | Iron tailings roller compacted concrete for pavement | |
CN108947464B (en) | Ground surface layer based on phosphorus-magnesium material and construction process thereof | |
CN105155387A (en) | Garden road structure | |
CN111042310A (en) | Basement bottom plate structure and construction method thereof | |
CN104878672A (en) | Stone-planted cement concrete bridge deck paving structure and method | |
CN213115347U (en) | Dampproof ground | |
CN102535493B (en) | Method for constructing inverted type foundation beam | |
CN114876155A (en) | Construction process for polishing ground by using non-ignition fine stone concrete | |
CN108179672A (en) | A kind of sponge-type road structure and its method for paving | |
CN109440572B (en) | Construction method for laying temporary road in coal mine pit by prefabricated slab | |
CN106436517A (en) | Construction method of soft soil anti-collapse concrete road surface | |
CN111851939A (en) | Oil-seepage-preventing ground structure and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170912 |
|
RJ01 | Rejection of invention patent application after publication |