CN108487291A - The installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam - Google Patents

The installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam Download PDF

Info

Publication number
CN108487291A
CN108487291A CN201810246462.XA CN201810246462A CN108487291A CN 108487291 A CN108487291 A CN 108487291A CN 201810246462 A CN201810246462 A CN 201810246462A CN 108487291 A CN108487291 A CN 108487291A
Authority
CN
China
Prior art keywords
upright post
contact net
girder
installation method
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810246462.XA
Other languages
Chinese (zh)
Other versions
CN108487291B (en
Inventor
游励晖
易大伟
余浪
黄毅
许志艳
廖文键
许敏
陈克坚
何庭国
田壮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201810246462.XA priority Critical patent/CN108487291B/en
Publication of CN108487291A publication Critical patent/CN108487291A/en
Application granted granted Critical
Publication of CN108487291B publication Critical patent/CN108487291B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of installation methods of contact net upright post basic on railway steel reinforced concrete bondbeam, including the assembling of support member, lifting and installation, then it embedded bar and is poured at the top of all support members and at the top of girder, completes the installation of upright post basic.It can be convenient for the construction of contact net upright post basic using this method, effectively improve the pouring molding quality of concrete layer, the temporary constructions measure such as template is separately provided in reduction, effectively improve the installation effectiveness and quality of upright post basic, shorten the construction period, facilitate the lifting and installation of follow-up column, advantageously ensure that the verticality and stability of column, avoid down bar and sedimentation, it is not necessary that the reinforcing bar on the bridge floor edge of a wing is encrypted, effectively reduce design strength and difficulty of construction, be conducive to save material, avoid the construction cost that science of bridge building is significantly increased, convenient for the installation site of planning arrangement column, improve the running quality of contact net, promote economy, increase the safety of railway transmission line of electricity.

Description

The installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam
Technical field
The present invention relates to railway steel reinforced concrete bondbeam technical field, more particularly to contact net is vertical on a kind of railway steel reinforced concrete bondbeam The installation method of column foundation.
Background technology
Steel reinforced concrete bondbeam be by steel and two kinds of materials of different nature of concrete it is combined made of a kind of new structure. It is the reasonable combination of two kinds of materials of steel and concrete, has given full play to that steel tensile strength is high, plasticity is good and concrete anti-compression Can good advantage, and the shortcomings that can overcome the disadvantages that each other, therefore in modern bridge structure, steel reinforced concrete bondbeam increasingly becomes bridge hair One of Main way of exhibition.Electric railway in recent years has become the mainstream type of modernized railway, is widely used in high fast In the construction of fast railway and urban track traffic, many non-electrified railways also realize electrified upgrading in succession, wherein connecing Net-fault is one of common two kinds of supply network modes of electric railway, is supplied to electric locomotive as what downline overhead was set up The transmission line of electricity of the special shape of electricity, mainly by contact suspension, support device, positioning device, pillar and a few part groups in basis At.
Existing mainly to have following two modes when contact net basic is arranged on steel reinforced concrete combination bridge, one is designs to exist On bridge pier, construction method is that the embedded bar of bridge pier top cap reinforcing bar and contact net basic has been bound on the cantilever slab of bridge pier, Contact net basic cantilever slab is poured together with bridge pier top cap, while reserving good column built-in bolt sleeve, pre-embedded bolt is installed With sleeve connection, contact net column is made to be connected firmly with basis, the base configuration is simple, but position must be near bridge pier, position It is equipped with limit, since bridge structure stress is complicated and changeable, is not easy to the reasonable layout of column;Another is that design is combined in steel reinforced concrete On the bridge floor flange plate of beam, construction method is the embedded bar of the encryption setting contact net basic on flange plate, by itself and master Beam steel is connected, and then pours the concrete on contact net basic bridge floor flange plate together with concrete on girder, while pre- Column built-in bolt sleeve has been stayed, pre-embedded bolt and sleeve connection are installed, so that contact net column is connected firmly with basis, the basis Although to installation position, there is no restriction, since the weight of column is very heavy, it is necessary to reinforce reinforcing bar on floorings, floorings Relatively thin to cause reinforcing bar overstocked, difficulty of construction is big, higher to construction requirement, and cost is higher, and construction efficiency is relatively low.
Invention content
It is an object of the invention to overcome in the prior art at installing contact net basis on steel reinforced concrete combination bridge, item is limited Part is more, and difficulty of construction is big, and cost is higher, and construction efficiency is relatively low, and the above-mentioned deficiency such as of poor quality provides a kind of railway steel reinforced concrete bondbeam The installation method of upper contact net upright post basic.
To achieve the goals above, the present invention provides following technical schemes:
The installation method of contact net upright post basic, comprises the following steps on a kind of railway steel reinforced concrete bondbeam:
A, support member is made, several sleeves and several WELDING STUDSs are connected at the top of the support member, it is all described Sleeve is arranged around column installation place;
B, all support members are lifted and is connected on girder;
C, embedded bar is set at the top of all support members and at the top of girder, and at the top of the support member and girder Top casting concrete forms reinforced concrete floor, completes the installation of upright post basic.
Specific installation method is first to make support member, and the support member is used to support column, in the support member On be connected and fixed sleeve and WELDING STUDS, the sleeve is for connecting contact net column, therefore around installation site, then by bridge It each needs to install on beam to lift at the position of column and connect the support member, after connection, in all supports Binding embedded bar and casting concrete at the top of component top and girder, the embedded bar being not necessarily in additional encryption support member, And the bed die when support member can be as casting concrete, conveniently pours, and reduces formwork expense, saves template turnover Loss effectively improves pouring molding quality, after forming upright post basic, is mounted on column by the connection of bolt and the sleeve On the upright post basic.
It can be convenient for the construction of contact net upright post basic using this method, effectively improve the pouring molding matter of concrete layer The temporary constructions measure such as template is separately provided in amount, reduction, effectively improves the installation effectiveness and quality of upright post basic, shortens construction work Phase facilitates the lifting and installation of follow-up column, advantageously ensures that the verticality and stability of column, avoids down bar and sedimentation, nothing Reinforcing bar on the bridge floor edge of a wing need to be encrypted, effectively reduce design strength and difficulty of construction, be conducive to save material, keep away Exempt from the construction cost that science of bridge building is significantly increased, convenient for the installation site of planning arrangement column, improve the running quality of contact net, Economy is promoted, the safety of railway transmission line of electricity is increased.
Preferably, also include to assemble the support member, the support member includes top plate, web and bottom in step a Plate, each column lower section are connected at least provided with two webs, the bottom of each web there are one the bottom plate, Top plate described in all web vertical connections, each bottom plate is perpendicular to the corresponding web.
It is further preferred that all top plates, web and bottom plate are steel construction piece, all top plates are welded to connect Girder, all webs and bottom plate are spliced by high-strength bolt and the girder.
It is further preferred that in the step a, several ribbed stiffeners are transversely connected in the top plate bottom.
Using above-mentioned set-up mode, the intensity of upright post basic can be reinforced, effectively stablize support post, further avoid standing Column is crooked or sinks, while ensureing to be stably connected with girder, effectively the stress of contact net is transferred to girder and bridge pier, guarantee Load rationally, uniformly transmits.
Preferably, in the step a, all sleeves and WELDING STUDS are welded to connect the top plate.
It is further preferred that the step a is completed in factory.
Using aforesaid way, be conducive to the molding matter for effectively improving the sleeve and WELDING STUDS welding quality and support member Amount improves construction quality and the safety of upright post basic, reduces pollution, improves efficiency.
Preferably, before the step b, the corresponding position connection of each support member is connected on the girder Stiffener.
Preferably, in the step c, the concrete one at the top of concrete and the girder at the top of the support member Body pours.
Using above-mentioned set-up mode, be conducive to rationally transmit stress, improve underlying strength and stability.
Preferably, the girder is plate girder or steel box-girder or Steel Truss Beam.
In conclusion compared with prior art, the beneficial effects of the invention are as follows:
1, using the installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam of the present invention, can be convenient for connecing The construction of net-fault upright post basic, effectively improves the pouring molding quality of concrete layer, and the temporary constructions such as template are separately provided in reduction Measure effectively improves the installation effectiveness and quality of upright post basic, shortens the construction period, facilitates the lifting and installation of follow-up column, The verticality and stability for advantageously ensuring that column, avoid down bar and sedimentation, it is not necessary that the reinforcing bar on the bridge floor edge of a wing is encrypted Processing effectively reduces design strength and difficulty of construction, is conducive to save material, avoids that being built into for science of bridge building is significantly increased This improves the running quality of contact net convenient for the installation site of planning arrangement column, promotes economy, increases railway power transmission line The safety on road.
2, using the installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam of the present invention, Neng Goujia The intensity of strong upright post basic effectively stablizes support post, and it is crooked or sink to further avoid column, while ensureing steady with girder Fixed connection, is effectively transferred to girder and bridge pier by the stress of contact net, ensures that load rationally, uniformly transmits.
3, using the installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam of the present invention, be conducive to The Forming Quality for effectively improving the sleeve and WELDING STUDS welding quality and support member, improve upright post basic construction quality and Safety reduces pollution, improves efficiency.
4, using the installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam of the present invention, be conducive to Stress is rationally transmitted, underlying strength and stability are improved.
Description of the drawings:
Fig. 1 is the flow chart of the installation method of upright post basic of the present invention;
The schematic diagram of the step of Fig. 2 is the installation method of upright post basic of the present invention one;
Fig. 3 is the side view of Fig. 2;
The schematic diagram of the step of Fig. 4 is the installation method of upright post basic of the present invention two;
The schematic diagram of the step of Fig. 5 is the installation method of upright post basic of the present invention three;
Fig. 6 is the vertical view of Fig. 5.
It is marked in figure:1- columns, 2- girders, 3- concrete layers, 41- top plates, 42- webs, 43- bottom plates, 44- ribbed stiffeners, 5- WELDING STUDSs, 6- stiffeners.
Specific implementation mode
Below in conjunction with the accompanying drawings and specific embodiment the present invention is described in further detail.But this should not be interpreted as to this The range for inventing above-mentioned theme is only limitted to embodiment below, all to belong to the present invention based on the technology that the content of present invention is realized Range.
Embodiment 1
As shown in Figure 1, on a kind of railway steel reinforced concrete bondbeam of the present invention contact net upright post basic installation method, including such as Lower step:
Step 1: making support member, several sleeves and several WELDING STUDSs 5 are connected at the top of the support member, institute There is the sleeve to be arranged around 1 installation place of column;
Step 2: all support members are lifted and are connected on girder 2;
Step 3: embedded bar is set at the top of all support members and at the top of girder 2, and at the top of the support member With 2 top casting concrete of girder, reinforced concrete floor 3 is formed, the installation of upright post basic is completed.
The support member is first assembled, the support member includes top plate 41, web 42 and the bottom plate 43 of steel construction, each It is set below the installation site of the column 1 there are two the web 42, there are one the bottom of each web 42 is welded to connect The bottom plate 43, all 42 vertical weldings of the web connect the top plate 41, and each bottom plate 43 is perpendicular to corresponding institute Web 42 is stated, several sleeves and several WELDING STUDSs 5 are then welded to connect in the support member, at 41 bottom of the top plate Portion transversely connects several ribbed stiffeners 44, and all sleeves are arranged around 1 installation place of column, as Figure 2-3, institute The welding of the making and sleeve and WELDING STUDS 5 that have the support member is completed in factory, then transports engineering site to, described The corresponding position that each support member is connected on girder 2 connects stiffener 6, then lifts all support members Spliced to each installation site with the girder 2, all top plates 41 are welded to connect girder 2, all webs 42 Spliced by high-strength bolt and the girder 2 with bottom plate 43, as shown in figure 4, then at the top of all support members and main The top of beam 2 binds embedded bar, and at the top of the support member and 2 top casting concrete of girder, the support member top The concrete formed by integrally casting at 2 top of the concrete in portion and the girder, forms reinforced concrete floor 3, completes the peace of upright post basic Dress, as seen in figs. 5-6.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement etc., should all be included in the protection scope of the present invention made by within refreshing and principle.

Claims (9)

1. the installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam, which is characterized in that comprise the following steps:
A, support member is made, several sleeves and several WELDING STUDSs (5) are connected at the top of the support member, Suo Yousuo Sleeve is stated around column (1) installation place to be arranged;
B, all support members are lifted and is connected on girder (2);
C, at the top of all support members and girder (2) at the top of be arranged embedded bar, and at the top of the support member and Casting concrete at the top of girder (2) forms reinforced concrete floor (3), completes the installation of upright post basic.
2. the installation method of contact net upright post basic according to claim 1, which is characterized in that in step a, also include The support member is assembled, the support member includes top plate (41), web (42) and bottom plate (43), each column (1) Lower section is at least provided with two webs (42), and there are one the bottom plate (43), institutes for the bottom connection of each web (42) There is top plate (41) described in the web (42) vertical connection, each bottom plate (43) is perpendicular to the corresponding web (42).
3. the installation method of contact net upright post basic according to claim 2, which is characterized in that all top plates (41), web (42) and bottom plate (43) are steel construction piece, and all top plates (41) are welded to connect girder (2), all described Web (42) and bottom plate (43) are spliced by high-strength bolt and the girder (2).
4. the installation method of contact net upright post basic according to claim 2, which is characterized in that in the step a, Top plate (41) bottom transversely connects several ribbed stiffeners (44).
5. according to the installation method of any contact net upright post basics of claim 1-4, which is characterized in that in the step In a, all sleeves and WELDING STUDS (5) are welded to connect the top plate (41).
6. the installation method of contact net upright post basic according to claim 5, which is characterized in that the step a is in factory It completes.
7. according to the installation method of any contact net upright post basics of claim 1-4, which is characterized in that in the step Before b, the corresponding position connection stiffener (6) of each support member is connected on the girder (2).
8. according to the installation method of any contact net upright post basics of claim 1-4, which is characterized in that in the step In c, the concrete formed by integrally casting at the top of concrete and the girder (2) at the top of the support member.
9. according to the installation method of any contact net upright post basics of claim 1-4, which is characterized in that the girder (2) it is plate girder or steel box-girder or Steel Truss Beam.
CN201810246462.XA 2018-03-23 2018-03-23 Installation method of contact net stand column foundation on railway steel-concrete composite beam Active CN108487291B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810246462.XA CN108487291B (en) 2018-03-23 2018-03-23 Installation method of contact net stand column foundation on railway steel-concrete composite beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810246462.XA CN108487291B (en) 2018-03-23 2018-03-23 Installation method of contact net stand column foundation on railway steel-concrete composite beam

Publications (2)

Publication Number Publication Date
CN108487291A true CN108487291A (en) 2018-09-04
CN108487291B CN108487291B (en) 2020-07-28

Family

ID=63319522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810246462.XA Active CN108487291B (en) 2018-03-23 2018-03-23 Installation method of contact net stand column foundation on railway steel-concrete composite beam

Country Status (1)

Country Link
CN (1) CN108487291B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343405A (en) * 2020-10-13 2021-02-09 中铁十九局集团第二工程有限公司 Construction method for high-speed railway bridge contact net foundation
CN113502755A (en) * 2021-08-13 2021-10-15 成都建工路桥建设有限公司 Construction method of steel-concrete composite beam flange plate

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007120051A (en) * 2005-10-26 2007-05-17 Dps Bridge Works Co Ltd Composite beam structure made of steel and concrete using composite floor slab and construction method for bridge girder having this structure
CN105735101A (en) * 2016-05-11 2016-07-06 石家庄铁道大学 High-speed railway rush repair beam capable of being converted into permanent bridge structure, and rush repair method of high-speed railway rush repair beam
CN107354857A (en) * 2017-08-30 2017-11-17 中铁工程设计咨询集团有限公司 A kind of high-speed railway repairing combined box beam and its assemble method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007120051A (en) * 2005-10-26 2007-05-17 Dps Bridge Works Co Ltd Composite beam structure made of steel and concrete using composite floor slab and construction method for bridge girder having this structure
CN105735101A (en) * 2016-05-11 2016-07-06 石家庄铁道大学 High-speed railway rush repair beam capable of being converted into permanent bridge structure, and rush repair method of high-speed railway rush repair beam
CN107354857A (en) * 2017-08-30 2017-11-17 中铁工程设计咨询集团有限公司 A kind of high-speed railway repairing combined box beam and its assemble method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
龙亮: "高铁大跨度单T刚构加劲钢析组合梁硏究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343405A (en) * 2020-10-13 2021-02-09 中铁十九局集团第二工程有限公司 Construction method for high-speed railway bridge contact net foundation
CN113502755A (en) * 2021-08-13 2021-10-15 成都建工路桥建设有限公司 Construction method of steel-concrete composite beam flange plate

Also Published As

Publication number Publication date
CN108487291B (en) 2020-07-28

Similar Documents

Publication Publication Date Title
CN106638304B (en) UHPC- normal concretes lamination composite deck plate structure and its construction method
CN108331158A (en) A kind of joint connection in site method of precast reinforced concrete beam column
CN104988844B (en) Two times tensioning prestressing force assembled Wavelike steel webplate combination beam
CN104294748B (en) A kind of hybrid beam cable-stayed bridge adapter section structure and construction method thereof
CN103938549B (en) The construction method of the oblique web combination beam of assembled waveform steel
CN102767141A (en) Construction method for huge capping beam utilizing reinforced concrete thin wall as permanent formwork
CN209260531U (en) The dual deck bridge of motor vehicle and non-motor vehicle layering circulation
CN113279324A (en) Semi-prefabricated UHPC-NC combined cover beam connecting structure and assembling method
CN208235312U (en) Precast segment assembly bridge pier
CN106976157A (en) A kind of post stretching precast beam pedestal for being applicable different length and cross sectional shape
CN108222051A (en) A kind of contact net upright post basic of railway steel reinforced concrete bondbeam and steel reinforced concrete combination bridge
CN105133486A (en) Corrugated steel web few-main-beam structure
CN109958049A (en) A kind of modularization steel-is mixed to combine small box girder freely-supported continuous bridge and its construction method
CN106087711A (en) Antinode work beam-steel concrete top board-external prestressing combines T-shaped simply supported beam
CN206438380U (en) The long overhanging crossbeam bridge structure of one kind
CN108487291A (en) The installation method of contact net upright post basic on a kind of railway steel reinforced concrete bondbeam
CN206109960U (en) Steel that can be under construction fast concrete integrated configuration bridge
CN102286932B (en) Construction method for off-site assembling and automatic mounting on bridge of mobile mould bridge abutment
CN106436591B (en) A kind of steel cantilever combined bridge deck widens reconstruction structure and its construction method
CN205257790U (en) Fixed high -low leg handle portal crane
CN205934687U (en) Antinode worker roof beam - steel concrete roof - external prestress combination T type simple beam
CN206655141U (en) A kind of steel cantilever combined bridge deck widens reconstruction structure
CN208702215U (en) Overhead station
CN104032862B (en) Assembled girder steel seam line L shape mixing coupled wall and construction method thereof
CN204112200U (en) Edge of a wing enhanced waveform steel web plate composite box girder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant