CN106978819B - It is a kind of without fertile slot construct basement barricade - Google Patents
It is a kind of without fertile slot construct basement barricade Download PDFInfo
- Publication number
- CN106978819B CN106978819B CN201710364637.2A CN201710364637A CN106978819B CN 106978819 B CN106978819 B CN 106978819B CN 201710364637 A CN201710364637 A CN 201710364637A CN 106978819 B CN106978819 B CN 106978819B
- Authority
- CN
- China
- Prior art keywords
- wall
- barricade
- basement
- moulding
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0275—Retaining or protecting walls characterised by constructional features cast in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a kind of without fertile slot construction basement barricade, including pouring the basement barricade ontology being arranged on the preset retaining wall foundation of basement foundation ditch earth's surface, basement barricade outer body face is provided with waterproof layer made from waterproof roll, it is characterized in that, waterproof layer foreign minister, which is sticked, is equipped with moulding wall, moulding wall main body obtains for concreting, pours and connects with foundation pit walls on the outside of moulding wall;Also there is vertical inbuilt support pile, being horizontally disposed between support pile and brick wall has welding screw rod, and welding screw rod one end is weldingly fixed in the aperture of support pile, and the welding screw rod other end, which sockets, is fixed on moulding within the walls in soil layer outside foundation pit walls.The advantages that present invention has construction is simple, and short time limit, expense is low, good water-proof effect is particularly suitable for practicing in the construction foundation working of the deeper skyscraper of foundation pit.
Description
Technical field
The invention belongs to building foundation engineering construction fields, and in particular to a kind of without fertile slot construction basement barricade.
Background technique
With the development of economy with the sustainable growth of population, land resource increasingly seems urgent.University is promoted from religion
Educating land used is commercialized land used transition to half Educational Return land used half, therewith it is adjoint be a large amount of comprehensive commercial mansion such as rain after
It has emitted and has come out as spring bamboo.But commercial mansion will not only meet the land for teaching requirement of school, and meet business
The benefit requirement of profit, so commercial mansion addressing generally can all be selected in close city road side, to largely increase
The difficulty of construction, and Deep Foundation Pit construction is more intended to excavate without fertile slot.
Building foundation pit refers to that the outer foundation pit inner wall of building basement exterior wall does not scrape out slope without fertile slot excavation construction method,
And state in a vertical shape, so that the operating space of outer wall of basement and foundation pit crater wall is than narrow building foundation pit construction method.
Traditional basement barricade waterproof construction first realizes that basement barricade (i.e. outer wall of basement) formwork pours, and waits gear
After wall maintenance molding, asphalt water-proof coiled material is pasted on the outside of barricade, then a protective layer is set again, construction foundation working is complete
It is backfilled again after finishing, completes entire construction.But basement barricade and foundation pit supporting system distance caused by thus being excavated without fertile slot
Cross close, it is more difficult that barricade outboard template installs, and waterproof coiled material construction no operatton face is difficult to construct, and institute is so as to the underground that needs one kind new
Room barricade and its construction technology solve problems.
Summary of the invention
In view of the above shortcomings of the prior art, the technical problems to be solved by the present invention are: how to provide a kind of construction letter
Single, short time limit, expense is low, and constructing basement barricade without fertile slot for good water-proof effect is particularly suitable for the deeper skyscraper of foundation pit
Construction foundation working in practice.
In order to solve the above-mentioned technical problem, present invention employs the following technical solutions:
It is a kind of without fertile slot construct basement barricade, including pour be arranged on the preset retaining wall foundation of basement foundation ditch earth's surface
Basement barricade ontology, basement barricade outer body face is provided with waterproof layer made from waterproof roll, which is characterized in that anti-
Water layer foreign minister, which is sticked, is equipped with moulding wall, and moulding wall main body obtains for concreting, pours and connects with foundation pit walls on the outside of moulding wall;
Also there is vertical inbuilt support pile, being horizontally disposed between support pile and brick wall has welding screw rod, welds in soil layer outside foundation pit walls
It connects screw rod one end to be weldingly fixed in the aperture of support pile, the welding screw rod other end, which sockets, is fixed on moulding within the walls.
In this way, waterproof layer is arranged on moulding wall in basement barricade of the invention, it can be using first after setting moulding wall
Realize that waterproof coiled material construction obtains barricade waterproof layer in moulding wall outer surface, barricade waterproof layer is generally by waterproof roll layer and sand
Slurry screed-coat obtains, and then relies on moulding wall and barricade waterproof layer again, and direct single side formwork realizes that basement barricade pours, in this way
The convenience and reliability of construction of waterproof layer are just greatly improved, there is construction is simple, short time limit, expense is low, waterproof effect
Good feature.The welding screw rod wherein used, it is ensured that moulding wall main body pouring construction stability and improve moulding wall knot
Structure intensity.
As optimization, steel plate for sealing water is additionally provided between retaining wall foundation and basement barricade, steel plate for sealing water is kept off along basement
The setting of wall length, steel plate for sealing water lower end are embedded in the middle part of retaining wall foundation, and steel plate for sealing water upper end is poured in basement barricade.Into one
Step ground steel plate for sealing water upper and lower ends are respectively inclined outwardly setting.In this way, leak can be better protected from.
As optimization, moulding wall includes the moulding wall main body that concreting obtains and on the outside of moulding wall main body
Brick wall, welding screw rod outer end, which sockets, to be fixed in brick wall.In this way, the moulding wall being arranged by the way of brick fetal membrane, so that
It is not necessarily to independent formwork when the construction that moulding wall main body pours, facilitates construction, the welding screw rod for socketing setting guarantees to moulding wall master
The construction reliability that body pours.
As optimization, brick wall includes the vertical construction of the multiple tracks that pours setting at interval of 4.5-4.8 meters along wall length direction
Column, and the multilayer collar tie beam of setting is poured along high every 4 meters of wall, masonry standard brick in the region that constructional column and collar tie beam surround;Welding
The outer end of screw rod is poured fixed in collar tie beam or constructional column.In this way, better assuring that the stability and reliability of brick wall itself.
As optimization, the present invention is obtained using construction method below, first in basement foundation ditch crater wall in the construction method
Upper setting moulding wall, moulding wall outer surface and basement barricade outer surface design shape correspond to it is consistent, then outside moulding wall
Side surface carries out waterproof coiled material construction and obtains barricade waterproof layer, is formed on the outside of basement barricade by moulding wall and barricade waterproof layer
Support carries out single side formwork on the inside of the binding of basement barricade reinforcing bar and barricade, completes basement barricade and pours;
Moulding wall is set in basement foundation ditch crater wall using the method for setting brick fetal membrane after-pouring moulding concrete, specific packet
Include following steps:
1) support pile is buried elevationally outward in foundation pit crater wall in advance;
2) surveying setting-out determines the welding screw rod setting position of brick fetal membrane setting position and bar planting;
3) bar planting, the soil layer plane by support pile in face of foundation pit side are opened, drill, will weld on the side surface that support pile exposes
It connects in the vertical implant holes in screw rod inner end and is welded and fixed, the horizontal face support pile in its outer end is made to extend outwardly fixation;
4) use standard brick masonry brick wall in brick fetal membrane setting position, when building in brick wall along wall length direction at interval of
4.5-4.8 meters pour one of vertical constructional column of setting, pour one layer of collar tie beam of setting along high every 4 meters of wall, constructional column and collar tie beam enclose
At region in build standard brick;The outer end of welding screw rod is poured fixed in collar tie beam or constructional column;
5) complete brick wall while, after completing one section of height of wall brick, i.e., the casting concrete in brick wall, wall brick build with
Inner concrete pours interval and carries out, until ultimately forming moulding wall wall base;
6) it is smooth that cement mortar coverage is smeared outside moulding wall wall base, can carry out waterproof coiled material construction.
In this way, having convenient, the high advantage of construction efficiency of constructing.
As optimization, brick wall is 240mm thickness wall brick, with proof strength.As optimization, collar tie beam arrangement of reinforcement is 4 10 steel of Φ
Muscle, stirrup are arranged according to spacing 250mm using 6 steel ring of Φ, are obtained using C20 concreting, to better ensure that intensity.
As optimization, constructional column column section is the square of 240mm × 240mm, uses 4 12 reinforcing bars of Φ for arrangement of reinforcement, is bound round
Muscle is arranged using 6 steel ring of Φ according to spacing 150mm, is obtained using C20 concreting, to better ensure that intensity.
Further, welding screw rod is obtained using 16 screw rod of Φ, can better ensure that supporting intensity and reliability.
As optimization, 4) step and 5) in step, realizes concreting, concrete using concreting distributing system
Pouring cloth system includes the concrete tank car and Vehicle loaded pump for being located at ground on the outside of foundation pit, and the material distributing machine being set in foundation pit, concrete
Tank car discharge port is connected with Vehicle loaded pump, and Vehicle loaded pump discharge pipe is connected by concrete conveyance conduit with the cloth pipeline in material distributing machine;
Material distributing machine includes the steel bracket being mounted vertically in foundation pit and steel bracket upper end can be arranged in steel crossbearer with horizontally rotating, and steel is horizontal
One end of frame is the discharge end that cloth pipeline is arranged, and cloth pipeline front end is connected with the pumping rubber vomit pipe extended downwardly, cloth
Pipe material rear end is arranged downwards along steel bracket and is connected with concrete conveyance conduit.
In this way, the concreting distributing system combined using concrete tank car and Vehicle loaded pump and material distributing machine, has knot
Structure is simple, easy to assembly, advantage easy to set up low in cost, greatly improves and pours efficiency and pour operation convenience.
Further, steel crossbearer is the Balance weight end for being provided with clump weight, discharge end distance away from the other end of discharge end
The length of steel bracket is greater than Balance weight end distance steel stent length.In this way, more convenient holding steel bracket balance, improves smooth operation
Property.
Further, steel bracket lower end has bottom support frame extended horizontally outward, and bottom support frame periphery is set
It is equipped with supporting leg straight down, supporting leg lower end has the cushion block being horizontally set in foundation pit, lower section and base in the middle part of the support frame of bottom
The first rubber tyre is provided between hole.In this way, installation and damping can be better ensured that, guarantee stability of strutting system, and avoid
Destruction of the material distributing machine to bottom of foundation ditch base.
Still further, bottom support frame quadrangle has four horizontal extension legs being arranged horizontally outward, the supporting leg is set
It sets below horizontal extension leg front end.In this way, can according to need the position of four each supporting legs of adjustment, keep its installation steady, simultaneously
It can according to need elongation Retractive leg outside as far as possible when installation, better ensure that stability of strutting system.
Further, the lower section that concrete conveyance conduit enters foundation pit corner, which is also padded, is equipped with the second rubber tyre.In this way, second
Rubber tyre can preferably concrete conveyance conduit whereabouts intersegmental part delivering concrete when impact buffered, preferably protection pipe
Road and corresponding bottom of foundation ditch base layer structure.
Further, steel crossbearer rear and front end respectively hangs downwards and is provided with adjustment drawstring.In this way, can be convenient worker
Front and back drawstring is pulled from below, carries out the adjustment rotated left and right to steel crossbearer, and structure is simple and easy to adjust quick, adjusts and stablizes
Property is good.
Further, water-proof concrete can be configured to using waterproof material when wherein concrete configures to be poured, make
Its barricade waterproof layer obtained with waterproof coiled material construction constitutes dual waterproof together, greatlys improve waterproof effect;Configure waterproof
Concrete is realized using water-proof concrete configuration device below, including concrete tank car, is further included an agitator, is set in agitator
It is equipped with a plastic water bag, plastic water bag upper end opening edge is consistent with agitator upper port edge and is connected, and plastic water bag prolongs
Length after exhibition is equal to or higher than agitator depth, and agitator bottom, which is located at below plastic water bag, is provided with electronic weigher, electricity
Sub- weighing apparatus has a horizontally disposed weighing face for being located at the top and the weighing face is located in the middle part of agitator, on agitator
End side is also provided with and communicated with water inlet pipe outward, and water inlet pipe inner end is sealingly connected to inside plastic water bag, is equipped on water inlet pipe
Water inlet switch valve, agitator lower end side are also provided with and communicated with outlet pipe outward, and outlet pipe inner end is sealingly connected to plastic water bag
Inside is provided with effluent switch valve and water pump on outlet pipe, and outlet pipe water outlet is connected to the entrance of agitator tank on concrete tank car.
In this way, open water inlet switch valve in use, effluent switch valve can be closed first, by water inlet pipe to plastic water bag
Interior water inlet closes water inlet switch valve after entering the water of fixed mass by electronic weigher metering, corresponding ratio is then added
In PNC waterproof material to plastic water bag, after mixing evenly, then opens effluent switch valve and water pump and uniformly will be mixed with PNC waterproof
The water of material is directly pumped into agitator tank, and concrete formulation is added and is stirred.In this way, first realizing that PNC is anti-by agitator
It is added directly into concrete drums after the stirring and evenly mixing of water material, ensure that PNC waterproof material is mixed in concrete
Even property and timeliness, the time conditions matching for using it with waterproof material itself, ensure that good waterproof effect.
It further include self- poking arrangement as optimization, self- poking arrangement includes a tripod, and tripod includes circumferential
Upper equally distributed three foot levers, foot lever inner end are fixedly connected with a motor, foot lever length and the matching of agitator radius and foot lever
Outer end under being it is curved for and the clamping of agitator edge bending, motor output end be connected with one extend straight down stir
Axis is mixed, agitating shaft lower end extends to agitator middle and lower part position and the lower end is provided with stirring blade.
In this way, stirring barrel edge can be fixed on by tripod foot lever, so that stirring blade is deep into agitator
Inside drives stirring blade to realize stirring to waterproof material by motor, more convenient and do not improve mixing effect again not
Weight calculation is influenced to weigh.
Be additionally provided with one piece of intermediate plate as optimization, between electronic weigher and plastic water bag, intermediate plate it is horizontally disposed and
Shape is consistent with agitator lumenal cross-section, and there are can slide up and down for intermediate plate between intermediate plate edge and stirring barrel cavity
Gap, intermediate plate upper surface is directly and plastic water bag is affixed setting, the weighing at intermediate plate lower surface middle part and electronic weigher
Face is affixed setting.It can improve and claim preferably by the weight transmitting to electronic weigher of plastic water bag by intermediate plate in this way
Weight accuracy.Further, intermediate plate lower surface is provided with one layer of elastic rubber material, in this way can preferably and electronics
The weighing face of weighing apparatus fits, and keeps its weighing accurate.
As optimization, electronic weigher has the display screen for being located at side, on the agitator side of display screen face
It is provided with watch window.In this way, being conducive to reading.
As optimization, realized on the inside of barricade after carrying out the binding of basement barricade reinforcing bar using sizing truss mould plate support system
Single side formwork,
The sizing truss mould plate support system includes vertically arranged barricade template, horizontal interval cloth on the outside of barricade template
Several vertical back cords are equipped with, arranged for interval has several lateral back cords, horizontal interval on the outside of lateral back cord to vertical back cord elevationally outward
If being provided with dry setting truss, the whole at right angles triangle of a sizing truss and right-angle side is mutually leaned on foundation pit ground, another
Right-angle side is mutually leaned on lateral back cord, further includes several single wire drawing bars, single wire drawing bar is horizontally disposed and inner end is weldingly fixed on barricade
In the barricade steel mesh bundled on the inside of template, outer end is fixed to be socketed on sizing truss.
In this way, sizing truss is prefabricated triangular framing knot using sizing truss as barricade template outside-supporting
Structure realizes the compression to back cord by single wire drawing bar, and then compresses support shuttering, therefore can be realized Fast Installation and guarantee to mould
The stability of strutting system of plate.
As optimization, the vertical back cord is that packet batten obtains in vertically arranged several shaped steels, batten side face
To and be fitted in barricade template outer surface.
In this way, the batten and barricade template outer surface on the inside of vertical back cord can be preferably bonded power transmission, improves and stablize
Property, several shaped steels in outside and lateral back cord contact the transmitting raising reliability that can preferably bear support force.
Further, lateral back cord is that the double flute steel back that the channel steel being arranged in pairs connects along its length is stupefied, in pairs
The channel steel length direction junction of setting is provided with the bloom being adjacent between two pairs of channel steels being mutually connected, and wears by steel pin
The connecting hole crossed on channel steel and bloom realizes connection;Bloom thickness is greater than single wire drawing shank diameter, and single wire drawing bar is arranged in double flute steel
Between the pairs of channel steel of back cord.In this way, the intensity of lateral back cord can be better ensured that, and facilitates and improve single wire drawing bar connection
The reliability of stability and force.
Further, single wire drawing bar outer end sockets on sizing truss by the way that truss fixed structure is fixed, truss fixed knot
Structure includes a round steel hanging part, has a through-hole passed through for single wire drawing bar in the middle part of round steel hanging part, on round steel hanging part
Lower both ends respectively have an outwardly extending hitching arm, and mounting facies medialis brachii is that arc and respective stress is socketed a purlin
Frame, which is socketed, is arranged on each sizing truss and transmits single wire drawing bar to sizing purlin on round steel, truss sockets to be extended transversely through with round steel
The pulling force of frame, is screwed on single wire drawing bar on the outside of round steel hanging part and the locking screw of the external screw thread cooperation of single wire drawing bar outer end
It is female.Further, the locking nut is arranged side by side two, and the abutting that can mutually be screwed on is realized locked.
In this way, facilitating the quick connection installation of single wire drawing bar and truss of being formed and stablizing force, truss is socketed with round steel also
It can make the entirety that common stress is constituted between each sizing truss, preferably raising stability.
As optimization, the sizing truss includes underlying surrounding whole right-angled trapezium in a rectangular trapezoid by steel bar
Lower frame is connected to above right-angled trapezium lower frame and surrounds frame on whole at right angles triangle, right angled triangle by steel bar
The vertical edge on the inside of vertical edge and right-angled trapezium lower frame on the inside of upper frame is located at same perpendicular, on right angled triangle outside frame
The bevel edge of side and the bevel edge on the outside of right-angled trapezium lower frame are located at same oblique plane;Right-angled trapezium lower frame upper surface institute is in place
It is bolted and fixed after the steel bar fitting of frame lower surface position on the steel bar and right angled triangle set.
In this way, sizing truss splices to obtain using two frames, the decomposition transport and spelling of the truss that more convenient can be formed
Installation is connect, and quick and easy for installation.
Further, the steel bar upper end of frame vertical edge position upwardly extends to form stage+module on right angled triangle
Portion, to being externally connected with the platform frame for surrounding rectangular triangle by steel bar, platform frame on the outside of stage+module portion
Upper surface is horizontally disposed steel bar and constitutes people's row platform after being used to be laid with support plate.In this way, can be flat with more convenient people's row
Platform sets up installation, carries out on people's row platform conducive to worker and the operation such as pours.
Further, platform frame outer end, which is fixed up, is connected with Terrace prevention bar.In this way, when setting up, it can
To set safety net by the drawing of Terrace prevention bar, with the safety of guarantor's row platform.
Further, reinforcement steel bar arranged in a crossed manner is also fixedly connected with inside right-angled trapezium lower frame.Further mention
The stability of high right-angled trapezium lower frame.
Further, the reinforcement that lower portion is additionally provided with that both ends are fixedly connected between each side on right angled triangle is used
Steel bar.Further increase the stability of frame on right angled triangle.
Further, steel bar upper position where frame bevel edge is additionally provided with lifting lug on right angled triangle, when installing in this way
The docking that right angled triangle upper ledge and right-angled trapezium lower frame can be first completed under foundation pit ground level state is fixed, then again
Sizing truss pull-up state in a vertical shape is completed into installation by lifting lug lifting, improves the convenience of in-site installation construction.
Further, on right-angled trapezium lower frame and right angled triangle the respective bevel edge of frame the fixed connection outward in outside
There is one section of support fashioned iron, support fashioned iron is used to shelve the connection that lateral truss joint steel pipe realizes each sizing truss.In this way, can
Each sizing truss is connected to become a common stress entirety to facilitate, guarantees the stability and reliability of single side formwork.
Further, also there is the lower margin spiral shell of perforation setting upwards at the steel bar outer end where right-angled trapezium lower frame bottom edge
Bolt connecting hole, foundation bolt connecting hole is used for and the vertical pre-buried foundation bolt in foundation pit ground is cooperatively connected.Sizing is achieved
Positioning and fixation on the outside of when truss installa-tion improve installation convenience and guarantee that supporting & stablizing is reliable.
Further, it is additionally provided with anchor pole link block at the interior angle of right-angled trapezium lower frame bottom edge, be arranged on anchor pole link block
There is anchor pole connecting hole, the also oblique outer lower side in steel bar lower end on the inside of right-angled trapezium lower frame where vertical edge is provided through anchor pole and wears
Hole, anchor perforation face anchor pole connecting hole are arranged and socket for fixation after running through for the oblique pre-buried embedded anchor bar in foundation pit ground
On anchor pole link block.
In this way, provide oblique pulling force by embedded anchor bar after facilitating installation, better ensure that the support of sizing truss unilateral side by
Dynamic balance further increases the stability and reliability of support.
After basement barricade is poured and conserved, sizing truss and barricade template is removed, cuts off single wire drawing bar, pre-buried
Basement Retaining wall is completed in foundation bolt and the extra exposed part of embedded anchor bar.
In conclusion the advantages that present invention has construction is simple, and short time limit, expense is low, good water-proof effect, is particularly suitable for base
It cheats and is practiced in the construction foundation working of deeper skyscraper.
Detailed description of the invention
Fig. 1 is the schematic diagram of obtained basement barrier wall structure in specific embodiment.
Fig. 2 is the structure schematic diagram of the concreting distributing system of use in specific embodiment.
Fig. 3 is the amplified structural schematic diagram of independent material distributing machine in the concreting distributing system of Fig. 2.
Fig. 4 is the structural schematic diagram of unillustrated concrete configuration device in the concreting distributing system of Fig. 2.
Fig. 5 is that moulding wall is arranged in basement foundation ditch crater wall and is made using setting brick fetal membrane after-pouring in specific embodiment
The moulding wall formwork erecting structure schematic diagram that the method for type concrete obtains.
Fig. 6 is the structural schematic diagram of Fig. 5 right view direction.
Fig. 7 is the structural schematic diagram in one support pile horizontal distance of Fig. 5 overlook direction.
Fig. 8 is the structural representation sketch of the sizing truss mould plate support system of use in specific embodiment.
Fig. 9 is the stupefied junction partial structurtes of double flute steel back in lateral back cord in Fig. 8 on the outside of barricade template, after component decomposes
Schematic perspective view.
Specific embodiment
The present invention is described in further detail with attached drawing With reference to embodiment.
Specific embodiment:
Fig. 1 is participated in, it is a kind of without fertile slot construction basement barricade, including pour and be arranged in the preset gear of basement foundation ditch earth's surface
Basement barricade ontology 2 in foundation of wall, 2 lateral surface of basement barricade ontology are provided with waterproof layer 3 made from waterproof roll,
Feature is that 3 foreign minister of waterproof layer, which is sticked, is equipped with moulding wall, and moulding wall main body obtains for concreting, moulding wall outside and base
Crater wall, which pours, to connect;Also there is vertical inbuilt support pile 8, level is set between support pile 8 and brick wall in soil layer 7 outside foundation pit walls
It is equipped with welding screw rod 9, welding 9 one end of screw rod is weldingly fixed in the aperture of support pile 8, and welding 9 other end of screw rod sockets fixation
Moulding within the walls.
In this way, above structure first can realize that waterproof coiled material construction obtains in moulding wall outer surface using after setting moulding wall
To barricade waterproof layer, barricade waterproof layer is generally obtained by waterproof roll layer and mortar levelling layer, then relies on moulding wall and gear again
Wall waterproof layer, direct single side formwork realize that basement barricade pours, thus greatly improve the convenience of construction of waterproof layer
And reliability, with the characteristics of construction is simple, short time limit, expense is low, good water-proof effect.
Wherein, steel plate for sealing water 4 is additionally provided between retaining wall foundation 1 and basement barricade ontology 2, steel plate for sealing water 4 is along underground
The setting of room barricade length, 4 lower end of steel plate for sealing water are embedded in the middle part of retaining wall foundation, and steel plate for sealing water upper end is poured in basement barricade
It is interior.Further 4 upper and lower ends of steel plate for sealing water are respectively inclined outwardly setting.In this way, leak can be better protected from.
Wherein, moulding wall includes the moulding wall main body 5 that concreting obtains and the brick positioned at 5 outside of moulding wall main body
Wall 6 also has vertical inbuilt support pile 8 in the soil layer 7 outside foundation pit walls, and being horizontally disposed between support pile 8 and brick wall has welding
Screw rod 9, welding 9 one end of screw rod are weldingly fixed in the aperture of support pile 8, and welding 9 other end of screw rod, which sockets, is fixed on brick wall 6
It is interior.In this way, the moulding wall being arranged by the way of brick fetal membrane so that moulding wall main body pour construction when without individually branch
Mould facilitates construction, and the welding screw rod for socketing setting guarantees the construction reliability poured to moulding wall main body.
Wherein, brick wall 6 includes the vertical constructional column of the multiple tracks that pours setting at interval of 4.5-4.8 meters along wall length direction
10, and the multilayer collar tie beam 11 of setting is poured along high every 4 meters of wall, masonry standard in the region that constructional column 10 and collar tie beam 11 surround
Brick;The outer end of welding screw rod 9 is poured fixed in collar tie beam or constructional column.In this way, better assuring that the stability of brick wall itself
And reliability.
Wherein, brick wall 6 is 240mm thickness wall brick, with proof strength.
Wherein, it is collar tie beam arrangement of reinforcement that 4 10 reinforcing bars of Φ are provided in collar tie beam 11 along rectangular arrangement, is provided with several 6 reinforcing bars of Φ
Circle is arranged to make up collar tie beam stirrup according to spacing 250mm;Collar tie beam pours to obtain using C20 concrete material.It in this way can be preferably
Proof strength.
Wherein, 10 column section of constructional column is the square of 240mm × 240mm, uses 4 12 reinforcing bar rectangles of Φ in constructional column
It is arranged as constructional column arrangement of reinforcement, arranges to form construction column tie-bar according to spacing 150mm using several 6 steel rings of Φ, constructional column uses
C20 concrete material pours to obtain.Intensity can be better ensured that in this way.
Wherein, welding screw rod 9 is obtained using 16 screw rod of Φ, can better ensure that supporting intensity and reliability.
Moulding wall, moulding wall is first arranged when it is implemented, in Retaining wall method in the present invention in basement foundation ditch crater wall
Outer surface corresponds to consistent with basement barricade outer surface design shape and there are the intervals for barricade waterproof layer is arranged, then
Moulding wall outer surface carries out waterproof coiled material construction and obtains barricade waterproof layer, forms basement by moulding wall and barricade waterproof layer
Barricade outside-supporting carries out single side formwork on the inside of the binding of basement barricade reinforcing bar and barricade, completes basement barricade and pours.
Wherein in basement foundation ditch crater wall be arranged moulding wall, using setting brick fetal membrane after-pouring moulding concrete method,
Specifically includes the following steps:
1) support pile is buried elevationally outward in foundation pit crater wall in advance;
2) surveying setting-out determines the welding screw rod setting position of brick fetal membrane setting position and bar planting;
3) bar planting, the soil layer plane by support pile in face of foundation pit side are opened, drill, will weld on the side surface that support pile exposes
It connects in the vertical implant holes in screw rod inner end and is welded and fixed, the horizontal face support pile in its outer end is made to extend outwardly fixation;
4) use standard brick masonry brick wall in brick fetal membrane setting position, when building in brick wall along wall length direction at interval of
4.5-4.8 meters pour one of vertical constructional column of setting, pour one layer of collar tie beam of setting along high every 4 meters of wall, constructional column and collar tie beam enclose
At region in build standard brick;The outer end of welding screw rod is poured fixed in collar tie beam or constructional column;
5) complete brick wall while, after completing one section of height of wall brick, i.e., the casting concrete in brick wall, wall brick build with
Inner concrete pours interval and carries out, until ultimately forming moulding wall wall base;
6) it is smooth that cement mortar coverage, is smeared outside moulding wall wall base, can carry out waterproof coiled material construction.
Wherein, brick wall is 240mm thickness wall brick, with proof strength.As optimization, collar tie beam arrangement of reinforcement is 4 10 reinforcing bars of Φ, hoop
Muscle is arranged using 6 steel ring of Φ according to spacing 250mm, is obtained using C20 concreting, to better ensure that intensity.
Wherein, constructional column column section is the square of 240mm × 240mm, uses 4 12 reinforcing bars of Φ for arrangement of reinforcement, stirrup is adopted
It is arranged, is obtained using C20 concreting, to better ensure that intensity according to spacing 150mm with 6 steel ring of Φ.
Wherein, welding screw rod is obtained using 16 screw rod of Φ, can better ensure that supporting intensity and reliability.
Above-mentioned use is arranged in the method for brick fetal membrane after-pouring moulding concrete, the moulding wall formwork obtained based on brick fetal membrane
Structure as illustrated in figs. 5-7, including the brick fetal membrane constituted by being vertically provided at the brick wall 6 on front side of foundation pit crater wall, its main feature is that foundation pit
Also there is vertical inbuilt support pile 8, being horizontally disposed between support pile 8 and brick wall 6 has welding screw rod 9, weldering in soil layer outside wall
It connects 9 one end of screw rod to be weldingly fixed in the aperture of support pile 8, sockets and socketed and be fixed in brick wall 6 with the welding screw rod other end.This
Sample, the moulding wall being arranged by the way of brick fetal membrane so that moulding wall main body pour construction when without independent formwork, side
Just it constructs, the welding screw rod for socketing setting takes full advantage of support pile as immobilizing foundation, no longer needs to independent formwork, guarantees to making
The construction reliability that type wall main body pours.
Wherein, brick wall 6 includes the vertical constructional column of the multiple tracks that pours setting at interval of 4.5-4.8 meters along wall length direction
10, and the multilayer collar tie beam 11 of setting is poured along high every 4 meters of wall, masonry standard in the region that constructional column 10 and collar tie beam 11 surround
Brick;The outer end of welding screw rod 9 is poured fixed in collar tie beam or constructional column.In this way, better assuring that the stability of brick wall itself
And reliability.
Wherein, brick wall 6 is 240mm thickness wall brick, with proof strength.
Wherein, it is collar tie beam arrangement of reinforcement 61 that 4 10 reinforcing bars of Φ are provided in collar tie beam 11 along rectangular arrangement, is provided with several 6 steel of Φ
Rib ring is arranged to make up collar tie beam stirrup 62 according to spacing 250mm;Collar tie beam pours to obtain using C20 concrete material.It in this way can be more
Proof strength well.
Wherein, 10 column section of constructional column is the square of 240mm × 240mm, uses 4 12 reinforcing bar rectangles of Φ in constructional column
It is arranged as constructional column arrangement of reinforcement 63, arranges to form construction column tie-bar 64, constructional column according to spacing 150mm using several 6 steel rings of Φ
It pours to obtain using C20 concrete material.Intensity can be better ensured that in this way.
Wherein, welding screw rod 9 is obtained using 16 screw rod of Φ, can better ensure that supporting intensity and reliability.
In above embodiment, using concreting distributing system (participate in Fig. 2-Fig. 4) realize concreting (and
Subsequent barricade pours), concreting distributing system includes the concrete tank car 33 and Vehicle loaded pump 34 positioned at ground on the outside of foundation pit, with
And it is set to the material distributing machine in foundation pit, 33 discharge port of concrete tank car is connected with Vehicle loaded pump 34, and Vehicle loaded pump discharge pipe is conveyed by concrete
Pipeline 35 is connected with the cloth pipeline 36 in material distributing machine;Material distributing machine includes the steel bracket 38 being mounted vertically in foundation pit and can be horizontal
It is rotatably arranged at the steel crossbearer 37 of steel bracket upper end, one end of steel crossbearer 37 is the discharge end that cloth pipeline 36 is arranged, cloth
36 front end of pipeline is connected with the pumping rubber vomit pipe 39 extended downwardly, 36 rear end of cloth pipeline arranged downwards along steel bracket and and
Concrete conveyance conduit 35 is connected.
In this way, the concreting distributing system combined using concrete tank car and Vehicle loaded pump and material distributing machine, has knot
Structure is simple, easy to assembly, advantage easy to set up low in cost, greatly improves and pours efficiency and pour operation convenience.
Wherein, steel crossbearer 37 is the Balance weight end for being provided with clump weight 31, discharge end distance away from the other end of discharge end
The length of steel bracket 38 is greater than Balance weight end distance steel stent length.In this way, more convenient holding steel bracket balance, it is flat to improve operation
Stability.
Wherein, 38 lower end of steel bracket has bottom support frame 32 extended horizontally outward, 32 periphery of bottom support frame
It is provided with supporting leg 40 straight down, 40 lower end of supporting leg has a cushion block 41 being horizontally set in foundation pit, in bottom support frame 32
The first rubber tyre 42 is provided between foundation pit below portion.In this way, installation and damping can be better ensured that, guarantee that support is steady
It is qualitative, and avoid destruction of the material distributing machine to bottom of foundation ditch base.
Wherein, there are four horizontal extension legs 43 being arranged horizontally outward 32 4 jiaos of bottom support frame, the supporting leg 40 is set
It sets below 43 front end of horizontal extension leg.In this way, can according to need the position of four each supporting legs of adjustment, keep its installation steady, together
When can according to need elongation Retractive leg outside as far as possible when installing, better ensure that stability of strutting system.
Wherein, the lower section that concrete conveyance conduit enters foundation pit corner, which is also padded, is equipped with the second rubber tyre 44.In this way, the second rubber
Rubber tire tire 44 can preferably concrete conveyance conduit whereabouts intersegmental part delivering concrete when impact buffered, preferably protection pipe
Road and corresponding bottom of foundation ditch base layer structure.
Wherein, steel crossbearer rear and front end respectively hangs downwards and is provided with adjustment drawstring 45.In this way, can be convenient worker from
Lower section pulls front and back drawstring, carries out the adjustment rotated left and right to steel crossbearer, and structure is simple and easy to adjust quick, adjusts stability
It is good.Further, adjustment is additionally provided with pull ring 46 with 45 lower end of drawstring, and worker is facilitated to pull force.
When implementation, can also be configured to water-proof concrete using waterproof material when concrete configures and poured, make itself and
The barricade waterproof layer that waterproof coiled material construction obtains constitutes dual waterproof together, greatlys improve waterproof effect;Configure anti-water coagulation
When native, realized using water-proof concrete configuration device below (participating in Fig. 4), including concrete tank car 33, further include an agitator
47, a plastic water bag 48,48 upper end opening edge of plastic water bag and agitator upper port edge one are provided in agitator 47
It causes and is connected, the length after plastic water bag 48 extends is equal to or higher than 47 depth of agitator, and 47 bottom of agitator is located at plastics water
Bag lower section is provided with electronic weigher 49, and electronic weigher 49 has the horizontally disposed weighing face for being located at the top and should
Weighing face is located in the middle part of agitator, and 47 upper end side of agitator is also provided with and communicated with water inlet pipe 50 outward, and 50 inner end of water inlet pipe is close
Envelope is connected to inside plastic water bag, water inlet switch valve 51 is equipped on water inlet pipe 50,47 lower end side of agitator is also connected to outward
It is provided with outlet pipe 52, outlet pipe inner end is sealingly connected to inside plastic water bag, and effluent switch valve 53 is provided on outlet pipe 52
With water pump 54, outlet pipe water outlet is connected to the entrance of agitator tank on concrete tank car.
In this way, open water inlet switch valve in use, effluent switch valve can be closed first, by water inlet pipe to plastic water bag
Interior water inlet closes water inlet switch valve after entering the water of fixed mass by electronic weigher metering, corresponding ratio is then added
In PNC waterproof material to plastic water bag, after mixing evenly, then opens effluent switch valve and water pump and uniformly will be mixed with PNC waterproof
The water of material is directly pumped into agitator tank, and concrete formulation is added and is stirred.In this way, first realizing that PNC is anti-by agitator
It is added directly into concrete drums after the stirring and evenly mixing of water material, adds cement and sandstone stirring, ensure that concrete
The mixed uniformity of middle PNC waterproof material and timeliness, the time conditions matching for using itself and waterproof material itself, guarantee
Good waterproof effect.
It wherein, further include self- poking arrangement, self- poking arrangement includes a tripod 55, and tripod 55 includes circumferential
Upper equally distributed three foot levers, foot lever inner end are fixedly connected with a motor 56, foot lever length and the matching of agitator radius and foot
Bar outer end under being it is curved for and agitator edge clamping bending, motor output end is connected with one and extends straight down
Agitating shaft 57, agitating shaft lower end extend to agitator middle and lower part position and the lower end are provided with stirring blade 58.
In this way, stirring barrel edge can be fixed on by tripod foot lever, so that stirring blade is deep into agitator
Inside drives stirring blade to realize stirring to waterproof material by motor, more convenient and do not improve mixing effect again not
Weight calculation is influenced to weigh.
Wherein, one piece of intermediate plate 59 is additionally provided between electronic weigher 49 and plastic water bag 48,59 level of intermediate plate is set
It sets and shape is consistent with agitator lumenal cross-section, there are can be on intermediate plate between 59 edge of intermediate plate and stirring barrel cavity
The gap of lower slider, 59 upper surface of intermediate plate is directly and plastic water bag is affixed setting, 59 lower surface of intermediate plate middle part and electronic scale
The weighing face of treasure 49 is affixed setting.It in this way can be preferably by the weight transmitting of plastic water bag to electronic-weighing by intermediate plate
On device, weighing accuracy is improved.Further, 59 lower surface of intermediate plate is provided with one layer of elastic rubber material, in this way can
It is enough preferably to fit with the weighing face of electronic weigher, keep its weighing accurate.
Wherein, electronic weigher 49 has the display screen for being located at side, sets on the agitator side of display screen face
It is equipped with watch window.In this way, being conducive to reading.
The present invention is when it is implemented, can be using sizing truss mould plate support system after carrying out the binding of basement barricade reinforcing bar
Realize single side formwork on the inside of barricade.
The sizing truss mould plate support system (participating in Fig. 8-9) includes vertically arranged barricade template 71, barricade template
71 outsides horizontal interval are disposed with several vertical back cords 72, and arranged for interval has several lateral back cords to vertical back cord 72 elevationally outward
73, if being horizontally spaced about on the outside of lateral back cord 73 has a dry setting truss, the whole at right angles triangle of sizing truss and one it is straight
The arm of angle is mutually leaned on foundation pit ground, another right-angle side is mutually leaned on lateral back cord, further includes several single wire drawing bars 74, single wire drawing bar 74
Horizontally disposed and inner end is weldingly fixed in the barricade steel mesh bundled on the inside of barricade template 71, and fixed socket in outer end is being formed
On truss.
In this way, sizing truss is prefabricated triangular framing knot using sizing truss as barricade template outside-supporting
Structure realizes the compression to back cord by single wire drawing bar, and then compresses support shuttering, therefore can be realized Fast Installation and guarantee to mould
The stability of strutting system of plate.
Wherein, the vertical back cord 72 is that packet batten obtains in vertically arranged several shaped steels, and batten side faces
And it is fitted in barricade template outer surface.
In this way, the batten and barricade template outer surface on the inside of vertical back cord can be preferably bonded power transmission, improves and stablize
Property, several shaped steels in outside and lateral back cord contact the transmitting raising reliability that can preferably bear support force.
Wherein, lateral back cord 73 is that the double flute steel back that the channel steel being arranged in pairs connects along its length is stupefied, is set in pairs
The channel steel length direction junction set is provided with the bloom 75 being adjacent between two pairs of channel steels being mutually connected, by steel pin 76
Connecting hole on channel steel and bloom 75 realizes connection;75 thickness of bloom is greater than single 74 diameter of wire drawing bar, and single wire drawing bar is worn
Between the stupefied pairs of channel steel of double flute steel back.In this way, can be convenient the installation settings of lateral back cord, and better ensure that lateral back
Stupefied intensity, additionally it is possible to facilitate the reliability of the stability and force that improve single wire drawing bar connection.
Wherein, single 74 outer end of wire drawing bar sockets on sizing truss by the way that truss fixed structure is fixed, truss fixed structure
Including a round steel hanging part 77, there is a through-hole passed through for single wire drawing bar 74, round steel mounting in the middle part of round steel hanging part 77
77 upper and lower ends of part respectively have an outwardly extending hitching arm, and mounting facies medialis brachii is that arc and respective stress sockets
One truss, which is socketed, to be arranged on each sizing truss on round steel, truss sockets to be extended transversely through with round steel and is transmitted single wire drawing bar pair
It is formed the pulling force of truss, is screwed on single wire drawing bar on the outside of round steel hanging part and the lock of the external screw thread cooperation of single wire drawing bar outer end
Tight nut.Further, the locking nut is arranged side by side two, and the abutting that can mutually be screwed on is realized locked.
In this way, facilitating the quick connection installation of single wire drawing bar and truss of being formed and stablizing force, truss is socketed with round steel also
It can make the entirety that common stress is constituted between each sizing truss, preferably raising stability.
Wherein, the sizing truss includes underlying surrounding whole right-angled trapezium lower frame in a rectangular trapezoid by steel bar
Frame 78, be connected to 78 top of right-angled trapezium lower frame surrounds frame 79 on whole at right angles triangle, right angle trigonometry by steel bar
Vertical edge in shape on the inside of the vertical edge and right-angled trapezium lower frame of 79 inside of frame is located at same perpendicular, right angled triangle upper ledge
The bevel edge on the outside of bevel edge and right-angled trapezium lower frame on the outside of frame is located at same oblique plane;Right-angled trapezium lower frame upper surface institute
It is bolted and fixed after the steel bar fitting of frame lower surface position on the steel bar and right angled triangle of position.
In this way, sizing truss splices to obtain using two frames, the decomposition transport and spelling of the truss that more convenient can be formed
Installation is connect, and quick and easy for installation.
Wherein, the steel bar upper end of 79 vertical edge position of frame upwardly extends to form stage+module portion on right angled triangle,
To being externally connected with the platform frame 80 for surrounding rectangular triangle by steel bar, platform frame 80 on the outside of stage+module portion
Upper surface is horizontally disposed steel bar and constitutes people's row platform after being used to be laid with support plate.In this way, can be flat with more convenient people's row
Platform sets up installation, carries out on people's row platform conducive to worker and the operation such as pours.
Wherein, 80 outer end of platform frame, which is fixed up, is connected with Terrace prevention bar 81.In this way, when setting up, it can
To set safety net by the drawing of Terrace prevention bar, with the safety of guarantor's row platform.
Wherein, reinforcement steel bar arranged in a crossed manner is also fixedly connected with inside right-angled trapezium lower frame 78.It further increases
The stability of right-angled trapezium lower frame.
Wherein, the reinforcement steel that both ends are fixedly connected between each side is additionally provided on right angled triangle inside frame 79
Item.Further increase the stability of frame on right angled triangle.
Wherein, steel bar upper position where 79 bevel edge of frame is additionally provided with lifting lug 82 on right angled triangle, when installing in this way
The docking that right angled triangle upper ledge and right-angled trapezium lower frame can be first completed under foundation pit ground level state is fixed, then again
Sizing truss pull-up state in a vertical shape is completed into installation by lifting lug lifting, improves the convenience of in-site installation construction.
Wherein, the fixed connection outward in the outside of the respective bevel edge of frame 79 on right-angled trapezium lower frame 78 and right angled triangle
There is one section of support fashioned iron 83, support fashioned iron 83 is used to shelve the connection that lateral truss joint steel pipe 84 realizes each sizing truss.
Each sizing truss is connected to become to a common stress is whole in this way, can be convenient, guarantee single side formwork stability and can
By property.
Wherein, also there is the foundation bolt of perforation setting upwards at the steel bar outer end where 78 bottom edge of right-angled trapezium lower frame
Connecting hole, foundation bolt connecting hole is used for and the vertical pre-buried foundation bolt 85 in foundation pit ground is cooperatively connected.Sizing is achieved
Positioning and fixation on the outside of when truss installa-tion improve installation convenience and guarantee that supporting & stablizing is reliable.
Wherein, it is additionally provided with anchor pole link block 86 at the interior angle of right-angled trapezium lower frame bottom edge, is provided on anchor pole link block
Anchor pole connecting hole, the also oblique outer lower side in steel bar lower end where the vertical edge of right-angled trapezium lower frame inside are provided through anchor pole and wear
Hole, anchor perforation face anchor pole connecting hole are arranged and draw for fixed after running through for the oblique pre-buried embedded anchor bar 87 in foundation pit ground
It connects on anchor pole link block.
In this way, provide oblique pulling force by embedded anchor bar after facilitating installation, better ensure that the support of sizing truss unilateral side by
Dynamic balance further increases the stability and reliability of support.
After basement barricade is poured and conserved, sizing truss and barricade template is removed, cuts off single wire drawing bar, pre-buried
Basement Retaining wall is completed in foundation bolt and the extra exposed part of embedded anchor bar.
Claims (7)
1. it is a kind of without fertile slot construction basement barricade, it is arranged on the preset retaining wall foundation of basement foundation ditch earth's surface including pouring
Basement barricade ontology, basement barricade outer body face are provided with waterproof layer made from waterproof roll, which is characterized in that waterproof
Layer foreign minister, which is sticked, is equipped with moulding wall, and moulding wall main body obtains for concreting, pours and connects with foundation pit walls on the outside of moulding wall;Base
Also there is vertical inbuilt support pile, being horizontally disposed between support pile and moulding wall has welding screw rod, welds in soil layer outside crater wall
It connects screw rod one end to be weldingly fixed in the aperture of support pile, the welding screw rod other end, which sockets, is fixed on moulding within the walls;
Moulding wall includes the moulding wall main body that concreting obtains and the brick wall on the outside of moulding wall main body, welds screw rod
Outer end, which sockets, to be fixed in brick wall;
Brick wall includes the vertical constructional column of the multiple tracks that pours setting at interval of 4.5-4.8 meters along wall length direction, and along wall height
The every 4 meters multilayer collar tie beams for pouring setting build standard brick in the region that constructional column and collar tie beam surround;The outer end of welding screw rod pours
Fixed in collar tie beam or constructional column;
It is obtained using construction method below, moulding wall, moulding wall is first set in basement foundation ditch crater wall in the construction method
Outer surface corresponded to basement barricade outer surface design shape it is consistent, then moulding wall outer surface carry out waterproof roll apply
Work obtains barricade waterproof layer, forms basement barricade outside-supporting by moulding wall and barricade waterproof layer, carries out basement barricade
Single side formwork on the inside of reinforcing bar binding and barricade is completed basement barricade and is poured;
In basement foundation ditch crater wall be arranged moulding wall using setting brick fetal membrane after-pouring moulding concrete method, specifically include with
Lower step:
1) support pile is buried elevationally outward in foundation pit crater wall in advance;
2) surveying setting-out determines the welding screw rod setting position of brick fetal membrane setting position and bar planting;
3) bar planting, the soil layer plane by support pile in face of foundation pit side are opened, are drilled on the side surface that support pile exposes, by welding wire
It in the vertical implant holes in bar inner end and is welded and fixed, the horizontal face support pile in its outer end is made to extend outwardly fixation;
4) standard brick masonry brick wall is used in brick fetal membrane setting position, along wall length direction at interval of 4.5- when building in brick wall
4.8 meters pour one of vertical constructional column of setting, pour one layer of collar tie beam of setting along high every 4 meters of wall, what constructional column and collar tie beam surrounded
Standard brick is built in region;The outer end of welding screw rod is poured fixed in collar tie beam or constructional column;
5) while completing brick wall, after completing one section of height of wall brick, i.e., the casting concrete in brick wall, wall brick is built and inside
Concreting interval carries out, until ultimately forming moulding wall wall base;
6) it is smooth that cement mortar coverage, is smeared outside moulding wall wall base, can carry out waterproof coiled material construction.
2. constructing basement barricade without fertile slot as described in claim 1, which is characterized in that retaining wall foundation and basement barricade it
Between be additionally provided with steel plate for sealing water, steel plate for sealing water is arranged along basement barricade length, and steel plate for sealing water lower end is embedded in retaining wall foundation
Portion, steel plate for sealing water upper end are poured in basement barricade.
3. constructing basement barricade without fertile slot as described in claim 1, which is characterized in that 4) step and 5) in step uses
Concreting distributing system realizes concreting, and concreting distributing system includes the concrete tank positioned at ground on the outside of foundation pit
Vehicle and Vehicle loaded pump, and the material distributing machine being set in foundation pit, concrete tank car discharge port are connected with Vehicle loaded pump, and Vehicle loaded pump discharge pipe is logical
Concrete conveyance conduit is crossed to be connected with the cloth pipeline in material distributing machine;Material distributing machine includes the steel bracket and Ke Shui being mounted vertically in foundation pit
The flat steel crossbearer for being rotatably arranged at steel bracket upper end, one end of steel crossbearer are the discharge end that cloth pipeline is arranged, cloth pipeline
Front end is connected with the pumping rubber vomit pipe extended downwardly, and cloth rear end of pipeline is arranged downwards along steel bracket and and concrete conveyance conduit
It is connected.
4. as claimed in claim 3 without fertile slot construction basement barricade, which is characterized in that steel crossbearer is another away from discharge end
End is the Balance weight end for being provided with clump weight, and length of the discharge end apart from steel bracket is greater than Balance weight end distance steel stent length.
5. as described in claim 1 without fertile slot construction basement barricade, which is characterized in that carry out the binding of basement barricade reinforcing bar
Single side formwork on the inside of barricade is realized using sizing truss mould plate support system afterwards,
The sizing truss mould plate support system includes vertically arranged barricade template, and horizontal interval is disposed on the outside of barricade template
Several vertical back cords, arranged for interval has several lateral back cords to vertical back cord elevationally outward, is horizontally spaced about on the outside of lateral back cord
If there is dry setting truss, the whole at right angles triangle of a sizing truss and right-angle side is mutually leaned on foundation pit ground, another right angle
Side is mutually leaned on lateral back cord, further includes several single wire drawing bars, single wire drawing bar is horizontally disposed and inner end is weldingly fixed on barricade template
In the barricade steel mesh that inside has bundled, outer end is fixed to be socketed on sizing truss.
6. as claimed in claim 5 without fertile slot construction basement barricade, which is characterized in that the vertical back cord is vertically arranged
Several shaped steels in packet batten obtain, batten side faces and is fitted in barricade template outer surface.
7. as claimed in claim 6 without fertile slot construction basement barricade, which is characterized in that the sizing truss includes under being located at
Side surrounds whole right-angled trapezium lower frame in a rectangular trapezoid by steel bar, be connected to above right-angled trapezium lower frame by steel bar
Frame on whole at right angles triangle is surrounded, it is perpendicular on the inside of the vertical edge and right-angled trapezium lower frame on right angled triangle on the inside of frame
Side is located at same perpendicular, and the bevel edge on the outside of bevel edge and right-angled trapezium lower frame on right angled triangle on the outside of frame is located at same
One oblique plane;Frame lower surface position on the steel bar and right angled triangle of right-angled trapezium lower frame upper surface position
Steel bar fitting after be bolted and fixed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710364637.2A CN106978819B (en) | 2017-05-22 | 2017-05-22 | It is a kind of without fertile slot construct basement barricade |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710364637.2A CN106978819B (en) | 2017-05-22 | 2017-05-22 | It is a kind of without fertile slot construct basement barricade |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106978819A CN106978819A (en) | 2017-07-25 |
CN106978819B true CN106978819B (en) | 2019-01-22 |
Family
ID=59342664
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710364637.2A Active CN106978819B (en) | 2017-05-22 | 2017-05-22 | It is a kind of without fertile slot construct basement barricade |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106978819B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111663540A (en) * | 2020-06-29 | 2020-09-15 | 河北建设勘察研究院有限公司 | Foundation pit supporting structure and wall formwork integrated construction method thereof |
CN113216606A (en) * | 2021-03-26 | 2021-08-06 | 中铁二十局集团第六工程有限公司 | Construction device and construction method for single-side formwork of outer wall |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08151645A (en) * | 1994-11-30 | 1996-06-11 | Nippon Steel Metal Prod Co Ltd | Deep foundation pile type earth retaining wall |
CN204357127U (en) * | 2014-12-10 | 2015-05-27 | 中建三局第一建设工程有限责任公司 | The monolateral formwork erecting structure of a kind of ultra-deep pre-buried Screw arbor with nut at both-ends of outer wall of basement narrow space |
CN104975614B (en) * | 2015-06-16 | 2017-03-15 | 中铁建大桥工程局集团第五工程有限公司 | Shaped steel combination formula single side formwork strengthening construction engineering method |
CN204849820U (en) * | 2015-06-16 | 2015-12-09 | 中铁建大桥工程局集团第五工程有限公司 | Unilateral formwork of shaped steel combination |
CN206752667U (en) * | 2017-05-22 | 2017-12-15 | 中冶建工集团有限公司 | A kind of basement barrier wall structure |
-
2017
- 2017-05-22 CN CN201710364637.2A patent/CN106978819B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN106978819A (en) | 2017-07-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106968269B (en) | A kind of basement Retaining wall method based on brick fetal membrane moulding wall | |
CN107130631B (en) | A kind of basement Retaining wall method based on concreting moulding wall | |
CN109736353A (en) | Construction method of composite single-side formwork deep foundation pit basement outer wall | |
CN112323823B (en) | Filling device and method for waste air-raid shelter of pile foundation construction site | |
CN110424460A (en) | A kind of tunnel open excavation construction technology | |
CN106978819B (en) | It is a kind of without fertile slot construct basement barricade | |
CN108035360B (en) | A method of for pattern foundation pit supporting structure | |
CN107366303A (en) | Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template | |
CN104695446B (en) | Basement construction method for supporting | |
KR101901368B1 (en) | A Permanent Retaining Wall Method Using by Double I Beam | |
CN109056844B (en) | Waterproof construction method for outer wall of basement of building | |
CN107503355A (en) | Shaped steel formula double-row pile foundation pit supporting system and its construction method are inserted after outer row | |
CN108005086B (en) | A kind of high buttress counter pull type inclined support structure for pattern foundation pit supporting structure | |
CN207469303U (en) | A kind of removable assembled template peace tears operating system open | |
CN108457662A (en) | A kind of control of weak soil shield launching and reinforcement means | |
CN207017271U (en) | Suitable for the concreting distributing system of basement construction | |
CN208870043U (en) | On the anti-pit accident across existing tunnel ruggedized construction | |
CN206722391U (en) | Basement barricade moulding wall formwork erecting structure based on brick fetal membrane | |
CN202299520U (en) | Inlet pumping station | |
CN206902721U (en) | A kind of foundation pit supporting system | |
CN207193947U (en) | It is a kind of to be used for rotary digging stake and the connection buckle of Larsen steel sheet pile | |
CN110306534A (en) | A kind of construction method of three-in-one underground diaphragm wall | |
JPS6198817A (en) | Method of forming concrete wall of underground structure employing composite sheet pile and composite sheet pile as weir panel | |
CN109826066A (en) | A kind of road structure and construction method of light soil roadbed combination steel-pipe pile | |
JPH06257169A (en) | Small-scale basement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |