CN107130719A - Floor system - Google Patents

Floor system Download PDF

Info

Publication number
CN107130719A
CN107130719A CN201710542074.1A CN201710542074A CN107130719A CN 107130719 A CN107130719 A CN 107130719A CN 201710542074 A CN201710542074 A CN 201710542074A CN 107130719 A CN107130719 A CN 107130719A
Authority
CN
China
Prior art keywords
keel
floor
floor system
fonts
cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710542074.1A
Other languages
Chinese (zh)
Other versions
CN107130719B (en
Inventor
盛雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chen Tai (Guangde) intelligent assembly building Limited by Share Ltd
Original Assignee
Chen Tai (guangde) Intelligent Technology Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chen Tai (guangde) Intelligent Technology Construction Co Ltd filed Critical Chen Tai (guangde) Intelligent Technology Construction Co Ltd
Priority to CN201710542074.1A priority Critical patent/CN107130719B/en
Publication of CN107130719A publication Critical patent/CN107130719A/en
Application granted granted Critical
Publication of CN107130719B publication Critical patent/CN107130719B/en
Priority to AU2018102135A priority patent/AU2018102135A4/en
Priority to AU2018296444A priority patent/AU2018296444A1/en
Priority to PCT/CN2018/092841 priority patent/WO2019007229A1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/10Load-carrying floor structures formed substantially of prefabricated units with metal beams or girders, e.g. with steel lattice girders
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/88Insulating elements for both heat and sound

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Acoustics & Sound (AREA)
  • Floor Finish (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention discloses a kind of floor system, include multiple floor modules units, each unit is in the second keel of C fonts in the first keel and two cross sections of C fonts provided with two cross sections, first keel and the second keel join end to end successively, rectangular box is formed, the main force structure of floor modules unit is used as.Rectangular box overlying cement plate, multiple floor modules units are connected to form floor system side by side by the second keel.In the present invention, the first keel and bicarinate size can be changed according to Force Calculation demand, it can be needed according to design and actual conditions form various sizes of floor by assembly, realize the modularized design for being applied to the requirement of different floor sizes and factorial praluction.The present invention dispatch from the factory complete after be complete product, scene only need to carry out assembly, it is not necessary to processing and fabricating, solve the problems such as common floor system work on the spot amount is big, construction technical requirement is high, and do not produce building waste.

Description

Floor system
Technical field
The present invention relates to a kind of floor system.
Background technology
Build a building and be usually constructed with not only one layer, need to set floor between adjacent two layers, two floors are separated.
At present, floor is mainly based on lightweight steel construction and reinforced concrete structure, and lightweight steel construction floor is by lightgage steel joist Build between girder steel, at an upper portion thereof and at a lower portion thereof shrouding, central filler insulation material, such mode of construction needs site operation, More building waste is produced, keel are more, installation is complicated, workload is big, and stability is general, soundproof effect is general.
And the floor of concrete structure, although preferably, structural strength is larger, but own wt is heavier for stability, except to perpendicular Required to primary structure member outside height, in addition it is also necessary to which big machinery participates in building, and for the conditional region of pavement conditions and does not apply to, together When field erected technical requirements it is higher, common laborer can not operate, and this kind of floor is after installation is complete, it is non-disconnectable remove after weight It is multiple to utilize, the requirement of green building is not met, soundproof effect is also poorer than insulation material.
The content of the invention
The invention provides a kind of floor system, to solve at least one in above-mentioned technical problem.
According to an aspect of the invention, there is provided a kind of floor system, including multiple floor modules units, each unit It is in the second keel of C fonts, the first keel and the second dragon in the first keel of C fonts and two cross sections provided with two cross sections Bone joins end to end successively, the first keel and the rectangular square frame of the second keel shape, covered with cement plate in rectangular box, multiple floors Modular unit is connected side by side by the second keel.
In the present invention, the first keel and the bicarinate size, Ke Yigen can be changed according to Force Calculation demand Need to form different size of floor by assembled according to design, realize the modularized design that is applied to the requirement of different floor sizes and Factorial praluction.
In addition, floor system installation process need not utilize heavy mechanical equipment, it is only necessary to which 2-3 people can complete erector Make, asking for heavy mechanical equipment can not be used by solving outdoor (such as Scenic Spot Area, mountain area, forest land etc.) special topography condition Topic.
The present invention dispatch from the factory complete after be complete product, scene only need to carry out assembly, it is not necessary to processing and fabricating, The problem of work on the spot amount is big is solved, and a large amount of building wastes will not be produced.
In some embodiments, in addition to multiple bending parts, one end of bending part is located on one of them second keel, The other end is located on another second keel, and multiple bending parts are in same absolute altitude.Bending part is fixed on by welding manner On second keel.
In some embodiments, in addition to bar-mat reinforcement, bar-mat reinforcement is welded in bending part bottom surface, and bar-mat reinforcement is by rectangular box Horizontal subdivision is into the first cavity and the second cavity.Sound-insulating material etc. is set in the first cavity, and the second cavity is then erector Sequence provides the facility of construction space, such as convenient connection and electric wire arrangement, has enough operations empty during the installation for carrying out bolt Between,.
In some embodiments, sound-insulating material is provided with the first cavity, cement plate is located at sound-insulating material one Side.Insulation material can play a part of insulation and sound insulation.
In some embodiments, in addition at least two girder steels, girder steel is overlapped on exterior building vertical applied force component, Girder steel side sets angle steel by stiffener, and one end of floor is located on the angle steel of one of girder steel, and the other end is located at another On the angle steel of individual girder steel.Thus, angle steel plays a part of load of floor being delivered on beam.
In some embodiments, two adjacent floor modules units are fixedly connected by crab-bolt.Thus, bolt is passed through Two adjacent floor modules units can be fixed together.
In some embodiments, bending part is in C fonts.Thus, the bending part of C fonts can play fixed reinforced mesh Effect.
In some embodiments, the width of floor is 0.6m or 1.2m.Thus, the width of floor using 0.6m or 1.2m conveniently can be processed and installed.
Brief description of the drawings
Fig. 1 is the structural representation (front view) of (a kind of floor system of embodiment) of the invention;
Fig. 2 is the structural representation (front view) of single floor modules unit in floor system shown in Fig. 1;
Fig. 3 is cross-sectional view of the floor along A-A directions shown in Fig. 2;
Fig. 4 is cross-sectional view of the floor system along B-B directions shown in Fig. 1;
Fig. 5 is the partial enlargement structural representation of floor system shown in Fig. 4;
Fig. 6 is the mounting structure schematic diagram of floor shown in Fig. 3.
Embodiment
The invention will now be described in further detail with reference to the accompanying drawings.
Fig. 1~Fig. 6 schematically illustrates the structure of the floor system of one embodiment of the present invention.
As shown in Fig. 1~Fig. 6, according to an aspect of the invention, there is provided a kind of floor system, the floor system includes (size and number of floor modules unit can be adjusted multiple floor modules units according to the size of whole floor, make it Reach design requirement).
In order to which the concrete structure of the present invention is described in detail, Fig. 1 is illustrated below, Fig. 1 is a kind of floor of the present invention The front view of system, when it is implemented, needing multiple floor modules units being installed together.It is many in Fig. 1 after installing The individual equal horizontal positioned of floor modules unit, the i.e. floor front of Fig. 1 is in horizontality.
With reference to Fig. 2 and Fig. 3, floor modules unit is actually first successively by two the first keel 1 and two the second keel 2 What tail was connected to form, the keel of Y-direction are the first keel 1 (each one of left and right) in Fig. 2, X to keel be then the second keel 2 (up and down each one), Fig. 3 is due to being that left and right two is represented in the first keel 1, Fig. 2 in profiles of the Fig. 2 along A-A directions, figure The second keel 2 do not show in figure 3.
With reference to Fig. 1 and Fig. 4, Fig. 4 is profiles of the Fig. 1 along B-B directions, and mainly two floor modules units of expression pass through the It is the second keel 2 (each one of left and right) that two keel 2 are connected to form Y-direction in floor system, Fig. 4 side by side, and the first keel 1 are not in figure Display.
With reference to Fig. 1,2,3 and 4, the present invention is further detailed explanation.
The length of the first keel 1 can be set as needed in the present invention, preferably 0.6m, the length of the second keel 2 Determined by the length of house floor Impact direction.
The cross section of the first keel 1 in the present invention is in C fonts (C fonts are as shown in Figure 3), the cross section of the second keel 2 In C fonts (C fonts are as shown in Figure 4), the first keel 1 and the second keel 2 are attached using end to end mode successively, from And floor modules unit is formed, end to end mode is as follows:In Fig. 1, the top and bottom of first keel 1 on the left side respectively with The left end of the second keel 2 above is connected with the left end of the second following keel 2, the top and bottom of first keel 1 on the right The right-hand member with the right-hand members of the second keel 2 above and the second following keel 2 is connected respectively, and connected mode can be using being integrally formed Or welding etc. mode,
In Fig. 1, multiple floor modules units can form floor system, two adjacent floor modules units by combination Between connected side by side by the second keel 2, i.e. the second keel 2 and following building slab in Fig. 1 above on the downside of floor modules units The second keel 2 on the upside of module unit are attached.
As shown in Figures 2 and 3, floor modules unit needs to be horizontally mounted, i.e., by the floor modules unit shown in Fig. 2 along X-axis It is rotated by 90 °, makes on Fig. 2 floor modules finite element rotation to the horizontal level shown in Fig. 3.As shown in Figures 2 and 3, the He of the first keel 1 Second keel 2 formation rectangular box, covered with cement plate on the upside of square frame.Second floor floor face load action is on cement plate 3, water The preferred 15mm of thickness of mud plate 3.
Bending part 4 is additionally provided with the rectangular box shown in Fig. 3, the front and back end of bending part 4 is respectively welded in Fig. 2 floors Above and below modular unit on two the second keel 2.
Meanwhile, there are multiple size identical bending parts 4 in Fig. 3, the top surface absolute altitude of multiple bending parts 4 is identical, can be in Fig. 3 The lower section of shown bending part 4 is installed by bar-mat reinforcement 5.
And the square frame horizontal subdivision that bar-mat reinforcement 5 can be formed the first keel 1 and the second keel 2 is opened, as the first cavity With the second cavity.Sound-insulating material 8 is set in the first cavity, i.e., sound-insulating material is filled into full whole first cavity, Second cavity is easy to the assembly of follow-up multiple floor modules units and the connection of electric wire.Sound-insulating material plays sound insulation and insulation Heat-insulated effect, Stall space and second floor are spatially separating and come, and form two relatively independent living space.
As shown in figure 3, in order to which floor is fixed in building, in addition it is also necessary to set at least two girder steels 6, (one, one side, two Spacing between individual girder steel 6 is identical with floor Impact direction length), when such as span is larger, then it can be calculated and tied according to floor load-bearing Really, multiple girder steels are set.Girder steel 6 is the part being fixed on building vertical applied force component, and the space between girder steel 6 and floor can With filling-foam insulation material, play insulation, go along with sb. to guard him and fireproof effect.
In order to which floor is fixed on girder steel 6, by plate weld angle steel 7 of putting more energy on girder steel 6, angle steel 7 is in L-shaped, building Template die module unit is installed according to shown in Fig. 3.Load of floor is delivered on beam by angle steel 7 as by force transmitting member.
The floor system of the present invention can be installed as follows:As shown in fig. 6,
1. the floor modules shipped that prefabrication is completed extremely needs architecture storey to be mounted;
2. the floor modules unit horizontal shown in Fig. 2 is placed, the left end of the floor modules system shown in Fig. 3 is placed on On the angle steel 7 of left side girder steel 6, right-hand member is placed on the angle steel 7 of the right girder steel 6;
3. according to the method described above, remaining floor modules unit is all placed;
4. after floor modules unit is placed, according to shown in Fig. 4, by the second adjacent dragon of two floor modules units Bone 2 is attached and (is attached using modes such as bolts in the range of the second cavity);
5. whole floor modules units are fixed on angle steel 7 using modes such as Self Drilling Screws, the peace of floor system is completed Dress;
6. as shown in figure 3, after the installation is complete, connecting the electric wire in house, then carry out follow-up installation of ceiling.
Above-mentioned various pieces (such as between two adjacent wallboards) can mode by screw or bolt pacified Dress, cement plate 3 can also be arranged on the second keel 2 and on bending part 4 (as shown in Figure 5) by modes such as screws, and is passed through The mode that the fissure of displacement is installed is further by the entirety of each floor modules unit one common stress of formation, and floor modules system can be with By being fixed on the first keel 1 with modes such as screw or bolts on angle steel 7.
In the present invention, the main force structure of floor modules unit is transversal in the first keel 1 of C fonts and two for two Face is in the second keel 2 of C fonts, can change the chi of the first keel 1 and the second keel 2 according to design requirement and actual conditions It is very little, the modular designs and factorial praluction of floor modules unit are realized, while different chis can be realized by the splicing of unit The construction of very little floor, and it is easy for installation, Path of Force Transfer is reasonable.
In addition, floor system installation process need not utilize heavy mechanical equipment, it is only necessary to which 2-3 people can complete erector Make, asking for heavy mechanical equipment can not be used by solving outdoor (such as Scenic Spot Area, mountain area, forest land etc.) special topography condition Topic.
The present invention dispatch from the factory complete after be complete product, scene only need to carry out assembly, it is not necessary to processing and fabricating, Electric welding field is avoided, the problem of work on the spot amount is big is solved, and a large amount of building wastes will not be produced, to the shadow of outdoor environment Ring very little.
Above-described is only some embodiments of the present invention.For the person of ordinary skill of the art, not On the premise of departing from the invention design, various modifications and improvements can be made, these belong to the protection model of the present invention Enclose.

Claims (8)

1. floor system, it is characterised in that including multiple floor modules units, the floor modules unit is provided with two cross sections It is in the second keel (2) of C fonts, the first keel (1) and the second keel (2) in the first keel (1) and two cross sections of C fonts Join end to end successively, first keel (1) and the second keel (2) are formed in rectangular box, the rectangular box covered with water Mud plate (3), multiple floor modules units are connected side by side by second keel (2).
2. floor system according to claim 1, it is characterised in that also including multiple bending parts (4), the bending part (4) one end is located on one of them second keel (2), and the other end is located on another second keel (2), multiple bending member tops Face is in same absolute altitude.
3. floor system according to claim 2, it is characterised in that also including bar-mat reinforcement (5), the bar-mat reinforcement (5) sets The square frame is horizontally divided into the first cavity and the second cavity by the downside in the bending part (4), the bar-mat reinforcement (5).
4. floor system according to claim 3, it is characterised in that sound-insulating material is provided with first cavity (8), the cement plate (3) is located at sound-insulating material (8) top.
5. floor system according to claim 4, it is characterised in that also including at least two girder steels (6), the girder steel (6) it is overlapped on building vertical applied force component, the girder steel (6) sets angle steel (7), the one of the floor by stiffener sideways End is located on the angle steel of one of girder steel (6) (7), and the other end is located on the angle steel (7) of another girder steel (6).
6. floor system according to claim 5, it is characterised in that two adjacent floor modules units are solid by bolt Fixed connection.
7. floor system according to claim 6, it is characterised in that the bending part (4) is in C fonts.
8. according to floor system according to any one of claims 1 to 7, it is characterised in that the width of the floor is 0.6m Or 1.2m.
CN201710542074.1A 2017-07-05 2017-07-05 Floor system Active CN107130719B (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
CN201710542074.1A CN107130719B (en) 2017-07-05 2017-07-05 Floor system
AU2018102135A AU2018102135A4 (en) 2017-07-05 2018-06-26 Floor slab system
AU2018296444A AU2018296444A1 (en) 2017-07-05 2018-06-26 Floor slab system
PCT/CN2018/092841 WO2019007229A1 (en) 2017-07-05 2018-06-26 Floor slab system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710542074.1A CN107130719B (en) 2017-07-05 2017-07-05 Floor system

Publications (2)

Publication Number Publication Date
CN107130719A true CN107130719A (en) 2017-09-05
CN107130719B CN107130719B (en) 2018-05-29

Family

ID=59737331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710542074.1A Active CN107130719B (en) 2017-07-05 2017-07-05 Floor system

Country Status (3)

Country Link
CN (1) CN107130719B (en)
AU (2) AU2018102135A4 (en)
WO (1) WO2019007229A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019007229A1 (en) * 2017-07-05 2019-01-10 辰泰(广德)智能科技建筑有限公司 Floor slab system

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7384165B2 (en) * 2018-08-27 2023-11-21 日本ゼオン株式会社 Styrenic block copolymer latex

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2235224B (en) * 1989-08-15 1993-10-27 Presco Int A floor construction for portable buildings
CN103498523A (en) * 2013-09-25 2014-01-08 张跃 Floor system
CN203701387U (en) * 2014-02-06 2014-07-09 李健鹏 Floor slab structure with embedded heat preservation cavities
CN203755511U (en) * 2013-12-30 2014-08-06 中国十七冶集团有限公司 Floor slab with two-layer steel structure and with embedded steel channel beam
CN204826348U (en) * 2015-07-17 2015-12-02 武斌华 Compound floor board of three -dimensional light steel frame structure
CN106760100A (en) * 2016-12-26 2017-05-31 中国电子工程设计院 A kind of floor system framework and floor system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202850288U (en) * 2012-09-28 2013-04-03 山东鲁帆集团有限公司 Modularization floor slab used for building
CN205035948U (en) * 2015-10-15 2016-02-17 重庆鼎豪建设工程有限公司 Concatenation formula steel construction board
CN206189685U (en) * 2016-09-28 2017-05-24 丽水山居文化发展有限公司 Integrated floor of modularization and house
CN206888302U (en) * 2017-07-05 2018-01-16 辰泰(广德)智能科技建筑有限公司 Floor system
CN107130719B (en) * 2017-07-05 2018-05-29 辰泰(广德)智能科技建筑有限公司 Floor system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2235224B (en) * 1989-08-15 1993-10-27 Presco Int A floor construction for portable buildings
CN103498523A (en) * 2013-09-25 2014-01-08 张跃 Floor system
CN203755511U (en) * 2013-12-30 2014-08-06 中国十七冶集团有限公司 Floor slab with two-layer steel structure and with embedded steel channel beam
CN203701387U (en) * 2014-02-06 2014-07-09 李健鹏 Floor slab structure with embedded heat preservation cavities
CN204826348U (en) * 2015-07-17 2015-12-02 武斌华 Compound floor board of three -dimensional light steel frame structure
CN106760100A (en) * 2016-12-26 2017-05-31 中国电子工程设计院 A kind of floor system framework and floor system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019007229A1 (en) * 2017-07-05 2019-01-10 辰泰(广德)智能科技建筑有限公司 Floor slab system

Also Published As

Publication number Publication date
WO2019007229A1 (en) 2019-01-10
AU2018102135A4 (en) 2019-10-10
AU2018296444A1 (en) 2019-06-20
CN107130719B (en) 2018-05-29

Similar Documents

Publication Publication Date Title
CN104712089B (en) Open the compound shear attachment structure of net
JP5643205B2 (en) Unit building system
WO2019178905A1 (en) Assembling structure for assembled steel structure building
CN100402765C (en) Box shaped house model of construction and fabricating method
WO2016197919A1 (en) Prefabricated light steel concrete plate column structure and construction method therefor
KR20180115737A (en) Construction method of multi-story building using steel wall truss for laminated structure
CN207063170U (en) The house that a kind of shear wall slab by steel square tube and steel plate splicing is assembled
CN107130684A (en) A kind of fabricated structure and its construction method
CN105951991B (en) A kind of assembling type steel structure frame system
CN108005410A (en) A kind of assembled Residential System of Steel-concrete Composite Structure and its construction method
CN204370562U (en) A kind of frame structure, frame structure body
CN104499567A (en) Frame structure, frame structure assembly and prefabricating and constructing methods of frame structure assembly
CN107386451A (en) Assembled Box Modular Building
CN202125104U (en) Residential building system formed by cast-in-place beam columns and prefabricated sandwich concrete wall slabs
CN107130719B (en) Floor system
CN106894504A (en) A kind of light-duty assembling type steel structure house and its method of construction
CN105133767A (en) Manufacturing method for regular hexagonal honeycomb latticed steel hollow floor frame box type structure
CN111727292B (en) Structural panel
CN104631629A (en) Assembling type frame structure
CN110284594B (en) Full-bolt connection assembly type floor composite beam steel pipe column frame joint and forming method thereof
CN108360682A (en) A kind of construction process of three-dimensional building module and three-dimensional building module
CN207110052U (en) The stair concatenation module of Box Modular Building
CN206888302U (en) Floor system
CN104594671A (en) Fully-assembled main control building for 500kV transformer substation in high-altitude and high-intensity seismic region
CN205776898U (en) Overall assembled reinforced concrete shear wall structure system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 242000 39 Peng Peng Road, Guangde Economic Development Zone, Anhui

Patentee after: Chen Tai (Guangde) Intelligent Technology Construction Co. Ltd.

Address before: 242000 Guangde Economic Development Zone, Xuancheng, Anhui

Patentee before: Chen Tai (Guangde) Intelligent Technology Construction Co. Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 242200 39 Peng Peng Road, Guangde Economic Development Zone, Anhui

Patentee after: Chen Tai (Guangde) intelligent assembly building Limited by Share Ltd

Address before: 242000 39 Peng Peng Road, Guangde Economic Development Zone, Anhui

Patentee before: Chen Tai (Guangde) Intelligent Technology Construction Co. Ltd.