CN207469303U - A kind of removable assembled template peace tears operating system open - Google Patents

A kind of removable assembled template peace tears operating system open Download PDF

Info

Publication number
CN207469303U
CN207469303U CN201721607968.6U CN201721607968U CN207469303U CN 207469303 U CN207469303 U CN 207469303U CN 201721607968 U CN201721607968 U CN 201721607968U CN 207469303 U CN207469303 U CN 207469303U
Authority
CN
China
Prior art keywords
operating system
removable
supporting rack
epimerite
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721607968.6U
Other languages
Chinese (zh)
Inventor
汪东兵
黄国涛
张飞强
刘翔
王宝生
任国钊
王之强
杨芳
种涛
刘振兴
黄绍模
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Construction Machine Construction Group Co ltd
Original Assignee
Shaanxi Construction Machine Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Construction Machine Construction Group Co ltd filed Critical Shaanxi Construction Machine Construction Group Co ltd
Priority to CN201721607968.6U priority Critical patent/CN207469303U/en
Application granted granted Critical
Publication of CN207469303U publication Critical patent/CN207469303U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of removable assembled template peaces to tear operating system open, including the cantilever beam for moving supporting rack and being fixed at the top of removable supporting rack, the both sides of the cantilever beam are separately installed with jack by hanging ring, have the steel wire rope for connecting and lifting by crane template on jack;The bottom of the removable supporting rack is equipped with the fixing bracket that can fix removable supporting rack current location.The utility model template peace tears operating system open in construction, it can quickly realize the assembling of template and operating system, suitable for narrow working face operation, reduce the application of large lifting equipment, avoid threat of the large lifting equipment to excavation slope, the labor intensity of operator is reduced, improves construction quality, shortens the construction period.

Description

A kind of removable assembled template peace tears operating system open
Technical field
The utility model is related to road construction fields, and in particular to a kind of removable assembled template peace tears operating system open.
Background technology
In Municipal Road Engineering, underground preburied pipeline is more and road width is limited, while in order to reduce as far as possible Original state soil layer disturbance below roadbed, the channel excavation relatively narrower of usual underground pipe canal, as underground space development puts more effort, ground Various line loads are continuously increased in lower electric power pipe trench, and the application that cast-in-place concrete wall body substitutes brick masonry wall body electric power pipe trench is got over Come more extensive, in order to improve concrete walls body construction quality, large-scale steel form utility ratio also greatly improves.
In the construction process, in order to ensure excavation slope safety, it is desirable that lifting equipment must keep certain with foundation pit edge Safe distance, it is corresponding to the requirement of the elevating capacity of lifting equipment to improve, while construction cost also significantly rises.
In town road construction, the aqueducts such as rain sewage are all using circular channel, for protection electric power, heating power, oil gas The pipe trench that underground piping is built is mostly using rectangular configuration, these rectangular configuration object bases are cement concrete, and wall body is adopted With brick setting or cast-in-place concrete structure.As modern city putting forward the appearance of the city and city aboveground space using the continuous of requirement It rises, all kinds of circuits such as electric power, communication that urban road both sides are as fine as a spider's web are required to embedment underground, and function original in this way is single The line facilities such as laying communication, communication will be increased in electric power pipe trench, the load of pipe trench wall will certainly be increased, to meet these Load requirement, existing underground pipe canal is then with coagulating cement cob wall as master.In town road process of construction, since underground is various Pipeline is more, and road width is limited, while for disturbance original soil structures few as possible and reduces backfill amount, reserves buried pipe Working space on the outside of ditch wall body is narrow, and such wall body model sheetinstallat is difficult.During using plank sheathing, since working space is narrow, Bracing reinforcement difficulty is big, is susceptible to the mass defects such as spillage, swollen mould;If constructing steel form, weight is big, needs in gutter safety Large-scale Hoisting equipment auxiliary construction is used apart from outer, and template peace tears that progress is slow, job safety increased risk open.
Utility model content
The problems in the purpose of this utility model is that for the above-mentioned prior art, a kind of removable assembled template is provided Peace tears operating system open, shortens template peace in limited working space and tears open the time, improves construction quality, reduce engineering cost.
To achieve these goals, the utility model moves assembled template peace and tears operating system open using following technology Scheme:
Including the cantilever beam for moving supporting rack and being fixed at the top of removable supporting rack, the both sides of the cantilever beam lead to It crosses hanging ring and is separately installed with jack, there is the steel wire rope for connecting and lifting by crane template on jack;The removable supporting rack Bottom is equipped with the fixing bracket that can fix removable supporting rack current location.
The removable supporting rack includes the base section, standard knot and the epimerite that set gradually from the bottom to top, the base section, The triangular structure that standard knot and epimerite are formed using steel-pipe welding;Base section bottom is installed by traveling wheel.
The upright bar height of base section and the standard knot is 1m, and the upright bar height of epimerite is 0.5m;
Connecting platform of the top welding steel of the epimerite as cantilever beam.
Pass through joint steel pipe between the base section, standard knot and epimerite and carry out plug-in type connection.
The cantilever beam uses 20a I-steel, and 20a I-steel is connected by the top of bolt and epimerite.
Cantilever beam both sides correspond to the position welding hanging ring of concrete walls body, and hanging ring uses U-shaped hanging ring.
Pass through bolt and sleeve cooperation installation between the bottom of the removable supporting rack and fixing bracket.
The fixing bracket is using the triangular structure stent for being symmetricly set on removable supporting rack both sides, triangle knot Being fixedly connected on the outside of structure stent can realize and hold out against fixed leading screw.
The utility model moves the construction method that assembled template peace tears operating system open, includes the following steps:
1) place cleaning;
2) the installation site line of measuring template;
3) on the basis of removable supporting rack being placed in pipe trench, fixing bracket is opened, it is ensured that removable supporting rack is stablized;It will Jack equipped with steel wire rope is hung on hanging ring, and steel wire rope is connect with template;
4) template carries out examination and hangs examination after the completion of fixing;
5) it gives work flowing water paragraph to complete model sheetinstallat and reinforce stabilization, then implements the concreting of wall body;
6) after concrete strength meets form removal condition, form removal and operating system.
The removable supporting rack includes the base section, standard knot and the epimerite that set gradually from the bottom to top;The step 3) on the basis of the base section with traveling wheel being placed in pipe trench first, the quadrangle of base section installs fixed branch by bolt respectively Frame opens fixing bracket, it is ensured that removable supporting rack is stablized;Then standard knot is installed at the top of base section, according to wall height Degree determines the quantity of required standard knot, and standard knot carries out plug-in type by joint steel pipe with base section and connect;Finally in standard knot Epimerite is installed at top, and plug-in type connection is carried out by joint steel pipe between epimerite and standard knot, and cantilever beam is mounted on by bolt On welding steel at the top of epimerite;During step 6) the dismantling operation system, disassembly sequence is opposite with step 3).
Compared with prior art, on the concrete pipe trench basic plane that the utility model is completed in construction, using removable Template is transported to the required construction location of concrete walls body by the walking function of supporting rack in pipe trench, reuses jack association Model sheetinstallat personnel is helped to adjust form height, complete model sheetinstallat and reinforcement.It completes the concreting of wall body and maintenance is arrived Behind position, finally form fixer's form removal is assisted using the utility model and transport next working face to.The utility model can be In limited work surface, make model sheetinstallat position accurate, shorten template peace and tear open the time, improve construction quality, reduce engineering cost.
Description of the drawings
The front view of Fig. 1 the utility model operating systems;
The side view of Fig. 2 the utility model operating systems;
The epimerite schematic diagram of Fig. 3 the utility model operating systems;
The standard knot schematic diagram of Fig. 4 the utility model operating systems;
The epimerite vertical view of Fig. 5 the utility model operating systems;
The vertical view of Fig. 6 the utility model operating systems;
The overall flow figure of Fig. 7 the utility model construction methods;
In attached drawing:1- moves supporting rack;2- base sections;3- standard knots;4- epimerite;5- cantilever beams;6- hanging rings;7- steel Plate;8- jacks;9- steel wire ropes;10- templates;11- fixing brackets;12- traveling wheels;13- leading screws.
Specific embodiment
The following describes the utility model in further detail with reference to the accompanying drawings.
Referring to Fig. 1-6, the utility model moves assembled template peace and tears operating system open, including removable supporting rack 1 with And the cantilever beam 5 at removable 1 top of supporting rack is fixed on, removable supporting rack 1 includes the base section set gradually from the bottom to top 2nd, standard knot 3 and epimerite 4, the triangular structure that base section 2, standard knot 3 and epimerite 4 are formed using steel-pipe welding, base section 2nd, plug-in type connection, 2 bottom of base section installation traveling wheel 12 are carried out by joint steel pipe between standard knot 3 and epimerite 4.Cantilever beam 5 use 20a I-steel, and 20a I-steel is connect by bolt with the top of epimerite 4.5 both sides of cantilever beam correspond to concrete walls body Position welding hanging ring 6, hanging ring 6 uses U-shaped hanging ring, and jack 8 is installed in the both sides of cantilever beam 5 respectively by hanging ring 6, on jack 8 With for connecting and lift by crane the steel wire rope 9 of template 10;The bottom of removable supporting rack 1, which is equipped with, can fix removable support The fixing bracket 11 of 1 current location of frame, fixing bracket 11 is using the triangular structure for being symmetricly set on removable 1 both sides of supporting rack Stent, being fixedly connected on the outside of triangular structure stent can realize and hold out against fixed leading screw 13.At the bottom of removable supporting rack 1 Pass through bolt and sleeve cooperation installation between portion and fixing bracket 11.
Connecting platform of the top welding steel 7 of epimerite 4 as cantilever beam 5.Joint steel pipe be welded and fixed it is more small-sized Number short steel pipes, the short steel pipes half between base section 2 and standard knot 3 are inserted at the top of the upright bar of base section 2, and half, which reserves, to be come Plug-in type is carried out with the standpipe lower part of standard knot 3 to connect, the short steel pipes half between standard knot 3 and epimerite 4 is inserted into standard knot 3 Upright bar at the top of, half reserve with the standpipe lower part of another standard knot 3 or epimerite 4 carry out plug-in type connect, standard knot 3 Quantity can be increased or decreased according to pipe trench wall height degree, be advisable with meeting needs.
Referring to Fig. 7, the utility model move assembled template peace tear open operating system construction method it is specific as follows:
1. project profile
Certain town road, link length 401.321m, Systems of Red Line in Planning Based width are 50m.Category of roads is major urban arterial highway, Rainwater, sewage groove, power pipe channel bottom be thicker burning into sand layer, good water permeability.Electric power pipe trench basis, wall are as cast-in-place mixed Xtah Crude Clay structure, rectangular section, top plate are prefabricated cover board, basic width 2200mm, wall body thickness 200mm, wall height 1500mm, within the walls 500mm working faces are stayed in lateral extent 1800mm, pipeline both sides, and work faciostenosis.Original ground absolute altitude:390.3m, pipe trench depth 2.7m, The gradient 0.3%;Groove top is collapsible loess, and lower part is sandy soils.
2. engineering geological condition:
Landforms residing for engineering are Feng rivers second bottom, and site topography is open along the line, and for topography than shallower, overall is in Nan Gaobei Low situation.Geological stratification is by ploughing (table) soil (Q4 pd), artificial earth fill (Q4 ml), the 4th is Holocene series alluviation (Q4 al) Loessial Soil, silty The compositions such as clay, sand, fine sand soil, silty sand.
3. preparation of construction:
This engineering underground electric pipe trench is reinforced concrete rectangular structure, basic for C20 concrete mass-type foundations, pipe trench wall Height 1500mm, wall thickness 200mm.Before the construction of wall body, first measuring goes out the reinforcing bar position line and mould on the basis of completion pipe trench has been poured Board position line, reinforcement installation prepare model sheetinstallat in place and after acceptance(check).
3.1. place cleaning;
Sundries on the basis of mucking before template operation system assembles, in order to avoid hinder template operation system operation.
3.2. measuring template position line;
The pipe trench basis top surface survey tool for meeting construction requirement in concrete strength releases wall body template line, and pop up The line of ink marker, it is ensured that model sheetinstallat position is accurate.
3.3. installation form operating system base section, standard knot;
The installation form operating system in both walls body template line on the basis of the pipe trench.First by the basis with traveling wheel 12 Section 2 is placed on the basis of pipe trench, has assigned fixing bracket 11, fixing bracket 11 and column pin respectively on its four corner post It is fixed, it can cannot be moved up and down along column left-right rotation;Fixing bracket 11 is opened, tightens leading screw 13, it is ensured that base section is steady It is fixed.
In the top of base section 2 installation standard knot, when standard knot 3 is installed the locality of connecting insertion upward, quadrangle standpipe Lower part steel pipe and the connecting insertion of 2 top surface of base section are aligned and inserted into.Check that 2 top connecting insertion of base section is complete after installation is complete It is fully inserted into 3 bottom steel pipe of standard knot, the column steel pipe alignment of standard knot 3 and base section 2 coincide.
The height of base section 2 and standard knot 3 is 1000mm, this engineering pipe trench wall height degree is 1500mm, and installation one saves Standard knot 3 disclosure satisfy that construction height requirement, if when wall height degree is larger on Other Engineering, can increase standard knot.
3.4. installation form operating system epimerite 4, cantilever beam 5;
In the top of standard knot 3 installation epimerite 4, when epimerite 4 is installed the locality of welding steel 7 upward, under the standpipe of quadrangle Portion's steel pipe and the connecting insertion of 3 top surface of standard knot are aligned and inserted into.Check criteria 3 top connecting insertions of section are complete after installation is complete It is inserted into the steel pipe of 4 bottom of epimerite, the column steel pipe alignment of standard knot 3 and epimerite 4 coincide.
Cantilever beam 5 makes of 20a I-steel, on the steel plate 7 of 4 top surface of epimerite, with bolt by accomplishing fluently in advance Bolt hole connects, and bolts on, fixation.The jack 8 for playing reuse is hung over and is fixed on the hanging ring 6 on cantilever beam 5 in advance, 8 lower part suspension hook connecting steel wire ropes 9 of jack, steel wire rope 9 will be connect with the hanging ring in template 10,8 lower part of jack when condition meets Suspension hook can be directly connected to the hanging ring on template top.
3.5. template operation system acceptance;
Template operation system checks its appearance using preceding after installation is complete:
Base section 2, standard knot 3,4 column axis of epimerite are straight, and interface is concordant, monolithic stability.Template 10 is hung in examination, and operation is flat Surely, 6 position of hanging ring of cantilever beam 5 is corresponding with wall body model sheetinstallat position.
4 model sheetinstallats pour walling body concrete:
Template 10 is sling by template operation symmetry system having symmetry, being transported to needs wall body construction area, opens fixing bracket 11, twists Tight leading screw 13, fixed form operating system, operation jack 8 adjust form height, install fixed form 10;Use template operation system Continuative transport installation form of uniting completes a construction flowing water paragraph, and (scene is long according to template number overall planning construction flowing water paragraph Degree, one construction flowing water paragraph of this project is 30m).It completes model sheetinstallat and implements wall body concreting after reinforcing stabilization.
5. form removal:
After the completion of one construction flowing water paragraph construction, this flowing water paragraph carries out next step concreting operation;Same luck The model sheetinstallat for continuing to install next construction flowing water paragraph with template operation system works.Treat that a construction flowing water paragraph mixes After solidifying soil intensity meets form removal condition, reuse template operation system and carry out form removable work.
By artificial moving die plate operating system to form removal region, fixing bracket 11 is opened, leading screw 13 is tightened and fixes, suspension hook Fixed form hanging ring, tightens jack 8, and form removal support system makes template 10 with concrete walls status from symmetry operation jack 8 two side templates 10 of lifting, withdraw fixing bracket 11, and the template 10 removed is transported to next construction continuous productive process region;It opens Fixing bracket 11 is tightened leading screw 13 and is fixed, and stablizes template operating system, removes remaining concrete in template 10, brushing template Interleaving agent, operation jack 8 adjust the position height of template 10, install fixed form 10, loosen jack 8, withdraw fixing bracket 11, It repeats to remove and transports next piece of template 10, until this continuous productive process is completed.
6. form removal operating system:
After the completion of the construction of electric power pipe trench wall body, form removal operating system.Fixing bracket 11 is opened first, tightens leading screw 13, fixed form operating system.Check that operating system security is stablized before removing, well-tended appearance.Demolishing process and installation process phase Instead:1) jack 8 is removed;2) cantilever beam 5 is removed;3) epimerite 4 is removed;4) standard knot 3 is removed;5) fixing bracket 11 is removed.
Using template operation system points for attention:
1) template operation system first checks whether the weld seam, connector and component of each component are intact before assembling.
2) template operation system must carry out an acceptance inspection after installation is complete, check whether each position connection is secured, and to carry out Trial operation.
3) road surface of template operation system walking is pipe trench concrete foundation, and concrete strength is grasped after reaching C15 Make.
4) symmetry operation is answered on both sides during template operation system transfer template.
5) fixing bracket 11 when carrying out lifting operation should be opened and tighten leading screw 13 by template operation system, and it is steady to increase it It is qualitative.
6) template operation system is when carrying out lifting operation, removing obstacles object in the range of running route, guarantee evenness of road surface, It is solid.
Rectangle concrete pipe trench wall body template movable stencil operation system technology is mainly used in municipal works electric power pipe trench wall Body model sheetinstallat is constructed.This engineering has developed the operation instrument suitable for narrow working face in the construction process, has worked out rationally Construction technology, reduce the application of large lifting equipment, avoid threat of the large lifting equipment to excavation slope, reduce The labor intensity of operator, improves construction quality, shortens the construction period, finally achieves satisfaction effect.
The utility model template peace tears operating system open in construction, can quickly realize the assembling of template and operating system, Suitable for narrow working face operation, reduce the application of large lifting equipment, avoid large lifting equipment to excavation slope It threatens, reduces the labor intensity of operator, improve construction quality, shorten the construction period.
The operating system divides base section, standard knot, epimerite, can be adjusted using height with wall height degree, except in municipal works Outside rectangle pipe trench wall body model sheetinstallat construction application, similar Other Engineering concrete walls body model sheetinstallat can also be applied to and applied Work.

Claims (8)

1. a kind of removable assembled template peace tears operating system open, it is characterised in that:Including removable supporting rack (1) and fix Cantilever beam (5) at the top of removable supporting rack (1), the both sides of the cantilever beam (5) are separately installed with jack by hanging ring (6) (8), there is the steel wire rope (9) for connecting and lifting by crane template (10) on jack (8);The bottom of the removable supporting rack (1) The fixing bracket (11) of removable supporting rack (1) current location can be fixed by being equipped with.
2. moving assembled template peace according to claim 1 tears operating system open, it is characterised in that:The removable support Frame (1) includes the base section (2), standard knot (3) and epimerite (4) that set gradually from the bottom to top, the base section (2), standard knot (3) and epimerite (4) uses the triangular structure that steel-pipe welding forms;Base section (2) bottom installation traveling wheel (12).
3. moving assembled template peace according to claim 2 tears operating system open, it is characterised in that:The base section (2) with the upright bar height of standard knot (3) it is 1m, the upright bar height of epimerite (4) is 0.5m;
Connecting platform of the top welding steel (7) of the epimerite (4) as cantilever beam (5).
4. moving assembled template peace according to claim 2 tears operating system open, it is characterised in that:The base section (2), plug-in type connection is carried out by joint steel pipe between standard knot (3) and epimerite (4).
5. moving assembled template peace according to claim 2 tears operating system open, it is characterised in that:The cantilever beam (5) using 20a I-steel, 20a I-steel is connect by bolt with the top of epimerite (4).
6. operating system is torn open according to the removable assembled template peace of claim 1 or 5, it is characterised in that:Cantilever beam (5) two Side corresponds to the position welding hanging ring (6) of concrete walls body, and hanging ring (6) uses U-shaped hanging ring.
7. moving assembled template peace according to claim 1 tears operating system open, it is characterised in that:The removable support Pass through bolt and sleeve cooperation installation between the bottom of frame (1) and fixing bracket (11).
8. operating system is torn open according to the removable assembled template peace of claim 1 or 7, it is characterised in that:The fixation Stent (11) using being symmetricly set on the triangular structure stents of removable supporting rack (1) both sides, triangular structure stent it is outer Side is fixedly connected and can realize and hold out against fixed leading screw (13).
CN201721607968.6U 2017-11-27 2017-11-27 A kind of removable assembled template peace tears operating system open Active CN207469303U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721607968.6U CN207469303U (en) 2017-11-27 2017-11-27 A kind of removable assembled template peace tears operating system open

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721607968.6U CN207469303U (en) 2017-11-27 2017-11-27 A kind of removable assembled template peace tears operating system open

Publications (1)

Publication Number Publication Date
CN207469303U true CN207469303U (en) 2018-06-08

Family

ID=62259836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721607968.6U Active CN207469303U (en) 2017-11-27 2017-11-27 A kind of removable assembled template peace tears operating system open

Country Status (1)

Country Link
CN (1) CN207469303U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107794945A (en) * 2017-11-27 2018-03-13 陕西建工机械施工集团有限公司 A kind of removable assembled template peace tears operating system and its construction method open
CN111705811A (en) * 2020-06-30 2020-09-25 中铁十六局集团北京轨道交通工程建设有限公司 Support dismantling device, system and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107794945A (en) * 2017-11-27 2018-03-13 陕西建工机械施工集团有限公司 A kind of removable assembled template peace tears operating system and its construction method open
CN111705811A (en) * 2020-06-30 2020-09-25 中铁十六局集团北京轨道交通工程建设有限公司 Support dismantling device, system and method

Similar Documents

Publication Publication Date Title
CN110439571B (en) Transverse channel construction method for leading flat pilot tunnel to main tunnel and transverse channel
CN109488347B (en) Excavation construction method for special stratum chamber
CN110318776A (en) Method for tunnel construction based on inverted arch and inverted arch filled layer substitution steel-concrete combined structure
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN108842819A (en) A kind of urban track traffic cable run method for tunnel construction
CN107964976A (en) Steel pipe-conversion steel platform tower crane top-down construction method
CN112376589A (en) Landslide belt pile plate type comprehensive protection construction system and construction method
WO2023077552A1 (en) Construction method for foundation pit enclosure and earth excavation
CN107806101A (en) Construction method of the bar shaped foundation ditch cast-in-place concrete to the prefabricated linking beam of support
CN110424455A (en) The underground confined space is without fertile slot structure side wall big steel form plate system and construction method
CN111455977A (en) Underground continuous wall construction method
CN110219667A (en) Tunnel inverted arch and inverted arch filled layer substitution steel-concrete combined structure and construction technology
CN108035379B (en) Comprehensive pipe gallery and construction method thereof
CN107794945A (en) A kind of removable assembled template peace tears operating system and its construction method open
CN114263168A (en) Construction method of rock-socketed diaphragm wall of stratum water-stopping enclosure structure
CN207469303U (en) A kind of removable assembled template peace tears operating system open
CN114673169A (en) Multi-layer large-span deep foundation pit cover-excavation forward-backward combined construction method for urban core area
CN109594581A (en) Cross a river segment pipe structure and its installation method
CN108708290A (en) The case crane span structure hollow structure and cast-in-situ construction method of minor radius railway curve unit
CN112177042A (en) Rail transit station construction method without affecting ground traffic
CN109930610A (en) Constrained environment foundation pit adds the construction method of steel pipe mixing diagonal brace using concrete
CN113898007B (en) Semi-inverse construction method for long-span corridor structure along street
CN215906845U (en) Large-span vestibule mounting structure in foundation pit
CN107090772B (en) Construction method of side span cast-in-place beam bracket of extra-large cable-stayed bridge
CN105986830A (en) Underground-excavation building method for roadside strip-shaped underground garage

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant