CN106930304A - Drift sand base pit dewatering construction method - Google Patents

Drift sand base pit dewatering construction method Download PDF

Info

Publication number
CN106930304A
CN106930304A CN201710184018.5A CN201710184018A CN106930304A CN 106930304 A CN106930304 A CN 106930304A CN 201710184018 A CN201710184018 A CN 201710184018A CN 106930304 A CN106930304 A CN 106930304A
Authority
CN
China
Prior art keywords
drainage groove
filter
pipe
filter pipe
coarse sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710184018.5A
Other languages
Chinese (zh)
Inventor
邓辉
梁永红
姚文伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201710184018.5A priority Critical patent/CN106930304A/en
Publication of CN106930304A publication Critical patent/CN106930304A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/20Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a kind of drift sand base pit dewatering construction method, comprise the following steps:1)All around a drainage groove is excavated in foundation ditch around foundation ditch;2)The filter pipe that some closed at both ends are set is obtained, being covered with filter pipe there are some treatment holes, then in the metafiltration net of filter pipe outer cladding one;3)One layer of coarse sand is laid in drainage groove bottom land, then by step 2)In some filter pipes be laid on coarse sand along drainage trench length direction, then obtain some vavuum pumps and be placed in by drainage groove, every filter pipe is connected with the pumping end of corresponding vavuum pump by exhaust tube;4)To coarse sand is inserted in drainage groove, form coarse sand integument and filter pipe is wrapped in inside it, then be compacted up to drainage groove top and to clay to clay is inserted in drainage groove;5)Starting all of vavuum pump carries out precipitation., using the dewatering mode for actively drawing water, not only pump-out is big, while precipitation efficiency is high, shortens the construction period for the present invention.

Description

Drift sand base pit dewatering construction method
Technical field
The present invention relates to the realm of building construction, and in particular to a kind of drift sand base pit dewatering construction method.
Background technology
With the development of construction technology, architecture Foundation Pit Engineering constantly extends to underground, and building foundation pit precipitation is one larger Problem, foundation ditch width and depth are larger in particularly present engineering, the big engineering of underground water content.Existing precipitation technology master There are well-point dewatering method and tube well dewatering method, tube well dewatering method is that some pipe wells for working independently are arranged around foundation ditch, underground Water is flowed under the influence of gravity into well, is taken away water with pumping equipment.And well-point dewatering method be one by well casing, water header, The drainage system of the compositions such as common centrifugal water pump, vavuum pump and header tank.Underground water relies on true from the filter pipe of well casing lower end The swabbing action of empty pump and water pump is flowed into pipe, imports water header, flows into header tank, is discharged by water pump.Tube well dewatering method one As with respect to compare with underground water depth that is abundant and excavating it is deep when use, underground water flows under the influence of gravity into well In, water is taken away with pumping equipment, precipitation is carried out by passive mode, not only precipitation efficiency is low, and the precipitation duration is also long in addition; And underground water is flowed into pipe from the filter pipe of well casing lower end by the swabbing action of vavuum pump and water pump in well-point dewatering method, import Water header, flows into header tank, is discharged by water pump, although carry out precipitation by the way of active, but usually cutting depth Used in the case that shallower and water level is little, well casing diameter is generally smaller in well-point dewatering method in addition, water yield is also corresponding smaller, Equally have impact on precipitation efficiency.
In the sand dirt band environment little for water penetration, particularly soil body osmotic coefficient it is moderate 50~100m/d it Between, water content of soil is larger, using above two precipitation method, not only reduces precipitation efficiency, while also extending construction work Phase.
The content of the invention
For above-mentioned the deficiencies in the prior art, the technical problems to be solved by the invention are:A kind of raising how is provided to drop Water efficiency, shortens the drift sand base pit dewatering construction method of construction period.
In order to solve the above-mentioned technical problem, present invention employs following technical scheme:
A kind of drift sand base pit dewatering construction method, comprises the following steps:
1)A drainage groove all around is excavated around foundation ditch in foundation ditch, the bottom land absolute altitude of drainage groove is marked less than the hole bottom of foundation ditch It is high;
2)The filter pipe that some closed at both ends are set is obtained, being covered with filter pipe there are some treatment holes, then outside filter pipe One layer of mesh number of cladding is 80~100 filter screen;
3)One layer of coarse sand is laid in drainage groove bottom land, then by step 2)In some filter pipes along drainage trench length direction spread It is located on coarse sand, adjacent two filter pipes head and the tail are affixed, then obtains some vavuum pumps and be placed in by drainage groove, by pumping Pipe makes every filter pipe be connected with the pumping end of corresponding vavuum pump;
4)To coarse sand is inserted in drainage groove, form coarse sand integument and filter pipe is wrapped in inside it, then in drainage groove Clay is inserted until being compacted at the top of drainage groove and to clay;
5)Starting all of vavuum pump carries out precipitation.
In the present invention, the waterline in order to make underground water is under the elevation line at Foundation Pit bottom all the time, will be dug The drainage groove bottom land absolute altitude of pick so when precipitation, can not only make to be located at water-filtering ditch less than the bottom land absolute altitude of foundation ditch Waterline outside groove declines, it is to avoid underground water product in foundation ditch, while under the waterline in drainage groove in foundation ditch can also be made Drop, makes Foundation Pit bottom keep dry state, it is to avoid ponding.Filter pipe is wrapped in inside it using coarse sand, coarse sand can be filtered Other impermeability materials such as clay, ratchel for being mingled with water, and the filter screen of drainage tube outer surface cladding can enter to coarse sand Row barrier, it is to avoid it is entered into filter pipe.Finally recycle clay that filter pipe and coarse sand are enclosed in drainage groove, energy Enough during filter pipe draws water, it is to avoid pressure release situation occur, filter pipe pumpage is reduced, influence precipitation efficiency.This hair It is bright to employ the method actively drawn water, drawn water using vavuum pump, filter pipe surrounding is formed a negative pressure space, it is actively right The moisture on periphery is extracted, and by the filter pipe set around foundation ditch, declines the waterline of foundation ditch surrounding, around foundation ditch Moisture is completely cut off, and allows foundation ditch to be in an environment for closing, improves the precipitation efficiency of foundation ditch.The pipe shaft of other filter pipe On some treatment holes for being covered with while drawn water, improve pump-out, further increase precipitation efficiency, and then shorten and apply Work works, and reduces construction cost.
Used as optimization, every two adjacent filter pipes, a vavuum pump and an exhaust tube are one group of drop Water unit, wherein being provided with T-shaped three-limb tube, two drainages between two filter pipes in every group of precipitation unit The relative one end of pipe connects with two athwartship legs of T-shaped three-limb tube respectively, and the vertical branch pipe of T-shaped three-limb tube is in perpendicular Directly set up and connected with one end of the exhaust tube, the other end of the exhaust tube connects with the pumping end of the vavuum pump It is logical.Two filter pipes are connected by T-shaped three-limb tube, is evacuated by an exhaust tube, reduce the number of exhaust tube Amount, can make a vavuum pump while carrying out operation of drawing water to two filter pipes, cost be not only reduced, while it also avoid Many exhaust tubes, because the reasons such as vibrations make to occur between clay pressure release caused by gap, influence precipitation efficiency.
Used as optimization, every drainage groove is excavated using order from top to bottom successively, every layer of excavation thickness In 0.3~0.6m.The drainage groove of too early excavation can be avoided because caving in occurs in influence on groundwater, while also avoiding excavation too early Drainage groove internal water accumulation, influence the later stage construction.
Used as optimization, the coarse sand wraps up minimum of the layer surface along the filter pipe radial direction to the drainage pipe surface Distance is 50mm.Filter pipe periphery is set there are enough coarse sands to be filtered, it is to avoid impurity blocks treatment hole.
In sum, the beneficial effects of the present invention are:The present invention uses the dewatering mode for actively drawing water, not only pump-out Greatly, while precipitation efficiency is high, the construction period is shortened.
Specific embodiment
The present invention is described in further detail below.
Drift sand base pit dewatering construction method in this specific embodiment, comprises the following steps:
1)A drainage groove all around is excavated around foundation ditch in foundation ditch, the bottom land absolute altitude of drainage groove is marked less than the hole bottom of foundation ditch It is high;
2)The filter pipe that some closed at both ends are set is obtained, being covered with filter pipe there are some treatment holes, then outside filter pipe One layer of mesh number of cladding is 80~100 filter screen;
3)One layer of coarse sand is laid in drainage groove bottom land, then by step 2)In some filter pipes along drainage trench length direction spread It is located on coarse sand, adjacent two filter pipes head and the tail are affixed, then obtains some vavuum pumps and be placed in by drainage groove, by pumping Pipe makes every filter pipe be connected with the pumping end of corresponding vavuum pump;
4)To coarse sand is inserted in drainage groove, form coarse sand integument and filter pipe is wrapped in inside it, then in drainage groove Clay is inserted until being compacted at the top of drainage groove and to clay;
5)Starting all of vavuum pump carries out precipitation.
In this specific embodiment, every two adjacent filter pipes, a vavuum pump and an exhaust tube It is one group of precipitation unit, wherein being provided with T-shaped three-limb tube, two between two filter pipes in every group of precipitation unit The relative one end of the filter pipe connects with two athwartship legs of T-shaped three-limb tube respectively, T-shaped three-limb tube it is vertical Branch pipe in setting straight up and being connected with one end of the exhaust tube, with the vavuum pump take out by the other end of the exhaust tube Gas end connects.
In this specific embodiment, every drainage groove is excavated using order from top to bottom successively, every layer Thickness is excavated in 0.3~0.6m.
In this specific embodiment, the coarse sand wraps up layer surface along the filter pipe radial direction to the filter pipe table The minimum range in face is 50mm.
During specific implementation, a diameter of 40~60mm of the filter pipe, pipe thickness is not more than 2mm, some The treatment hole is staggered along the filter pipe circumferential and axial, and the aperture of each treatment hole is 4~6mm, adjacent two The pitch-row of the individual treatment hole is 20~30mm.Treatment hole is set to be distributed on filter pipe more uniform, can be uniformly to surrounding Drawn water, improved precipitation efficiency.
Finally illustrate, the above embodiments are merely illustrative of the technical solutions of the present invention and it is unrestricted, although by ginseng According to the preferred embodiments of the present invention, invention has been described, it should be appreciated by those of ordinary skill in the art that can To make various changes to it in the form and details, without departing from the present invention that appended claims are limited Spirit and scope.

Claims (4)

1. a kind of drift sand base pit dewatering construction method, it is characterised in that:Comprise the following steps:
1)A drainage groove all around is excavated around foundation ditch in foundation ditch, the bottom land absolute altitude of drainage groove is marked less than the hole bottom of foundation ditch It is high;
2)The filter pipe that some closed at both ends are set is obtained, being covered with filter pipe there are some treatment holes, then outside filter pipe One layer of mesh number of cladding is 80~100 filter screen;
3)One layer of coarse sand is laid in drainage groove bottom land, then by step 2)In some filter pipes along drainage trench length direction spread It is located on coarse sand, adjacent two filter pipes head and the tail are affixed, then obtains some vavuum pumps and be placed in by drainage groove, by pumping Pipe makes every filter pipe be connected with the pumping end of corresponding vavuum pump;
4)To coarse sand is inserted in drainage groove, form coarse sand integument and filter pipe is wrapped in inside it, then in drainage groove Clay is inserted until being compacted at the top of drainage groove and to clay;
5)Starting all of vavuum pump carries out precipitation.
2. the drift sand base pit dewatering construction method according to claim, it is characterised in that:Every two adjacent filter pipes, One vavuum pump and an exhaust tube are one group of precipitation unit, wherein two drainages in every group of precipitation unit Be provided with T-shaped three-limb tube between pipe, the relative one end of two filter pipes respectively with two horizontal strokes of T-shaped three-limb tube Connected to branch pipe, the vertical branch pipe of T-shaped three-limb tube is described in setting straight up and being connected with one end of the exhaust tube The other end of exhaust tube is connected with the pumping end of the vavuum pump.
3. drift sand base pit dewatering construction method according to claim 1, it is characterised in that:Every the drainage groove is used From top to bottom order successively is excavated, and every layer is excavated thickness in 0.3~0.6m.
4. drift sand base pit dewatering construction method according to claim 1, it is characterised in that:The coarse sand parcel layer surface edge The filter pipe radial direction to the minimum range of the drainage pipe surface is 50mm.
CN201710184018.5A 2017-03-24 2017-03-24 Drift sand base pit dewatering construction method Pending CN106930304A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710184018.5A CN106930304A (en) 2017-03-24 2017-03-24 Drift sand base pit dewatering construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710184018.5A CN106930304A (en) 2017-03-24 2017-03-24 Drift sand base pit dewatering construction method

Publications (1)

Publication Number Publication Date
CN106930304A true CN106930304A (en) 2017-07-07

Family

ID=59425140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710184018.5A Pending CN106930304A (en) 2017-03-24 2017-03-24 Drift sand base pit dewatering construction method

Country Status (1)

Country Link
CN (1) CN106930304A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736337A (en) * 2019-02-22 2019-05-10 宁蔚蔚 A kind of substrate elevator catch pit drift sand processing guarantees the dewatering device and method of bed course integrality
CN110644498A (en) * 2019-09-23 2020-01-03 李贺清 Deep foundation pit slope quicksand handling method
CN111021385A (en) * 2019-12-18 2020-04-17 宁蔚蔚 Precipitation method for treating quicksand when manual hole digging pile hole digging meets quicksand layer
CN111305241A (en) * 2019-12-18 2020-06-19 宁蔚蔚 Method for treating quicksand in hole digging of manual hole digging pile through light well point dewatering

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61117327A (en) * 1984-11-14 1986-06-04 Taiyo Gijutsu Kaihatsu Kk Drain reinforcing earthwork method
CN205152968U (en) * 2015-11-19 2016-04-13 中国建筑第七工程局有限公司 Precipitation tubular well structure
CN205530381U (en) * 2016-01-20 2016-08-31 中国建筑第二工程局有限公司 Water filtering tank for directionally guiding underground water outside basement outer wall
CN106013045A (en) * 2016-06-01 2016-10-12 上海建研地基基础工程有限公司 Fast drainage method for shallow soil body

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61117327A (en) * 1984-11-14 1986-06-04 Taiyo Gijutsu Kaihatsu Kk Drain reinforcing earthwork method
CN205152968U (en) * 2015-11-19 2016-04-13 中国建筑第七工程局有限公司 Precipitation tubular well structure
CN205530381U (en) * 2016-01-20 2016-08-31 中国建筑第二工程局有限公司 Water filtering tank for directionally guiding underground water outside basement outer wall
CN106013045A (en) * 2016-06-01 2016-10-12 上海建研地基基础工程有限公司 Fast drainage method for shallow soil body

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736337A (en) * 2019-02-22 2019-05-10 宁蔚蔚 A kind of substrate elevator catch pit drift sand processing guarantees the dewatering device and method of bed course integrality
CN110644498A (en) * 2019-09-23 2020-01-03 李贺清 Deep foundation pit slope quicksand handling method
CN111021385A (en) * 2019-12-18 2020-04-17 宁蔚蔚 Precipitation method for treating quicksand when manual hole digging pile hole digging meets quicksand layer
CN111305241A (en) * 2019-12-18 2020-06-19 宁蔚蔚 Method for treating quicksand in hole digging of manual hole digging pile through light well point dewatering

Similar Documents

Publication Publication Date Title
CN105178289B (en) Precast dewatering pile tube and its application method in building foundation pit
CN106930304A (en) Drift sand base pit dewatering construction method
CN103967028A (en) Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure
CN103031834B (en) Low-position vacuum preloading rapid reinforcement method of soft foundation in hydraulic filling and reclamation
CN210066791U (en) A precipitation combined system that is used for foundation ditch pressure release precipitation and dredges precipitation
CN110439503B (en) Selective water plugging method for fractured low-permeability reservoir multi-section plug oil well
CN104314090A (en) Deep foundation pit bedrock drainage culvert and drainage system and drainage construction method thereof
CN105544573B (en) Water pressure jetting type well completion construction method of dewatering tube well
CN105064383A (en) Pipe-inserting negative pressure air jet deep-well dewatering device
CN110984200B (en) Method for draining water of foundation pit of binary geological structure layer
CN113279421A (en) Vacuum dewatering process for deep foundation pit
CN105453748A (en) Stereo totally-closed greening vacuum alkali removing device and application method thereof
CN105359659A (en) Wind-power vacuum alkali reduction apparatus for reclamation of saline and alkaline land and use method of apparatus
CN103615014B (en) A kind of dewatering device of soft soil foundation pit and using method thereof
CN206256457U (en) A kind of priming device of foundation pit side-wall
CN205012325U (en) Prefabricated precipitation tubular pile in building foundation
CN112195945A (en) Deep foundation pit construction method for keeping groundwater dynamically balanced
CN204401640U (en) Dewatering installation at the bottom of Foundation Pit
CN204609897U (en) A kind of pipe curtain freezing process supporting and protection structure
CN110185051A (en) Deep narrow excavation water discharge method
CN205348204U (en) Light well point precipitation system
CN114575359A (en) Weak-permeability soil layer slope groundwater disaster treatment method
CN106988330A (en) Soft soil foundation is layered dewatering construction structure and construction method
CN203475453U (en) Deeply-buried type bearing platform curtain structure of bridge
CN107268547A (en) Karst funnel reservoir and its flood releasing structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170707