CN107130492A - A kind of asphalt roads construction technology of antiskid - Google Patents

A kind of asphalt roads construction technology of antiskid Download PDF

Info

Publication number
CN107130492A
CN107130492A CN201710303364.0A CN201710303364A CN107130492A CN 107130492 A CN107130492 A CN 107130492A CN 201710303364 A CN201710303364 A CN 201710303364A CN 107130492 A CN107130492 A CN 107130492A
Authority
CN
China
Prior art keywords
construction
asphalt roads
joint
section
antiskid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710303364.0A
Other languages
Chinese (zh)
Inventor
安秀山
李建明
李亮
朱龙
娄雅冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority to CN201710303364.0A priority Critical patent/CN107130492A/en
Publication of CN107130492A publication Critical patent/CN107130492A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/18Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders
    • E01C7/187Repairing bituminous covers, e.g. regeneration of the covering material in situ, application of a new bituminous topping
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • E01C11/04Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
    • E01C11/06Methods of making joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/35Toppings or surface dressings; Methods of mixing, impregnating, or spreading them
    • E01C7/353Toppings or surface dressings; Methods of mixing, impregnating, or spreading them with exclusively bituminous binders; Aggregate, fillers or other additives for application on or in the surface of toppings with exclusively bituminous binders, e.g. for roughening or clearing

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • Road Paving Machines (AREA)

Abstract

The present invention is a kind of asphalt roads construction technology of antiskid, using first passing through on-the-spot investigation headed by step, determine construction section, closure construction the intensive traffic section, then construction section is laid, construction section rolled by using vibrated roller, transverse joint joint treatment and longitudinal joint joint treatment are carried out after the completion of rolling, finally asphalt roads construction quality is carried out an acceptance inspection, can just recover road traffic operation after acceptance(check).The present invention provides a kind of asphalt roads construction technology of antiskid, the construction technology is simple, stability is good, by using synchronous macadam seal paver and use level form of construction work so that asphalt roads the different degrees of service life for collapsing, substantially prolongs asphalt roads will not occur because by rolling repeatedly, particle size is used for 6mm single rubble, the voidage of laying is controlled between 26%~30%, improves the skid resistance of asphalt roads, traffic safety is improved to a certain extent.

Description

A kind of asphalt roads construction technology of antiskid
Technical field
The present invention relates to the asphalt roads construction technology of a kind of technical field of road construction, more particularly to a kind of antiskid.
Background technology
Asphalt roads has obtained extensive because its is smooth, wear-resisting, the advantages of be adapted to driving in China's road construction road surface Using with the fast development of society, the increasingly increase of the magnitude of traffic flow, the pitch road that traditional asphalt roads construction technology is laid Road occurs the different degrees of service life for collapsing, substantially reducing asphalt roads because being rolled repeatedly, simultaneously because drip Blue or green road skid resistance is not enough easily to trigger traffic accident, drastically influence traffic safety.
The content of the invention
Present invention seek to address that the deficiencies in the prior art, and a kind of asphalt roads construction technology of antiskid is provided.
The present invention to achieve the above object, using following technical scheme:A kind of asphalt roads construction technology of antiskid, it is special Levy and be, the method for use is comprised the following steps that:
(1) by on-the-spot investigation, construction section, closure construction the intensive traffic section are determined, and cleans road surface, makes basic unit's mineral aggregate It is exposed, keeps the drying of sub-surface, the section repairing out-of-flatness is smooth;
(2) it is using level form of construction work that pitch and rubble is same according to traffic route by using synchronous macadam seal paver Step is sprinkled upon on road surface, and the particle size of rubble is 6mm, and the voidage of laying is controlled between 26%~30%, to construction section Laid, the paving width of every synchronous macadam seal paver is 8~9.5m, by longitudinal joint control in the range of 8~16cm, transverse joint Control is in the range of 0.9~1.2m;
(3) construction section in step (2) is rolled by using vibrated roller, by the temperature of compound when rolling Degree control is more than 90 DEG C, and rolling layer is 5~6, and rolling speed is 6.5~7km/h;
(4) transverse joint joint treatment is carried out after the completion of rolling, transverse joint is measured seam when carrying out seam and paved first Thickness, and the thickness of pine paving is calculated according to coefficient of loose laying, while in seam crossing brushing sticking layer oil, then being carried out using paver Seam crossing fills and leads up processing, fills and leads up after processing and rolls processing in repeat step (3), after pending end, using the inspection of 3m rulers Flatness is looked into, longitudinal joint joint treatment is carried out after flatness is qualified;
(5) longitudinal joint seam uses the cold joint technology that half range is constructed, and adds untreated good side after baffle plate with cutting machine Clipped corner, pave another half range when tape edge edge is cleaned up, overlap in laying, and processing is rolled in repeat step (3), Carry out grinding compacting;
(6) finally asphalt roads construction quality is carried out an acceptance inspection, can just recovers road traffic operation after acceptance(check).
Particularly, asphalt content is 1.4~1.5kg/m in described step (2)2
Particularly, the vibrated roller in described step (3) replaces with drum roller.
The beneficial effects of the invention are as follows:The present invention provides a kind of asphalt roads construction technology of antiskid, construction technology letter Single, stability is good, by using synchronous macadam seal paver and using level form of construction work so that asphalt roads will not be because by anti- Multiple rolls and the different degrees of service life for collapsing, substantially prolongs asphalt roads occurs, uses particle size for 6mm's Single rubble, the voidage of laying is controlled between 26%~30%, is improved the skid resistance of asphalt roads, is carried to a certain extent High traffic safety.
Embodiment
With reference to embodiment, the invention will be further described:
Embodiment 1
A kind of asphalt roads construction technology of antiskid, the method for use is comprised the following steps that:
(1) by on-the-spot investigation, construction section, closure construction the intensive traffic section are determined, and cleans road surface, makes basic unit's mineral aggregate It is exposed, keeps the drying of sub-surface, the section repairing out-of-flatness is smooth;
(2) it is using level form of construction work that pitch and rubble is same according to traffic route by using synchronous macadam seal paver Step is sprinkled upon on road surface, and the particle size of rubble is 6mm, and the voidage of laying is 30%, and asphalt content is 1.4kg/m2, to construction Section is laid, and the paving width of every synchronous macadam seal paver is 8m, and longitudinal joint is 8cm, and transverse joint is 0.9m;
(3) construction section in step (2) is rolled by using vibrated roller, the temperature of compound when rolling For 95 DEG C, rolling layer is 5, and rolling speed is 6.5km/h;
(4) transverse joint joint treatment is carried out after the completion of rolling, transverse joint is measured seam when carrying out seam and paved first Thickness, and the thickness of pine paving is calculated according to coefficient of loose laying, while in seam crossing brushing sticking layer oil, then being carried out using paver Seam crossing fills and leads up processing, fills and leads up after processing and rolls processing in repeat step (3), after pending end, using the inspection of 3m rulers Flatness is looked into, longitudinal joint joint treatment is carried out after flatness is qualified;
(5) longitudinal joint seam uses the cold joint technology that half range is constructed, and adds untreated good side after baffle plate with cutting machine Clipped corner, pave another half range when tape edge edge is cleaned up, overlap in laying, and processing is rolled in repeat step (3), Carry out grinding compacting;
(6) finally asphalt roads construction quality is carried out an acceptance inspection, can just recovers road traffic operation after acceptance(check).
Embodiment 2
A kind of asphalt roads construction technology of antiskid, the method for use is comprised the following steps that:
(1) by on-the-spot investigation, construction section, closure construction the intensive traffic section are determined, and cleans road surface, makes basic unit's mineral aggregate It is exposed, keeps the drying of sub-surface, the section repairing out-of-flatness is smooth;
(2) it is using level form of construction work that pitch and rubble is same according to traffic route by using synchronous macadam seal paver Step is sprinkled upon on road surface, and the particle size of rubble is 6mm, and the voidage of laying is 26%, and asphalt content is 1.5kg/m2, to construction Section is laid, and the paving width of every synchronous macadam seal paver is 9.5m, and longitudinal joint is 16cm, and transverse joint is 1.2m;
(3) construction section in step (2) is rolled by using drum roller, the temperature of compound when rolling Spend for 100 DEG C, rolling layer is 6, rolling speed is 7km/h;
(4) transverse joint joint treatment is carried out after the completion of rolling, transverse joint is measured seam when carrying out seam and paved first Thickness, and the thickness of pine paving is calculated according to coefficient of loose laying, while in seam crossing brushing sticking layer oil, then being carried out using paver Seam crossing fills and leads up processing, fills and leads up after processing and rolls processing in repeat step (3), after pending end, using the inspection of 3m rulers Flatness is looked into, longitudinal joint joint treatment is carried out after flatness is qualified;
(5) longitudinal joint seam uses the cold joint technology that half range is constructed, and adds untreated good side after baffle plate with cutting machine Clipped corner, pave another half range when tape edge edge is cleaned up, overlap in laying, and processing is rolled in repeat step (3), Carry out grinding compacting;
(6) finally asphalt roads construction quality is carried out an acceptance inspection, can just recovers road traffic operation after acceptance(check).
The present invention is exemplarily described above, it is clear that the present invention, which is implemented, to be not subject to the restrictions described above, As long as employing the various improvement of inventive concept and technical scheme of the present invention progress, or not improved directly apply to other fields Close, within protection scope of the present invention.

Claims (3)

1. the asphalt roads construction technology of a kind of antiskid, it is characterised in that the method for use is comprised the following steps that:
(1) by on-the-spot investigation, construction section, closure construction the intensive traffic section are determined, and cleans road surface, makes basic unit's mineral aggregate exposure Out, the drying of sub-surface is kept, the section repairing out-of-flatness is smooth;
(2) by using synchronous macadam seal paver, pitch and rubble are synchronously spilt using level form of construction work according to traffic route On road surface, the particle size of rubble is 6mm, and the voidage of laying controls between 26%~30%, construction section is carried out Laying, the paving width of every synchronous macadam seal paver is 8~9.5m, by longitudinal joint control in the range of 8~16cm, transverse joint control In the range of 0.9~1.2m;
(3) construction section in step (2) is rolled by using vibrated roller, by the temperature control of compound when rolling System is more than 90 DEG C, and rolling layer is 5~6, and rolling speed is 6.5~7km/h;
(4) transverse joint joint treatment is carried out after the completion of rolling, transverse joint measures the thickness that seam has paved first when carrying out seam Degree, and the thickness that pine spreads is calculated according to coefficient of loose laying, while in seam crossing brushing sticking layer oil, then carrying out seam using paver Processing is filled and led up at place, is filled and led up after processing and is rolled processing in repeat step (3), flat using the inspection of 3m rulers after pending end Whole degree, longitudinal joint joint treatment is carried out after flatness is qualified;
(5) longitudinal joint seam uses the cold joint technology that half range is constructed, and adds after baffle plate and to be cut untreated good corner with cutting machine Remove, pave another half range when tape edge edge is cleaned up, overlap in laying, and processing is rolled in repeat step (3), progress Grinding compacting;
(6) finally asphalt roads construction quality is carried out an acceptance inspection, can just recovers road traffic operation after acceptance(check).
2. a kind of asphalt roads construction technology of antiskid according to claim 1, it is characterised in that described step (2) Middle asphalt content is 1.4~1.5kg/m2
3. a kind of asphalt roads construction technology of antiskid according to claim 1, it is characterised in that described step (3) In vibrated roller replace with drum roller.
CN201710303364.0A 2017-05-03 2017-05-03 A kind of asphalt roads construction technology of antiskid Withdrawn CN107130492A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710303364.0A CN107130492A (en) 2017-05-03 2017-05-03 A kind of asphalt roads construction technology of antiskid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710303364.0A CN107130492A (en) 2017-05-03 2017-05-03 A kind of asphalt roads construction technology of antiskid

Publications (1)

Publication Number Publication Date
CN107130492A true CN107130492A (en) 2017-09-05

Family

ID=59715490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710303364.0A Withdrawn CN107130492A (en) 2017-05-03 2017-05-03 A kind of asphalt roads construction technology of antiskid

Country Status (1)

Country Link
CN (1) CN107130492A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867231A (en) * 2018-07-13 2018-11-23 阜阳师范学院 A kind of antiskid type asphalt pavement construction technique
CN109868699A (en) * 2019-03-29 2019-06-11 重庆建工住宅建设有限公司 Road noise reduction antiskid process of surface treatment
CN112211198A (en) * 2020-11-10 2021-01-12 中建四局第五建筑工程有限公司 Municipal road engineering pavement construction technology

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148856A (en) * 2007-11-12 2008-03-26 徐培华 Asphalt macadam stress absorption layer and construction method thereof
CN102815891A (en) * 2012-08-24 2012-12-12 河南省高远公路养护技术有限公司 Fine anti-slide asphalt pavement protection layer and its paving method
CN102995514A (en) * 2012-12-05 2013-03-27 黑龙江省龙建路桥第四工程有限公司 Construction method of high-performance asphalt mixture on asphalt pavement in cold region
CN103993534A (en) * 2014-06-06 2014-08-20 江苏道润智能交通技术有限公司 Road construction method
CN204282149U (en) * 2014-11-28 2015-04-22 河南省路嘉路桥股份有限公司 The meticulous antiskid protective layer structure of a kind of flexible pavement
CN104762858A (en) * 2015-03-16 2015-07-08 夏旻淑 Asphalt concrete construction method for soft soil matrix pavement

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101148856A (en) * 2007-11-12 2008-03-26 徐培华 Asphalt macadam stress absorption layer and construction method thereof
CN102815891A (en) * 2012-08-24 2012-12-12 河南省高远公路养护技术有限公司 Fine anti-slide asphalt pavement protection layer and its paving method
CN102995514A (en) * 2012-12-05 2013-03-27 黑龙江省龙建路桥第四工程有限公司 Construction method of high-performance asphalt mixture on asphalt pavement in cold region
CN103993534A (en) * 2014-06-06 2014-08-20 江苏道润智能交通技术有限公司 Road construction method
CN204282149U (en) * 2014-11-28 2015-04-22 河南省路嘉路桥股份有限公司 The meticulous antiskid protective layer structure of a kind of flexible pavement
CN104762858A (en) * 2015-03-16 2015-07-08 夏旻淑 Asphalt concrete construction method for soft soil matrix pavement

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张争奇: "《高速公路沥青路面维修养护技术》", 30 September 2010, 人民交通出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867231A (en) * 2018-07-13 2018-11-23 阜阳师范学院 A kind of antiskid type asphalt pavement construction technique
CN109868699A (en) * 2019-03-29 2019-06-11 重庆建工住宅建设有限公司 Road noise reduction antiskid process of surface treatment
CN112211198A (en) * 2020-11-10 2021-01-12 中建四局第五建筑工程有限公司 Municipal road engineering pavement construction technology

Similar Documents

Publication Publication Date Title
CN102815891B (en) Fine anti-slide asphalt pavement protection layer and its paving method
CN103922645B (en) A kind of asphalt and preparation method thereof
CN107130492A (en) A kind of asphalt roads construction technology of antiskid
CN105442423B (en) Milling, spraying, stirring and material-collecting integrated device for heating milling machine
Rasmussen et al. How to reduce tire-pavement noise: better practices for constructing and texturing concrete pavement surfaces.
CN102704366A (en) High-performance rubberized asphalt composite seal coat and construction method thereof
CN108978389A (en) A kind of construction method of bituminous pavement
CN106758710A (en) Bituminous concrete Novel layered rolling method
CN105908589A (en) Fiber-broken stone synchronous-sealing pavement maintenance method
Rashid et al. Study of defects in flexible pavement and its maintenance
CN104612014A (en) Asphalt pavement crack-preventing base fabric construction method
CN102352596A (en) Thermal regeneration repairing method for deep tracks on asphalt pavement
CN107386111B (en) Composite high-modulus asphalt concrete bridge deck structure and setting method
CN107151961A (en) A kind of construction method of town road
CN105735079A (en) Treatment method for bituminous pavement transverse reflection cracks
CN109797622A (en) A kind of local hot reproduction construction method
CN202509361U (en) High-performance rubber asphalt composite seal coat
CN109322224B (en) Construction method for roadbed replacement
CN211171471U (en) High-performance steel slag pavement
CN113417182A (en) Asphalt pavement paving method capable of reducing air bubbles for highway engineering
Kim et al. Extending the use of chip seals to high volume roads by using polymer-modified emulsions and optimized construction procedures
CN113931032A (en) Construction method for upper surface layer of asphalt pavement in saline-containing high-humidity-resistant environment
Ji et al. Evaluation for UTBWC on SR-11 as pavement preservation treatment: A case study
CN204608537U (en) A kind of overlay type in-situ heat regeneration asphalt pavement structure
CN211446437U (en) Hot recycled asphalt road structure of plantmix

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20170905

WW01 Invention patent application withdrawn after publication