CN107119549A - Bicycle expressway and the construction method that bicycle expressway is set up under BRT - Google Patents

Bicycle expressway and the construction method that bicycle expressway is set up under BRT Download PDF

Info

Publication number
CN107119549A
CN107119549A CN201710367549.8A CN201710367549A CN107119549A CN 107119549 A CN107119549 A CN 107119549A CN 201710367549 A CN201710367549 A CN 201710367549A CN 107119549 A CN107119549 A CN 107119549A
Authority
CN
China
Prior art keywords
steel
girder
steel box
lid beam
steel column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710367549.8A
Other languages
Chinese (zh)
Inventor
马义俊
戴立先
郑伟盛
韦晓琪
胡哲
黄航斌
袁晓民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science and Industry Corp Ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201710367549.8A priority Critical patent/CN107119549A/en
Publication of CN107119549A publication Critical patent/CN107119549A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D18/00Bridges specially adapted for particular applications or functions not provided for elsewhere, e.g. aqueducts, bridges for supporting pipe-lines
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention is applied to technical field of building construction, the construction method of bicycle expressway is set up there is provided a kind of bicycle expressway and under BRT, wherein, bicycle expressway includes some sections, and each section includes steel box-girder, steel lid beam, steel column, embedded part and concrete.Concrete is embedded at subsurface, and embedded part is embedded in concrete, and steel column is vertically fixed on concrete, and steel lid beam is installed on steel column.Support platform is extended in steel lid beam both sides, and steel box-girder is connected by bearing with the support platform of steel lid beam.Present invention utilizes original BRT overhead roads bicycle expressway, suit measures to local conditions, comprehensively utilize existing resource, reduce cost;Combined closely by bicycle expressway with existing BRT circuits, be easy to people to go on a journey.Meanwhile, bicycle expressway is to promote low-carbon ecological urban construction, advocates the new way of green low-carbon trip, is also that there is provided the new tunnel of a variety of citizen's movable functions for alleviation city commuting demand on and off duty.

Description

Bicycle expressway and the construction method that bicycle expressway is set up under BRT
Technical field
The invention belongs to technical field of building construction, more particularly to a kind of bicycle expressway and set up voluntarily under BRT The construction method of car expressway.
Background technology
The final purpose of Traffic Development is the outside environment that sequence is provided with for the mankind, with it is people-oriented, green go out The proposition of the Modern City Traffic theories such as row, the city slow-vehicle system by representative of bicycle expressway is progressively taken seriously.
Bicycle expressway refers to the urban transportation infrastructure for being exclusively used in cycling, with 3 features:1) row Sail speed fast, traffic efficiency is high.Due to Computer method in current city, the travel speed of bicycle is less than 10km/h, and voluntarily Scooter 30km/h during the design of car highway, the efficiency that can greatly improve that cyclists only alleviates gathering around for large size city indirectly Stifled effect.2) it is people-oriented, embody fair.Bicycle highway carries out the non-separation of machine so that bicycle enjoys independent right of way, Adequately protect injury of the cycling person from motor vehicle, and reduces influencing each other for two kinds of vehicles.3) environmental protection, Low-carbon health.Green Travel is advocated in bicycle expressway, life idea, the life of protection city to improving modern city low-carbon environment-friendly State environment has positive meaning.
At home, the urban planning and construction of the past few decades too pursues motorization traffic, and progressively compression is even eliminated Cycle track, the cycling trip rate in Guangzhou and Shenzhen is only 9% according to statistics, trip rate highest Xiamen City in peak period also only Have 20%, far below the trip rate index of the Western European countries 30%~50%.Going from bad to worse for traffic environment promotes domestic each big city City accelerates to propose reconstruction, the scheme of newly-built bicycle expressway system.The bicycle traffic system of current domestic city is still in Starting stage, its planning and designing, manufacture install theory and technology and far fall behind countries in Europe.Fast public traffic system (Bus Rapid Transit) abbreviation BRT, it is a kind of new mass transit system between rail rapid transit and regular public traffic, It is a kind of middle freight volume mode of transportation, is generally also referred to as " subway on ground " by people.It is to utilize to modernize the cooperation of public transport technology Intelligent transportation and operation management (Integrated dispatching system), open up busway and build novel bus station, realize track The operating service of travel pattern, reaches a kind of unique urban transit system of light rail excellent service standard.At present, fast public traffic system Underlying space do not make full use of also, for this reason, it is necessary to reference to BRT to the planning of large size city bicycle expressway and build close Key Study on Problems, by reasonably planning, perfect design and overall process construction, proposes city bicycles expressway system one Change solution, it is significant to the green in promotion city, low-carbon and sustainable development.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of bicycle expressway and voluntarily overall height are set up under BRT The construction method on fast road.
The present invention is achieved in that a kind of bicycle expressway, including some sections, and each section includes steel Box beam, steel lid beam, steel column, embedded part and concrete;The concrete is embedded at subsurface, and the embedded part is embedded at the coagulation In native, the steel column is vertically fixed on the concrete, and the steel lid beam is installed on the steel column;The bottom of the steel lid beam Portion both sides each extend over out support platform, and the steel box-girder includes view picture steel box-girder, abnormity steel box girder and framing steel box-girder, phase The adjacent view picture steel box-girder and view picture steel box-girder, the adjacent view picture steel box-girder and abnormity steel box girder and adjacent described Abnormity steel box girder is connected by bearing with the support platform of the steel lid beam both sides respectively with framing steel box-girder.
Further, the junction of the steel box-girder and the steel lid beam in another section is provided with expansion joint.
Further, the bearing is laminated rubber bearing, and it includes upper bracket plate, lower support plate, tetrafluoro slide plate, rubber And stiffened steel plates, the upper bracket plate is welded in the bottom of the steel box-girder, and the lower support plate is welded in the steel lid beam Support platform on, the rubber is fixed in the lower support plate, and the stiffened steel plates are embedded in the rubber, described four Fluorine slide plate is fixed on the rubber.
Further, expose at the top of the embedded part and some add is welded with the top of the concrete, the embedded part Strength plate, some stiffeners enclose the shape for being set as matching with the steel column outer peripheral edge, and the steel column outer peripheral edge is put more energy into described Plate weld.
The present invention is in order to solve the above technical problems, additionally provide a kind of construction party that bicycle expressway is set up under BRT Method, comprises the following steps:
S10, using automobile hanging device by embedded part lift in place, spot welding fix after, correction is measured to the embedded part;
S20, after the embedded part meets required precision, placing concrete;
S30, using automobile hanging device steel column is sling, after allocation and transportation to installation site, make steel column close to embedded part, pass through vapour Car hanging device coordinates the mode of artificial traction to guide steel column to complete to dock with embedded part;
S40, in being welded with multiple stiffeners on steel column, steel column is carried out spacing, is corrected by padding chock and reach that precision will Ask, multiple stiffeners are then welded again, and full penetration is carried out to the steel plate of steel column and embedded part;
S50, interim moulding bed is set up, the top shape of interim moulding bed is matched with steel lid beam bottom profile, welded on steel lid beam Hanger is connect, steel lid beam is sling using automobile hanging device, guides and hangs by way of automobile hanging device coordinates artificial traction Steel loading bent cap completes to dock in place with steel column;Correction is measured after in place;
S60, in being completed lower support plate positioning welding in factory on steel lid beam, by upper bracket plate positioning welding in steel case Liang Shang;
S70, hanger is welded on steel box-girder, the steel box-girder that will be welded with upper bracket plate using automobile hanging device lifts in place Afterwards, being located by connecting for bearing rubber part is completed;
S80, foundation above-mentioned steps, carry out the location and installation of each embedded part, steel column, steel box-girder and steel lid beam, until complete Into the construction of bicycle expressway.
6th, the construction method of bicycle expressway is set up under BRT as claimed in claim 5, it is characterised in that the step Also comprise the following steps after rapid S20:
The steel column is cut in two, is divided into longer one section and shorter one section;By one section of shorter steel column and institute After the bottom connection for stating steel lid beam, a lifting elements are formed.
Further, the step S30 also comprises the following steps:
The lifting elements are sling, one section longer with steel column is hinged using connecting plate after the lifting elements are in place.
Further, also comprise the following steps after the step S60:
By after the view picture steel box-girder in section is assembled in component stockyard, whole Transporting is in place to on-site hoisting, described interim Moulding bed long axis direction is parallel with road direction.
Further, also comprise the following steps after the step S70:
Framing steel box-girder is hung to behind BRT projections lower section using automobile hanging device, another automobile hanging device is used Coordinate and carry out the lifting of homonymy erect-position double-machine lifting crane.
Compared with prior art, beneficial effect is the present invention:Present invention utilizes original BRT overhead roads bicycle Expressway, suits measures to local conditions, and comprehensively utilizes existing resource, reduces cost;It is close by bicycle expressway and existing BRT circuits With reference to making the driving system conversion of plugging into of the chronic traffic system in city convenient, be easy to people to go on a journey.Meanwhile, bicycle expressway It is to promote low-carbon ecological urban construction, advocates the new way of green low-carbon trip, is also to alleviate city commuting demand on and off duty, carries For the new tunnel of a variety of citizen's movable functions.
Brief description of the drawings
One or more embodiments are illustrative by the picture in corresponding accompanying drawing, these exemplary theorys The element with same reference numbers label is expressed as similar element in the bright restriction not constituted to embodiment, accompanying drawing, removes Composition is not limited the non-figure having in special statement, accompanying drawing.
Fig. 1 is the partial structural diagram of bicycle expressway provided in an embodiment of the present invention;
Fig. 2 is the attachment structure schematic diagram of steel column in Fig. 1 and embedded part;
Fig. 3 is the schematic diagram of the steel lid beam in Fig. 1;
Fig. 4 is framing steel box-girder in Fig. 1 and BRT position relationship schematic diagram;
Fig. 5 is view picture steel box-girder in Fig. 1 and BRT position relationship schematic diagram;
Fig. 6 is the schematic diagram for the steel lid beam for being welded with the steel box-girder of upper bracket plate and being welded with lower support plate;
Fig. 7 is in the schematic diagram that tetrafluoro slide plate, rubber and stiffened steel plates are installed in upper bracket plate;
Fig. 8 is the schematic diagram for using the framing steel lid beam in two-shipper erection drawing 1.
Embodiment
In order that technical problems, technical solutions and advantages to be solved are more clearly understood, tie below Drawings and Examples are closed, the present invention will be described in further detail.It should be appreciated that specific embodiment described herein is only To explain the present invention, it is not intended to limit the present invention.
As shown in figure 1, for a preferred embodiment of the invention, there is provided a kind of bicycle expressway, including some roads Section, each section includes steel box-girder 1, steel lid beam 2, steel column 3, embedded part 4 and concrete 5.
Fig. 2 is referred to, above-mentioned concrete 5 is embedded at subsurface, and the embedded part 4 is embedded in the concrete 5.The steel Post 3 is vertically fixed on the concrete 5, also, concrete 5 is exposed at the top of the embedded part 4, and the top welding of embedded part 5 is solid Surely there are some stiffeners 6, some stiffeners 6 enclose the shape for being set as matching with the outer peripheral edge of steel column 3, and the outer peripheral edge of steel column 3 adds with described Strength plate 6 is welded.Fig. 3 is referred to, the steel lid beam 2 is installed on the steel column 3;The two bottom sides of steel lid beam 2 are each extended over out Support platform 20.
Above-mentioned steel box-girder 1 includes view picture steel box-girder 11, abnormity steel box girder 12 and framing steel box-girder 13.Adjacent view picture steel Box beam 11 and view picture steel box-girder 11, adjacent view picture steel box-girder 11 and abnormity steel box girder 12 and adjacent abnormity steel box girder 12 with Framing steel box-girder 13 is connected by bearing 7 with the support platform 20 of the both sides of steel lid beam 2 respectively.Fig. 4 and Fig. 5 is referred to, it is whole Width steel box-girder 11 is located at immediately below BRT 200, and framing steel box-girder 13 is located at the outer side edges of BRT 200, and abnormity steel box girder 12 is connected to Between view picture steel box-girder 11 and framing steel box-girder 13.
Specifically, the steel lid beam 2 include view picture steel lid beam 21, at view picture point connection steel lid beam 22, framing steel lid beam 23 with And steel lid beam 24 at framing point connection.The adjacent view picture steel box-girder 11 in same two, section passes through institute with view picture steel box-girder 11 View picture steel lid beam 21 is stated to connect;Two view picture steel box-girders 11 in adjacent two section pass through described whole with view picture steel box-girder 11 Steel lid beam 22 is connected at width point connection;The framing steel box-girder 13 in same section passes through the framing steel with framing steel box-girder 13 Bent cap 23 is connected;Two framing steel box-girders 13 in adjacent two section are divided at connection with framing steel box-girder 13 by the framing Steel lid beam 24 is connected.
Wherein, the junction of the steel box-girder 1 and the steel lid beam 2 in another section is provided with expansion joint.
Fig. 6 and Fig. 7 is referred to, above-mentioned bearing 7 is laminated rubber bearing, and it includes upper bracket plate 71, lower support plate 72, four Fluorine slide plate 73, rubber 74 and stiffened steel plates 75.The upper bracket plate 71 is welded in the bottom of the steel box-girder 1, the lower branch Seat board 72 is welded on the support platform 20 of steel lid beam 2, and the rubber 74 is fixed in the lower support plate 71, described to put more energy into Steel plate 75 is embedded in the rubber 74, and the tetrafluoro slide plate 73 is fixed on the rubber 74.
The present embodiment additionally provides a kind of construction method that bicycle expressway is set up under BRT, comprises the following steps:
S10, using automobile hanging device 300 embedded part 4 is lifted in place, after spot welding is fixed, the embedded part 4 measured Correction.
S20, after the embedded part 4 meets required precision, placing concrete 5;The steel column 3 is cut in two, be divided into compared with One section of long steel column 31 and one section of shorter steel column 32.One section of steel column of processing shorter 32, makes its top surface shape and steel lid beam 2 Bottom shape is matched, after the bottom of this section of steel column 3 and the steel lid beam 2 is welded to connect, and forms a lifting elements.
S30, using automobile hanging device 300 one section of longer steel column 31 is sling, after allocation and transportation to installation site, make steel column 31 close to embedded part 4, guides steel column 31 to complete to dock with embedded part 4 by way of automobile hanging device 300 coordinates artificial traction;Hang The lifting elements are played, are hinged after the lifting elements are in place with one section of longer steel column 31 using connecting plate 8.
S40, in being welded with multiple stiffeners on steel column 3, steel column 3 is carried out spacing, precision is reached by padding chock to correct It is required that, multiple stiffeners 6 are then welded again, and full penetration is carried out to the steel plate of steel column 3 and embedded part 4.
S50, in being completed the positioning welding of lower support plate 72 in factory on steel lid beam 2, by the positioning welding of upper bracket plate 71 In on steel box-girder 1;
S60, Fig. 8 is referred to, in order to ensure unstability of not toppled in the installation process of steel lid beam 2, taken in the two ends of steel lid beam 2 If interim moulding bed 400, the top shape of interim moulding bed 400 is matched with the bottom profile of steel lid beam 2, and is joined using distribution beam System, in order to ensure minimum road occupying, the interim long axis direction of moulding bed 400 is parallel with road direction;
Hanger is welded on steel lid beam 2, steel lid beam 2 is sling using automobile hanging device 300, passes through automobile hanging device The mode of 300 cooperation artificial tractions guides lifting steel lid beam 2 to complete to dock in place with steel column 3;Correction is measured after in place.
S70, in order to ensure traffic dispersion, by across the view picture steel box-girder 11 in section after component stockyard is assembled, whole Transporting It is in place to on-site hoisting;
Hanger is welded on view picture steel box-girder 11, framing steel box-girder 13 is hung to BRT200 projections using automobile hanging device Behind lower section, coordinated using another automobile hanging device 300 and carry out the lifting of homonymy erect-position double-machine lifting crane;
After the steel box-girder 1 for being welded with upper bracket plate 11 is lifted in place using automobile hanging device 300, the rubber of bearing 7 is completed 74 parts are located by connecting.
S80, foundation above-mentioned steps, carry out the location and installation of each embedded part 4, steel column 3, steel box-girder 1 and steel lid beam 2, directly To the construction for completing a section, the construction in other sections is then completed further in accordance with same method.
The present embodiment make use of original overhead road bicycle expressways of BRT 200, suit measures to local conditions, and comprehensively utilize existing Resource, reduces cost;Combined closely by bicycle expressway with the existing circuits of BRT 200, allow the chronic traffic system in city The conversion of plugging into of driving system it is convenient, be easy to people to go on a journey.Meanwhile, bicycle expressway is to promote low-carbon ecological urban construction, The new way of green low-carbon trip is advocated, is also that there is provided the new of a variety of citizen's movable functions for alleviation city commuting demand on and off duty Passage.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention Any modifications, equivalent substitutions and improvements made within refreshing and principle etc., should be included in the scope of the protection.

Claims (9)

1. a kind of bicycle expressway, it is characterised in that including some sections, each section includes steel box-girder, steel lid Beam, steel column, embedded part and concrete;The concrete is embedded at subsurface, and the embedded part is embedded in the concrete, described Steel column is vertically fixed on the concrete, and the steel lid beam is installed on the steel column;The two bottom sides of the steel lid beam point Do not extend support platform, the steel box-girder includes view picture steel box-girder, abnormity steel box girder and framing steel box-girder, and adjacent is described View picture steel box-girder and view picture steel box-girder, the adjacent view picture steel box-girder and abnormity steel box girder and the adjacent profile iron case Beam is connected by bearing with the support platform of the steel lid beam both sides respectively with framing steel box-girder.
2. bicycle expressway as claimed in claim 1, it is characterised in that the steel box-girder and the steel lid beam in another section Junction be provided with expansion joint.
3. bicycle expressway as claimed in claim 2, it is characterised in that the bearing is laminated rubber bearing, and it includes Upper bracket plate, lower support plate, tetrafluoro slide plate, rubber and stiffened steel plates, the upper bracket plate are welded in the bottom of the steel box-girder Portion, the lower support plate is welded on the support platform of the steel lid beam, and the rubber is fixed in the lower support plate, described Stiffened steel plates are embedded in the rubber, and the tetrafluoro slide plate is fixed on the rubber.
4. bicycle expressway as claimed in claim 1, it is characterised in that expose the concrete at the top of the embedded part, Some stiffeners are welded with the top of the embedded part, some stiffeners, which enclose, is set as what is matched with the steel column outer peripheral edge Shape, the steel column outer peripheral edge and the plate weld of putting more energy into.
5. a kind of construction method that bicycle expressway as claimed in claim 1 is set up under BRT, it is characterised in that including Following steps:
S10, using automobile hanging device by embedded part lift in place, spot welding fix after, correction is measured to the embedded part;
S20, after the embedded part meets required precision, placing concrete;
S30, using automobile hanging device steel column is sling, after allocation and transportation to installation site, make steel column close to embedded part, pass through truck crane The standby mode for coordinating artificial traction of installing guides steel column to complete to dock with embedded part;
S40, in being welded with multiple stiffeners on steel column, steel column is carried out spacing, is corrected by padding chock and reach required precision, so Weld multiple stiffeners again afterwards, and full penetration is carried out to the steel plate of steel column and embedded part;
S50, interim moulding bed is set up, the top shape of interim moulding bed matches with steel lid beam bottom profile, welds and hang on steel lid beam Ear, is sling steel lid beam using automobile hanging device, and lifting steel is guided by way of automobile hanging device coordinates artificial traction Bent cap completes to dock in place with steel column;Correction is measured after in place;
S60, in being completed lower support plate positioning welding in factory on steel lid beam, by upper bracket plate positioning welding in steel box-girder On;
S70, hanger is welded on steel box-girder, using automobile hanging device will be welded with the steel box-girder of upper bracket plate lift it is in place after, Complete being located by connecting for bearing rubber part;
S80, foundation above-mentioned steps, carry out the location and installation of each embedded part, steel column, steel box-girder and steel lid beam, until completing certainly The construction of driving expressway.
6. the construction method of bicycle expressway is set up under BRT as claimed in claim 5, it is characterised in that the step S20 Also comprise the following steps afterwards:
The steel column is cut in two, is divided into longer one section and shorter one section;By one section of shorter steel column and the steel After the bottom connection of bent cap, a lifting elements are formed.
7. the construction method of bicycle expressway is set up under BRT as claimed in claim 6, it is characterised in that the step S30 Also comprise the following steps:
The lifting elements are sling, one section longer with steel column is hinged using connecting plate after the lifting elements are in place.
8. the construction method of bicycle expressway is set up under BRT as claimed in claim 5, it is characterised in that the step S60 Also comprise the following steps afterwards:
By after the view picture steel box-girder in section is assembled in component stockyard, whole Transporting is in place to on-site hoisting, the interim moulding bed Long axis direction is parallel with road direction.
9. the construction method of bicycle expressway is set up under BRT as claimed in claim 5, it is characterised in that the step S70 Also comprise the following steps afterwards:
Framing steel box-girder is hung to behind BRT projections lower section using automobile hanging device, coordinated using another automobile hanging device Carry out the lifting of homonymy erect-position double-machine lifting crane.
CN201710367549.8A 2017-05-23 2017-05-23 Bicycle expressway and the construction method that bicycle expressway is set up under BRT Pending CN107119549A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710367549.8A CN107119549A (en) 2017-05-23 2017-05-23 Bicycle expressway and the construction method that bicycle expressway is set up under BRT

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710367549.8A CN107119549A (en) 2017-05-23 2017-05-23 Bicycle expressway and the construction method that bicycle expressway is set up under BRT

Publications (1)

Publication Number Publication Date
CN107119549A true CN107119549A (en) 2017-09-01

Family

ID=59730010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710367549.8A Pending CN107119549A (en) 2017-05-23 2017-05-23 Bicycle expressway and the construction method that bicycle expressway is set up under BRT

Country Status (1)

Country Link
CN (1) CN107119549A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086126A (en) * 2017-12-19 2018-05-29 厦门市市政建设开发有限公司 Monoblock type bicycle occupation bridge structure and its construction method
CN108301307A (en) * 2017-12-19 2018-07-20 厦门市市政建设开发有限公司 Separation type bicycle occupation bridge structure and its construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002266316A (en) * 2001-03-08 2002-09-18 Ohbayashi Corp Cycling way annexed to bridge
CN201485781U (en) * 2009-07-29 2010-05-26 中铁二院工程集团有限责任公司 Large station rail switch beam structure of high-speed railway
CN201835220U (en) * 2010-07-23 2011-05-18 四川西南交大土木工程设计有限公司 City viaduct structure
CN203200914U (en) * 2013-04-10 2013-09-18 上海嘉实(集团)有限公司 Steel structure socle outward exposed connecting structure
CN106498842A (en) * 2016-12-19 2017-03-15 厦门市市政工程设计院有限公司 A kind of voluntarily axle beam and its method of construction under existing elevated bridge
CN206157557U (en) * 2016-10-26 2017-05-10 中铁第四勘察设计院集团有限公司 Hollow gate -type mound of railway bearing formula large -span prestressed concrete
CN207017132U (en) * 2017-05-23 2018-02-16 中建钢构有限公司 A kind of bicycle expressway

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002266316A (en) * 2001-03-08 2002-09-18 Ohbayashi Corp Cycling way annexed to bridge
CN201485781U (en) * 2009-07-29 2010-05-26 中铁二院工程集团有限责任公司 Large station rail switch beam structure of high-speed railway
CN201835220U (en) * 2010-07-23 2011-05-18 四川西南交大土木工程设计有限公司 City viaduct structure
CN203200914U (en) * 2013-04-10 2013-09-18 上海嘉实(集团)有限公司 Steel structure socle outward exposed connecting structure
CN206157557U (en) * 2016-10-26 2017-05-10 中铁第四勘察设计院集团有限公司 Hollow gate -type mound of railway bearing formula large -span prestressed concrete
CN106498842A (en) * 2016-12-19 2017-03-15 厦门市市政工程设计院有限公司 A kind of voluntarily axle beam and its method of construction under existing elevated bridge
CN207017132U (en) * 2017-05-23 2018-02-16 中建钢构有限公司 A kind of bicycle expressway

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086126A (en) * 2017-12-19 2018-05-29 厦门市市政建设开发有限公司 Monoblock type bicycle occupation bridge structure and its construction method
CN108301307A (en) * 2017-12-19 2018-07-20 厦门市市政建设开发有限公司 Separation type bicycle occupation bridge structure and its construction method

Similar Documents

Publication Publication Date Title
CN107740350B (en) The bridge pier column construction method and its passing method of full precast bridge Bridge Erector
CN204919245U (en) Overhead bridge in city - mixed transportation systems of sky rail
CN108374296A (en) The construction method of straddle type monorail rail tracks installation
CN204780569U (en) It jumps attachment strap structure of car to reduce abutment
CN109458006A (en) A kind of combined highway and metro integral cast-in-situ frame-type overhead station and its construction method
CN107119549A (en) Bicycle expressway and the construction method that bicycle expressway is set up under BRT
CN108221698A (en) Bridge Erector low level transition engineering method
CN207017132U (en) A kind of bicycle expressway
CN205893824U (en) Stride a formula single track and stride two line track girder systems greatly all
CN104612007A (en) City viaduct tramcar road network passenger transport system
CN110219242A (en) A kind of double-deck construction method of installation for synchronizing beam in beam
CN206530340U (en) A kind of tunnel structure suitable for suspension type monorail
CN107326793B (en) A kind of bicycle high speed is across overpass and its construction method
CN207259937U (en) Bicycle high speed steel box girder
CN207017165U (en) A kind of temporary support for being used to support steel box-girder
CN207775719U (en) A kind of Bridge Erector for setting up full precast beam
CN202214676U (en) Bridge extension device
CN108487291A (en) The installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam
CN208395594U (en) A kind of Traffic Systems
CN107130518A (en) A kind of temporary support and its construction method for being used to support steel box-girder
CN205387646U (en) Aerial rail train's foundation pile roof beam improves structure
CN212477465U (en) Assembled platform
CN208472493U (en) Aerocycle road traffic core
CN207314179U (en) A kind of sound barrier monoblock type rim of a cup mounting structure
CN207503266U (en) A kind of Urban Rail Transit Stations siteselecting planning device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170901