CN107061867A - A kind of reinforced concrete drainage pipe is rested the head on pipe - Google Patents

A kind of reinforced concrete drainage pipe is rested the head on pipe Download PDF

Info

Publication number
CN107061867A
CN107061867A CN201710244954.0A CN201710244954A CN107061867A CN 107061867 A CN107061867 A CN 107061867A CN 201710244954 A CN201710244954 A CN 201710244954A CN 107061867 A CN107061867 A CN 107061867A
Authority
CN
China
Prior art keywords
side plate
groove
pipe
pillow
head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710244954.0A
Other languages
Chinese (zh)
Inventor
王咬齐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuancheng Municipal Construction Group Co Ltd
Original Assignee
Xuancheng Municipal Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuancheng Municipal Construction Group Co Ltd filed Critical Xuancheng Municipal Construction Group Co Ltd
Priority to CN201710244954.0A priority Critical patent/CN107061867A/en
Publication of CN107061867A publication Critical patent/CN107061867A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L3/00Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
    • F16L3/02Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets partly surrounding the pipes, cables or protective tubing

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Sink And Installation For Waste Water (AREA)
  • Sewage (AREA)

Abstract

The present invention proposes a kind of reinforced concrete drainage pipe and rested the head on pipe, including the pillow in frame structure, pillow includes the first side plate, the second side plate, the 3rd side plate, the 4th side plate of head and the tail connection successively, first side plate and the 3rd side plate are positioned opposite, second side plate and the 4th side plate are positioned opposite, and the first side plate, the upper surface of the 3rd side plate are respectively provided with the first groove of pipe laying, the second groove.Pipe pillow is placed on the ground of the groove dug by the present invention, and then pipeline is placed in the bearing plate of pipe pillow, convenient and swift, ensure that the elevation and straight cis degree of pipeline, reduces labor intensity, reduces the construction period, improves construction quality and construction production safety;By setting the first bar-shaped trough, the second bar-shaped trough, pipeline is applied to pressure dissipation on bearing plate in the first side plate, the 3rd side plate both sides, pipe pillow weight capacity is improved, extends its service life;Pillow uses frame structure, saves material, saves labour cost, reduces pillow weight.

Description

A kind of reinforced concrete drainage pipe is rested the head on pipe
Technical field
Rested the head on the present invention relates to municipal works technical field, more particularly to a kind of reinforced concrete drainage pipe with pipe.
Background technology
Buried at present in outdoor in the installation practice of municipal various pipes, in order to prevent pipeline operationally due to producing bending Stress is excessive and occurs interface destruction, and because part makes sending out for the rough sledding such as tube wall rupture by big bear power It is raw, so must have good foundation support below pipeline.General from concrete duct basis in current engineering, it is The thick plain concrete or blotter of certain thickness is laid in the pipe trench bottom for meeting design bearing capacity requirement, bed course intensity reaches After installation requirement, the assembling reinforcement on bed course, installation form, joints cement concrete makes flat base, and the flat base of precast concrete is needed Conserved, then form removal, fixed a drainpipe.But above-mentioned Guan Ji is only applicable to the preferable region of foundation bearing capacity, And in pipe laying, the elevation and straight cis degree of pipeline are also difficult to control to so that construction is complicated.
The content of the invention
Based on technical problem present in background technology, the present invention proposes a kind of reinforced concrete drainage pipe pipe Pillow.
A kind of reinforced concrete drainage pipe proposed by the present invention is rested the head on pipe, including pillow in frame structure and is used for The bearing plate of pipe laying, pillow includes the first side plate, the second side plate, the 3rd side plate, the 4th side plate of head and the tail connection successively, the Side plate and the 3rd side plate are positioned opposite, and the second side plate and the 4th side plate are positioned opposite, the first side plate, the upper surface of the 3rd side plate It is respectively equipped with the groove of shape identical first, the second groove;The shape of bearing plate is adapted with the first groove, the second groove, and Bearing plate bottom two ends are separately fixed at the first groove, in the second groove.
It is preferred that, the first groove, the second groove are curved, and the central angle corresponding to the first groove and the second groove institute Corresponding central angle is equal.
It is preferred that, the first groove, the second groove are V-shaped, and the V-arrangement opening angle and the V of the second groove of the first groove Shape opening angle is equal.
It is preferred that, the first groove medium position is located on the first side plate and is provided with the first bar-shaped trough extended downwardly.
It is preferred that, the second groove medium position is located on the 3rd side plate and is provided with the second bar-shaped trough extended downwardly.
It is preferred that, the first side plate, the second side plate, the 3rd side plate, the 4th side plate are integrally formed.
It is preferred that, pillow is made of armored concrete.
It is preferred that, by multiple link of boards between the first side plate and the 3rd side plate, and the upper surface of gusset is not higher by One groove, the second groove.
It is preferred that, bearing plate uses steel plate.
It is preferred that, slip-resistant texture is distributed with away from pillow one side in bearing plate.
In the present invention, pillow is formed by the first side plate, the second side plate, the 3rd side plate, the 4th side plate of head and the tail connection successively, First side plate, the upper surface of the 3rd side plate are respectively equipped with the present groove of identical first, the second groove, the shape of bearing plate and the One groove, the second groove are adapted, and bearing plate bottom two ends are separately fixed at the first groove, in the second groove;In use, will Pipe pillow is placed on the ground of the groove dug, and then pipeline is placed in the bearing plate of pipe pillow, convenient and swift, ensure that The elevation and straight cis degree of pipeline, reduce labor intensity, reduce the construction period, improve construction quality and construction production safety;Pass through First bar-shaped trough, the second bar-shaped trough are set, pipeline is applied to pressure dissipation on bearing plate in the first side plate, the 3rd side plate two Side, improves the weight capacity of pipe pillow, extends its service life;Pillow uses frame structure, saves material, saves labour cost, Pillow weight is reduced, convenient construction reduces environmental pollution;By multiple link of boards between the first side plate and the 3rd side plate, Gusset can share the first side plate, the pressure on the second side plate, improve the first side plate, the weight capacity of the second side plate, extension tube The service life of pillow.
Brief description of the drawings
Fig. 1 is the structural representation that a kind of reinforced concrete drainage pipe that embodiment one is proposed is rested the head on pipe;
Fig. 2 is the structural representation of pillow during a kind of reinforced concrete drainage pipe that embodiment one is proposed is rested the head on pipe;
Fig. 3 is to rest the head on pipeline in the method for laying pipeline using the pipe of embodiment one to be placed in the schematic diagram on pipe pillow;
Fig. 4 is the structural representation that a kind of reinforced concrete drainage pipe that embodiment two is proposed is rested the head on pipe;
Fig. 5 is the structural representation of pillow during a kind of reinforced concrete drainage pipe that embodiment two is proposed is rested the head on pipe;
Fig. 6 is to rest the head on pipeline in the method for laying pipeline using the pipe of embodiment two to be placed in the schematic diagram on pipe pillow.
Embodiment
Embodiment one
Reference picture 1, Fig. 2, Fig. 3, the present invention propose that a kind of reinforced concrete drainage pipe is rested the head on pipe, including in frame structure Pillow 1 and be made for the pillow 1 of bearing plate 2. of pipe laying of armored concrete, pillow 1 includes from beginning to end connecting successively The first side plate 11, the second side plate 12, the 3rd side plate 13, the 4th side plate 14 connect, the first side plate 11, the second side plate 12, the 3rd side Plate 13, the 4th side plate 14 are integrally formed, and the first side plate 11 and the 3rd side plate 13 are positioned opposite, the second side plate 12 and the 4th side plate 14 It is positioned opposite.First side plate 11, the upper surface of the 3rd side plate 13 are respectively provided with the first groove 111, second of pipe laying Groove 131;First groove 111, the second groove 131 are curved, and central angle and the second groove corresponding to the first groove 111 Central angle corresponding to 131 is equal, is connected between the first side plate 11 and the 3rd side plate 13 by multiple gussets 15, and gusset 15 Upper surface is not higher by the first groove 111, the second groove 131.On first side plate 11 be located at the medium position of the first groove 111 be provided with to First bar-shaped trough 112 of lower extension;It is located at the medium position of the second groove 131 on 3rd side plate 13 and is provided with the Article 2 extended downwardly Shape groove 132.Bearing plate 2 is curved and bearing plate 2 corresponding to central angle and the first groove 111, the second groove 131 corresponding to Central angle is equal, and the bottom two ends of bearing plate 2 are separately mounted to the first groove 111, in the second groove 131;In the present embodiment, load-bearing Plate 2 is using steel plate and bearing plate 2 away from slip-resistant texture 21 is distributed with the one side of pillow 1.
Embodiment two
Reference picture 4, Fig. 5, Fig. 6, the present invention propose that a kind of reinforced concrete drainage pipe is rested the head on pipe, including in frame structure Pillow 1 and bearing plate 2 for pipe laying.Pillow 1 is made of armored concrete, and pillow 1 includes from beginning to end connecting successively The first side plate 11, the second side plate 12, the 3rd side plate 13, the 4th side plate 14 connect, the first side plate 11, the second side plate 12, the 3rd side Plate 13, the 4th side plate 14 are integrally formed, and the first side plate 11 and the 3rd side plate 13 are positioned opposite, the second side plate 12 and the 4th side plate 14 It is positioned opposite.First side plate 11, the upper surface of the 3rd side plate 13 are respectively provided with the first groove 111, second of pipe laying Groove 131, the first groove 111, the second groove 131 are V-shaped, and the V-arrangement opening angle and the second groove of the first groove 111 131 V-arrangement opening angle is equal, is connected between the first side plate 11 and the 3rd side plate 13 by multiple gussets 15, and gusset 15 Upper surface is not higher by the first groove 111, the second groove 131.On first side plate 11 be located at the medium position of the first groove 111 be provided with to First bar-shaped trough 112 of lower extension;It is located at the medium position of the second groove 131 on 3rd side plate 13 and is provided with the Article 2 extended downwardly Shape groove 132.Bearing plate 2 is V-shaped and V-arrangement opening angle of bearing plate 2 and the first groove 111, the V-arrangement opening of the second groove 131 Angle is equal, and the bottom two ends of bearing plate 2 are separately mounted to the first groove 111, in the second groove 131;In the present embodiment, bearing plate 2 using steel plates and bearing plate 2 away from slip-resistant texture 21 is distributed with the one side of pillow 1.
A kind of reinforced concrete drainage pipe proposed by the present invention is rested the head on pipe, in use, pipe to be rested the head on to the ditch for being placed in and digging On the ground of groove, then pipeline 3 is placed in the bearing plate 2 of pipe pillow, slip-resistant texture 21 can prevent from managing when pipeline 3 is installed Road 3 skids, convenient and swift, ensure that the elevation and straight cis degree of pipeline, reduces labor intensity, reduces the construction period, improves work Cheng Zhiliang and construction production safety;By setting the first bar-shaped trough 112, the second bar-shaped trough 132, pipeline 2 is applied to bearing plate 2 On pressure dissipation connected in the first side plate 11, the both sides of the 3rd side plate 13, and in the first side plate 11, the 3rd side plate 13 by gusset 15 Connect, gusset 15 can share the first side plate 11, the pressure on the second side plate 13, can effectively improve the weight capacity of pipe pillow, prolong Long its pipe pillow service life;Pillow uses frame structure, saves material, saves labour cost, reduces the weight of pillow 1, conveniently applies Work, reduces environmental pollution.
The foregoing is only a preferred embodiment of the present invention, but protection scope of the present invention be not limited thereto, Any one skilled in the art the invention discloses technical scope in, technique according to the invention scheme and its Inventive concept is subject to equivalent substitution or change, should all be included within the scope of the present invention.

Claims (10)

1. a kind of reinforced concrete drainage pipe is rested the head on pipe, it is characterised in that including the pillow (1) in frame structure and be used for The bearing plate (2) of pipe laying, pillow (1) includes the first side plate (11) of head and the tail connection, the second side plate (12), the 3rd side successively Plate (13), the 4th side plate (14), the first side plate (11) and the 3rd side plate (13) are positioned opposite, the second side plate (12) and the 4th side plate (14) positioned opposite, the first side plate (11), the upper surface of the 3rd side plate (13) are respectively equipped with the groove of shape identical first (111), the second groove (131);The shape of bearing plate (2) is adapted with the first groove (111), the second groove (131), and load-bearing Plate (2) bottom two ends are separately fixed in the first groove (111), the second groove (131).
2. reinforced concrete drainage pipe according to claim 1 is rested the head on pipe, it is characterised in that the first groove (111), Two grooves (131) are curved, and the center of circle corresponding to the central angle and the second groove (131) corresponding to the first groove (111) Angle is equal.
3. reinforced concrete drainage pipe according to claim 1 is rested the head on pipe, it is characterised in that the first groove (111), Two grooves (131) are V-shaped, and the V-arrangement opening angle phase of the V-arrangement opening angle and the second groove (131) of the first groove (111) Deng.
4. the reinforced concrete drainage pipe according to any one of claim 1-3 is rested the head on pipe, it is characterised in that the first side It is located at the first groove (111) medium position on plate (11) and is provided with the first bar-shaped trough (112) extended downwardly.
5. the reinforced concrete drainage pipe according to any one of claim 1-3 is rested the head on pipe, it is characterised in that the 3rd side It is located at the second groove (131) medium position on plate (13) and is provided with the second bar-shaped trough (132) extended downwardly.
6. the reinforced concrete drainage pipe according to any one of claim 1-3 is rested the head on pipe, it is characterised in that the first side Plate (11), the second side plate (12), the 3rd side plate (13), the 4th side plate (14) are integrally formed.
7. the reinforced concrete drainage pipe according to any one of claim 1-3 is rested the head on pipe, it is characterised in that pillow (1) it is made of armored concrete.
8. the reinforced concrete drainage pipe according to any one of claim 1-3 is rested the head on pipe, it is characterised in that the first side It is connected between plate (11) and the 3rd side plate (13) by multiple gussets (15), and the upper surface of gusset (15) is not higher by the first groove (111), the second groove (131).
9. the reinforced concrete drainage pipe according to any one of claim 1-3 is rested the head on pipe, it is characterised in that bearing plate (2) steel plate is used.
10. the reinforced concrete drainage pipe according to any one of claim 1-3 is rested the head on pipe, it is characterised in that load-bearing Slip-resistant texture (21) is distributed with away from pillow (1) one side in plate (2).
CN201710244954.0A 2017-04-14 2017-04-14 A kind of reinforced concrete drainage pipe is rested the head on pipe Pending CN107061867A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710244954.0A CN107061867A (en) 2017-04-14 2017-04-14 A kind of reinforced concrete drainage pipe is rested the head on pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710244954.0A CN107061867A (en) 2017-04-14 2017-04-14 A kind of reinforced concrete drainage pipe is rested the head on pipe

Publications (1)

Publication Number Publication Date
CN107061867A true CN107061867A (en) 2017-08-18

Family

ID=59600039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710244954.0A Pending CN107061867A (en) 2017-04-14 2017-04-14 A kind of reinforced concrete drainage pipe is rested the head on pipe

Country Status (1)

Country Link
CN (1) CN107061867A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914569A (en) * 2019-03-27 2019-06-21 宣城市政建设集团有限公司 A kind of cement water-supply-pipe
CN110670698A (en) * 2019-10-17 2020-01-10 三河市恒通水泥构件有限公司 Multifunctional system and intelligent method for repairing defects after concrete forming

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5697021A (en) * 1979-12-29 1981-08-05 Mitsubishi Plastics Ind Ltd Burying method for pipe
CN1294647A (en) * 1999-01-29 2001-05-09 马蒂艾尔专利公司 Pressurized liquid circulation duct and method for prodn. thereof
CN203373772U (en) * 2013-08-01 2014-01-01 上海市城市建设设计研究总院 Foundation structure of reinforced concrete drainage pipeline under condition of soft soil foundation
CN104500842A (en) * 2014-12-08 2015-04-08 北京四方如钢混凝土制品有限公司 Pipe pillow and method of paving pipeline by utilizing pipe pillow
CN104896195A (en) * 2015-05-11 2015-09-09 张雪燕 Hot water pipe support mechanism
CN105020476A (en) * 2015-07-29 2015-11-04 河南中托力合化学有限公司 Support device of oil pipeline
CN105113607A (en) * 2015-08-28 2015-12-02 济南城建集团有限公司 Rainwater pipeline structure and construction method thereof
CN204940330U (en) * 2015-08-28 2016-01-06 苏州同尚工程设计咨询有限公司 A kind of pipeline foundation
CN205171638U (en) * 2015-11-19 2016-04-20 浙江三门市政工程有限公司 Municipal administration drain pipe structure
CN206723595U (en) * 2017-04-14 2017-12-08 宣城市政建设集团有限公司 A kind of reinforced concrete drainage pipe is rested the head on pipe

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5697021A (en) * 1979-12-29 1981-08-05 Mitsubishi Plastics Ind Ltd Burying method for pipe
CN1294647A (en) * 1999-01-29 2001-05-09 马蒂艾尔专利公司 Pressurized liquid circulation duct and method for prodn. thereof
CN203373772U (en) * 2013-08-01 2014-01-01 上海市城市建设设计研究总院 Foundation structure of reinforced concrete drainage pipeline under condition of soft soil foundation
CN104500842A (en) * 2014-12-08 2015-04-08 北京四方如钢混凝土制品有限公司 Pipe pillow and method of paving pipeline by utilizing pipe pillow
CN104896195A (en) * 2015-05-11 2015-09-09 张雪燕 Hot water pipe support mechanism
CN105020476A (en) * 2015-07-29 2015-11-04 河南中托力合化学有限公司 Support device of oil pipeline
CN105113607A (en) * 2015-08-28 2015-12-02 济南城建集团有限公司 Rainwater pipeline structure and construction method thereof
CN204940330U (en) * 2015-08-28 2016-01-06 苏州同尚工程设计咨询有限公司 A kind of pipeline foundation
CN205171638U (en) * 2015-11-19 2016-04-20 浙江三门市政工程有限公司 Municipal administration drain pipe structure
CN206723595U (en) * 2017-04-14 2017-12-08 宣城市政建设集团有限公司 A kind of reinforced concrete drainage pipe is rested the head on pipe

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109914569A (en) * 2019-03-27 2019-06-21 宣城市政建设集团有限公司 A kind of cement water-supply-pipe
CN109914569B (en) * 2019-03-27 2024-01-30 宣城市政建设集团有限公司 Cement water delivery pipe
CN110670698A (en) * 2019-10-17 2020-01-10 三河市恒通水泥构件有限公司 Multifunctional system and intelligent method for repairing defects after concrete forming
CN110670698B (en) * 2019-10-17 2021-07-16 三河市恒通水泥构件有限公司 Multifunctional system and intelligent method for repairing defects after concrete forming

Similar Documents

Publication Publication Date Title
CN103074890B (en) Plastic sleeve and steel pipe combined cast-in-place concrete hollow pipe pile and construction method thereof
CN204491666U (en) A kind of steel corrugated sheet Urban Underground pipe gallery
CN104947709A (en) Pre-assembled single-compartment municipal tunnel and construction method thereof
CN202559224U (en) Masonry arch bridge using lightweight concrete as arch upper packing
CN205530344U (en) Utility tunnel is pour to split type no mould
CN203961012U (en) A kind of prefabricated housing element of construction that is applied to big-and-middle-sized building
CN104695608B (en) Floor construction between architecture pipe and construction method thereof
CN104179249A (en) Assembled composite-structure earthquake-resistant wall and assembly method thereof
CN105401593A (en) Assembly type square underground pipe gallery
CN208586722U (en) Precast concrete assembled piping shaft
CN204825557U (en) Job site interim construction road combination ground structure
CN104631674A (en) Composite floor slab and construction method thereof
CN107061867A (en) A kind of reinforced concrete drainage pipe is rested the head on pipe
CN208168032U (en) Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node
CN214362655U (en) Can have enough to meet need assembled road system
CN107268675A (en) The laying method and structure of a kind of many storehouse underground pipe galleries of combined type
CN206723595U (en) A kind of reinforced concrete drainage pipe is rested the head on pipe
CN105244835A (en) L-shaped concrete cable trench prefabricated component and production technology
CN202247719U (en) Corresponding corrugated pre-stressed anti-sedimentation culvert pipe for bridge
CN205116220U (en) Pour cable pit after assembly of L type precast concrete spare
CN203891071U (en) Road structure of immersed tube tunnels
CN114321494B (en) Municipal pipeline protection structure and construction method thereof
CN203452103U (en) Waterstop
CN202577086U (en) Reinforced concrete precast pavement slab
CN205753309U (en) Prefabricated cable duct

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination