CN106845847A - Project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method - Google Patents

Project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method Download PDF

Info

Publication number
CN106845847A
CN106845847A CN201710062859.9A CN201710062859A CN106845847A CN 106845847 A CN106845847 A CN 106845847A CN 201710062859 A CN201710062859 A CN 201710062859A CN 106845847 A CN106845847 A CN 106845847A
Authority
CN
China
Prior art keywords
project
transmitting
data
cost
converting electricity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710062859.9A
Other languages
Chinese (zh)
Inventor
刘钊
徐楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710062859.9A priority Critical patent/CN106845847A/en
Publication of CN106845847A publication Critical patent/CN106845847A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method, including project of transmitting and converting electricity history cost Data Collection and treatment;Project of transmitting and converting electricity quickly organizes the research of valency model building method;Project of transmitting and converting electricity analysis of prices data intelligence extraction mechanism and technique study;Based on the capital construction technical economy security management system research that Technological Economy is theoretical.Application of the invention can be realized analyzing contrast, application of the propulsion General Engineering Cost in engineering proposal decision-making work in the General Engineering Cost of capital project design, evaluation, closing in different phase;The efficiency and quality of construction investment scheme control decision, propulsion General Engineering Cost standardization popularization and application can be lifted;Project of transmitting and converting electricity full dose technical-economic index requirement can be on the whole held, Investor's Decision construction costs is easy in the grasp of control and cost information beneficial to analysis of prices personnel's cost process.Analysis of prices result output and application can be realized.

Description

Project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method
Technical field
The present invention relates to a kind of project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method, belong to power technology Field.
Background technology
Electricity power engineering control of investment is the important foundation sex work of electricity power engineering implementation management, electricity power engineering investment control point Analysis is the important step of electricity power engineering total investment processes management, be adapt to strong intelligent grid construction realize construction costs it is controllable, Supported in the important technology of control and administrative decision, be the important means for lifting electricity power engineering Cost Management lean level, while It is also one of necessary work of the analysis of power grid construction operational diagnosis, Cost Management.Feasibility study is estimated and budget estimate of preliminary design As control cost and ceiling that power engineering is invested, there is important management and control to the investment of engineering overall process and instruct to anticipate Justice.
Project of transmitting and converting electricity General Engineering Cost embodies the average level of project of transmitting and converting electricity cost in recent years, with universal design as base Plinth, fully with modular means, enhances adaptability and the flexibility of General Engineering Cost, is conducive to setting up construction costs mark Standard, rational evaluation engineering technological economy index effectively controls construction investment, reduces electricity power engineering construction cost, is conducive to accelerating Feasibility study, design, the progress of evaluation, improve operating efficiency, are the works such as power network project feasibility study, preliminary design, centralized bidding and final account of project The development of work provides foundation, creates advantage, improves electricity power engineering construction efficiency, is to strengthen Corporation system construction costs Management, the important means for reducing construction costs, increasing investment returns.
To implement Grid Construction Project intensive management, cost rationally being controlled, to lift technical economy operating efficiency, specification business Management principle for the purpose of flow and standard, Innovative Management Mode, there is provided project of transmitting and converting electricity analysis of prices data intelligent is extracted Mechanism and method are necessary.
The content of the invention
The purpose of the present invention is directed to a kind of not enough project of transmitting and converting electricity analysis of prices data intelligent of offer of prior art and carries Take mechanism and method.
The method of the invention is comprised the following steps:
The first step:Project of transmitting and converting electricity history cost Data Collection and treatment
Collect different voltage class, different engineering type project of transmitting and converting electricity cost data, including technology and economic two parts data. And the project data to collecting is pre-processed, special engineering, irrational data are rejected, the data of analysis is tended to be steady water It is flat, for follow-up study content provides data supporting, it is ensured that the accuracy of follow-up study achievement;
Second step:Project of transmitting and converting electricity quickly organizes the research of valency model building method
Based on General Engineering Cost, quick group valency mechanism and the method for research project of transmitting and converting electricity investment, including decompose-integrated, module splicing The utilization of theoretical method, excavates different voltage class, different engineering types and quickly organizes valency mechanism and method, and combine Practical Project Cost condition, will quickly organize valency model and be simulated practical application, for construction costs investment decision provides guidance and technical support;
3rd step:Project of transmitting and converting electricity analysis of prices data intelligence extraction mechanism and technique study
Based on cost basic data and the valency model application of quick group, with analytic hierarchy process (AHP) and cost whole process theory, realize making The standardization of valency data structure, standardization, composition and structure of the research analysis of prices data in construction costs source file, set up Analysis of prices data set up analysis of prices data intelligence extraction model from the intelligent securing mechanism in cost source file with this, For project of transmitting and converting electricity control of investment provides powerful data supporting;
4th step:Based on the capital construction technical economy security management system research that Technological Economy is theoretical
It is theoretical with risk management theory, Technological Economy, with reference to Utilities Electric Co.'s capital construction technical economy safety management requirement, study and set up Capital construction security management system, including management objectives, supervision evaluate etc. syllabus and content, auxiliary carry out infrastructure project Technical and economical level Evaluation work.
Beneficial effects of the present invention:Application of the invention can be realized in capital project design, evaluation, closing in different phase General Engineering Cost analysis contrast, propulsion application of the General Engineering Cost in engineering proposal decision-making work;Construction investment side can be lifted The efficiency and quality of case control decision, propulsion General Engineering Cost standardization popularization and application;Project of transmitting and converting electricity can on the whole be held Investment is easy in full dose technical-economic index requirement, the grasp of control and cost information beneficial to analysis of prices personnel's cost process Person's decision engineering cost.Analysis of prices result output and application can be realized.
Specific embodiment
The method of the invention is comprised the following steps:
The first step:Project of transmitting and converting electricity history cost Data Collection and treatment
Collect different voltage class, different engineering type project of transmitting and converting electricity cost data, including technology and economic two parts data. And the project data to collecting is pre-processed, special engineering, irrational data are rejected, the data of analysis is tended to be steady water It is flat, for follow-up study content provides data supporting, it is ensured that the accuracy of follow-up study achievement;
Second step:Project of transmitting and converting electricity quickly organizes the research of valency model building method
Based on General Engineering Cost, quick group valency mechanism and the method for research project of transmitting and converting electricity investment, including decompose-integrated, module splicing The utilization of theoretical method, excavates different voltage class, different engineering types and quickly organizes valency mechanism and method, and combine Practical Project Cost condition, will quickly organize valency model and be simulated practical application, for construction costs investment decision provides guidance and technical support;
3rd step:Project of transmitting and converting electricity analysis of prices data intelligence extraction mechanism and technique study
Based on cost basic data and the valency model application of quick group, with analytic hierarchy process (AHP) and cost whole process theory, realize making The standardization of valency data structure, standardization, composition and structure of the research analysis of prices data in construction costs source file, set up Analysis of prices data set up analysis of prices data intelligence extraction model from the intelligent securing mechanism in cost source file with this, For project of transmitting and converting electricity control of investment provides powerful data supporting;
4th step:Based on the capital construction technical economy security management system research that Technological Economy is theoretical
It is theoretical with risk management theory, Technological Economy, with reference to Utilities Electric Co.'s capital construction technical economy safety management requirement, study and set up Capital construction security management system, including management objectives, supervision evaluate etc. syllabus and content, auxiliary carry out infrastructure project Technical and economical level Evaluation work.

Claims (1)

1. a kind of project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method, it is characterised in that:
The first step:Project of transmitting and converting electricity history cost Data Collection and treatment
Collect different voltage class, different engineering type project of transmitting and converting electricity cost data, including technology and economic two parts data; And the project data to collecting is pre-processed, special engineering, irrational data are rejected, the data of analysis is tended to be steady water It is flat, for follow-up study content provides data supporting, it is ensured that the accuracy of follow-up study achievement;
Second step:Project of transmitting and converting electricity quickly organizes the research of valency model building method
Based on General Engineering Cost, quick group valency mechanism and the method for research project of transmitting and converting electricity investment, including decompose-integrated, module splicing The utilization of theoretical method, excavates different voltage class, different engineering types and quickly organizes valency mechanism and method, and combine Practical Project Cost condition, will quickly organize valency model and be simulated practical application, for construction costs investment decision provides guidance and technical support;
3rd step:Project of transmitting and converting electricity analysis of prices data intelligence extraction mechanism and technique study
Based on cost basic data and the valency model application of quick group, with analytic hierarchy process (AHP) and cost whole process theory, realize making The standardization of valency data structure, standardization, composition and structure of the research analysis of prices data in construction costs source file, set up Analysis of prices data set up analysis of prices data intelligence extraction model from the intelligent securing mechanism in cost source file with this, For project of transmitting and converting electricity control of investment provides powerful data supporting;
4th step:Based on the capital construction technical economy security management system research that Technological Economy is theoretical
It is theoretical with risk management theory, Technological Economy, with reference to Utilities Electric Co.'s capital construction technical economy safety management requirement, study and set up Capital construction security management system, including management objectives, supervision evaluate etc. syllabus and content, auxiliary carry out infrastructure project Technical and economical level Evaluation work.
CN201710062859.9A 2017-02-03 2017-02-03 Project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method Pending CN106845847A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710062859.9A CN106845847A (en) 2017-02-03 2017-02-03 Project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710062859.9A CN106845847A (en) 2017-02-03 2017-02-03 Project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method

Publications (1)

Publication Number Publication Date
CN106845847A true CN106845847A (en) 2017-06-13

Family

ID=59121327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710062859.9A Pending CN106845847A (en) 2017-02-03 2017-02-03 Project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method

Country Status (1)

Country Link
CN (1) CN106845847A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107527185A (en) * 2017-08-04 2017-12-29 昆明理工大学 A kind of project cost documentation and the parallel practice method examined
CN110135671A (en) * 2018-02-08 2019-08-16 国网青海省电力公司经济技术研究院 The method for building up of project of transmitting and converting electricity technical-economic index analysis model building sample database
CN112232627A (en) * 2020-09-07 2021-01-15 国网宁夏电力有限公司经济技术研究院 Estimation method for cost design elements of power transmission and transformation project
CN112669055A (en) * 2020-12-15 2021-04-16 山东鲁能软件技术有限公司 Power transmission and transformation project exploitable estimation simulation group price method and device
CN113487347A (en) * 2021-06-22 2021-10-08 南方电网能源发展研究院有限责任公司 Intelligent cost analysis method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107527185A (en) * 2017-08-04 2017-12-29 昆明理工大学 A kind of project cost documentation and the parallel practice method examined
CN107527185B (en) * 2017-08-04 2020-11-20 昆明理工大学 Parallel implementation method for compiling and examining construction project cost file
CN110135671A (en) * 2018-02-08 2019-08-16 国网青海省电力公司经济技术研究院 The method for building up of project of transmitting and converting electricity technical-economic index analysis model building sample database
CN112232627A (en) * 2020-09-07 2021-01-15 国网宁夏电力有限公司经济技术研究院 Estimation method for cost design elements of power transmission and transformation project
CN112669055A (en) * 2020-12-15 2021-04-16 山东鲁能软件技术有限公司 Power transmission and transformation project exploitable estimation simulation group price method and device
CN113487347A (en) * 2021-06-22 2021-10-08 南方电网能源发展研究院有限责任公司 Intelligent cost analysis method

Similar Documents

Publication Publication Date Title
CN106845847A (en) Project of transmitting and converting electricity analysis of prices data intelligent extraction mechanism and method
CN102355004B (en) Distributed photovoltaic power generation regional integrated control system
CN102545212B (en) Electrical energy quality centralized monitoring and auxiliary management decision support system
CN204858607U (en) Mobile payment intelligent charging stake with networking function
CN103217953A (en) System and method for temperature control and crack prevention intelligent monitoring of concrete dam
CN106251452A (en) A kind of unattended operation transformer station enters the station long-range Licensing Methods and execution system
CN105226959B (en) The control device and control method of modular multilevel high-voltage frequency converter
CN102244677A (en) Green energy Cloud computing method and system
CN106160219A (en) The monitoring method of remote forced monitoring system for transformer station switching operation
CN106803156A (en) The quick group of foundation of valency model based on General Engineering Cost
CN102355005A (en) Distributed photovoltaic power generation regional integrated control method
CN104156900A (en) Smart water plant management information monitoring system
CN107818449A (en) A kind of power transformation fortune inspection management system based on mobile solution platform
CN101436779B (en) Transient, dynamic stabilization aid decision-making automatic searching method based on parallel calculation
CN105591469A (en) Community microgrid distributed control system
CN110110759A (en) Power grid electric information pointing method and system based on the identification of various dimensions information
CN109299915A (en) A kind of scaffold operational method
CN104778564A (en) Prefabricated part construction management method based on information coding
CN103915901A (en) Transformer area load management system
CN106611385A (en) Intelligent reviewing method for power distribution network engineering cost
CN209322441U (en) A kind of novel cover plate for cable trench headstock gear
CN208792988U (en) Oil-well rig intelligence driller's system
CN205384639U (en) Step power station crowd instructs dispatching management system
CN111082522A (en) Distribution network state monitoring and fault processing system based on ubiquitous power Internet of things
CN203504292U (en) Power system protection device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Xu Nan

Inventor after: Yang Hongwei

Inventor after: Wang Dongchao

Inventor after: Liu Zhao

Inventor after: Song Yan

Inventor before: Liu Zhao

Inventor before: Xu Nan

CB03 Change of inventor or designer information
RJ01 Rejection of invention patent application after publication

Application publication date: 20170613

RJ01 Rejection of invention patent application after publication