CN106846168A - The processing unit and system of transmission line of electricity scissors crossing - Google Patents
The processing unit and system of transmission line of electricity scissors crossing Download PDFInfo
- Publication number
- CN106846168A CN106846168A CN201611132740.6A CN201611132740A CN106846168A CN 106846168 A CN106846168 A CN 106846168A CN 201611132740 A CN201611132740 A CN 201611132740A CN 106846168 A CN106846168 A CN 106846168A
- Authority
- CN
- China
- Prior art keywords
- information
- module
- transmission line
- hidden danger
- electricity
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000005540 biological transmission Effects 0.000 title claims abstract description 81
- 230000005611 electricity Effects 0.000 title claims abstract description 73
- 238000012545 processing Methods 0.000 title claims abstract description 32
- 238000004364 calculation method Methods 0.000 claims abstract description 13
- 238000005259 measurement Methods 0.000 claims abstract description 5
- 238000004458 analytical method Methods 0.000 claims description 12
- 238000012986 modification Methods 0.000 claims description 8
- 230000004048 modification Effects 0.000 claims description 8
- 238000004519 manufacturing process Methods 0.000 abstract description 10
- 238000010586 diagram Methods 0.000 description 17
- 238000000034 method Methods 0.000 description 9
- 238000007726 management method Methods 0.000 description 6
- 230000008439 repair process Effects 0.000 description 5
- 230000000694 effects Effects 0.000 description 4
- 230000008569 process Effects 0.000 description 4
- 238000004891 communication Methods 0.000 description 3
- 238000010168 coupling process Methods 0.000 description 3
- 238000005859 coupling reaction Methods 0.000 description 3
- 238000012423 maintenance Methods 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 230000008878 coupling Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000007689 inspection Methods 0.000 description 2
- 230000007257 malfunction Effects 0.000 description 2
- 239000000047 product Substances 0.000 description 2
- 238000012800 visualization Methods 0.000 description 2
- 241000405414 Rehmannia Species 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000003086 colorant Substances 0.000 description 1
- 230000006870 function Effects 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Health & Medical Sciences (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of processing unit and system of transmission line of electricity scissors crossing.Wherein, the device includes:Information module, the information for obtaining route and shaft tower;Typing information module, for receiving typing information, wherein, typing information includes at least one following:Transmission of electricity scissors crossing information, tree line are apart from point-to-point measurement, conducting wire sag and ground wire information;Analytical calculation module, is connected with typing information module, for analyzing typing information, obtains the prompt message whether transmission line of electricity breaks down;The present invention solves and causes to be supported and supervision, the technical problem that early warning pre-control and production decision are mutually supported in advance without operation field due to lacking transmission line of electricity scissors crossing management platform.
Description
Technical field
The present invention relates to the field of powering, a kind of processing unit in particular to transmission line of electricity scissors crossing and it is
System.
Background technology
At present, to transmission line of electricity and shaft tower, house, river, street lamp, communication line, standard highway, railway (electrified iron
Road) etc. friendship across record information, mainly passed on by written information and information carried by multiple departments needed for job applications
For easily causing and being gone wrong using inconvenience and information record.
Existing transmission line of electricity scissors crossing, the relevant information needed for original is mostly hand-kept, primitive information for by hand
Affix one's seal, the information of transmission line of electricity scissors crossing is collected, reorganized by hand by personnel, the efficiency of management is very low, while retrieval is looked into
The maintenances of information such as inquiry, modification, supplement are inconvenient, and during information transfer, archive etc., information is easily lost or damages, mistake;
Transmission line of electricity scissors crossing information is chronically at plane and affixes one's seal by hand shape state, and graphic documentation cannot provide the bar of scissors crossing
The accurate graphic documentation such as tower, house, street lamp, river, railway, does not form data, graph Integrat ion.
Again, application system is only capable of achieving transmission line of electricity scissors crossing letter, does not have formation to show circuit and hand over
Visual intuitive platform of the fork across letter.Therefore the support and supervision with operation field are not formed, is not carried out in advance
Early warning pre-control and long term the technological means mutually supported of production decision.
For above-mentioned problem, effective solution is not yet proposed at present.
The content of the invention
The embodiment of the invention provides a kind of processing unit and system of transmission line of electricity scissors crossing, with least solve by
No operation field is caused to support with supervision, early warning pre-control and production are determined in advance in transmission line of electricity scissors crossing management platform is lacked
The technical problem that plan is mutually supported.
A kind of one side according to embodiments of the present invention, there is provided processing unit of transmission line of electricity scissors crossing, including:
Information module, the information for obtaining route and shaft tower;Typing information module, for receiving typing information, its
In, typing information includes at least one following:Transmission of electricity scissors crossing information, tree line are measured apart from point-to-point, conducting wire sag and are connect
Ground wire information;Analytical calculation module, is connected with typing information module, for analyzing typing information, obtains whether transmission line of electricity is sent out
The prompt message of raw failure.
Further, information module includes:Update module, the information for changing route and shaft tower.
Further, information module also includes:Enquiry module, the information of route and shaft tower is obtained for inquiring about.
Further, information module also includes:Enquiry module, the information of route and shaft tower is obtained for inquiring about.
Further, typing information includes at least one following:Hidden danger event type and circuit types, shaft tower type, exhale
Claim height, arboreal growth speed, local meteorological condition, conducting wire sag.
Further, analytical calculation module includes:Processing module, for being calculated automatically in transmission line of electricity scissors crossing figure
Go out circuit hidden danger position and hidden danger kind of information.
Further, device also includes:Prediction scheme module, obtains and hidden danger prediction scheme pair for typing hidden danger prediction scheme, and inquiry
The fault countermeasure answered;Sort module, is connected with prediction scheme module, for hidden danger prediction scheme to be classified and is shown classification results;It is defeated
Go out module, the analysis electronics shelves for exporting the transmission line of electricity scissors crossing.
Further, prediction scheme module includes:Display module, for according to hidden danger event type, it is hidden that display inquiry is obtained
Suffer from prediction scheme content, wherein, hidden danger prediction scheme content includes:Hidden danger type, cause the information of line fault.
Further, sort module includes:Setup module, for the order of severity according to hidden danger prediction scheme, sets and notifies letter
Breath.
Further, output module includes:Data supporting module, is power transmission line for the analysis electronics shelves according to output
Road modification planning information provides support.
Another aspect according to embodiments of the present invention, additionally provides a kind of processing system of transmission line of electricity scissors crossing, bag
Include:The processing unit of the transmission line of electricity scissors crossing of any one.
In embodiments of the present invention, using information module, the information for obtaining route and shaft tower;Typing information mould
Block, for receiving typing information, wherein, typing information includes at least one following:Transmission of electricity scissors crossing information, tree line range points
To measurement, conducting wire sag and ground wire information;Analytical calculation module, is connected with typing information module, for analyzing typing letter
Breath, obtains the mode of the prompt message whether transmission line of electricity breaks down, and the three-dimensional visualization module provided by system is realized
Failure completes the management and control of overall process from occurring to processing, and more accurately formulates Rush Repair Scheme, it is ensured that what line fault was processed can
Control property, has reached the accuracy rate and operating efficiency for improving transmission line of electricity scissors crossing Data Enter, improves the work that transmission of electricity is maked an inspection tour
Production run personnel are facilitated to understand the purpose of all information of circuit in time while efficiency, it is achieved thereby that transmission of electricity is substantially improved
The technique effect of the accuracy of net information, diversity, promptness and transmission line malfunction Rush Repair Scheme accuracy, and then solve
No operation field is caused to support and supervision, in advance early warning pre-control and production due to lacking transmission line of electricity scissors crossing management platform
The technical problem that decision-making is mutually supported.
Brief description of the drawings
Accompanying drawing described herein is used for providing a further understanding of the present invention, constitutes the part of the application, this hair
Bright schematic description and description does not constitute inappropriate limitation of the present invention for explaining the present invention.In the accompanying drawings:
Fig. 1 is a kind of processing unit schematic diagram of transmission line of electricity scissors crossing according to embodiments of the present invention;
Fig. 2 is a kind of interface schematic diagram of transmission line of electricity scissors crossing according to embodiments of the present invention;
Fig. 3 is a kind of interface schematic diagram of transmission line of electricity scissors crossing editor according to embodiments of the present invention;
Fig. 4 is the processing unit schematic diagram of a kind of optional transmission line of electricity scissors crossing according to embodiments of the present invention;
Fig. 5 is the processing unit schematic diagram of a kind of optional transmission line of electricity scissors crossing according to embodiments of the present invention;
Fig. 6 is the processing unit schematic diagram of a kind of optional transmission line of electricity scissors crossing according to embodiments of the present invention;With
And
Fig. 7 is a kind of processing system schematic diagram of transmission line of electricity scissors crossing editor according to embodiments of the present invention.
Specific embodiment
In order that those skilled in the art more fully understand the present invention program, below in conjunction with the embodiment of the present invention
Accompanying drawing, is clearly and completely described to the technical scheme in the embodiment of the present invention, it is clear that described embodiment is only
The embodiment of a part of the invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill people
The every other embodiment that member is obtained under the premise of creative work is not made, should all belong to the model of present invention protection
Enclose.
It should be noted that term " first ", " in description and claims of this specification and above-mentioned accompanying drawing
Two " it is etc. for distinguishing similar object, without for describing specific order or precedence.It should be appreciated that so using
Data can exchange in the appropriate case, so as to embodiments of the invention described herein can with except illustrating herein or
Order beyond those of description is implemented.Additionally, term " comprising " and " having " and their any deformation, it is intended that cover
Lid is non-exclusive to be included, for example, the process, method, system, product or the equipment that contain series of steps or unit are not necessarily limited to
Those steps or unit clearly listed, but may include not list clearly or for these processes, method, product
Or other intrinsic steps of equipment or unit.
Embodiment 1
According to embodiments of the present invention, there is provided a kind of processing unit embodiment of transmission line of electricity scissors crossing, Fig. 1 is basis
The processing unit of a kind of transmission line of electricity scissors crossing of the embodiment of the present invention, as shown in figure 1, the device includes:Information module 10,
Typing information module 20, analytical calculation module 30.
Wherein, information module 10, the information for obtaining route and shaft tower;Typing information module 20, records for receiving
Enter information, wherein, typing information includes at least one following:Transmission of electricity scissors crossing information, tree line are measured apart from point-to-point, wire
Sag and ground wire information;Analytical calculation module 30, is connected with typing information module, for analyzing the typing information, obtains
The prompt message whether transmission line of electricity breaks down.
In said apparatus, circuit and the essential information of shaft tower that information module 10 can be related to newly-built, modification and inquiry;
The essential information of route and shaft tower includes:Shaft tower numbering, overhead line structures type where shaft tower, exhale title height, arboreal growth speed
Degree, the meteorological condition in shaft tower location;Can be also used for inquiring about and showing fault countermeasure and hidden danger prediction scheme, wherein, above-mentioned hidden danger
Prediction scheme can include:Hidden danger type, cause the information such as line fault form.
In a kind of optional embodiment, by shaft tower numbering, shaft tower type, title height, arboreal growth speed, shaft tower institute are exhaled
The information such as the meteorological condition on ground are with typing route in the form of sectional schematic diagram and floor map.
Fig. 2 is a kind of interface schematic diagram of transmission line of electricity scissors crossing according to embodiments of the present invention, as shown in figure 5, defeated
The interface of electric line scissors crossing can include:Tower number, shaft tower region sectional schematic diagram and shaft tower region plane
Schematic diagram.
By above- mentioned information module 10, it is possible to achieve obtain the purpose of the information of route and shaft tower.
In said apparatus, typing information module 20 can be used for typing transmission of electricity scissors crossing information, tree line range points and arrive
Point measurement, conducting wire sag and ground wire information, while typing and updating maintenance hidden danger prediction scheme.
In a kind of optional embodiment, typing information module 20 can be with patterned form typing route and shaft tower
Information;Fig. 3 is a kind of interface schematic diagram of transmission line of electricity scissors crossing editor according to embodiments of the present invention, as shown in fig. 6, defeated
The interface of electric line scissors crossing editor can include:Shaft tower title, away from small size lateral extent, away from large size lateral extent and whether same
Step plan.
By above-mentioned typing information module 20, it is possible to achieve receive the purpose of typing information.
In said apparatus, analytical calculation module 30 can be used for according to typing information, and analysis draws line failure
Early warning information, in a kind of optional embodiment, according to tree line distance, conducting wire sag and ground connection in analytical calculation module 30
The information of line, prompt message is sent on scissors crossing figure.
By above-mentioned analytical calculation module 30, it is possible to achieve analysis typing information, obtain whether transmission line of electricity breaks down
Purpose.
In the technical scheme that said apparatus are provided, the information of route and shaft tower is obtained using information module 10;Typing
Information module 20 receives typing information, and the analysis typing information of analytical calculation module 30 obtains what whether transmission line of electricity broke down
The mode of prompt message, the three-dimensional visualization module provided by system realizes that failure completes the pipe of overall process from occurring to processing
Control, more accurately formulates Rush Repair Scheme, it is ensured that the controllability of line fault treatment, has reached raising transmission line of electricity scissors crossing
The accuracy rate and operating efficiency of Data Enter, facilitate production run personnel timely while the operating efficiency for improving transmission of electricity tour
The purpose of all information of circuit is solved, it is achieved thereby that the accuracy of power transmission network information, diversity, promptness and defeated is substantially improved
The technique effect of line fault Rush Repair Scheme accuracy, and then solve due to lacking transmission line of electricity scissors crossing management platform
Cause to be supported and supervision, the technical problem that early warning pre-control and production decision are mutually supported in advance without operation field.
Based on the technical scheme that above-described embodiment is provided, present invention also offers following preferred scheme:
Optionally, Fig. 4 is a kind of processing unit schematic diagram of transmission line of electricity scissors crossing according to embodiments of the present invention, such as
Shown in Fig. 4, in a kind of optional embodiment, information module 10 includes:Update module 12, enquiry module 14.
Wherein, update module 12, the information for changing route and shaft tower;Enquiry module 14, road is obtained for inquiring about
The information of line and shaft tower.
Used as a kind of optional embodiment, update module 12 can be used for changing the geographical position of route and bar where shaft tower
The specifying information of tower;Enquiry module 14 can be used for inquiring about the specifying information of route and shaft tower where shaft tower;Wherein, geographical position
Put including:The railway of the vicinity where shaft tower, highway and river.
Optionally, typing information includes at least one following:Hidden danger event type and circuit types, shaft tower type, exhale title
Highly, arboreal growth speed, local meteorological condition, conducting wire sag.
Used as a kind of optional embodiment, hidden danger event type can be able to be flat for one-level event, route type
Highway, shaft tower type can for three-level shaft tower, to exhale highly can be called that 40cm, arboreal growth speed can be 10cm h, locality
Weather conditions can be able to be 1.65m for good, conducting wire sag.
Optionally, Fig. 5 is a kind of processing unit schematic diagram of transmission line of electricity scissors crossing according to embodiments of the present invention, such as
Shown in Fig. 5, in a kind of optional embodiment, analytical calculation module 30 includes:Processing module 32.
Wherein, processing module 32, for calculating circuit hidden danger position automatically in transmission line of electricity scissors crossing figure
And hidden danger kind of information, wherein, hidden danger kind of information includes:The grade of hidden danger event.
As a kind of optional embodiment, in transmission line of electricity scissors crossing figure, according to typing in typing information module 20
Information, it is automatic in transmission line of electricity scissors crossing figure to calculate and overstriking display hidden danger circuit particular geographic location be with Beijing
Chaoyang District Ba Li village South 8, the grade of hidden danger event can be one-level.
Optionally, Fig. 6 is a kind of processing unit schematic diagram of transmission line of electricity scissors crossing according to embodiments of the present invention, such as
Shown in Fig. 6, in a kind of optional embodiment, device also includes:Prediction scheme module 40, sort module 50, output module 60.
Wherein, prediction scheme module 40, for typing hidden danger prediction scheme, and inquiry obtains fault countermeasure corresponding with hidden danger prediction scheme;
Sort module 50, is connected with prediction scheme module, for hidden danger prediction scheme to be classified and is shown classification results;Output module 60, uses
In the analysis electronics shelves of output transmission line of electricity scissors crossing.
Used as a kind of optional embodiment, it is pre- that the hidden danger prediction scheme according to typing in prediction scheme module 40 inquires correspondence failure
Case, and hidden danger prediction scheme is classified and using various different colours display hidden danger prediction scheme according to the spot of prediction scheme, will be defeated
The result for going out transmission line of electricity scissors crossing is in electronic form exported.
Optionally, prediction scheme module 40 includes:Display module, for according to the hidden danger event type, display inquiry to be obtained
The hidden danger prediction scheme content, wherein, the hidden danger prediction scheme content includes:Hidden danger type, cause the information of line fault.
Used as a kind of optional embodiment, according to one-level hidden danger event type, the content of one-level hidden danger prediction scheme is inquired about in display,
The content of hidden danger prediction scheme also includes:The reason for spot, generation of hidden danger event of hidden danger event;Wherein, the hair of hidden danger event
The reason for dried rhizome of rehmannia can be the unit of Chaoyang District Ba Li village South Building 82, the generation of hidden danger event can be extra torrential rain.
Optionally, sort module 50 includes:Setup module, for the order of severity according to hidden danger prediction scheme, sets and notifies letter
Breath, wherein, the order of severity of hidden danger prediction scheme can be serious, normal and slight three ranks;Setting announcement information includes:Hidden danger
The advice range of prediction scheme and the content of announcement of hidden danger prediction scheme.
Used as a kind of optional embodiment, the order of severity of hidden danger prediction scheme can be notice that is normal, setting hidden danger prediction scheme
The content of announcement of scope and hidden danger prediction scheme;Wherein, the advice range of hidden danger prediction scheme can be the Chaoyang District Ba Li village, hidden danger prediction scheme
Content of announcement can be reduction outdoor activity.
Optionally, output module 60 includes:Data supporting module, is power transmission line for the analysis electronics shelves according to output
Road modification planning information provides support.
Used as a kind of optional embodiment, system can be when power transmission line meets burst significant problem on the way, such as mountain torrents, especially big sudden and violent
Rain, snow disaster, fire, earthquake, blast etc. cause the circuit operations staff cannot to reach the spot, and scene is understood by data supporting module
Environment, there is provided the support of necessary data.
Embodiment 2
Another aspect according to embodiments of the present invention, additionally provides a kind of processing system of transmission line of electricity scissors crossing, Fig. 7
It is a kind of processing system of transmission line of electricity scissors crossing according to embodiments of the present invention, as shown in fig. 7, the system includes:It is above-mentioned
The processing unit of the transmission line of electricity scissors crossing of any one.Further, above-mentioned processing system includes:Client 70, it is middle
End 80, service end 90.
Wherein, client 70, are connected with intermediate ends 80, the information for obtaining route and shaft tower;Intermediate ends 80, with visitor
The service end 90 of family end 70 is connected, for receiving typing information, wherein, typing information includes at least one following:Transmission of electricity intersect across
More information, tree line are apart from point-to-point measurement, conducting wire sag and ground wire information;Service end 90, is connected with intermediate ends 80, for dividing
Analysis typing information, obtains the prompt message whether transmission line of electricity breaks down.
In said system, circuit and the essential information of shaft tower that client 70 can be related to newly-built, modification and inquiry;Road
The essential information of line and shaft tower includes:Shaft tower numbering, overhead line structures type where shaft tower, exhale title height, arboreal growth speed,
The meteorological condition in shaft tower location;Can be also used for inquiring about and showing fault countermeasure and hidden danger prediction scheme, wherein, above-mentioned hidden danger prediction scheme
Can include:Hidden danger type, cause the information such as line fault form.
In a kind of optional embodiment, by shaft tower numbering, shaft tower type, title height, arboreal growth speed, shaft tower institute are exhaled
The information such as the meteorological condition on ground are with typing route in the form of sectional schematic diagram and floor map.
By above-mentioned client 70, it is possible to achieve obtain the purpose of the information of route and shaft tower.
In said system, intermediate ends 80 can be used for typing transmission of electricity scissors crossing information, tree line and be measured apart from point-to-point,
Conducting wire sag and ground wire information, while typing and updating maintenance hidden danger prediction scheme.
In a kind of optional embodiment, intermediate ends 80 can be with patterned form typing route and the information of shaft tower;
Fig. 3 is a kind of interface schematic diagram of transmission line of electricity scissors crossing editor according to embodiments of the present invention, as shown in fig. 6, power transmission line
The interface of road scissors crossing editor can include:Shaft tower title, away from small size lateral extent, away from large size lateral extent and whether synchronous flat
Face figure.
By above-mentioned intermediate ends 80, it is possible to achieve receive the purpose of typing information.
In said system, service end 90 can be used for according to typing information, and analysis show that line failure early warning is carried
Show information, in a kind of optional embodiment, according to tree line distance, the information of conducting wire sag and ground wire in service end 90,
Prompt message is sent on scissors crossing figure.
By above-mentioned service end 90, it is possible to achieve analysis typing information, the purpose whether transmission line of electricity breaks down is obtained.
In such scheme, the accuracy rate and operating efficiency for improving transmission line of electricity scissors crossing Data Enter are reached, carried
Production run personnel are facilitated to understand the purpose of all information of circuit in time while the operating efficiency that height transmission of electricity is maked an inspection tour, so that real
The skill of accuracy, diversity, promptness and transmission line malfunction Rush Repair Scheme accuracy that power transmission network information is substantially improved is showed
Art effect, so solve due to lack transmission line of electricity scissors crossing management platform cause no operation field support with supervision,
The technical problem that early warning pre-control is mutually supported with production decision in advance.
The embodiments of the present invention are for illustration only, and the quality of embodiment is not represented.
In the above embodiment of the present invention, the description to each embodiment all emphasizes particularly on different fields, and does not have in certain embodiment
The part of detailed description, may refer to the associated description of other embodiment.
In several embodiments provided herein, it should be understood that disclosed technology contents, can be by other
Mode is realized.Wherein, device embodiment described above is only schematical, such as division of described unit, Ke Yiwei
A kind of division of logic function, can there is other dividing mode when actually realizing, such as multiple units or component can combine or
Person is desirably integrated into another system, or some features can be ignored, or does not perform.Another, shown or discussed is mutual
Between coupling or direct-coupling or communication connection can be the INDIRECT COUPLING or communication link of unit or module by some interfaces
Connect, can be electrical or other forms.
The unit that is illustrated as separating component can be or may not be it is physically separate, it is aobvious as unit
The part for showing can be or may not be physical location, you can with positioned at a place, or can also be distributed to multiple
On unit.Some or all of unit therein can be according to the actual needs selected to realize the purpose of this embodiment scheme.
In addition, during each functional unit in each embodiment of the invention can be integrated in a processing unit, it is also possible to
It is that unit is individually physically present, it is also possible to which two or more units are integrated in a unit.Above-mentioned integrated list
Unit can both be realized in the form of hardware, it would however also be possible to employ the form of SFU software functional unit is realized.
If the integrated unit is to realize in the form of SFU software functional unit and as independent production marketing or use
When, can store in a computer read/write memory medium.Based on such understanding, technical scheme is substantially
The part for being contributed to prior art in other words or all or part of the technical scheme can be in the form of software products
Embody, the computer software product is stored in a storage medium, including some instructions are used to so that a computer
Equipment (can be personal computer, server or network equipment etc.) perform each embodiment methods described of the invention whole or
Part steps.And foregoing storage medium includes:USB flash disk, read-only storage (ROM, Read-Only Memory), arbitrary access are deposited
Reservoir (RAM, Random Access Memory), mobile hard disk, magnetic disc or CD etc. are various can be with store program codes
Medium.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should
It is considered as protection scope of the present invention.
Claims (10)
1. a kind of processing unit of transmission line of electricity scissors crossing, it is characterised in that including:
Information module, the information for obtaining route and shaft tower;
Typing information module, for receiving typing information, wherein, the typing information includes at least one following:Transmission of electricity intersects
Across information, tree line apart from point-to-point measurement, conducting wire sag and ground wire information;
Analytical calculation module, is connected with typing information module, for analyzing the typing information, obtains whether transmission line of electricity occurs
The prompt message of failure.
2. device according to claim 1, it is characterised in that described information module includes:
Update module, the information for changing the route and shaft tower.
3. device according to claim 1 and 2, it is characterised in that described information module also includes:
Enquiry module, the information of the route and shaft tower is obtained for inquiring about.
4. device according to claim 1, it is characterised in that the typing information includes at least one following:It is described hidden
Suffer from event type and the circuit types, the shaft tower type, exhale title height, arboreal growth speed, local meteorological condition, wire
Sag.
5. device according to claim 1, it is characterised in that the analytical calculation module includes:
Processing module, for calculating circuit hidden danger position and hidden danger species automatically in transmission line of electricity scissors crossing figure
Information.
6. device according to claim 2, it is characterised in that described device also includes:
Prediction scheme module, for typing hidden danger prediction scheme, and inquiry obtains fault countermeasure corresponding with the hidden danger prediction scheme;
Sort module, is connected with the prediction scheme module, for the hidden danger prediction scheme to be classified and is shown classification results;
Output module, the analysis electronics shelves for exporting the transmission line of electricity scissors crossing.
7. device according to claim 6, it is characterised in that the prediction scheme module includes:
Display module, for the hidden danger prediction scheme content obtained according to the hidden danger event type, display inquiry, wherein, institute
Stating hidden danger prediction scheme content includes:Hidden danger type, cause the information of line fault.
8. device according to claim 6, it is characterised in that the sort module includes:
Setup module, for the order of severity according to the hidden danger prediction scheme, sets announcement information.
9. device according to claim 6, it is characterised in that the output module includes:
Data supporting module, for the analysis electronics shelves according to output, for transmission line of electricity modification planning information is provided
Support.
10. a kind of processing system of transmission line of electricity scissors crossing, it is characterised in that including any one institute in claim 1 to 9
The processing unit of the transmission line of electricity scissors crossing stated.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611132740.6A CN106846168A (en) | 2016-12-09 | 2016-12-09 | The processing unit and system of transmission line of electricity scissors crossing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611132740.6A CN106846168A (en) | 2016-12-09 | 2016-12-09 | The processing unit and system of transmission line of electricity scissors crossing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106846168A true CN106846168A (en) | 2017-06-13 |
Family
ID=59140778
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611132740.6A Pending CN106846168A (en) | 2016-12-09 | 2016-12-09 | The processing unit and system of transmission line of electricity scissors crossing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106846168A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108597326A (en) * | 2018-03-14 | 2018-09-28 | 国网四川省电力公司技能培训中心 | Transmission line of electricity crossed crossing distance measures simulator and its emulation mode |
CN109583735A (en) * | 2018-11-21 | 2019-04-05 | 北京国网富达科技发展有限责任公司 | Patrolling transmission line method, system, mobile terminal and fortune inspection control platform |
CN110378491A (en) * | 2019-01-29 | 2019-10-25 | 国网江西省电力有限公司莲花县供电分公司 | A kind of power distribution network operation and maintenance method and system |
CN110889542A (en) * | 2019-11-19 | 2020-03-17 | 国网电力科学研究院武汉南瑞有限责任公司 | Dynamic prediction method for electrical safety distance of crossing of conducting wires and ground wires of power transmission line |
CN110955363A (en) * | 2019-11-22 | 2020-04-03 | 国网福建省电力有限公司莆田供电公司 | Method and system for improving outdoor power transmission operation efficiency |
CN113052474A (en) * | 2021-03-31 | 2021-06-29 | 广东电网有限责任公司 | Cross crossing key part early warning method and system based on power grid |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103246936A (en) * | 2013-04-24 | 2013-08-14 | 广东电网公司中山供电局 | System and method for pre-warning of typhoon risks of overhead transmission lines of grid |
CN103779808A (en) * | 2013-12-30 | 2014-05-07 | 国家电网公司 | Power transmission line intelligent inspection system based on LiDAR |
CN103869219A (en) * | 2012-12-14 | 2014-06-18 | 国家电网公司 | Fault handling method and device for power transmission network |
CN106771864A (en) * | 2016-12-12 | 2017-05-31 | 国网北京市电力公司 | The early warning system and transmission line of electricity of transmission line of electricity |
-
2016
- 2016-12-09 CN CN201611132740.6A patent/CN106846168A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103869219A (en) * | 2012-12-14 | 2014-06-18 | 国家电网公司 | Fault handling method and device for power transmission network |
CN103246936A (en) * | 2013-04-24 | 2013-08-14 | 广东电网公司中山供电局 | System and method for pre-warning of typhoon risks of overhead transmission lines of grid |
CN103779808A (en) * | 2013-12-30 | 2014-05-07 | 国家电网公司 | Power transmission line intelligent inspection system based on LiDAR |
CN106771864A (en) * | 2016-12-12 | 2017-05-31 | 国网北京市电力公司 | The early warning system and transmission line of electricity of transmission line of electricity |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108597326A (en) * | 2018-03-14 | 2018-09-28 | 国网四川省电力公司技能培训中心 | Transmission line of electricity crossed crossing distance measures simulator and its emulation mode |
CN108597326B (en) * | 2018-03-14 | 2020-04-21 | 国网四川省电力公司技能培训中心 | Power transmission line crossing distance measurement simulation device and simulation method thereof |
CN109583735A (en) * | 2018-11-21 | 2019-04-05 | 北京国网富达科技发展有限责任公司 | Patrolling transmission line method, system, mobile terminal and fortune inspection control platform |
CN109583735B (en) * | 2018-11-21 | 2021-10-01 | 北京国网富达科技发展有限责任公司 | Power transmission line inspection method and system, mobile terminal and operation inspection management and control platform |
CN110378491A (en) * | 2019-01-29 | 2019-10-25 | 国网江西省电力有限公司莲花县供电分公司 | A kind of power distribution network operation and maintenance method and system |
CN110889542A (en) * | 2019-11-19 | 2020-03-17 | 国网电力科学研究院武汉南瑞有限责任公司 | Dynamic prediction method for electrical safety distance of crossing of conducting wires and ground wires of power transmission line |
CN110955363A (en) * | 2019-11-22 | 2020-04-03 | 国网福建省电力有限公司莆田供电公司 | Method and system for improving outdoor power transmission operation efficiency |
CN110955363B (en) * | 2019-11-22 | 2023-08-11 | 国网福建省电力有限公司莆田供电公司 | Method and system for improving outdoor operation efficiency of power transmission |
CN113052474A (en) * | 2021-03-31 | 2021-06-29 | 广东电网有限责任公司 | Cross crossing key part early warning method and system based on power grid |
CN113052474B (en) * | 2021-03-31 | 2023-04-28 | 广东电网有限责任公司 | Cross-crossing key part early warning method and system based on power grid |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106846168A (en) | The processing unit and system of transmission line of electricity scissors crossing | |
CN105005827B (en) | A kind of emergency response method for early warning based on electric power accident | |
CN103914791A (en) | Electrical equipment state maintenance system | |
CN104951993A (en) | Comprehensive monitoring and early warning system based on meteorology and power grid GIS and method thereof | |
CN106654987A (en) | Power line multi-robot collaborative inspection method | |
CN104992254B (en) | Mountain fire based on power grid GIS and the meteorological trend pre-judging method combined | |
CN104077552A (en) | Rail traffic signal comprehensive operation and maintenance method and system based on cloud computing | |
CN109657912A (en) | A kind of visual power grid risk management and control method and system | |
CN106771864A (en) | The early warning system and transmission line of electricity of transmission line of electricity | |
CN105590160A (en) | Three-dimensional emergency command method and system on the basis of GIS | |
CN101819245A (en) | Monitoring method and system of transmission line | |
CN109902948A (en) | A kind of power transmission line monitoring system and method based on big data | |
CN105447623A (en) | Tree obstacle hidden trouble automatic pre-warning system for overhead transmission line and pre-warning method for above system | |
CN106469356A (en) | Transmission facility state evaluation based on multidimensional data and risk analysis method and device | |
CN106373391A (en) | Multi-dimensional intelligent scheduling service platform usage method serving for urban traffic | |
CN109146836A (en) | A kind of system and method carrying out power transmission tower and wireline inspection based on point cloud data | |
CN102646150A (en) | Lightning stroke link risk judging method based on thunder and lightning information | |
CN103544561A (en) | Method for realizing dynamic display of power transmission circuits, method for realizing operational maintenance of power transmission circuits and system for realizing management of power transmission circuits | |
CN108268972A (en) | Led to based on day and monitor prewarning analysis system and method on-line with the aviation integral admittance electric power facility of big-dipper satellite | |
CN106250570A (en) | A kind of subdrainage pipe network intelligent management system | |
CN102946069A (en) | Three-dimensional visualized intelligent monitoring system for extra-high voltage transmission line | |
CN103218694A (en) | Power emergency monitoring method and system | |
CN103150598A (en) | Processing system and method for sudden failure of power transmission network | |
CN105375631B (en) | Buried cable monitoring system for power network | |
CN111146866B (en) | Power transmission channel control method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170613 |
|
RJ01 | Rejection of invention patent application after publication |