CN106920068A - Electricity power engineering pricing management of the one kind based on big data and " internet+" - Google Patents
Electricity power engineering pricing management of the one kind based on big data and " internet+" Download PDFInfo
- Publication number
- CN106920068A CN106920068A CN201710038373.1A CN201710038373A CN106920068A CN 106920068 A CN106920068 A CN 106920068A CN 201710038373 A CN201710038373 A CN 201710038373A CN 106920068 A CN106920068 A CN 106920068A
- Authority
- CN
- China
- Prior art keywords
- cost
- data
- deviation
- project
- internet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000005611 electricity Effects 0.000 title claims abstract description 29
- 238000010276 construction Methods 0.000 claims abstract description 43
- 238000004458 analytical method Methods 0.000 claims abstract description 37
- 238000005516 engineering process Methods 0.000 claims abstract description 33
- 238000007726 management method Methods 0.000 claims abstract description 23
- 238000000034 method Methods 0.000 claims abstract description 11
- 238000000205 computational method Methods 0.000 claims description 7
- 238000013461 design Methods 0.000 claims description 5
- 210000004556 brain Anatomy 0.000 claims description 3
- 238000004891 communication Methods 0.000 claims description 3
- 238000012544 monitoring process Methods 0.000 claims description 3
- 238000003012 network analysis Methods 0.000 claims description 3
- 230000005540 biological transmission Effects 0.000 abstract description 3
- 239000000463 material Substances 0.000 description 4
- 238000011161 development Methods 0.000 description 3
- 238000004140 cleaning Methods 0.000 description 2
- 238000009430 construction management Methods 0.000 description 2
- 230000006378 damage Effects 0.000 description 2
- 238000007405 data analysis Methods 0.000 description 2
- 238000011156 evaluation Methods 0.000 description 2
- 208000027418 Wounds and injury Diseases 0.000 description 1
- 230000002159 abnormal effect Effects 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 239000003086 colorant Substances 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 238000013480 data collection Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 208000014674 injury Diseases 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Theoretical Computer Science (AREA)
- Health & Medical Sciences (AREA)
- Entrepreneurship & Innovation (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Public Health (AREA)
- Primary Health Care (AREA)
- General Health & Medical Sciences (AREA)
- Data Mining & Analysis (AREA)
- Water Supply & Treatment (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The electricity power engineering pricing management based on big data and " internet+" the invention discloses one kind, the method is mainly with big data technology, collect and count the history cost data of the power network construction project built, it is analyzed with project in construction Construction Cost Data, it was found that the problems such as cost overrun or progress fall behind, carries out early warning;With " internet+" technology, develop a set of site supervision mobile terminal of mobile telephone, occurs early warning signal when in system logging data and when the cost accounting stage Cost Problems occurs and alarmed, triggering system sends messages to field engineering supervisor, mobile phone A PP receives the message of background system transmission and pushes, onsite lookup analysis produces the concrete reason of Cost Problems after supervisor receives message, and then takes measures to remedy.
Description
Technical field
It is a kind of power network based on big data and " internet+" specifically the present invention relates to electricity power engineering cost field
Engineering Cost Management method.
Background technology
Power industry is the important energy source industrial department of Chinese national economy, is protected for Chinese society economic development provides the energy
Barrier, the construction and stable operation of electricity power engineering not only directly affect the development of macroeconomy and power industry itself, how to do
Good electricity power engineering cost is all the time a huge difficult problem in electricity power engineering process of construction.Current Engineering Cost Management mould
Under formula, constituent parts carry out analysis of prices basic data collection work and are mainly by collecting and collecting calculating manually, to cost
Need to be collected substantial amounts of data in analysis foundation data-gathering process, count, calculate the treatment such as analysis, these Information Numbers
According to measuring, huge, data structure is complicated, collection is arranged and amount of calculation is big, easily causes that analysis of prices result is inaccurate, and influence is made
Valency analyze data accuracy, influences the fairness and science of cost horizontal analysis.
With the development of big data and " internet+" technology, big data technology is dissolved into electricity power engineering Cost Management, number
According to becoming more comprehensive, accurate, the accuracy and reliability of electricity power engineering Cost Management are greatly improved, by " internet+"
Technology is dissolved into electricity power engineering Cost Management, and data results are sent in real time with alert data by tool of communications of APP
Engineering site supervisor, so that staff takes emergency measures in time when there is deviation pre-alert, greatly
Improve the accuracy and reliability of construction costs cost accounting.
The content of the invention
Scientific and reasonable it is an object of the present invention to provide one kind, data system is comprehensive, true and reliable, and practical value is high, can
Scientific and reasonable construction costs prediction and the cost reality based on big data He " internet+" is effectively carried out to power network construction project
When the management method that monitors.
Realizing the technical scheme that the object of the invention is used is, electricity power engineering of the one kind based on big data and " internet+" is made
Valency management method, it is characterized in that, it includes based on big data and internet+authorizing standard, data inputting, monitor in real time with it is pre-
Police, cost accounting, deviation alarm and the partial content of variance analysis six.
The authorizing standard:One is before project carries out cost always estimation, according to project location according to file and items
Expense basis, works out a set of universal general expenses computational methods and foundation for being adapted to all power network construction projects.Two
It is using big data technology, with reference to all of establishing criteria, while power network construction project and individual character standard to some individual characteies are not
Give use and use for reference, the general expenses computational methods of design is possessed versatility and practicality as far as possible;
The data inputting:One is to calculate standard according to the data of establishment to carry out the typing of this projects cost information,
Including architectural engineering expense, original equipment cost, installing engineering expense and general expenses etc. other expenditure;Two is to utilize big data technology,
Horizontal database (the similar electricity power engineering project other regions database built both at home and abroad) and longitudinal database are extracted in real time
(this area similar projects database) selection indicators, and different weights are assigned respectively, an a reference value is calculated, with such
Push away, each expense obtains a reference value with the method.Then when the typing of each item data is carried out, a reference value is used for and is building
Project this expense is analyzed, and is easy to promptly and accurately find deviation;Three is to utilize internet+technology, can supported web page
Form distant inputing;
The monitor in real time and early warning:One is according to horizontal database (the similar electricity power engineering project built both at home and abroad
Other regions database) and longitudinal database (this area similar projects database) cost estimate data, emphasize cost management
Implementing monitoring.In the project implementation process, the cost data and horizontal database and longitudinal data that each progress record is arranged
Kucheng's notebook data is contrasted, and to complete monitor in real time, both differences is analyzed and adjusted, the ring to producing larger difference
Section carries out emergency advance warning in time, is controlled with taking emergency measures;Two is that early warning is carried out when emphasizing to occur cost warp.In reality
During the data inputting of border, according to history item Construction Cost Data and this project budget expense, if there is deviation beyond rule
Fixed disparity range, then system send signal, carry out first time early warning;
The cost accounting:One is the engineering general expenses cost such as brain tactic, plant equipment cost and social cost
Adjust;Two is that, using big data technology, the cost of accounting compared with this project budget cost data, and will will not only pass through
It is compared with horizontal database and longitudinal database cost accounting information, whether analysis project in construction produces deviation, and will divide
The data of analysis are stored in this project database, are finally incorporated to longitudinal database, are easy to future reference to use for reference;
The deviation alarm:On the one hand the result of cost accounting is shown in the form of form, and when deviation is produced,
System can automatically send alarm, and alert methods have three kinds, and one is the green alarm signal of system display, two when deviation is within 3%
It is that, when deviation is in 3%-5%, system shows yellow alarm signal, three is the system display red alarm letter when deviation is more than 5%
Number;On the other hand " internet+" technology is used, when deviation is produced, a set of site supervision mobile phone A PP is developed, once in cost
There are Cost Problems in the accounting stage (including interim and final accounting) when being alarmed, and PUSH message gives field engineering supervisor
Member, is easy to analysis to produce the concrete reason of deviation;
The variance analysis:One is first 3 that this deviation is produced using analysis in big data technology at home and abroad engineering
Main cause, and be according to this that foundation is pushed in the APP of supervisor, allow it to be selected, if other side does not approve these three
Reason, can also illustrate the viewpoint of oneself and upload in APP interfaces;Two is to carry out retrospective analysis to the deviation for occurring, and finds expense
The root place of deviation is produced with data, i.e., most starts the data of deviation occur, then in conjunction with field engineering supervisor feedback
The deviation concrete reason and the network analysis result that are possible to produce be combined analysis, obtain last variance analysis result,
And showed in the form of form.
Electricity power engineering pricing management based on big data He " internet+" of the invention, due to possess authorizing standard,
Data inputting, monitor in real time and early warning, cost accounting, deviation alarm and a set of specific flow comprehensively of variance analysis, use
Big data technology, collects and counts the history cost data of the power network construction project built, with project in construction construction costs number
According to being analyzed, the problems such as cost overrun or progress fall behind is found, carry out early warning;With " internet+" technology, exploitation one
Set site supervision mobile terminal of mobile telephone, occurs early warning signal when in system logging data and occurs into the cost accounting stage
When this problem is alarmed, triggering system sends messages to field engineering supervisor, and mobile phone A PP receives background system transmission
Message is simultaneously pushed, and onsite lookup analysis produces the concrete reason of Cost Problems after supervisor receives message, and then takes measures
Remedy.With scientific and reasonable, data system is comprehensive, true and reliable, and practical value is high, can effectively to power network construction project work
Journey cost information carries out full forecast and cost monitor in real time, so as to the loss for avoiding occurring because cost control is improper.
Brief description of the drawings
Fig. 1 is the Grid Construction Project cost flow chart based on big data He " internet+".
Specific embodiment
To realize the purpose of the present invention, the present invention is described in detail below:
As shown in figure 1, a kind of electricity power engineering pricing management based on big data and " internet+" of the invention, will
Big data technology and " internet+" technology are dissolved into electricity power engineering Cost Management;By data results and alert data with APP
It is sent to engineering site supervisor in real time for tool of communications, is adjusted to occur to be taken emergency measures in time during deviation pre-alert
Control.
Authorizing standard, data inputting, monitor in real time and early warning, cost accounting, deviation based on big data and " internet+"
Alarm and the partial content of variance analysis six;
(1) level of organization:Before project carries out cost always estimation, by big data analysis platform, horizontal database is extracted
(the similar electricity power engineering project other regions database built both at home and abroad) and longitudinal database (this area similar projects data
Storehouse) preferred generic index as establishment general expenses computational methods and foundation, it is noted that with reference to all when selection gist
Establishing criteria, delete it is small-scale use, personalized standard, some highly versatiles, practical application rate standard high are refined
Out, the general expenses computational methods of design are made to possess versatility and practicality as far as possible, so that it is a set of suitable all to conclude establishment
The universal general expenses computational methods and foundation of power network construction project, that is, the so-called universal standard.
(2) data inputting:Calculating standard according to the data of establishment carries out the typing of projects cost information, can entry item
Mesh expense includes four major classes, is respectively architectural engineering expense, original equipment cost, installing engineering expense and other expenditure.Wherein, work is built
Journey is taken including installation cost, fee of material and labour cost.Installing engineering expense includes direct cost, indirect expense, profit and tax, directly
Expense include direct engineering cost and measure expense, wherein direct engineering cost include labour cost, fee of material (quota fee of material and mainly
Fee of material) and construction machinery usage charges, measure expense includes that fees for construction site facilities, safety construction measure expense, construction tool are used
Amount usage charges, construction during rainy and winter season increase expense, the increase that carries on construction work at night and take and Special section construction increase expense;Indirect expense includes enterprise
Administration fee and set-fee, wherein set-fee take including cost of social security, public accumalation fund for housing construction and dangerous operation accident/injury insurance.Other take
With including build place take over for use and cleaning take, project construction management expense, project construction technical service fee, engineering construction supervisory detection
Take, Operational preparation takes and basic reserve fund.Wherein, build place requisition and clear up and take including excess cleaning expense, the interim rent of construction
Expense, road construction damages and other fees;Project construction management take including project management funds, project supervision expense and other
Expense;Project construction technical service fee include engineering design expense, design document evaluation take, after project evaluation take, Technological Economy mark
Quasi- establishment administration fee and other fees.
While data inputting, by big data analysis platform, (that has built both at home and abroad is similar to extract horizontal database
Electricity power engineering project other regions database) and longitudinal database (this area similar projects database) in it is above-mentioned can typing expense
Preference data, and assign different weight coefficients respectively, be calculated a reference value of each fee forecast, a reference value is used for
Each cost data with the typing of this project is analyzed, caused by both can timely having avoided staff due to carelessness
The huge mistake of data inputting, while also allow for finding deviation in time, and utilizes internet+technology, can supported web page form it is remote
Journey typing.
(3) monitor in real time and early warning.
Using big data technology, according to the history cost estimate data and project of having built same type electricity power engineering project
The cost estimate data of the same type electricity power engineering project that location is being built, to the cost management implementing monitoring of project.
In the project implementation process, it is right that the cost data that each progress record of grassroot project is arranged is carried out with horizontal and vertical data
Than so as to realize monitor in real time, will not only produce abnormal information collect being stored in this project database, while being incorporated to local
Area's similar projects database, and both differences are analyzed and adjusted, the link for producing larger difference is met an urgent need
Early warning, so that staff takes emergency measures in time.During actually data inputting is carried out, if it find that
When the deviation of logging data is beyond the disparity range of regulation, that is, when there are gross differences, system is simultaneously emitted by signal, carries out
First time early warning.
(4) cost accounting.
System can be adjusted to the engineering general expenses cost such as brain tactic, plant equipment cost and social cost, no
Only account cost is compared with this project budget cost data, and can utilize big data technology, by account cost with it is built
If the cost accounting situation of the same type electricity power engineering project that same type electricity power engineering project and project location are being built
It is compared, whether analysis project in construction produces deviation, and data and analysis result then are stored in into this project database, while
This area similar projects database is incorporated to, is easy to future reference to use for reference.
(5) deviation alarm.
When there is deviation alarm, alarm signal in different colors is shown different deviation levels by system, works as appearance
Within 3%, the green alarm signal of display, when deviation is between 3%-5%, shows yellow alarm signal, when deviation is big to deviation
When 5%, red alarm signal is shown.At the same time, deviation alarm information is stored in this project database and this area is same
Intermediate item database.With " internet+" technology, when deviation is produced, develop a set of site supervision mobile phone A PP, once into
There are Cost Problems in this accounting stage (including interim and final accounting) when being alarmed, and PUSH message gives field engineering management
Personnel, are easy to analysis to produce the concrete reason of deviation.
(6) variance analysis.
Variance analysis detailed process includes two stages, and one is to collect deviating cause, using big data technology at home and abroad
Preceding 3 main causes for producing this deviation are analyzed in engineering, then is that foundation is pushed to supervision by this based on internet+technology
In the APP of personnel, allow it to be selected, if other side does not approve these three reasons, the sight of oneself can be also illustrated in APP interfaces
Put and upload;Two is deviation comprehensive analysis, and system carries out retrospective analysis to the deviation for occurring, and finds cost data and produces deviation
Where root, i.e., most start the data of deviation occur, the deviation then in conjunction with field engineering supervisor feedback is possible to produce
Concrete reason and network analysis result be combined analysis, obtain last variance analysis result, and be in the form of form
Reveal and.
Electricity power engineering pricing management based on big data He " internet+" of the invention, due to possess authorizing standard,
Data inputting, monitor in real time and early warning, cost accounting, deviation alarm and a set of specific flow comprehensively of variance analysis, use
Big data technology, collects and counts the history cost data of the power network construction project built, with project in construction construction costs number
According to being analyzed, the problems such as cost overrun or progress fall behind is found, carry out early warning;With " internet+" technology, exploitation one
Set site supervision mobile terminal of mobile telephone, occurs early warning signal when in system logging data and occurs into the cost accounting stage
When this problem is alarmed, triggering system sends messages to field engineering supervisor, and mobile phone A PP receives background system transmission
Message is simultaneously pushed, and onsite lookup analysis produces the concrete reason of Cost Problems after supervisor receives message, and then takes measures
Remedy.With scientific and reasonable, data system is comprehensive, true and reliable, and practical value is high, can effectively to power network construction project work
Journey cost information carries out full forecast and cost monitor in real time, so as to the loss for avoiding occurring because cost control is improper.
Claims (4)
1. one kind is based on the electricity power engineering pricing management of big data and " internet+", it is characterised in that by big data technology
" internet+" technology is dissolved into electricity power engineering Cost Management;By data results and alert data with APP as tool of communications
Engineering site supervisor is sent in real time, to occur to take emergency measures in time during deviation pre-alert.
2. one kind according to claim 1 is based on the electricity power engineering pricing management of big data and " internet+", and it is special
Levy and be, including the authorizing standard based on big data and " internet+", data inputting, monitor in real time and early warning, cost accounting,
Deviation alarm and the partial content of variance analysis six;
Authorizing standard:One is before project carries out cost always estimation, to be calculated according to file and general expenses according to project location
Foundation, works out a set of universal general expenses computational methods and foundation for being adapted to all power network construction projects;Two is using big
Data technique, with reference to all of establishing criteria, while the power network construction project and individual character standard to some individual characteies refuse using and
Use for reference, the general expenses computational methods of design is possessed versatility and practicality as far as possible;
Data inputting:One is to calculate standard according to the data of establishment to carry out the typing of this projects cost information, including building
The general expenses such as engineering cost, original equipment cost, installing engineering expense and other expenditure;Two is, using big data technology, to extract in real time
Horizontal database and longitudinal database selection indicators, and different weights are assigned respectively, an a reference value is calculated, with such
Push away, each expense obtains a reference value with the method;Then when the typing of each item data is carried out, a reference value is used for and is building
Project this expense is analyzed, and is easy to promptly and accurately find deviation;Three is to utilize internet+technology, can supported web page
Form distant inputing;
Monitor in real time and early warning:One is, according to horizontal database and longitudinal database cost estimate data, to emphasize cost management
Implementing monitoring;In the project implementation process, the cost data and horizontal database and longitudinal data that each progress record is arranged
Kucheng's notebook data is contrasted, and to complete monitor in real time, both differences is analyzed and adjusted, the ring to producing larger difference
Section carries out emergency advance warning in time, is controlled with taking emergency measures;Two is that early warning is carried out when emphasizing to occur cost warp;In reality
During the data inputting of border, according to history item Construction Cost Data and this project budget expense, if there is deviation beyond rule
Fixed disparity range, then system send signal, carry out first time early warning;
Cost accounting:One is the accounting of the engineering general expenses cost such as brain tactic, plant equipment cost and social cost;Two are
Using big data technology, the cost of accounting not only will compared with this project budget cost data, and will by with horizontal number
It is compared according to storehouse and longitudinal database cost accounting information, whether analysis project in construction produces deviation, and the data that will be analyzed
This project database is stored in, longitudinal database is finally incorporated to, is easy to future reference to use for reference;
Deviation alarm:On the one hand the result of cost accounting is shown in the form of form, and when deviation is produced, system can be certainly
Dynamic to send alarm, alert methods have three kinds, and one is the green alarm signal of system display when deviation is within 3%, and two is to work as deviation
In 3%-5%, system display yellow alarm signal, three is the system display red alarm signal when deviation is more than 5%;The opposing party
Face uses " internet+" technology, when deviation is produced, develops a set of site supervision mobile phone A PP, once go out in the cost accounting stage
When existing Cost Problems are alarmed, PUSH message gives field engineering supervisor, is easy to analysis to produce the concrete reason of deviation;
Variance analysis:One is preceding 3 main causes that this deviation is produced using analysis in big data technology at home and abroad engineering,
And be according to this according to being pushed in the APP of supervisor, to allow it to be selected, if other side does not approve these three reasons, also may be used
The viewpoint of oneself is illustrated in APP interfaces and is uploaded;Two is to carry out retrospective analysis to the deviation for occurring, and finds cost data generation
Where the root of deviation, i.e., most start the data of deviation occur, the deviation fed back then in conjunction with field engineering supervisor has can
The concrete reason that can be produced is combined analysis with network analysis result, obtains last variance analysis result, and with form
Form is showed.
3. one kind according to claim 2 is based on the electricity power engineering pricing management of big data and " internet+", and it is special
Levy and be, with big data technology, collected from horizontal and vertical two dimensions and power network construction project that statistics has been built is gone through
History cost data, are analyzed using two weighted sums of each index of dimension and project in construction Construction Cost Data,
It was found that the problems such as cost overrun or progress fall behind, carries out early warning.
4. one kind according to claim 2 is based on the electricity power engineering pricing management of big data and " internet+", and it is special
Levy and be, the horizontal database is the similar electricity power engineering project other regions database built both at home and abroad;The longitudinal direction
Database is this area similar projects database.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710038373.1A CN106920068A (en) | 2017-01-19 | 2017-01-19 | Electricity power engineering pricing management of the one kind based on big data and " internet+" |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710038373.1A CN106920068A (en) | 2017-01-19 | 2017-01-19 | Electricity power engineering pricing management of the one kind based on big data and " internet+" |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106920068A true CN106920068A (en) | 2017-07-04 |
Family
ID=59454038
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710038373.1A Pending CN106920068A (en) | 2017-01-19 | 2017-01-19 | Electricity power engineering pricing management of the one kind based on big data and " internet+" |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106920068A (en) |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107527148A (en) * | 2017-08-24 | 2017-12-29 | 北京融通智慧科技有限公司 | The building site project management system of power network wisdom building site control platform |
CN107527185A (en) * | 2017-08-04 | 2017-12-29 | 昆明理工大学 | A kind of project cost documentation and the parallel practice method examined |
CN108182521A (en) * | 2017-12-25 | 2018-06-19 | 浙江东南建设管理有限公司 | A kind of project supervision approaches to IM and system |
CN108549988A (en) * | 2018-04-17 | 2018-09-18 | 万翼科技有限公司 | The treating method and apparatus of problem |
CN109213816A (en) * | 2018-08-06 | 2019-01-15 | 国网福建省电力有限公司信息通信分公司 | A method of early warning analysis is carried out based on the electric network data obtained in real time |
CN109447522A (en) * | 2018-12-03 | 2019-03-08 | 今天誉讯(北京)科技有限公司 | A method of it is applied based on project cost internet big data |
CN109493003A (en) * | 2018-11-08 | 2019-03-19 | 国家电网有限公司 | Item data management method and terminal device |
CN109784689A (en) * | 2018-12-28 | 2019-05-21 | 远光软件股份有限公司 | A kind of power grid infrastructure project method for processing report data |
CN110428275A (en) * | 2019-01-28 | 2019-11-08 | 北京海数宝科技有限公司 | Data processing method, device, storage medium and the computer equipment of multizone price |
CN110610318A (en) * | 2019-09-18 | 2019-12-24 | 邓嘉明 | Engineering cost management system based on big data |
CN111062827A (en) * | 2019-12-30 | 2020-04-24 | 四川省城市建设工程监理有限公司 | Engineering supervision method based on artificial intelligence mode |
CN111695833A (en) * | 2020-06-22 | 2020-09-22 | 陕西国防工业职业技术学院 | Engineering cost risk prediction and assessment method |
CN111861725A (en) * | 2020-07-30 | 2020-10-30 | 重庆富民银行股份有限公司 | Three-party data source cost accounting method and system |
CN111882453A (en) * | 2020-06-21 | 2020-11-03 | 国网河北省电力有限公司信息通信分公司 | Power grid enterprise management system based on novel technology application of cloud migration intelligence |
CN112036815A (en) * | 2020-08-20 | 2020-12-04 | 湖北四位元电力有限公司 | Method for establishing power distribution network engineering cost index system |
CN112035539A (en) * | 2020-08-20 | 2020-12-04 | 湖北四位元电力有限公司 | Power distribution network engineering cost compiling and auditing application system |
CN112396336A (en) * | 2020-11-27 | 2021-02-23 | 国网天津市电力公司 | Intelligent evaluation system and evaluation method for power transmission and transformation project cost |
CN112734369A (en) * | 2020-12-31 | 2021-04-30 | 大为国际工程咨询有限公司 | Engineering cost management system based on big data |
CN112990532A (en) * | 2020-12-26 | 2021-06-18 | 广东电网有限责任公司 | Power distribution network construction cost accounting system and method |
CN113269529A (en) * | 2021-05-31 | 2021-08-17 | 重庆创新工程咨询有限公司 | Building engineering cost's control system based on BIM model |
CN113568935A (en) * | 2021-07-30 | 2021-10-29 | 重庆电子工程职业学院 | Engineering cost quota dynamic management platform based on big data |
CN113885447A (en) * | 2021-01-04 | 2022-01-04 | 蒙娜丽莎集团股份有限公司 | Real-time process cost accounting equipment suitable for building pottery trade |
CN114611980A (en) * | 2022-03-23 | 2022-06-10 | 武汉有方设计有限公司 | Engineering project cost analysis method, equipment and computer storage medium |
-
2017
- 2017-01-19 CN CN201710038373.1A patent/CN106920068A/en active Pending
Cited By (29)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107527185A (en) * | 2017-08-04 | 2017-12-29 | 昆明理工大学 | A kind of project cost documentation and the parallel practice method examined |
CN107527148A (en) * | 2017-08-24 | 2017-12-29 | 北京融通智慧科技有限公司 | The building site project management system of power network wisdom building site control platform |
CN107527148B (en) * | 2017-08-24 | 2021-04-02 | 北京融通智慧科技有限公司 | Building site project management system of power grid smart building site management and control platform |
CN108182521A (en) * | 2017-12-25 | 2018-06-19 | 浙江东南建设管理有限公司 | A kind of project supervision approaches to IM and system |
CN108549988A (en) * | 2018-04-17 | 2018-09-18 | 万翼科技有限公司 | The treating method and apparatus of problem |
CN109213816A (en) * | 2018-08-06 | 2019-01-15 | 国网福建省电力有限公司信息通信分公司 | A method of early warning analysis is carried out based on the electric network data obtained in real time |
CN109493003A (en) * | 2018-11-08 | 2019-03-19 | 国家电网有限公司 | Item data management method and terminal device |
CN109447522A (en) * | 2018-12-03 | 2019-03-08 | 今天誉讯(北京)科技有限公司 | A method of it is applied based on project cost internet big data |
CN109784689A (en) * | 2018-12-28 | 2019-05-21 | 远光软件股份有限公司 | A kind of power grid infrastructure project method for processing report data |
CN109784689B (en) * | 2018-12-28 | 2022-03-15 | 远光软件股份有限公司 | Power grid infrastructure project report data processing method |
CN110428275A (en) * | 2019-01-28 | 2019-11-08 | 北京海数宝科技有限公司 | Data processing method, device, storage medium and the computer equipment of multizone price |
CN110610318A (en) * | 2019-09-18 | 2019-12-24 | 邓嘉明 | Engineering cost management system based on big data |
CN111062827A (en) * | 2019-12-30 | 2020-04-24 | 四川省城市建设工程监理有限公司 | Engineering supervision method based on artificial intelligence mode |
CN111062827B (en) * | 2019-12-30 | 2023-07-18 | 四川省城市建设工程咨询集团有限公司 | Engineering supervision method based on artificial intelligence mode |
CN111882453A (en) * | 2020-06-21 | 2020-11-03 | 国网河北省电力有限公司信息通信分公司 | Power grid enterprise management system based on novel technology application of cloud migration intelligence |
CN111882453B (en) * | 2020-06-21 | 2023-09-08 | 国网河北省电力有限公司信息通信分公司 | Power grid enterprise management system based on application of cloud object intelligent-shifting new technology |
CN111695833A (en) * | 2020-06-22 | 2020-09-22 | 陕西国防工业职业技术学院 | Engineering cost risk prediction and assessment method |
CN111861725A (en) * | 2020-07-30 | 2020-10-30 | 重庆富民银行股份有限公司 | Three-party data source cost accounting method and system |
CN111861725B (en) * | 2020-07-30 | 2023-04-07 | 重庆富民银行股份有限公司 | Three-party data source cost accounting method and system |
CN112036815A (en) * | 2020-08-20 | 2020-12-04 | 湖北四位元电力有限公司 | Method for establishing power distribution network engineering cost index system |
CN112035539A (en) * | 2020-08-20 | 2020-12-04 | 湖北四位元电力有限公司 | Power distribution network engineering cost compiling and auditing application system |
CN112396336A (en) * | 2020-11-27 | 2021-02-23 | 国网天津市电力公司 | Intelligent evaluation system and evaluation method for power transmission and transformation project cost |
CN112990532A (en) * | 2020-12-26 | 2021-06-18 | 广东电网有限责任公司 | Power distribution network construction cost accounting system and method |
CN112734369A (en) * | 2020-12-31 | 2021-04-30 | 大为国际工程咨询有限公司 | Engineering cost management system based on big data |
CN113885447A (en) * | 2021-01-04 | 2022-01-04 | 蒙娜丽莎集团股份有限公司 | Real-time process cost accounting equipment suitable for building pottery trade |
CN113885447B (en) * | 2021-01-04 | 2024-05-17 | 蒙娜丽莎集团股份有限公司 | Real-time process cost accounting equipment suitable for ceramic building industry |
CN113269529A (en) * | 2021-05-31 | 2021-08-17 | 重庆创新工程咨询有限公司 | Building engineering cost's control system based on BIM model |
CN113568935A (en) * | 2021-07-30 | 2021-10-29 | 重庆电子工程职业学院 | Engineering cost quota dynamic management platform based on big data |
CN114611980A (en) * | 2022-03-23 | 2022-06-10 | 武汉有方设计有限公司 | Engineering project cost analysis method, equipment and computer storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106920068A (en) | Electricity power engineering pricing management of the one kind based on big data and " internet+" | |
CN105416343B (en) | A kind of track construction comprehensive pre-warning method and system | |
CN104952212A (en) | Power-grid-GIS-based early warning method of geological disaster and apparatus thereof | |
CN104678954A (en) | Dam safety intelligent monitoring and pre-warning system based on full life circle and method thereof | |
CN110858334A (en) | Road safety assessment method and device and road safety early warning system | |
KR101285044B1 (en) | Decision method for spillway discharge of hydroelectronic power plant at a flood season | |
CN104281920A (en) | Tailing pond layered index safety assessment and early-warning method and system | |
CN111074954A (en) | Deep foundation pit engineering safety monitoring system based on BIM | |
CN105096532A (en) | Geological disaster predication system | |
CN111042143A (en) | Foundation pit engineering early warning method and system based on analysis of large amount of monitoring data | |
CN106651074A (en) | Intelligent underground pipeline management system | |
CN112232722B (en) | Building equipment management system based on building information model technology | |
CN207301751U (en) | The engineering machinery vehicle operation monitoring system of power grid wisdom building site control platform | |
CN105388826A (en) | Method for establishing hybrid type rare earth mining area water environment quality monitoring and early warning system | |
CN106874671A (en) | A kind of algorithm of the data-driven for spontaneous fire in coal mine big data platform | |
CN114219289A (en) | Construction cost control method based on BIM and Internet of things technology | |
CN110121053A (en) | A kind of video monitoring method of situ of drilling well risk stratification early warning | |
CN103528613A (en) | Internet of Things dynamic monitoring and early warning method of major hazard source under coal mine | |
CN108448721A (en) | The method of electric system main station monitoring signal and standard signal Auto-matching | |
CN114483196A (en) | Subway shield tunnel structure safety state evaluation system | |
CN116579607A (en) | Multi-source data collaborative regional tailing pond risk monitoring method | |
CN104346695A (en) | Emergency dispatching circumstance generation method for water pollution emergency | |
Wu et al. | Research and application of intelligent monitoring system platform for safety risk and risk investigation in urban rail transit engineering construction | |
Jin et al. | The construction of builder safety supervision system based on CPS | |
CN117275188A (en) | Mountain torrent disaster monitoring and early warning system and mountain torrent disaster monitoring and early warning method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170704 |