CN107119917B - Increase the construction method of basement structure behind strip footing house - Google Patents

Increase the construction method of basement structure behind strip footing house Download PDF

Info

Publication number
CN107119917B
CN107119917B CN201710032748.3A CN201710032748A CN107119917B CN 107119917 B CN107119917 B CN 107119917B CN 201710032748 A CN201710032748 A CN 201710032748A CN 107119917 B CN107119917 B CN 107119917B
Authority
CN
China
Prior art keywords
pile
concrete
construction
basement
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710032748.3A
Other languages
Chinese (zh)
Other versions
CN107119917A (en
Inventor
叶长青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tancheng Medical Chemical Industry Development Group Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710032748.3A priority Critical patent/CN107119917B/en
Publication of CN107119917A publication Critical patent/CN107119917A/en
Application granted granted Critical
Publication of CN107119917B publication Critical patent/CN107119917B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0266Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Foundations (AREA)

Abstract

The invention discloses the construction methods for increasing basement structure behind a kind of strip footing house, it is characterized in that construction procedure includes: that reinforcing pile is pressed into soil by (1), the weld horizontal anchor rib at the top of reinforcing pile;(2) construction load wall;(3) it excavates ground to support replacement beam bottom portion or less 5cm and does brick fetal membrane;(4) support replacement beam steel is bound, supporting beam concrete is poured;(5) earth excavation cuts bar shaped cushion cap and foundation beam concrete to bar shaped cushion cap bottom;(6) 20~30cm below spoil to basement bottom board bottom absolute altitude carries out pile connection construction;(7) bumper pad is placed after stake top leveling after pile connection construction;(8) engineering pile and basement bottom board delivery position are cut into concrete, exposed steel bar stress is welded to connect muscle on the outside of steel bar stress, and dowel is square, welds seal ring in basement bottom board medium position;(9) waterproof steel plate for burying load wall and basement bottom board handover internal corner part, is laid with basement bottom board reinforcing bar, pours basement bottom board concrete;(10) construction basement bottom board top waterproof mortar.

Description

Increase the construction method of basement structure behind strip footing house
Technical field
The present invention relates to basement structure is increased after one kind, in particular to increase the construction of basement structure behind strip footing house Method.
Background technique
With urbanization construction go deep into, the requirement in garage is higher and higher, part house because functional requirement is transformed, Existing building lower part increases basement, but is related to many structure problems in the process for increasing basement, and such as: original basis cushion cap is logical It is frequently located in basement position, if structural bearing capacity cannot be met the requirements after removal, even if newly-increased reinforcing pile, reinforcing pile and former work Journey stake rigidity mismatches.In addition, during structure of modification, it is also noted that the waterproof problem of basement.
Summary of the invention
The present invention is to provide the construction method for increasing basement structure behind a kind of strip footing house, solves asking for the prior art Topic.
For this purpose, support replacement beam is arranged in load bearing wall bottom, support replacement depth of beam is 60~90cm, and support replacement beam width is 30cm, support replacement Case bay be 1.1~1.5m, support replacement beam concrete strength be C30 or more than, support replacement beam is shelved on load wall, load wall width For 30cm, load wall depth is 2~3 times of design of basement height, load wall concrete strength be C30 or more than.It reinforces Support replacement 30~40cm of beam, weld horizontal anchor rib at the top of reinforcing pile are protruded into stake, and anchor rib length is 50~60cm, reinforcement and support replacement Beam connection.Pile extension is set above engineering pile, bumper pad is set between pile extension and support replacement beam, and bumper pad is with a thickness of 10cm.? Muscle is welded to connect on the outside of steel bar stress, dowel is square, welds seal ring in basement bottom board medium position, seal ring is straight Diameter is 30~40mm, and seal ring is with a thickness of 3mm.Support replacement beam is in pile extension position setting shear reinforcement to avoid punching failure, shearing resistance For reinforcing bar in bowl-shape, shear reinforcement diameter is 25mm or 28mm.Basement bottom board is with a thickness of 30cm, the setting of basement bottom board top Waterproof mortar, for waterproof mortar with a thickness of 10~20cm, waterproof mortar intensity is M10.It is easy between load wall and basement bottom board Waterproof steel plate is arranged in the internal corner part of load wall and basement bottom board handover in leakage, and waterproof steel plate is with a thickness of 3~5mm.
Construction procedure includes:
(1) reinforcing pile is pressed into soil, the weld horizontal anchor rib at the top of reinforcing pile.
Reinforcing pile uses small-sized tubular pole, due to that in house interior construction, can only carry out piling using small machine, when construction Using the weight of existing building as pressurization counter-force.In addition, being sealed to make reinforcing pile give full play to load effect using prestressing force Stake.
Construction technology is using as follows:
(1) pile crown is handled.Pile crown leveling is guaranteed in order to which future makes force transmission shaft completely attach to pile crown in envelope stake Its stress equalization.The levelling construction of pile crown uses sulphide mastic, can pressurize after screed-coat reaches intensity requirement and seal stake.
(2) prestressed seals stake device.Prestressed is carried out in the following order and seals stake device: 1. steel pad is installed Plate and power transmission steel column, 2. install force transmission beam, 3. install upper cap nut, 4. install jack, 5. install pressure pile reaction beam.Each component Middle line alignment guarantees the power energy symmetrical equilibrium application of jack during piling, it is ensured that force transmission beam has enough displacement spaces, Jack is caused to be unable to reach requirement to avoid because displacement is excessive.
(3) secondary piling.Envelope stake device starts to carry out secondary piling to reinforcing pile after the installation is completed, and secondary piling is most Big pressure is the design final pressure value of reinforcing pile.When jack reach design final pressure value, nut is tightened, use double nut fastening with Guarantee envelope stake effect, after tightening nuts, cannot horse back release, jack should be made to keep design pressure, after a period of stabilisation, then After secondary fastening nut, release can be carried out to jack.
(4) jack and pile driving frame are shed.After the complete release of jack, jack and pile driving frame can be gradually removed.
(5) envelope pile concrete is poured.Pile concrete is sealed using expansion early strength concrete.
(2) construction load wall.
Load is married again since load wall not only undertakes support replacement beam, also to prevent the water room of permeating the ground around house from applying Workshop, so to carry out the seepage control measure of load wall, the especially load wall joint position weak link that is antiseepage.Load wall Using channel steel joint form, first slotted line steel reinforcement cage both ends are welded with channel steel, and the steel reinforcement cage both ends of subsequent slot section are embedded in channel steel.By It is big in load wall depth, it is all risen with connector case on rear side of channel steel and pulls out that difficulty is big, and lower part is backfilled using sand pocket, top 24m uses terraced The form of shape connector case backfill, can effectively prevent concrete flow-disturbing.Sand pocket, which is filled, to be transported to aperture using small-sized machine and manually throws Fill out method, prevent it is mechanically direct topple over, two sides are filled simultaneously, and steel reinforcement cage is prevented to be subjected to displacement.To guarantee sand pocket compactness, using ladder Shape connector case carries out shock compaction after often filling in 2~3m.Filling depth every time is 0.4~0.6m, erection joint after sand pocket compacting Case, connector case is critical to lean on channel steel, if any gap after connector case, it is necessary to fill up compacting with sand pocket.
Underwater gliders use internal diameter for the quick coupling steel conduit of 250mm, save a length of 3m, and most next section length is 4m.Mouth is away from 300~500mm of bottom hole under conduit.2 conduits are arranged in standard cell section, and conduit spacing is less than 3m, and conduit is away from slot section end No more than 1.5m, balanced rising is answered in slot inner concrete face, and the concrete surface height difference at two conduits is not more than 0.5m, pours coagulation eventually Native face elevation should be higher than that design requirement 0.5m.
(3) it excavates ground to support replacement beam bottom portion or less 5cm and does brick fetal membrane.
(4) support replacement beam steel is bound, support replacement beam concrete is poured.
(5) earth excavation cuts bar shaped cushion cap and foundation beam concrete to bar shaped cushion cap bottom.
(6) 20~30cm below spoil to basement bottom board bottom absolute altitude carries out pile connection construction.
Pile connection construction uses following technical scheme:
Pile extension uses tubular pole.Engineering pile top rebars welding flange, engineering pile and tubular pole bottom use flanged joint.? Binding it is good and be welded with the steel reinforcement cage of supporting plate be put into pile pipe it is hollow in, casting concrete forms core stake, core pile length is 1.5~ 1.8m, core pile concrete intensity are greater than or equal to C30, and core stake shearing resistance stirrup diameter is 12mm, and spacing is 5~10cm.
Pile connection construction also uses following technical scheme:
Pile extension uses in situ concrete pile.First remove engineering pile top concrete, exposed engineering pile top rebars, top steel The exposed length of muscle is 20~30mm, the principal rod of exposed reinforcement welding in situ concrete pile, in situ concrete pile at the top of engineering pile Steel pile casting is installed, then casting concrete after reinforcement installation.
(7) bumper pad is placed after stake top leveling after pile connection construction.
Bumper pad is set between support replacement beam and pile extension in the present invention and plays the role of compatible deformation, due to former strip footing Rigidity is larger, and the rigidity of anchoring pile is relatively small, can alleviate the two poor rigidity by bumper pad setting, stress is involutory Reason.Valve rubber can alleviate the punching shear that engineering pile passes over simultaneously.
(8) engineering pile and basement bottom board delivery position are cut into concrete, exposed steel bar stress, on the outside of steel bar stress It is welded to connect muscle, dowel is square, seal ring is welded in basement bottom board medium position, to block infiltration path.
(9) waterproof steel plate for burying load wall and basement bottom board handover internal corner part, is laid with basement bottom board reinforcing bar, pours Build basement bottom board concrete.
(10) construction basement bottom board top waterproof mortar.
The present invention takes full advantage of the characteristics of original strip footing, and construction quality is easy to ensure, structural behaviour is good, operation It is convenient.
Detailed description of the invention
Fig. 1 be strip footing house after increase structural schematic diagram.
In each attached drawing: 1, support replacement beam, 2, shear reinforcement, 3, reinforcing pile, 4, engineering pile, 5, dowel, 6, seal ring, 7, Lower room bottom plate, 8, waterproof mortar, 9, waterproof steel plate, 10, load wall, 11, bumper pad, 12, pile extension, 13, load bearing wall.
Specific embodiment
Support replacement beam 1 is arranged in 13 bottom of load bearing wall, and 1 height of support replacement beam is 60~90cm, and 1 width of support replacement beam is 30cm, support replacement 1 spacing of beam is 1.2m, and 1 concrete strength of support replacement beam is C30, and support replacement beam 1 is shelved on waterproof steel plate 9, and 9 width of waterproof steel plate is 30cm, 9 depth of waterproof steel plate are 2.5 times of design of basement height, and 9 concrete strength of waterproof steel plate is C30.Reinforcing pile 3 is stretched Enter support replacement beam 35cm, 3 top weld horizontal anchor rib of reinforcing pile, anchor rib length is 55cm, and reinforcement is connect with support replacement beam 1.Work Pile extension 12 is arranged in journey stake 4 above, bumper pad 11 is arranged between pile extension 12 and support replacement beam 1, bumper pad 11 is with a thickness of 10cm.? Muscle 5 is welded to connect on the outside of steel bar stress, dowel 5 is square, welds seal ring 6, sealing in basement bottom board medium position 6 diameter of ring is 35mm, and seal ring 6 is with a thickness of 3mm.Support replacement beam 1 is broken to avoid punching in 12 position of pile extension setting shear reinforcement 2 Bad, for shear reinforcement 2 in bowl-shape, 2 diameter of shear reinforcement is 25mm.Basement bottom board 7 is with a thickness of 30cm, 7 top of basement bottom board Waterproof mortar 8 is set, and for waterproof mortar 8 with a thickness of 15cm, waterproof mortar Final 8 degree is M10.In waterproof steel plate 9 and basement bottom board 7 Waterproof steel plate 9 is arranged in the internal corner part of handover, and waterproof steel plate 9 is with a thickness of 4mm.
Construction procedure includes:
(1) reinforcing pile 3 is pressed into soil, in 3 top weld horizontal anchor rib of reinforcing pile.
Reinforcing pile 3 uses small-sized tubular pole, applies the weight of utilization of hour existing building as pressurization counter-force, is sealed using prestressing force Stake.
Construction technology is using as follows:
(1) pile crown is handled.Pile crown leveling is guaranteed in order to which future makes force transmission shaft completely attach to pile crown in envelope stake Its stress equalization.The levelling construction of pile crown uses sulphide mastic, can pressurize after screed-coat reaches intensity requirement and seal stake.
(2) prestressed seals stake device.Prestressed is carried out in the following order and seals stake device: 1. steel pad is installed Plate and power transmission steel column, 2. install force transmission beam, 3. install upper cap nut, 4. install jack, 5. install pressure pile reaction beam.Each component Middle line is aligned when construction, guarantees the power energy symmetrical equilibrium application of jack during piling, it is ensured that force transmission beam has enough positions Space is moved, causes jack to be unable to reach requirement to avoid because displacement is excessive.
(3) secondary piling.Envelope stake device starts to carry out reinforcing pile 3 secondary piling after the installation is completed, and secondary piling is most Big pressure is the design final pressure value of reinforcing pile 3.Final pressure value is designed when jack reaches, nut is tightened, is fastened using double nut To guarantee to seal stake effect, after tightening nuts, cannot horse back release, jack should be made to keep design pressure, after a period of stabilisation, Again after fastening nut, release can be carried out to jack.
(4) jack and pile driving frame are shed.After the complete release of jack, jack and pile driving frame can be gradually removed.
(5) envelope pile concrete is poured.Pile concrete is sealed using expansion early strength concrete.
(2) construction waterproof steel plate 9.
Waterproof steel plate 9 uses channel steel joint form, and first slotted line steel reinforcement cage both ends are welded with channel steel, the steel reinforcement cage of subsequent slot section Both ends are embedded in channel steel.It is all risen with connector case since 9 depth of waterproof steel plate is big, on rear side of channel steel and pulls out that difficulty is big, and lower part is using sand Bag backfill, top 24m use the form of trapezoidal connector case backfill, can effectively prevent concrete flow-disturbing.Sand pocket is filled using small Type machinery is transported to the artificial throwing method in aperture, prevent it is mechanically direct topple over, two sides are filled simultaneously, and steel reinforcement cage is prevented to be subjected to displacement.For Guarantee that sand pocket compactness carries out shock compaction after often filling in 2~3m using trapezoidal connector case.Every time fill depth be 0.4~ 0.6m, erection joint case after sand pocket compacting, connector case is critical to lean on channel steel, if any gap after connector case, it is necessary to fill up pressure with sand pocket It is real.
Underwater gliders use internal diameter for the quick coupling steel conduit of 250mm, save a length of 3m, and most next section length is 4m.Mouth is away from 300~500mm of bottom hole under conduit.2 conduits are arranged in standard cell section, and conduit spacing is less than 3m, and conduit is away from slot section end No more than 1.5m, balanced rising is answered in slot inner concrete face, and the concrete surface height difference at two conduits is not more than 0.5m, pours coagulation eventually Native face elevation should be higher than that design requirement 0.5m.
(3) it excavates ground to 1 bottom of support replacement beam or less 5cm and does brick fetal membrane.
(4) 1 reinforcing bar of support replacement beam is bound, 1 concrete of support replacement beam is poured.
(5) earth excavation cuts bar shaped cushion cap and foundation beam concrete to bar shaped cushion cap bottom.
(6) 20~30cm below spoil to 7 bottom absolute altitude of basement bottom board carries out pile extension 12 and constructs.
The construction of pile extension 12 uses following technical scheme:
Pile extension 12 uses tubular pole.4 top rebars welding flange of engineering pile, engineering pile 4 and tubular pole bottom are connected using flange It connects.Binding it is good and be welded with the steel reinforcement cage of supporting plate be put into pile pipe it is hollow in, casting concrete forms core stake, and core pile length is 1.7m, core pile concrete intensity are equal to C30, and core stake shearing resistance stirrup diameter is 12mm, and spacing is 5~10cm.
(7) bumper pad 11 is placed after stake top leveling after pile extension 12 is constructed.
(8) engineering pile 4 and 7 delivery position of basement bottom board are cut into concrete, exposed steel bar stress, outside steel bar stress Side is welded to connect muscle 5, and dowel 5 is square, seal ring 6 is welded in 7 medium position of basement bottom board, to block water seepage road Diameter.
(9) it buries waterproof steel plate 9 and basement bottom board 7 joins the waterproof steel plate 9 of internal corner part, be laid with basement bottom board 7 Reinforcing bar pours 7 concrete of basement bottom board.
(10) construction 7 top waterproof mortar 8 of basement bottom board.

Claims (6)

1. increase the construction method of basement structure behind a kind of strip footing house, it is characterized in that support replacement beam is arranged in load bearing wall bottom, Support replacement beam is shelved on load wall, and reinforcing pile protrudes into support replacement 30~40cm of beam, weld horizontal anchor rib at the top of reinforcing pile;On engineering pile Pile extension is arranged in face, and bumper pad is arranged between pile extension and support replacement beam, muscle is welded to connect on the outside of steel bar stress, dowel is right angle Shape welds seal ring in basement bottom board medium position;Waterproof mortar is arranged in basement bottom board top, in load wall and basement Waterproof steel plate is arranged in the internal corner part of bottom plate handover;
Construction procedure includes:
(1) reinforcing pile is pressed into soil, the weld horizontal anchor rib at the top of reinforcing pile;
Reinforcing pile uses small-sized tubular pole, and the weight for applying utilization of hour existing building is used as pressurization counter-force,
(2) construction load wall;
Load wall uses channel steel joint form, and first slotted line steel reinforcement cage both ends are welded with channel steel, and the steel reinforcement cage both ends of subsequent slot section are embedding Enter in channel steel;Channel steel back lower is backfilled using sand pocket, and top 24m uses the form of trapezoidal connector case backfill;
Underwater gliders use internal diameter for the quick coupling steel conduit of 250mm, save a length of 3m, and most next section length is 4m; Mouth is away from 300~500mm of bottom hole under conduit;Standard cell section be arranged 2 conduits, conduit spacing be less than 3m, conduit away from slot section end not Greater than 1.5m, balanced rising is answered in slot inner concrete face, and the concrete surface height difference at two conduits is not more than 0.5m, whole pouring concrete Face elevation should be higher than that design requirement 0.5m;
(3) it excavates ground to support replacement beam bottom portion or less 5cm and does brick fetal membrane;
(4) support replacement beam steel is bound, supporting beam concrete is poured;
(5) earth excavation cuts bar shaped cushion cap and foundation beam concrete to bar shaped cushion cap bottom;
(6) 20~30cm below spoil to basement bottom board bottom absolute altitude carries out pile connection construction;
(7) bumper pad is placed after stake top leveling after pile connection construction;
(8) engineering pile and basement bottom board delivery position are cut into concrete, exposed steel bar stress welds on the outside of steel bar stress Dowel, dowel are square, weld seal ring in basement bottom board medium position;
(9) waterproof steel plate for burying load wall and basement bottom board handover internal corner part, is laid with basement bottom board reinforcing bar, pours ground Lower room underplate concrete;
(10) construction basement bottom board top waterproof mortar.
2. increasing the construction method of basement structure behind strip footing house according to claim 1, it is characterized in that reinforcing pile Construction seals stake using prestressing force;Construction technology is using as follows:
(1) pile crown is handled;Pile crown leveling be in order to future envelope stake make force transmission shaft completely attach to pile crown, guarantee its by Power is balanced;The levelling construction of pile crown uses sulphide mastic, can pressurize after screed-coat reaches intensity requirement and seal stake;
(2) prestressed seals stake device;In the following order carry out prestressed seal stake device: 1. install billet and 2. power transmission steel column installs force transmission beam, 3. install upper cap nut, 4. installs jack, 5. installs pressure pile reaction beam;Each component construction When middle line be aligned, guarantee piling during jack power energy symmetrical equilibrium apply;
(3) secondary piling;Envelope stake device starts to carry out reinforcing pile secondary piling after the installation is completed, the maximum pressure of secondary piling Power is the design final pressure value of reinforcing pile;
(4) jack and pile driving frame are shed;After the complete release of jack, jack and pile driving frame can be gradually removed;
(5) envelope pile concrete is poured;Pile concrete is sealed using expansion early strength concrete.
3. increasing the construction method of basement structure behind strip footing house according to claim 1, it is characterized in that sand pocket is filled out Build and the artificial throwing method in aperture be transported to using small-sized machine, prevent it is mechanically direct topple over, two sides are filled simultaneously;To guarantee that sand pocket is closely knit Degree, using trapezoidal connector case, carries out shock compaction after often filling in 2~3m;Filling depth every time is 0.4~0.6m, sand pocket compacting Erection joint case afterwards, connector case is critical to lean on channel steel, if any gap after connector case, it is necessary to fill up compacting with sand pocket.
4. increasing the construction method of basement structure behind strip footing house according to claim 1, it is characterized in that pile extension is applied Work uses following technical scheme: pile extension uses tubular pole;Engineering pile top rebars welding flange, engineering pile and tubular pole bottom use Flanged joint;Binding it is good and be welded with the steel reinforcement cage of supporting plate be put into pile pipe it is hollow in, casting concrete forms core stake, and core stake is long Degree be 1.5~1.8m, core pile concrete intensity be greater than or equal to C30, core stake shearing resistance stirrup diameter be 12mm, spacing be 5~ 10cm。
5. increasing the construction method of basement structure behind strip footing house according to claim 1, it is characterized in that pile extension is applied Work uses following technical scheme: pile extension uses in situ concrete pile;First remove engineering pile top concrete, exposed engineering pile top Reinforcing bar, the exposed length of top rebars are 20~30mm, and the principal rod of exposed reinforcement welding in situ concrete pile, existing at the top of engineering pile Steel pile casting is installed after pouring concrete stake reinforcement installation, then casting concrete.
6. increasing the construction method of basement structure behind strip footing house according to claim 1, it is characterized in that when very heavy Top reaches design final pressure value, and nut is tightened, and uses double nut fastening to guarantee to seal stake effect;It, cannot be at once after tightening nuts Release should make jack that design pressure be kept again after fastening nut, can to unload after a period of stabilisation to jack Pressure.
CN201710032748.3A 2015-05-19 2015-05-19 Increase the construction method of basement structure behind strip footing house Active CN107119917B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710032748.3A CN107119917B (en) 2015-05-19 2015-05-19 Increase the construction method of basement structure behind strip footing house

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710032748.3A CN107119917B (en) 2015-05-19 2015-05-19 Increase the construction method of basement structure behind strip footing house
CN201510284621.1A CN104878835B (en) 2015-05-19 2015-05-19 Strip footing increases basement structure behind house

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201510284621.1A Division CN104878835B (en) 2015-05-19 2015-05-19 Strip footing increases basement structure behind house

Publications (2)

Publication Number Publication Date
CN107119917A CN107119917A (en) 2017-09-01
CN107119917B true CN107119917B (en) 2018-12-14

Family

ID=53946496

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201710032748.3A Active CN107119917B (en) 2015-05-19 2015-05-19 Increase the construction method of basement structure behind strip footing house
CN201510284621.1A Active CN104878835B (en) 2015-05-19 2015-05-19 Strip footing increases basement structure behind house

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201510284621.1A Active CN104878835B (en) 2015-05-19 2015-05-19 Strip footing increases basement structure behind house

Country Status (1)

Country Link
CN (2) CN107119917B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107269023A (en) * 2016-03-02 2017-10-20 叶香雄 Floor reinforcement means
CN108360561A (en) * 2016-07-26 2018-08-03 朱奎 The Basement reconstruction of raft foundation constructs
CN106285032B (en) * 2016-07-26 2018-12-14 朱奎 Basement reconstruction construction with raft foundation building
CN106988337B (en) * 2017-04-20 2019-02-01 南京工大桥隧与轨道交通研究院有限公司 It is a kind of for reducing the reinforcement means of bar shaped shallow foundation house differential settlement
CN107143149B (en) * 2017-05-24 2019-02-15 广东省建筑科学研究院集团股份有限公司 A kind of existing masonry structure building adds the construction method of basement
CN107605173A (en) * 2017-10-17 2018-01-19 叶香雄 The ruggedized construction of building
CN109680700B (en) * 2019-02-21 2019-12-03 西华大学 A kind of dedicated unit and construction method carrying out foundation underpinning under strip footing
CN114319162B (en) * 2020-10-09 2023-06-13 华鸿建设集团有限公司 Cover plate culvert continuous casting construction device and construction method thereof
CN113529693B (en) * 2021-06-03 2023-02-03 中建一局集团建设发展有限公司 Construction method for penetrating pipeline through cutter-suction type corner amplitude diaphragm wall
CN113482394A (en) * 2021-08-06 2021-10-08 中建三局集团(深圳)有限公司 Structural beam plate back-jacking reinforcing method

Family Cites Families (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2898759A (en) * 1956-03-07 1959-08-11 Verner H Pebley Method of repairing a basement wall
JP2640969B2 (en) * 1988-07-08 1997-08-13 株式会社竹中工務店 Basement expansion method for existing buildings
JPH093927A (en) * 1995-06-15 1997-01-07 Sekisui Chem Co Ltd Basement construction method and basement structure
JP4550534B2 (en) * 2004-09-14 2010-09-22 森 直樹 Building basic structure
CN1970897A (en) * 2005-11-23 2007-05-30 张准胜 Method and device for building underground space structure for established building by using public land
CN201095770Y (en) * 2007-09-06 2008-08-06 长业建设集团有限公司 Embedded single-layer basement wooden pile composite brad wall structure
CN101397852B (en) * 2007-09-26 2010-05-19 上海市第二建筑有限公司 Construction method for increasing to build multi-storey basement to original building
CN101886479B (en) * 2010-07-14 2011-09-28 山东建筑大学 Underground storey-adding process of frame structural building by one-by-one independent foundation underpinning method
CN201809774U (en) * 2010-09-16 2011-04-27 中建三局建设工程股份有限公司 Foundation ditch support replacement and inner support removal construction structure
CN102704957B (en) * 2012-05-11 2014-05-07 北京工业大学 Shed-frame method for shallowly burying large-sized underground structure construction
CN102864946B (en) * 2012-10-23 2014-07-16 山东建筑大学 Process for supporting existing buildings through structural steel and horizontal rachel rod member and additionally adding multilayer basement
CN103321231B (en) * 2013-06-10 2015-11-25 叶长青 Base pit stand construction
CN103437567B (en) * 2013-08-30 2015-06-10 山东建筑大学 Method for supporting existing building underground added storey through original pile foundations
CN103912134B (en) * 2014-03-21 2016-09-14 上海建工四建集团有限公司 Existing building underground space structure and construction method in situ
CN104328789B (en) * 2014-10-31 2016-04-13 天津三建建筑工程有限公司 The overhanging type support replacement construction method of the horizontal inner support of a kind of steel concrete

Also Published As

Publication number Publication date
CN107119917A (en) 2017-09-01
CN104878835B (en) 2017-06-20
CN104878835A (en) 2015-09-02

Similar Documents

Publication Publication Date Title
CN107119917B (en) Increase the construction method of basement structure behind strip footing house
CN104018436B (en) Prefabricated box culvert system and its installation method
US4697955A (en) Method of constructing reinforced concrete works such as underground galleries, road tunnels, et cetera; pre-fabricated contrete elements for constructing such works
CN105155551A (en) Pressure compensation type foundation pit supporting structure and construction method
CN104018518A (en) Prefabricated underground diaphragm wall and method for constructing outer basement wall and floor slabs
CN103696784A (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN112663624B (en) Composite support for foundation pit and construction method
CN104988884A (en) Void deformation monitoring device for face rockfill dam and mounting method
KR20210154337A (en) Construction Method of Underground Structures
CN103410144B (en) Prestressed reinforcement piles set into rock and construction method
CN108035379A (en) A kind of pipe gallery and its construction method
CN103015414A (en) Precast concrete post grouting pile and grouting process
KR20190022132A (en) Top-down method using precast-concrete colum
CN103122642A (en) Construction method of vertical post support change
KR102149473B1 (en) Prestressing using PC steel wire apply Construction method of underground non-adhesive steel composite concrete tunnel
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall
CN110241863B (en) Soft soil foundation pit excavation process pipe gallery deformation control device and control method thereof
CN210766861U (en) Portal formula building pile foundation underpins structure under narrow and small space
CN111305182A (en) Soft foundation reinforcement construction method
CN108643215B (en) Construction method of anchor pier type foundation after rotary spraying and pressing into variable cross section
CN204059361U (en) A kind of braced structures adopting resistance to plucking PHC pile tube to do column
US5871307A (en) Pre-cast concrete panel wall
CN210888953U (en) Tunnel pile and arch combined primary support system
CN210975403U (en) Treatment structure of high water level soft soil bridgehead roadbed
CN209040103U (en) Assembled type special-shaped hollow slab pile wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201130

Address after: No. 100, North Ring Road, Hede Town, Sheyang County, Yancheng City, Jiangsu Province

Patentee after: Gu Yaobin

Address before: 325000 No. 4, Jinchuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Zhejiang, China

Patentee before: Ye Changqing

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231208

Address after: 276100 Development Zone Management Committee of Tancheng County, Linyi City, Shandong Province 707

Patentee after: Tancheng Medical Chemical Industry Development Group Co.,Ltd.

Address before: No. 100, North Ring Road, Hede Town, Sheyang County, Yancheng City, Jiangsu Province

Patentee before: Gu Yaobin