CN106871381B - Defrosting operation method for air conditioner without stopping - Google Patents

Defrosting operation method for air conditioner without stopping Download PDF

Info

Publication number
CN106871381B
CN106871381B CN201710214072.XA CN201710214072A CN106871381B CN 106871381 B CN106871381 B CN 106871381B CN 201710214072 A CN201710214072 A CN 201710214072A CN 106871381 B CN106871381 B CN 106871381B
Authority
CN
China
Prior art keywords
heat exchanger
control valve
outdoor heat
outdoor
controlling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710214072.XA
Other languages
Chinese (zh)
Other versions
CN106871381A (en
Inventor
许文明
王飞
付裕
张明杰
丁爽
李波
任志强
罗荣邦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Haier Air Conditioner Gen Corp Ltd
Haier Smart Home Co Ltd
Qingdao Haier Jiaozhou Air Conditioner Co Ltd
Original Assignee
Qingdao Haier Air Conditioner Gen Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Haier Air Conditioner Gen Corp Ltd filed Critical Qingdao Haier Air Conditioner Gen Corp Ltd
Priority to CN201710214072.XA priority Critical patent/CN106871381B/en
Publication of CN106871381A publication Critical patent/CN106871381A/en
Application granted granted Critical
Publication of CN106871381B publication Critical patent/CN106871381B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F2110/00Control inputs relating to air properties
    • F24F2110/10Temperature
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/30Control or safety arrangements for purposes related to the operation of the system, e.g. for safety or monitoring
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/62Control or safety arrangements characterised by the type of control or by internal processing, e.g. using fuzzy logic, adaptive control or estimation of values
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B47/00Arrangements for preventing or removing deposits or corrosion, not provided for in another subclass
    • F25B47/02Defrosting cycles
    • F25B47/022Defrosting cycles hot gas defrosting
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B49/00Arrangement or mounting of control or safety devices
    • F25B49/02Arrangement or mounting of control or safety devices for compression type machines, plants or systems
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F11/00Control or safety arrangements
    • F24F11/62Control or safety arrangements characterised by the type of control or by internal processing, e.g. using fuzzy logic, adaptive control or estimation of values
    • F24F11/63Electronic processing
    • F24F11/64Electronic processing using pre-stored data

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Atmospheric Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Fuzzy Systems (AREA)
  • Mathematical Physics (AREA)
  • Signal Processing (AREA)
  • Air Conditioning Control Device (AREA)

Abstract

The invention discloses a defrosting operation method without shutdown of an air conditioner. The defrosting method for the air conditioner without stopping the machine comprises the following steps: controlling the heating operation of the air conditioner; detecting the outdoor environment temperature; adjusting the working state of the outdoor heat exchanger according to the outdoor environment temperature; detecting a temperature deviation between an indoor temperature and a set temperature when the outdoor heat exchanger is adjusted to a preset condition; and adjusting the working state of the outdoor heat exchanger according to the temperature deviation. According to the technical scheme, a proper control mode can be selected in the air conditioner operation process, the operation energy efficiency of the air conditioner is improved, and defrosting without stopping is achieved.

Description

Defrosting operation method for air conditioner without stopping
Technical Field
The invention relates to the technical field of air conditioning, in particular to a defrosting operation method without shutdown of an air conditioner.
Background
The existing air conditioner has the possibility of frosting in the heating operation process, and defrosting is needed after the frosting reaches a certain degree, otherwise, the heating effect is increasingly poor, but the indoor heating of the existing air conditioner is stopped in the defrosting process, even the indoor temperature is reduced, namely, the existing air conditioner is uncomfortable and cannot save energy.
Disclosure of Invention
The invention aims to provide a defrosting operation method without stopping an air conditioner, which can enable the air conditioner to defrost without stopping the air conditioner and improve the comfort level of the air conditioner.
According to an aspect of the present invention, there is provided a defrosting method for an air conditioner without stopping operation, comprising: controlling the heating operation of the air conditioner; detecting the outdoor environment temperature; adjusting the working state of the outdoor heat exchanger according to the outdoor environment temperature; detecting a temperature deviation between an indoor temperature and a set temperature when the outdoor heat exchanger is adjusted to a preset condition; and adjusting the working state of the outdoor heat exchanger according to the temperature deviation, so that one of the first outdoor heat exchanger and the second outdoor heat exchanger operates to absorb heat, and the other one operates to release heat and defrost.
Preferably, the step of adjusting the operating state of the outdoor heat exchanger according to the outdoor ambient temperature includes: and when the outdoor environment temperature is less than or equal to T1, the first control valve, the fourth control valve, the fifth control valve and the seventh control valve are controlled to be opened, the second control valve, the third control valve and the sixth control valve are controlled to be closed, the first outdoor heat exchanger is controlled to absorb heat, and the second outdoor heat exchanger releases heat and defrosts.
Preferably, the preset conditions include: the coil temperature of the second outdoor heat exchanger is greater than T2 for more than time T1.
Preferably, the step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: and when the temperature deviation pn is less than or equal to T3, the second control valve, the third control valve, the fifth control valve and the seventh control valve are controlled to be opened, the first control valve, the fourth control valve and the sixth control valve are controlled to be closed, the first outdoor heat exchanger is controlled to release heat and defrost, and the second outdoor heat exchanger absorbs heat.
Preferably, the step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: when the temperature deviation pn is greater than T3, the second outdoor heat exchanger stops defrosting operation, and the first outdoor heat exchanger and the second outdoor heat exchanger are controlled to absorb heat simultaneously and last for T2 time; and the second control valve, the third control valve, the fifth control valve and the seventh control valve are controlled to be opened, the first control valve, the fourth control valve and the sixth control valve are controlled to be closed, the first outdoor heat exchanger is controlled to release heat and defrost, and the second outdoor heat exchanger is controlled to absorb heat.
Preferably, the step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: detecting the coil temperature of the first outdoor heat exchanger; and when the coil temperature of the first outdoor heat exchanger is more than T4 and the duration exceeds T3, controlling the third control valve, the fifth control valve and the sixth control valve to be opened, controlling the first control valve, the second control valve, the fourth control valve and the seventh control valve to be closed, and controlling the first outdoor heat exchanger and the second outdoor heat exchanger to absorb heat.
Preferably, the step of adjusting the operating state of the outdoor heat exchanger according to the outdoor ambient temperature includes: when the outdoor environment temperature is higher than T1, the second control valve, the third control valve, the fifth control valve and the seventh control valve are controlled to be opened, the first control valve, the fourth control valve and the sixth control valve are controlled to be closed, the first outdoor heat exchanger is controlled to release heat and defrost, and the second outdoor heat exchanger is controlled to absorb heat.
Preferably, the preset conditions include: the coil temperature of the first outdoor heat exchanger is greater than T5 for more than time T4.
Preferably, the step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: and when the temperature deviation pn is less than or equal to T6, controlling the first control valve, the fourth control valve, the fifth control valve and the seventh control valve to be opened, controlling the second control valve, the third control valve and the sixth control valve to be closed, controlling the first outdoor heat exchanger to absorb heat, and controlling the second outdoor heat exchanger to release heat and defrost.
Preferably, the step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: when the temperature deviation pn is greater than T6, the first outdoor heat exchanger stops defrosting operation, and the first outdoor heat exchanger and the second outdoor heat exchanger are controlled to absorb heat simultaneously and last for T5 time; and controlling the first control valve, the fourth control valve, the fifth control valve and the seventh control valve to be opened, controlling the second control valve, the third control valve and the sixth control valve to be closed, controlling the first outdoor heat exchanger to absorb heat, and controlling the second outdoor heat exchanger to release heat and defrost.
Preferably, the step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: detecting the coil temperature of the second outdoor heat exchanger; and when the coil temperature of the second outdoor heat exchanger is greater than T7 and the duration exceeds T6, controlling the third control valve, the fifth control valve and the sixth control valve to be opened, controlling the first control valve, the second control valve, the fourth control valve and the seventh control valve to be closed, and controlling the first outdoor heat exchanger and the second outdoor heat exchanger to absorb heat.
According to the technical scheme of the invention, in the operation process of the air conditioner, the outdoor environment temperature is detected firstly, and when the outdoor environment temperature is greater than a preset value, the heat exchange quantity between the outdoor environment temperature and the outdoor heat exchanger can meet the requirement of indoor heating, so that the operation mode of the outdoor heat exchanger can be adjusted according to the outdoor environment temperature, the first outdoor heat exchanger and the second outdoor heat exchanger are enabled to alternatively defrost, the energy consumption of the air conditioner is lower while the indoor temperature is kept in a proper range, and meanwhile, the defrosting without stopping is realized; when the outdoor heat exchanger is adjusted to the preset condition, the indoor temperature deviation can be detected, the air conditioner operation is further adjusted according to the detection result, the air conditioner can rapidly adjust the indoor temperature on the basis of keeping high operation energy efficiency, the indoor temperature can rapidly meet the user requirement, the operation energy efficiency of the air conditioner is improved, and the operation cost is reduced.
It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the invention, as claimed.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the invention and together with the description, serve to explain the principles of the invention.
Fig. 1 is a block diagram of an air conditioner according to an embodiment of the present invention;
FIG. 2 is a flow chart of a defrosting method for an air conditioner without stopping operation according to an embodiment of the present invention;
fig. 3 is a flowchart of a defrosting method for an air conditioner without stopping operation according to an embodiment of the present invention.
Description of reference numerals: 110. a compressor; 120. a four-way valve; 130. an indoor heat exchanger; 140. a first throttling device; 150. a first outdoor heat exchanger; 160. a second outdoor heat exchanger; 170. a second throttling device; 181. a first control valve; 182. a second control valve; 183. a third control valve; 184. a fourth control valve; 185. a fifth control valve; 186. a sixth control valve; 187. a seventh control valve.
Detailed Description
The following description and the drawings sufficiently illustrate specific embodiments of the invention to enable those skilled in the art to practice them. Other embodiments may incorporate structural, logical, electrical, process, and other changes. The examples merely typify possible variations. Individual components and functions are optional unless explicitly required, and the sequence of operations may vary. Portions and features of some embodiments may be included in or substituted for those of others. The scope of embodiments of the invention encompasses the full ambit of the claims, as well as all available equivalents of the claims. Embodiments may be referred to herein, individually or collectively, by the term "invention" merely for convenience and without intending to voluntarily limit the scope of this application to any single invention or inventive concept if more than one is in fact disclosed. Herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other like elements in a process, method or apparatus that comprises the element. The embodiments are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other. As for the methods, products and the like disclosed by the embodiments, the description is simple because the methods correspond to the method parts disclosed by the embodiments, and the related parts can be referred to the method parts for description.
Referring to fig. 1 in combination, an embodiment of the present invention provides an air conditioner, including a compressor 110, a four-way valve 120, an indoor heat exchanger 130, an outdoor heat exchanger, and a first throttling device 140, where the first throttling device 140 is disposed between the indoor heat exchanger 130 and the outdoor heat exchanger, the outdoor heat exchanger includes a first outdoor heat exchanger 150 and a second outdoor heat exchanger 160, and when the air conditioner is in heating operation, the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 have a first operating state in which the first outdoor heat exchanger 150 absorbs heat and the second outdoor heat exchanger 160 releases heat, a second operating state in which the first outdoor heat exchanger 150 releases heat and the second outdoor heat exchanger 160 absorbs heat, and a third operating state in which both the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 absorb heat, where a heat exchange area of the first outdoor heat exchanger 150 is S1, a heat exchange area of the second outdoor heat exchanger 160 is S2, wherein S1> S2.
When the second outdoor heat exchanger 160 needs defrosting, the air conditioner can be controlled to be in the first working state, at this time, the high-temperature and high-pressure refrigerant compressed by the compressor 110 firstly releases heat through the second outdoor heat exchanger 160 and the indoor heat exchanger 130, the refrigerant is used for indoor heating and defrosting of the second outdoor heat exchanger 160, and the refrigerant after heat exchange returns to the compressor 110 after absorbing heat through the first outdoor heat exchanger 150; when the first outdoor heat exchanger 150 needs defrosting, the air conditioner can be controlled to be in the second working state, at this time, the high-temperature and high-pressure refrigerant compressed by the compressor 110 firstly releases heat through the first outdoor heat exchanger 150 and the indoor heat exchanger 130, the refrigerant is used for indoor heating and defrosting of the first outdoor heat exchanger 150, and the refrigerant after heat exchange returns to the compressor 110 after absorbing heat through the second outdoor heat exchanger 160; when the outdoor unit of the air conditioner does not need defrosting, the air conditioner may be controlled to be in the third operating state, at this time, the high-temperature and high-pressure refrigerant compressed by the compressor 110 first releases heat through the indoor heat exchanger 130 for indoor heating, and the heat-exchanged refrigerant returns to the compressor 110 after absorbing heat through the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160.
The heat exchange area of the first outdoor heat exchanger 150 is S1, the heat exchange area of the second outdoor heat exchanger 160 is S2, the heat exchange area S of the outdoor heat exchanger is S1+ S2, optionally S1 is 70% S, and S2 is 30% S. The sizes of S1 and S2 can be set by those skilled in the art according to actual needs, S1 and S2 can be the same, and the heat exchange areas of the two outdoor heat exchangers are set to different values, so that the air conditioner can be adjusted according to different heat exchange amounts of indoor requirements, the indoor heating requirement can be met, and the outdoor heat exchangers can be ensured to defrost alternately, and the comfort level of the air conditioner can be improved.
According to the above technical scheme, when the air conditioner is operated for heating, when the outdoor heat exchange is required to be defrosted, the second outdoor heat exchanger 160 can be defrosted firstly, namely, the air conditioner is in the first working state, or the first outdoor heat exchanger 150 can be defrosted firstly, namely, the air conditioner is in the second working state, after the defrosting of the firstly defrosted outdoor heat exchanger is finished, the other outdoor heat exchanger is defrosted, so that when the air conditioner is defrosted, the indoor heating is not stopped, the indoor heat exchanger 130 is always in the heat release working state, and the comfort level of the air conditioner is improved.
As shown in fig. 1, an embodiment of the present invention provides an air conditioner, wherein a first end C of a first outdoor heat exchanger 150 is connected to a first interface a of a four-way reversing valve through a first pipeline, and is connected to a second interface B of the four-way reversing valve through a second pipeline, a first end E of a second outdoor heat exchanger 160 is connected to the first interface a of the four-way reversing valve through a third pipeline, and is connected to the second interface B of the four-way reversing valve through a fourth pipeline, a fifth pipeline, a sixth pipeline and a seventh pipeline are included between an indoor heat exchanger 130 and an outdoor heat exchanger, a first end G of the fifth pipeline is connected to a first end of the indoor heat exchanger 130, first ends of the sixth pipeline and the seventh pipeline are commonly connected to a second end H of the fifth pipeline, a second end of the sixth pipeline is connected to the first end C of the first outdoor heat exchanger 150, a second end of the seventh pipeline is respectively connected to a first branch and a second branch, the first branch is connected to the second end D of the first outdoor heat exchanger 150, the second branch is connected to the second end F of the second outdoor heat exchanger 160, the first pipeline is provided with a first control valve 181, the second pipeline is provided with a second control valve 182, the third pipeline is provided with a third control valve 183, the fourth pipeline is provided with a fourth control valve 184, the fifth pipeline is provided with a fifth control valve 185 and a first throttling device 140, the sixth pipeline is provided with a sixth control valve 186, the seventh pipeline is provided with a seventh control valve 187, and the second branch is provided with a second throttling device 170.
The fifth control valve 185 is used to cut off the paths of the indoor heat exchanger 130 and the outdoor heat exchanger, so that no new refrigerant flows into the outdoor heat exchanger after the refrigerant flows back to the compressor during later air-conditioning maintenance.
When the air conditioner is in heating operation, a high-temperature and high-pressure refrigerant flows out from the second interface B of the four-way valve 120, the first end C of the first outdoor heat exchanger 150 is connected with the second interface B of the four-way valve 120 through a second pipeline, the second control valve 182 is used for controlling the high-temperature and high-pressure refrigerant to flow through the first outdoor heat exchanger 150 to release heat and defrosting the first outdoor heat exchanger 150, meanwhile, the first end C of the first outdoor heat exchanger 150 is connected with the first interface a of the four-way valve 120 through a first pipeline, the first control valve 181 is used for controlling the refrigerant absorbing heat through the first outdoor heat exchanger 150 to flow back to the compressor 110, when the first outdoor heat exchanger 150 normally works, the second control valve 182 is closed, the first control valve 181 is opened, and when the first outdoor heat exchanger 150 needs defrosting, the second control valve 182 is opened and the first control valve 181 is. The first end E of the second outdoor heat exchanger 160 is connected to the second interface B of the four-way valve 120 through a fourth pipeline, the fourth control valve 184 is configured to control a high-temperature and high-pressure refrigerant to flow through the second outdoor heat exchanger 160 for heat release, and is used for defrosting the second outdoor heat exchanger 160, meanwhile, the first end E of the second outdoor heat exchanger 160 is connected to the first interface a of the four-way valve 120 through a third pipeline, the third control valve 183 is configured to control a refrigerant that absorbs heat through the second outdoor heat exchanger 160 to flow back to the compressor 110, when the second outdoor heat exchanger 160 normally operates, the fourth control valve 184 is closed, the third control valve 183 is opened, and when the second outdoor heat exchanger 160 needs defrosting, the fourth control valve 184 is opened, and the third control valve 183 is closed.
In the air heating defrosting operation process, when the air conditioner is in the first operating state, the first control valve 181, the fourth control valve 184, the fifth control valve 185 and the seventh control valve 187 are opened, the second control valve 182, the third control valve 183 and the sixth control valve 186 are closed, the refrigerant compressed by the compressor 110 flows out through the second interface B of the four-way valve 120, a part of the refrigerant flows into the second outdoor heat exchanger 160 to release heat, a part of the refrigerant flows into the indoor heat exchanger 130 to release heat, the refrigerant flowing through the second outdoor heat exchanger 160 returns to the first outdoor heat exchanger 150 to absorb heat after passing through the second throttling device 170, the high-temperature and high-pressure refrigerant flowing through the indoor heat exchanger 130 also returns to the first outdoor heat exchanger 150 to absorb heat after passing through the first throttling device 140, and the refrigerant flows back to the compressor 110 after absorbing heat from the first outdoor heat exchanger 150 through the first interface a of the four-way valve 120; when the air conditioner is in the second operating state, the second control valve 182, the third control valve 183, the fifth control valve 185, and the seventh control valve 187 are opened, the first control valve 181, the fourth control valve 184, and the sixth control valve 186 are closed, the refrigerant compressed by the compressor 110 flows out through the second port B of the four-way valve 120, a portion of the refrigerant flows into the first outdoor heat exchanger 150 to release heat, a portion of the refrigerant flows into the indoor heat exchanger 130 to release heat, the refrigerant flowing through the first outdoor heat exchanger 150 flows through the second throttling device 170 and then returns to the first outdoor heat exchanger 150 to absorb heat, the refrigerant flowing through the indoor heat exchanger 130 flows back to the second outdoor heat exchanger 160 through the second throttling device 170 again after passing through the first throttling device 140 to absorb heat, and the refrigerant flows back to the compressor 110 after absorbing heat from the second outdoor heat exchanger 160 through the first port a of the four-way valve 120.
In the heating non-defrosting operation process of the air conditioner, when the air conditioner is in a third operation state, when the air conditioner is in the third operation state, the third control valve 183, the fifth control valve 185 and the sixth control valve 186 are opened, the first control valve 181, the second control valve 182, the fourth control valve 184 and the seventh control valve 187 are closed, the refrigerant compressed by the compressor 110 flows out through the second interface B of the four-way valve 120, all flows into the indoor heat exchanger 130 to release heat, the refrigerant flowing out of the indoor heat exchanger 130 firstly absorbs heat through the first outdoor heat exchanger 150 after passing through the first throttling device 140, and then absorbs heat through the second outdoor heat exchanger 160 after passing through the second throttling device 170, and all the refrigerants are throttled twice and are gasified more thoroughly; the air conditioner can be in a fourth working state during the heating and defrosting-free working process, when the air conditioner is in the fourth working state, the first control valve 181, the third control valve 183, the fifth control valve 185 and the seventh control valve 187 are opened, the second control valve 182, the fourth control valve 184 and the sixth control valve 186 are closed, the refrigerant compressed by the compressor 110 flows out through the second interface B of the four-way valve 120, all flows into the indoor heat exchanger 130 to release heat, the refrigerant flowing out of the indoor heat exchanger 130 firstly passes through the indoor heat exchanger 130 to release heat, after passing through the first throttling device 140, a part of the refrigerant absorbs heat through the first outdoor heat exchanger 150 and directly returns to the compressor 110 through the first interface a of the four-way valve 120, the other part of the refrigerant absorbs heat through the second outdoor heat exchanger 160 after passing through the second throttling device 170 and then returns to the compressor 110 through the first interface a of the four-way valve 120, and the refrigerant passing through the second outdoor heat exchanger is throttled, the gasification is more thorough.
As shown in fig. 2 and fig. 3, an embodiment of the present invention further provides a defrosting method for an air conditioner without shutdown, including: controlling the heating operation of the air conditioner; detecting the outdoor environment temperature; adjusting the working state of the outdoor heat exchanger according to the outdoor environment temperature, wherein one of the first outdoor heat exchanger and the second outdoor heat exchanger operates to absorb heat, and the other one operates to release heat and defrost; detecting a temperature deviation between an indoor temperature and a set temperature when the outdoor heat exchanger is adjusted to a preset condition; and adjusting the working state of the outdoor heat exchanger according to the temperature deviation, so that one of the first outdoor heat exchanger and the second outdoor heat exchanger operates to absorb heat, and the other one operates to release heat and defrost.
In the operation process of the air conditioner, firstly, the outdoor environment temperature is detected, and when the outdoor environment temperature is greater than a preset value, the heat exchange quantity between the outdoor environment temperature and the outdoor heat exchanger can meet the requirement of indoor heating, so that the operation mode of the outdoor heat exchanger can be adjusted according to the outdoor environment temperature, the first outdoor heat exchanger and the second outdoor heat exchanger are enabled to alternatively defrost, the energy consumption of the air conditioner is low while the indoor temperature is kept in a proper range, and meanwhile, the defrosting without stopping is realized; when the outdoor heat exchanger is adjusted to the preset condition, the indoor temperature deviation can be detected, the air conditioner operation is further adjusted according to the detection result, the air conditioner can rapidly adjust the indoor temperature on the basis of keeping high operation energy efficiency, the indoor temperature can rapidly meet the user requirement, the operation energy efficiency of the air conditioner is improved, and the operation cost is reduced.
The step of adjusting the working state of the outdoor heat exchanger according to the outdoor environment temperature comprises the following steps: when the outdoor environment temperature is less than or equal to T1, the first control valve 181, the fourth control valve 184, the fifth control valve 185 and the seventh control valve 187 are controlled to be opened, the second control valve 182, the third control valve 183 and the sixth control valve 186 are controlled to be closed, the first outdoor heat exchanger 150 is controlled to absorb heat, and the second outdoor heat exchanger 160 releases heat and defrosts. When the outdoor environment temperature is less than or equal to T1, the temperature difference between the outdoor environment temperature and the outdoor heat exchanger is larger, the heat required by sufficient heating can be provided for the indoor heat exchanger, so that the first outdoor heat exchanger 150 having a large heat exchange amount absorbs heat, the second outdoor heat exchanger 160 having a small heat exchange amount releases heat and defrosts, since the defrosting time of the first outdoor heat exchanger 150 is longer than that of the second outdoor heat exchanger 160, therefore, the second outdoor heat exchanger 160 is controlled to defrost before the first outdoor heat exchanger 150, which can also ensure the smooth operation of indoor heating, reduce the defrosting time of the outdoor heat exchanger, while ensuring stable heating indoors by the first outdoor heat exchanger 150 having a large heat exchange amount, on the basis of realizing the efficient and energy-saving operation of the air conditioner, the defrosting treatment of the second outdoor heat exchanger 160 can be synchronously completed, and the defrosting operation of the second outdoor heat exchanger 160 is not stopped.
The preset conditions include: the coil temperature of the second outdoor heat exchanger 160 is greater than T2 for more than time T1. When the coil temperature of the second outdoor heat exchanger 160 is greater than T2 and continues to exceed the time T1, it indicates that the defrosting temperature and defrosting time of the second outdoor heat exchanger 160 are sufficient to provide enough defrosting heat to satisfy the heat requirement of the second outdoor heat exchanger 160 for sufficient defrosting, and therefore, it can be considered that the second outdoor heat exchanger 160 has finished defrosting.
The step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: and when the temperature deviation pn is less than or equal to T3, controlling the second control valve 182, the third control valve 183, the fifth control valve 185 and the seventh control valve 187 to be opened, controlling the first control valve 181, the fourth control valve 184 and the sixth control valve 186 to be closed, controlling the first outdoor heat exchanger 150 to release heat and defrost, and controlling the second outdoor heat exchanger 160 to absorb heat. After the second outdoor heat exchanger 160 completes defrosting, if the indoor temperature deviation is smaller than the preset value, the indoor heating requirement can be met with less heat, and even if only the second outdoor heat exchanger 160 absorbs heat, enough heat can be provided for indoor heating. Therefore, at this time, after it is determined that the second outdoor heat exchanger 160 has finished defrosting, the first outdoor heat exchanger 150 may be controlled to release heat for defrosting, and the second outdoor heat exchanger 160 may be controlled to absorb heat for heating the indoor space, so as to ensure normal operation of indoor heating and achieve non-stop defrosting operation of the outdoor heat exchanger.
The step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: when the temperature deviation pn is greater than T3, the second outdoor heat exchanger 160 stops defrosting operation, and the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 are controlled to simultaneously absorb heat for T2 time; the second control valve 182, the third control valve 183, the fifth control valve 185, and the seventh control valve 187 are controlled to be opened, the first control valve 181, the fourth control valve 184, and the sixth control valve 186 are controlled to be closed, the first outdoor heat exchanger 150 is controlled to release heat and defrost, and the second outdoor heat exchanger 160 is controlled to absorb heat.
If the temperature deviation pn is greater than T3, it indicates that there is a large difference between the indoor temperature and the set temperature, so when the indoor temperature needs to be adjusted quickly and reaches the user set temperature as soon as possible, it is necessary that the outdoor heat exchanger can provide a large amount of heat to meet the heating requirement of the indoor heat exchanger 130, at this time, the amount of heat which can be provided by only the first outdoor heat exchanger 150 or the second outdoor heat exchanger 160 is not enough to meet the indoor heating requirement, so at this time, after the second outdoor heat exchanger 160 completes defrosting, defrosting and heat releasing of the second outdoor heat exchanger 160 can be stopped, at the same time, the first outdoor heat exchanger 150 is temporarily not controlled to perform heat releasing and defrosting, so that the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 absorb heat at the same time to ensure the indoor heating requirement, when the two outdoor heat exchangers absorb heat at the same time for a period of time, at this time, can only rely on second outdoor heat exchanger 160 to provide the heat transfer heat for indoor, consequently can release heat to first outdoor heat exchanger 150 this moment and change the frost, also can reduce the influence that causes the room temperature regulation when taking this kind of operating condition, reduce uncomfortable when the user uses and go, improve user's use impression.
The step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: detecting a coil temperature of the first outdoor heat exchanger 150; when the coil temperature of the first outdoor heat exchanger 150 is greater than T4 and the duration exceeds T3, the third control valve 183, the fifth control valve 185 and the sixth control valve 186 are controlled to be opened, the first control valve 181, the second control valve 182, the fourth control valve 184 and the seventh control valve 187 are controlled to be closed, and the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 are controlled to absorb heat. When the coil temperature of the first outdoor heat exchanger 150 is greater than T4 and the duration exceeds T3, it indicates that the defrosting of the first outdoor heat exchanger 150 has continued for a sufficient time, and it can be ensured that the defrosting of the first outdoor heat exchanger 150 is completed, at this time, both the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 complete one defrosting cycle, and both the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 can be controlled to absorb heat, so as to increase the regulation speed of the indoor temperature, and the indoor temperature can meet the requirements of users as soon as possible.
The step of adjusting the working state of the outdoor heat exchanger according to the outdoor environment temperature comprises the following steps: when the outdoor ambient temperature is greater than T1, the second control valve 182, the third control valve 183, the fifth control valve 185, and the seventh control valve 187 are controlled to open, the first control valve 181, the fourth control valve 184, and the sixth control valve 186 are controlled to close, the first outdoor heat exchanger 150 is controlled to release heat and defrost, and the second outdoor heat exchanger 160 is controlled to absorb heat. When the outdoor environment temperature is greater than T1, it indicates that there is a large temperature difference between the outdoor heat exchanger and the outdoor environment temperature, and the indoor heating requirement can be maintained only by the heat exchanger with a small capacity, so at this time, the first outdoor heat exchanger 150 with a long defrosting time can be defrosted first with the main purpose of defrosting. Because the indoor heating requirement can be provided only by exchanging heat between the second outdoor heat exchanger 160 and the outdoor environment, the first outdoor heat exchanger 150 can be controlled to release heat and defrost, the second outdoor heat exchanger 160 absorbs heat, one of the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 defrosts, the other provides heat required by indoor heating, the non-stop defrosting operation of the air conditioner is realized, meanwhile, the great influence on indoor temperature regulation is avoided, the indoor temperature can be always kept in a proper range, and the comfort requirement of a human body is met.
When the first outdoor heat exchanger 150 is first defrosted, the preset conditions include: the coil temperature of the first outdoor heat exchanger 150 is greater than T5 for more than time T4. When the coil temperature of the first outdoor heat exchanger is greater than T5 and lasts for more than time T4, it indicates that the defrosting temperature and defrosting time of the first outdoor heat exchanger 150 are sufficient to provide enough defrosting heat to satisfy the heat requirement of the first outdoor heat exchanger 150 for sufficient defrosting, and thus the first outdoor heat exchanger 150 can be considered to have finished defrosting.
The step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: and when the temperature deviation pn is less than or equal to T6, controlling the first control valve 181, the fourth control valve 184, the fifth control valve 185 and the seventh control valve 187 to be opened, controlling the second control valve 182, the third control valve 183 and the sixth control valve 186 to be closed, controlling the first outdoor heat exchanger 150 to absorb heat, and controlling the second outdoor heat exchanger 160 to release heat and defrost. After the first outdoor heat exchanger 150 completes defrosting, if the difference between the indoor environment temperature and the set temperature is within the preset value range, it is indicated that the indoor environment temperature is basically adjusted in place, and only a small amount of heat is needed to meet the indoor heating requirement, that is, only the first outdoor heat exchanger 150 absorbs heat, and enough heat can be provided for indoor heating, therefore, at this moment, after it is determined that the first outdoor heat exchanger 150 completes defrosting, the second outdoor heat exchanger 160 can be controlled to release heat and defrost, and at the same time, the first outdoor heat exchanger 150 is controlled to absorb heat to heat indoors, so that normal operation of indoor heating is ensured, and meanwhile, non-stop defrosting operation of the outdoor heat exchanger is realized.
The step of adjusting the operating state of the outdoor heat exchanger according to the temperature deviation further includes: when the temperature deviation pn is greater than T6, the first outdoor heat exchanger 150 stops defrosting operation, and the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 are controlled to simultaneously absorb heat for T5 time; the first control valve 181, the fourth control valve 184, the fifth control valve 185 and the seventh control valve 187 are controlled to be opened, the second control valve 182, the third control valve 183 and the sixth control valve 186 are controlled to be closed, the first outdoor heat exchanger 150 is controlled to absorb heat, and the second outdoor heat exchanger 160 releases heat and defrosts.
If the difference between the indoor environment temperature and the set temperature exceeds the preset value range, the difference between the indoor environment temperature and the set temperature is large, and the heat which can be provided by only the first outdoor heat exchanger 150 is not enough to meet the requirement of quickly adjusting the indoor temperature, so that the defrosting and heat releasing of the first outdoor heat exchanger 150 can be stopped after the first outdoor heat exchanger 150 completes defrosting, and simultaneously the second outdoor heat exchanger 160 is not controlled to release heat and defrost temporarily, so that the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 absorb heat simultaneously, the indoor heating requirement is ensured, when the two outdoor heat exchangers absorb heat simultaneously for a period of time, the indoor temperature deviation is reduced, the heat exchange heat can be provided for the indoor by only the first outdoor heat exchanger 150, therefore, the heat releasing and defrosting can be performed on the second outdoor heat exchanger 160 at the moment, and the influence on the indoor temperature adjustment when the working state is adopted can also be reduced, the discomfort of the user during the use is reduced, and the use feeling of the user is improved.
The step of adjusting the working state of the outdoor heat exchanger according to the outdoor ambient temperature further comprises: detecting the coil temperature of the second outdoor heat exchanger 160; when the coil temperature of the second outdoor heat exchanger 160 is greater than T7 and the duration exceeds T6, the third control valve 183, the fifth control valve 185 and the sixth control valve 186 are controlled to be opened, the first control valve 181, the second control valve 182, the fourth control valve 184 and the seventh control valve 187 are controlled to be closed, and the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 are controlled to absorb heat. When the coil temperature of the second outdoor heat exchanger 160 is greater than T7 and the duration exceeds T6, it indicates that the defrosting of the second outdoor heat exchanger 160 has continued for a sufficient time, and it can be ensured that the defrosting of the second outdoor heat exchanger 160 is completed, at this time, both the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 complete one defrosting cycle, and both the first outdoor heat exchanger 150 and the second outdoor heat exchanger 160 can be controlled to absorb heat, so as to increase the adjustment speed of the indoor temperature, and the indoor temperature can meet the requirements of users as soon as possible.
Among the above parameters, T1 is, for example, 3 ℃, T2 is, for example, 6 ℃, T3 is, for example, 2 ℃, T4 is, for example, 6 ℃, T5 is, for example, 6 ℃, T6 is, for example, 2 ℃, T7 is, for example, 6 ℃, T1 is, for example, 1min, T2 is, for example, 10min, T3 is, for example, 1min, T4 is, for example, 1min, T5 is, for example, 15min, and T6 is, for example, 1 min.
It is to be understood that the present invention is not limited to the procedures and structures described above and shown in the drawings, and that various modifications and changes may be made without departing from the scope thereof. The scope of the invention is limited only by the appended claims.

Claims (9)

1. A defrosting method for an air conditioner running without stopping is characterized in that the air conditioner comprises a first outdoor heat exchanger, a second outdoor heat exchanger, a four-way reversing valve and an indoor heat exchanger; the first end of the first outdoor heat exchanger is connected with the first interface of the four-way reversing valve through a first pipeline and is connected with the second interface of the four-way reversing valve through a second pipeline, the first end of the second outdoor heat exchanger is connected with the first interface of the four-way reversing valve through a third pipeline and is connected with the second interface of the four-way reversing valve through a fourth pipeline, a fifth pipeline, a sixth pipeline and a seventh pipeline are arranged between the indoor heat exchanger and the outdoor heat exchanger, the first end of the fifth pipeline is connected with the first end of the indoor heat exchanger, the first ends of the sixth pipeline and the seventh pipeline are connected to the second end of the fifth pipeline together, the second end of the sixth pipeline is connected with the first end of the first outdoor heat exchanger, and the second end of the seventh pipeline is connected with a first branch and a second branch respectively, the defrosting method of the air conditioner comprises the following steps that a first branch is connected to a second end of a first outdoor heat exchanger, a second branch is connected to a second end of a second outdoor heat exchanger, a first control valve is arranged on a first pipeline, a second control valve is arranged on a second pipeline, a third control valve is arranged on a third pipeline, a fourth control valve is arranged on a fourth pipeline, a fifth control valve and a first throttling device are arranged on a fifth pipeline, a sixth control valve is arranged on a sixth pipeline, a seventh control valve is arranged on a seventh pipeline, a second throttling device is arranged on a second branch, and the defrosting method of the air conditioner comprises the following steps that:
controlling the heating operation of the air conditioner;
detecting the outdoor environment temperature;
adjusting the working state of the outdoor heat exchanger according to the outdoor environment temperature;
detecting a temperature deviation between an indoor temperature and a set temperature when the outdoor heat exchanger is adjusted to a preset condition;
adjusting the working state of the outdoor heat exchanger according to the temperature deviation, so that one of the first outdoor heat exchanger and the second outdoor heat exchanger operates to absorb heat, and the other one operates to release heat and defrost;
wherein, adjust the operating condition of outdoor heat exchanger according to outdoor ambient temperature, include:
when the outdoor environment temperature is less than or equal to T1, the first control valve, the fourth control valve, the fifth control valve and the seventh control valve are controlled to be opened, the second control valve, the third control valve and the sixth control valve are controlled to be closed, the first outdoor heat exchanger is controlled to absorb heat, and the second outdoor heat exchanger releases heat and defrosts; and/or when the outdoor environment temperature is higher than T1, controlling the second control valve, the third control valve, the fifth control valve and the seventh control valve to be opened, controlling the first control valve, the fourth control valve and the sixth control valve to be closed, controlling the first outdoor heat exchanger to release heat and defrost, and controlling the second outdoor heat exchanger to absorb heat; the heat exchange area of the first outdoor heat exchanger is S1, the heat exchange area of the second outdoor heat exchanger is S2, and S1 is greater than S2.
2. The defrosting method without stopping operation of an air conditioner according to claim 1, wherein the preset conditions include:
when the outdoor ambient temperature is met to be less than or equal to T1, the coil temperature of the second outdoor heat exchanger is greater than T2 and continues for more than time T1.
3. The defrosting method without stopping operation of an air conditioner according to claim 2, wherein the step of adjusting the operation state of the outdoor heat exchanger according to the temperature deviation further comprises:
and when the temperature deviation pn is less than or equal to T3, controlling the second control valve, the third control valve, the fifth control valve and the seventh control valve to be opened, controlling the first control valve, the fourth control valve and the sixth control valve to be closed, controlling the first outdoor heat exchanger to release heat and defrost, and controlling the second outdoor heat exchanger to absorb heat.
4. The defrosting method without stopping operation of an air conditioner according to claim 2, wherein the step of adjusting the operation state of the outdoor heat exchanger according to the temperature deviation further comprises:
when the temperature deviation pn is greater than T3, the second outdoor heat exchanger stops defrosting operation, and the first outdoor heat exchanger and the second outdoor heat exchanger are controlled to absorb heat simultaneously and last for T2 time;
and the second control valve, the third control valve, the fifth control valve and the seventh control valve are controlled to be opened, the first control valve, the fourth control valve and the sixth control valve are controlled to be closed, the first outdoor heat exchanger is controlled to release heat and defrost, and the second outdoor heat exchanger is controlled to absorb heat.
5. The defrosting method without shutdown operation of air conditioner according to claim 3 or 4, wherein after controlling the first outdoor heat exchanger to release heat and defrost and the second outdoor heat exchanger to absorb heat at the temperature deviation pn ≦ T3, or after controlling the first outdoor heat exchanger and the second outdoor heat exchanger to absorb heat simultaneously and lasting for T2 time, controlling the first outdoor heat exchanger to release heat and defrost and the second outdoor heat exchanger to absorb heat, further comprising:
detecting the coil temperature of the first outdoor heat exchanger;
and when the coil temperature of the first outdoor heat exchanger is more than T4 and the duration exceeds T3, controlling the third control valve, the fifth control valve and the sixth control valve to be opened, controlling the first control valve, the second control valve, the fourth control valve and the seventh control valve to be closed, and controlling the first outdoor heat exchanger and the second outdoor heat exchanger to absorb heat.
6. The defrosting method without stopping operation of an air conditioner according to claim 1, wherein the preset conditions include:
when the outdoor ambient temperature is greater than T1, the coil temperature of the first outdoor heat exchanger is greater than T5 and continues for more than time T4.
7. The defrosting method without stopping operation of an air conditioner according to claim 6, wherein the step of adjusting the operation state of the outdoor heat exchanger according to the temperature deviation further comprises:
and when the temperature deviation pn is less than or equal to T6, controlling the first control valve, the fourth control valve, the fifth control valve and the seventh control valve to be opened, controlling the second control valve, the third control valve and the sixth control valve to be closed, controlling the first outdoor heat exchanger to absorb heat, and controlling the second outdoor heat exchanger to release heat and defrost.
8. The defrosting method without stopping operation of an air conditioner according to claim 6, wherein the step of adjusting the operation state of the outdoor heat exchanger according to the temperature deviation further comprises:
when the temperature deviation pn is greater than T6, the first outdoor heat exchanger stops defrosting operation, and the first outdoor heat exchanger and the second outdoor heat exchanger are controlled to absorb heat simultaneously and last for T5 time;
and controlling the first control valve, the fourth control valve, the fifth control valve and the seventh control valve to be opened, controlling the second control valve, the third control valve and the sixth control valve to be closed, controlling the first outdoor heat exchanger to absorb heat, and controlling the second outdoor heat exchanger to release heat and defrost.
9. The defrosting method without shutdown of an air conditioner according to claim 7 or 8, wherein after controlling the first outdoor heat exchanger to absorb heat and the second outdoor heat exchanger to release heat and defrost when the temperature deviation pn is less than or equal to T6, or after controlling the first outdoor heat exchanger and the second outdoor heat exchanger to absorb heat and the second outdoor heat exchanger to release heat and defrost when the first outdoor heat exchanger and the second outdoor heat exchanger are controlled to absorb heat and last for T5 time, the method further comprises:
detecting the coil temperature of the second outdoor heat exchanger;
and when the coil temperature of the second outdoor heat exchanger is greater than T7 and the duration exceeds T6, controlling the third control valve, the fifth control valve and the sixth control valve to be opened, controlling the first control valve, the second control valve, the fourth control valve and the seventh control valve to be closed, and controlling the first outdoor heat exchanger and the second outdoor heat exchanger to absorb heat.
CN201710214072.XA 2017-04-01 2017-04-01 Defrosting operation method for air conditioner without stopping Active CN106871381B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710214072.XA CN106871381B (en) 2017-04-01 2017-04-01 Defrosting operation method for air conditioner without stopping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710214072.XA CN106871381B (en) 2017-04-01 2017-04-01 Defrosting operation method for air conditioner without stopping

Publications (2)

Publication Number Publication Date
CN106871381A CN106871381A (en) 2017-06-20
CN106871381B true CN106871381B (en) 2020-05-29

Family

ID=59160719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710214072.XA Active CN106871381B (en) 2017-04-01 2017-04-01 Defrosting operation method for air conditioner without stopping

Country Status (1)

Country Link
CN (1) CN106871381B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108954676A (en) * 2018-07-17 2018-12-07 苏州韵之秋智能科技有限公司 A kind of intelligent air condition does not shut down defrosting method
CN109269040B (en) * 2018-08-10 2019-12-31 珠海格力电器股份有限公司 Air conditioner control system and control method
CN109974203B (en) * 2019-03-06 2021-03-23 青岛海信日立空调***有限公司 Defrosting method of air conditioner and air conditioner
CN110173825A (en) * 2019-05-31 2019-08-27 广东美的制冷设备有限公司 Progress control method, control device, air conditioner and computer readable storage medium
CN113357843A (en) * 2020-03-04 2021-09-07 青岛海尔空调电子有限公司 Air conditioning system and defrosting control method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104089427A (en) * 2014-06-24 2014-10-08 珠海格力电器股份有限公司 Air conditioner system and control method thereof
CN104101127A (en) * 2013-04-01 2014-10-15 珠海格力电器股份有限公司 VRV (Varied Refrigerant Volume) air conditioning system and VRV air conditioning defrosting control method
WO2015059792A1 (en) * 2013-10-24 2015-04-30 三菱電機株式会社 Air conditioner
CN104930618A (en) * 2015-05-26 2015-09-23 广东美的制冷设备有限公司 Air conditioner and method for controlling air conditioner
JP2016106211A (en) * 2016-01-20 2016-06-16 三菱電機株式会社 Air conditioner
CN106016808A (en) * 2016-05-23 2016-10-12 珠海格力电器股份有限公司 Air-conditioning system and control method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104101127A (en) * 2013-04-01 2014-10-15 珠海格力电器股份有限公司 VRV (Varied Refrigerant Volume) air conditioning system and VRV air conditioning defrosting control method
WO2015059792A1 (en) * 2013-10-24 2015-04-30 三菱電機株式会社 Air conditioner
CN104089427A (en) * 2014-06-24 2014-10-08 珠海格力电器股份有限公司 Air conditioner system and control method thereof
CN104930618A (en) * 2015-05-26 2015-09-23 广东美的制冷设备有限公司 Air conditioner and method for controlling air conditioner
JP2016106211A (en) * 2016-01-20 2016-06-16 三菱電機株式会社 Air conditioner
CN106016808A (en) * 2016-05-23 2016-10-12 珠海格力电器股份有限公司 Air-conditioning system and control method thereof

Also Published As

Publication number Publication date
CN106871381A (en) 2017-06-20

Similar Documents

Publication Publication Date Title
CN106871381B (en) Defrosting operation method for air conditioner without stopping
CN106918122B (en) Defrosting operation method for air conditioner without stopping
CN107023950B (en) Defrosting operation method for air conditioner without stopping
US11320185B2 (en) Defrosting control method for multi-split system
JP6207600B2 (en) Circulation heating device
WO2019134509A1 (en) Outdoor unit, air conditioning system, and control method
CN111076446A (en) Heat pump air conditioning system and control method thereof
CN101975422A (en) Warm/cool air-conditioner and defrosting method thereof
CN107023946B (en) Defrosting operation method for air conditioner without stopping
WO2022022642A1 (en) Air conditioner and dehumidification method
JP5741723B1 (en) Ventilation equipment
CN107023944B (en) Defrosting operation method for air conditioner without stopping
CN112665036A (en) Four-pipe system, cold and heat capacity adjusting and controlling method and device and air conditioner
CN111237857A (en) Air conditioner dehumidification method and system capable of keeping constant temperature
CN110822544A (en) Fixed-frequency air conditioning system for improving indoor comfort
CN107023948B (en) Air conditioner and non-stop defrosting operation method thereof
CN106871382B (en) Defrosting operation method for air conditioner without stopping
CN214223244U (en) Multi-split air conditioner
CN104879875A (en) Method for controlling inner devices of multi-device-connected air-conditioning system and multi-device-connected air-conditioning system
JP2010236816A (en) Heat pump type air conditioner and method of controlling heat pump type air conditioner
MX2022012054A (en) Heating, ventilation, and air-conditioning system with reheat.
CN111121337B (en) Air conditioner double-condenser defrosting method and air conditioner
JP4226284B2 (en) Air conditioner
CN211781449U (en) Air conditioner dehumidification system capable of keeping constant temperature
JPH1123036A (en) Air conditioner

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200914

Address after: 266101 Haier Industrial Park, Haier Road, Laoshan District, Shandong, Qingdao, China

Co-patentee after: QINGDAO HAIER (JIAOZHOU) AIR CONDITIONER Co.,Ltd.

Patentee after: QINGDAO HAIER AIR CONDITIONER GENERAL Corp.,Ltd.

Address before: 266101 Haier Industrial Park, Haier Road, Laoshan District, Shandong, Qingdao, China

Patentee before: QINGDAO HAIER AIR CONDITIONER GENERAL Corp.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201104

Address after: 266101 Haier Industrial Park, Haier Road, Laoshan District, Shandong, Qingdao, China

Patentee after: QINGDAO HAIER AIR CONDITIONER GENERAL Corp.,Ltd.

Patentee after: QINGDAO HAIER (JIAOZHOU) AIR CONDITIONER Co.,Ltd.

Patentee after: Haier Zhijia Co.,Ltd.

Address before: 266101 Haier Industrial Park, Haier Road, Laoshan District, Shandong, Qingdao, China

Patentee before: QINGDAO HAIER AIR CONDITIONER GENERAL Corp.,Ltd.

Patentee before: QINGDAO HAIER (JIAOZHOU) AIR CONDITIONER Co.,Ltd.

TR01 Transfer of patent right