CN106786266B - Prefabrication and assembly construction steel house cable and wire laying system and its construction method - Google Patents

Prefabrication and assembly construction steel house cable and wire laying system and its construction method Download PDF

Info

Publication number
CN106786266B
CN106786266B CN201611145896.8A CN201611145896A CN106786266B CN 106786266 B CN106786266 B CN 106786266B CN 201611145896 A CN201611145896 A CN 201611145896A CN 106786266 B CN106786266 B CN 106786266B
Authority
CN
China
Prior art keywords
cable
branch pipe
prefabrication
wire casing
steel house
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611145896.8A
Other languages
Chinese (zh)
Other versions
CN106786266A (en
Inventor
汤伟
金永华
王红兵
郎卫国
陈晓明
贾宝荣
龚明
马良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Design And Research Institute Co Ltd
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Construction Design And Research Institute Co Ltd
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Design And Research Institute Co Ltd, Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Construction Design And Research Institute Co Ltd
Priority to CN201611145896.8A priority Critical patent/CN106786266B/en
Publication of CN106786266A publication Critical patent/CN106786266A/en
Application granted granted Critical
Publication of CN106786266B publication Critical patent/CN106786266B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/36Installations of cables or lines in walls, floors or ceilings
    • H02G3/38Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts
    • H02G3/386Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts in walls
    • H02G3/388Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts in walls in modular walls, e.g. wall panels
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/08Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs
    • H02G3/0431Wall trunking

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Installation Of Indoor Wiring (AREA)

Abstract

It is formed in wall in advance for existing cable poling, the inconvenient problem of later stage modification, laying radius larger the problem of being unfavorable for saving installation space caused by cable installation in pipe, the present invention provides a kind of prefabrication and assembly construction steel house cable and wire laying system and its construction methods, the system includes several water power wallboards and several cables, the vertical branch pipe wire casing for cabling is opened up on water power wallboard, cable is fixed by several clip bunchys, clip is bonded in vertical branch pipe wire casing, it is easy for construction, the upper end of cable runs to indoor distribution box in furred ceiling along top plate, the lower end of cable is connected with socket or switch respectively.Later stage changes or repair, cable fix i.e. not cable installation in pipe by several clip bunchys, can reduce laying radius in water power wallboard, can facilitating for cable laying, saves installation space.In addition, power distribution room is connect with each indoor distribution box respectively with emanant power supply mode, it can directly power after the completion of every layer of assembly, temporary electricity application can be reduced.

Description

Prefabrication and assembly construction steel house cable and wire laying system and its construction method
Technical field
The present invention relates to electromechanical construction technology fields more particularly to a kind of prefabrication and assembly construction steel house cable and wire to lay System and its construction method.
Background technology
For a long time, the electric wiring laying installation of traditional prefabrication and assembly construction house is divided into two parts:Supply main portion Divide and electric terminal part.
Supply main part refers to electric power, (supporter refers to building to communication trunk line arrangement in house supporter The resident families such as the beam in the part that immobilizes, including load-carrying members, column, floor and load bearing wall, community installations, equipment are built to utilize jointly Part).Electric terminal part refers to the laying installations such as secondary distribution piping part, socket, switch (filling in house obturator Body refers to the privately owned parts such as building variable part, including interior decoration, internal partition wall, kitchen and toilet facility and life pipeline).
The characteristics of coordinating this traditional prefabrication and assembly construction house, from plant produced is designed into, will largely the equipment such as electrical it match Pipe, wiring are embedded in as the pre-buried component of PC plate in reinforced concrete prefabricated board, due to the prefabricated component of prefabricated dwelling house It is all disposably machined in factory, does not allow live trepanning, fluting, for electric specialty, in the design process It has to the arrangement of equipment and pipeline there are one accurate positioning, this just proposes higher requirement to electrical design:First The quantity of electrical equipment will be considered comprehensively by calculating;Trepanning, fluting size on the prefabricated boards such as its secondary determining floor, exterior wall and position It sets;The pre-buried electrical power distribution pipe position in prefabricated component is finally marked.And these positioning will carry out more with structure discipline Closely cooperation, the fitness between profession require higher;Even late design change but will damage precast wall body.
Invention content
The purpose of the present invention is to provide a kind of prefabrication and assembly construction steel house cable and wire laying system and its construction parties Method, by by cable laying, in that in water power wallboard, can facilitate, the later stage changes or repair, cable are solid by several clip bunchys Fixed, the clip is bonded in the vertical branch pipe wire casing of water power wallboard, compares existing cable cable installation in pipe, can reduce laying half Diameter saves installation space.
In order to solve the above technical problems, the present invention provides the following technical solutions:
A kind of prefabrication and assembly construction steel house cable and wire laying system, including several water power wallboards and several cables, The water power wallboard is distributed according to indoor power demand in the prefabrication and assembly construction steel house, is opened on the water power wallboard If for the vertical branch pipe wire casing of cabling, the cable is fixed by several clip bunchys, and the clip is bonded in described In vertical branch pipe wire casing, the upper end of the cable runs to indoor distribution box, the lower end of the cable in furred ceiling along top plate It is connected respectively with socket or switch.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the cable is in furred ceiling It is fixed by several clip bunchys, the clip is bonded on the bottom surface of top plate.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, on the water power wallboard also Open up one and the perpendicular horizontal branch pipe wire casing of the vertical branch pipe wire casing.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the lower end of the cable exists The vertical branch pipe wire casing is walked with after the intersection turning of the horizontal branch pipe wire casing along the horizontal branch pipe wire casing.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the cable is propped up in level It is fixed by clip bunchy in chase, the clip is bonded in horizontal branch pipe wire casing.
Preferably, further include cover board in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the lid The detachable outside for being set to vertical the branch pipe wire casing and horizontal branch pipe wire casing of plate, the cover board are equipped with the switch And/or socket.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the top plate is equipped with bee Nest beam, the reserved threading casing of setting in the hole that current supply cable passes through in the Honeycomb Beam.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the water power wallboard it is upper End is equipped with upper lateral chase, and the upper lateral chase is connected to the vertical branch pipe wire casing, the upper lateral pipe Plaster decoration line is arranged with furred ceiling link position in wire casing.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, power distribution room is with emanant confession Electric mode is connect with each indoor distribution box respectively, and the service entrance cable between power distribution room and each indoor distribution box passes through cable testing bridge It is set in floor cup prefabricated components, size is directly formed in floor cup prefabricated components the cable testing bridge in advance on demand.
The invention also discloses a kind of constructions of prefabrication and assembly construction steel house cable and wire laying system as described above Method includes the following steps:
Step 1 provides several water power wallboards and several cables;
The water power wallboard is set to the prefabrication and assembly construction steel house by step 2 according to indoor power demand It is interior, the vertical branch pipe wire casing for cabling is opened up on the water power wallboard, the cable is fixed by several clip bunchys, The clip is bonded in the vertical branch pipe wire casing, and the upper end of the cable runs to indoor distribution in furred ceiling along top plate The lower end of case, the cable is connected with socket or switch respectively;
Step 3, power distribution room are connect with each indoor distribution box respectively with emanant power supply mode, power distribution room with it is each indoor Service entrance cable between distribution box is set to by cable testing bridge in floor cup prefabricated components, and the cable testing bridge is big on demand It is small to be directly formed in advance in floor cup prefabricated components.
By techniques disclosed above scheme it is found that compared with prior art, beneficial effects of the present invention are as follows:
One, prefabrication and assembly construction steel house cable and wire laying system provided by the invention and its construction method, in water power The vertical branch pipe wire casing for cabling is opened up on wallboard, the cable is fixed by several clip bunchys, and the clip is viscous Tie in the vertical branch pipe wire casing, by by cable laying in the later stage in water power wallboard, can be facilitated to change or repair;Electricity Cable is fixed by several clip bunchys, and the clip is bonded in the vertical branch pipe wire casing of water power wallboard, is worn compared to existing cable Pipe is laid, and can reduce laying radius, saves installation space.The clip is bonded in the vertical branch pipe wire casing of water power wallboard, Bonding mode compares other connection types, and construction is more convenient convenient.
Two, prefabrication and assembly construction steel house cable and wire laying system provided by the invention and its construction method, at one layer Total ammeter metering room is set, and power distribution room is connect with each indoor distribution box respectively with emanant power supply mode, power distribution room and each family Cable between interior distribution box is set to by cable testing bridge in floor cup prefabricated components, cable testing bridge size on demand Directly it is formed in advance in floor cup prefabricated components.Existing normal cable main line crane span structure is installed in electric shaft, and present invention electricity Size is directly formed in floor cup prefabricated components cable crane span structure in advance on demand, can complete each layer distributing box for household in factory in advance Service entrance cable is prefabricated, is laid by floor so as to the scene of directly taking, and length is according to actual needs and the progress of pre- allowance is prefabricated, in Between be not required to connector, can directly power after the completion of every layer of assembly, so as to reduce temporary electricity application.
Description of the drawings
Fig. 1 is the structural schematic diagram of the prefabrication and assembly construction steel house cable and wire laying system of one embodiment of the invention.
Fig. 2 is that the distribution of vertical branch pipe wire casing and horizontal branch pipe wire casing on water power wallboard in one embodiment of the invention is illustrated Figure.
In figure:1- water power wallboard, 2- cables, 3- clips, 4 vertical branch pipe wire casings, 5- top plates, 6- horizontal branch pipees wire casing, 7- The reserved threading casing of cover board, 8- Honeycomb Beams, 9-, 10- upper laterals chase, 11- lower, transverses chase, 12- gypsum decoratives Lines, 13- walls inner cavity, 14- skirtings.
Specific implementation mode
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.According to following explanation and right Claim, advantages and features of the invention will become apparent from.To this hair be described in detail by cited embodiment combination attached drawing below Bright technology contents and feature.Need in addition it illustrate, attached drawing is all made of very simplified form and uses non-accurate ratio Example, only for the purpose of facilitating and clarifying the purpose of the embodiments of the invention.For sake of convenience, "upper" described below, "lower" is consistent with the upper and lower direction of attached drawing, but this can't be the limitation of technical solution of the present invention.
Embodiment one
It please refers to Fig.1 and Fig. 2, present embodiment discloses a kind of prefabrication and assembly construction steel house cable and wire laying system, Including several water power wallboards 1 and several cables 2 (can become inside cable), the water power wallboard 1 is according to indoor electricity consumption Demand is distributed in the prefabrication and assembly construction steel house, and the vertical branch pipe for cabling 2 is opened up on the water power wallboard 1 Wire casing 4, the cable 2 are fixed by 3 bunchy of several clips, and the clip 3 is bonded in the vertical branch pipe wire casing 4, described The upper end of cable 2 runs to indoor distribution box (not shown) in furred ceiling along top plate, and the upper end of the cable 2 is stretched into furred ceiling Indoor distribution box connection is run to, i.e. the upper end of the cable 2 is stretched into furred ceiling runs to indoor distribution box inside furred ceiling, institute The lower end for stating cable 2 is connect with socket or switch (not shown) respectively.On the one hand, the present embodiment is by the way that cable 2 to be laid in In water power wallboard 1, the later stage can be facilitated to change or repair.On the other hand, in the present embodiment cable 2 by several clips 3 at Beam is fixed, and the clip 3 is bonded in the vertical branch pipe wire casing 4 of water power wallboard 1, it is seen that the cable 2 of the present embodiment is used and do not worn Bright system of laying is managed, 2 cable installation in pipe mode of existing cable is compared, laying radius can be reduced, saves installation space.The card Folder 3 is bonded in the vertical branch pipe wire casing 4 of water power wallboard 1, and bonding mode compares other connection types so that construction is more convenient It is convenient.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the cable 2 is in furred ceiling It is fixed by 3 bunchy of several clips, the clip 3 is bonded on the top plate 5 i.e. bottom surface of floor of steel structure.Likewise, cable 2 Using the bright system of laying of not poling, 2 cable installation in pipe mode of existing cable is compared, laying radius can be reduced, it is empty to save installation Between;The clip 3 is bonded on the bottom surface of top plate 5, and bonding mode compares other connection types so that construction is more convenient just It is prompt
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, on the water power wallboard 1 also Open up one and the perpendicular horizontal branch pipe wire casing 6 of the vertical branch pipe wire casing 4.The lower end of the cable 2 is in the vertical branch pipe Wire casing 4 is walked with after the intersection turning of the horizontal branch pipe wire casing 6 along the horizontal branch pipe wire casing 6.It is horizontal by being arranged Cable 2 can be led to required horizontal position by the setting of branch pipe wire casing 6.Preferably, it is lived in above-mentioned prefabrication and assembly construction steel construction In home telephone cable electrical line setting system, the cable 2 is fixed in horizontal branch pipe wire casing 6 by 3 bunchy of clip, and the clip 3 is viscous It ties in horizontal branch pipe wire casing 6, bonding mode compares other connection types so that construction is more convenient convenient.
Preferably, further include cover board 7 in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, it is described The detachable outside for being set to vertical the branch pipe wire casing 4 and horizontal branch pipe wire casing 6 of cover board 7.The cover board 7 is equipped with described Switch and/or socket (not shown).It can not only be protected in vertical branch pipe wire casing 4 and horizontal branch pipe wire casing 6 by the way that cover board 7 is arranged Cable 2, convenient for switch or socket installation.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the top plate 5 is equipped with bee Nest beam 8, the reserved threading casing 9 of setting in the hole that current supply cable 2 passes through in the Honeycomb Beam 8.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, the water power wallboard 1 it is upper End and lower end are respectively equipped with upper lateral chase 10 and lower, transverse chase 11, the upper lateral chase 10 with it is described Vertical branch pipe wire casing 4 is connected to, and plaster decoration line 12 is arranged with furred ceiling link position in the upper lateral chase 10.The water There is electric wallboard 1 wall inner cavity 13, the side of the water power wallboard 1 to be equipped with the opening being connected to interior wall intracoelomic cavity 13, for Pipeline level is passed through.The outside of the lower, transverse chase 11 is provided with skirting 14.
Preferably, in above-mentioned prefabrication and assembly construction steel house cable and wire laying system, in prefabrication and assembly construction steel construction One layer of total ammeter metering room (not shown) of setting of house, power distribution room are connected with each indoor distribution box respectively with emanant power supply mode It connecing, the service entrance cable between power distribution room and each indoor distribution box is set to by cable testing bridge in floor cup prefabricated components, Size is directly formed in floor cup prefabricated components the cable testing bridge in advance on demand.Compared to existing normal cable crane span structure electrical Installation in vertical shaft, and size is directly formed in floor cup prefabricated components cable testing bridge of the present invention in advance on demand, in advance can be It is prefabricated that each layer distributing box for household service entrance cable is completed in factory, is laid by floor so as to the scene of directly taking, length is by practical It needs and the progress of pre- allowance is prefabricated, centre is not required to connector, can directly power after the completion of every layer of assembly, interim so as to reduce Electricity consumption application.
Embodiment two
Please continue to refer to Fig. 1 and Fig. 2, the present embodiment provides the prefabrication and assembly construction steel house cable electricity described in embodiment one The construction method of wire routing system, includes the following steps:
Step 1 provides several water power wallboards and several cables.
The water power wallboard is set to the prefabrication and assembly construction steel house by step 2 according to indoor power demand It is interior, the vertical branch pipe wire casing 4 for cabling 2 is opened up on the water power wallboard 1, the cable 2 passes through 3 bunchy of several clips Fixed, the clip 3 is bonded in the vertical branch pipe wire casing 4, and the upper end of the cable 2 is walked in furred ceiling along top plate 5 To indoor distribution box, the lower end of the cable 2 is connected with socket or switch respectively.On the one hand, the present embodiment is by by cable 2 It is laid in water power wallboard 1, the later stage can be facilitated to change or repair.On the other hand, cable 2 passes through several cards in the present embodiment It presss from both sides 3 bunchys to fix, the clip 3 is bonded in the vertical branch pipe wire casing 4 of water power wallboard 1, it is seen that the cable 2 of the present embodiment uses The not bright system of laying of poling compares 2 cable installation in pipe mode of existing cable, can reduce laying radius, saves installation space.Institute It states clip 3 to be bonded in the vertical branch pipe wire casing 4 of water power wallboard 1, bonding mode compares other connection types so that construction is more It is convenient to facilitate.
Step 3, power distribution room are connect with each indoor distribution box respectively with emanant power supply mode, power distribution room with it is each indoor Service entrance cable between distribution box is set to by cable testing bridge in floor cup prefabricated components, and the cable testing bridge is big on demand It is small to be directly formed in advance in floor cup prefabricated components.It is installed in electric shaft compared to existing normal cable crane span structure, and it is of the invention Size is directly formed in floor cup prefabricated components cable testing bridge in advance on demand, can complete each layer resident family distribution in factory in advance Case service entrance cable is prefabricated, is laid by floor so as to the scene of directly taking, and length is according to actual needs and the progress of pre- allowance is prefabricated, Centre is not required to connector, can directly power after the completion of every layer of assembly, so as to reduce temporary electricity application.
In conclusion the present invention has the beneficial effect that:
One, prefabrication and assembly construction steel house cable and wire laying system provided by the invention, use is opened up on water power wallboard In the vertical branch pipe wire casing of cabling, the cable is fixed by several clip bunchys, and the clip is bonded in described vertical In branch pipe wire casing, by by cable laying in water power wallboard, can facilitate the later stage change or repair;Cable passes through several cards Folder bunchy is fixed, and the clip is bonded in the vertical branch pipe wire casing of water power wallboard, is compared existing cable cable installation in pipe, can be subtracted Small laying radius saves installation space.The clip is bonded in the vertical branch pipe wire casing of water power wallboard, and bonding mode compares it His connection type, construction are more convenient convenient.
Two, total ammeter meter is arranged at one layer for prefabrication and assembly construction steel house cable and wire laying system provided by the invention Between amount, power distribution room is connect with each indoor distribution box respectively with emanant power supply mode, between power distribution room and each indoor distribution box Cable be set in floor cup prefabricated components by cable testing bridge, size is directly formed on building to the cable testing bridge in advance on demand In layer cup prefabricated component.Existing normal cable main line crane span structure is installed in electric shaft, and cable testing bridge of the present invention is on demand Size is directly formed in advance in floor cup prefabricated components, and it is pre- can to complete each layer distributing box for household service entrance cable in factory in advance System is laid so as to the scene of directly taking by floor, and length is according to actual needs and the progress of pre- allowance is prefabricated, and centre is not required to connect Head can directly be powered after the completion of every layer of assembly, so as to reduce temporary electricity application.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Range.

Claims (9)

1. a kind of construction method of prefabrication and assembly construction steel house cable and wire laying system, which is characterized in that described a kind of pre- System assembly steel house cable and wire laying system, including several water power wallboards and several cables, the water power wallboard root It is distributed in the prefabrication and assembly construction steel house according to indoor power demand, is opened up for cabling on the water power wallboard Vertical branch pipe wire casing, the cable fixed by several clip bunchys, and the clip is bonded in the vertical branch pipe wire casing, The upper end of the cable runs to indoor distribution box in furred ceiling along top plate, the lower end of the cable respectively with socket or open Connection connects, and the construction method includes the following steps:
Step 1 provides several water power wallboards and several cables;
The water power wallboard is set in the prefabrication and assembly construction steel house, institute by step 2 according to indoor power demand The vertical branch pipe wire casing opened up on water power wallboard for cabling is stated, the cable is fixed by several clip bunchys, described Clip is bonded in the vertical branch pipe wire casing, and the upper end of the cable runs to indoor distribution box in furred ceiling along top plate, The lower end of the cable is connected with socket or switch respectively;
Step 3, power distribution room are connect with each indoor distribution box respectively with emanant power supply mode, power distribution room and each indoor distribution Service entrance cable between case is set to by cable testing bridge in floor cup prefabricated components, and size is straight on demand for the cable testing bridge Connect pre- be formed in floor cup prefabricated components.
2. the construction method of prefabrication and assembly construction steel house cable and wire laying system as described in claim 1, feature exist In the cable is fixed in furred ceiling by several clip bunchys, and the clip is bonded on the bottom surface of top plate.
3. the construction method of prefabrication and assembly construction steel house cable and wire laying system as described in claim 1, feature exist In also opening up one and the perpendicular horizontal branch pipe wire casing of the vertical branch pipe wire casing on the water power wallboard.
4. the construction method of prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 3, feature exist In the lower end of, the cable along the water after the turning of the intersection of the vertical branch pipe wire casing and the horizontal branch pipe wire casing Flat branch pipe wire casing walking.
5. the construction method of prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 4, feature exist In the cable is fixed in horizontal branch pipe wire casing by clip bunchy, and the clip is bonded in horizontal branch pipe wire casing.
6. the construction method of prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 3, feature exist In further including cover board, the detachable outside for being set to vertical the branch pipe wire casing and horizontal branch pipe wire casing of the cover board is described Cover board is equipped with the switch and/or socket.
7. the construction method of prefabrication and assembly construction steel house cable and wire laying system as claimed in claim 2, feature exist It is equipped with Honeycomb Beam in, the top plate, setting is reserved in the hole that current supply cable passes through in the Honeycomb Beam threads casing.
8. the construction method of prefabrication and assembly construction steel house cable and wire laying system as described in claim 1, feature exist In the upper end of the water power wallboard is equipped with upper lateral chase, the upper lateral chase and the vertical branch pipe wire casing Plaster decoration line is arranged with furred ceiling link position in connection, the upper lateral chase.
9. the construction of the prefabrication and assembly construction steel house cable and wire laying system as described in any one of claim 1-8 Method, which is characterized in that power distribution room is connect with each indoor distribution box respectively with emanant power supply mode, power distribution room with it is each indoor Service entrance cable between distribution box is set to by cable testing bridge in floor cup prefabricated components, and the cable testing bridge is big on demand It is small to be directly formed in advance in floor cup prefabricated components.
CN201611145896.8A 2016-12-13 2016-12-13 Prefabrication and assembly construction steel house cable and wire laying system and its construction method Active CN106786266B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611145896.8A CN106786266B (en) 2016-12-13 2016-12-13 Prefabrication and assembly construction steel house cable and wire laying system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611145896.8A CN106786266B (en) 2016-12-13 2016-12-13 Prefabrication and assembly construction steel house cable and wire laying system and its construction method

Publications (2)

Publication Number Publication Date
CN106786266A CN106786266A (en) 2017-05-31
CN106786266B true CN106786266B (en) 2018-08-31

Family

ID=58876503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611145896.8A Active CN106786266B (en) 2016-12-13 2016-12-13 Prefabrication and assembly construction steel house cable and wire laying system and its construction method

Country Status (1)

Country Link
CN (1) CN106786266B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110499861A (en) * 2018-05-16 2019-11-26 深圳市君盈建筑科技有限公司 A kind of furred ceiling electricity separation system
CN111201358A (en) * 2018-05-16 2020-05-26 深圳市君盈建筑科技有限公司 Residence with water pipe and weak current electric wire separated from main structure
WO2019218177A1 (en) * 2018-05-16 2019-11-21 深圳市君盈建筑科技有限公司 Construction method for house having pipe and wire separate from main structure
CN110945198A (en) * 2018-05-16 2020-03-31 广东博智林机器人有限公司 House with separated strong current wire and main body structure
CN110499933A (en) * 2018-05-16 2019-11-26 深圳市君盈建筑科技有限公司 A kind of house that pipeline is separated with main structure
CN112106265A (en) * 2018-05-16 2020-12-18 东莞市碧桂园房地产开发有限公司 House with separated water pipe, strong current electric wire and main body structure
CN110731038A (en) * 2018-05-16 2020-01-24 深圳市君盈建筑科技有限公司 Construction method of house with water pipe, strong electric wire and main body structure separated
WO2019218235A1 (en) * 2018-05-16 2019-11-21 深圳市君盈建筑科技有限公司 Construction method for house having high-voltage wire separate from main structure
WO2019218223A1 (en) * 2018-05-16 2019-11-21 深圳市君盈建筑科技有限公司 House having electrical wire separate from main structure
CN110474267A (en) * 2019-08-19 2019-11-19 福建省顺安建筑工程有限公司 A kind of reserved water, electricity and gas comprehensive wire casing structure and its construction method

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004064816A (en) * 2002-07-25 2004-02-26 Aoki Engineering:Kk Routing method of conduit in building
CN103061515B (en) * 2012-12-29 2015-10-14 陕西省第三建筑工程公司 Concrete hollow block infilled wall pre-buried PVC conduit poling mounting method
CN204216515U (en) * 2014-10-18 2015-03-18 福州万山电力咨询有限公司 The mounting structure of distribution engineering cable testing bridge
CN104453085B (en) * 2014-10-28 2016-06-15 成都市第四建筑工程公司 A kind of line box installation method of light aggregate concrete hollow partition board
CN106149880B (en) * 2015-03-20 2020-10-09 万平华 Adopt equipment room of new construction system
CN204741240U (en) * 2015-04-07 2015-11-04 自贡市博雅装饰工程有限公司 Strong and weak electric winding displacement system
CN204651834U (en) * 2015-06-09 2015-09-16 上海绿地建设(集团)有限公司 The pre-buried structure of electric pipeline in a kind of brick wall
CN206313397U (en) * 2016-12-13 2017-07-07 上海市建工设计研究总院有限公司 Prefabrication and assembly construction steel house cable and wire laying system

Also Published As

Publication number Publication date
CN106786266A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
CN106786266B (en) Prefabrication and assembly construction steel house cable and wire laying system and its construction method
CN206313397U (en) Prefabrication and assembly construction steel house cable and wire laying system
CN109707091B (en) Assembly type invisible beam composite floor slab with separated pipelines installed from top to bottom
CN107171189A (en) A kind of cable tunnel integrated with substation equipment basis
CN106906843A (en) Underground pipe gallery and its construction method
CN208803681U (en) Piping shaft and building structure
CN216344379U (en) Pipeline node two-way connecting piece
CN109469099A (en) Assembled underground pipe gallery
CN108551151A (en) Big closed High-Voltage Cable Branching Case apart
CN205335810U (en) Cable distribution box
CN206625257U (en) Underground pipe gallery
CN209040352U (en) It can the live precast light round-hole partition wall board slotted
CN210857599U (en) Pipeline separation waterproof heat preservation integration wall body and building that constitutes thereof
CN206844150U (en) A kind of shallow embedding formula pipe gallery
CN212935272U (en) Mounting structure of indoor distribution box and household distribution box of residence
CN209211764U (en) Preheating embedding line mounting groove for reinforced concrete wall panel
CN216195868U (en) Line box embedded structure and coincide floor
CN104878857B (en) A kind of lightweight prefabricated combined wall body
CN211063308U (en) Large-scale cell body cable channel
CN213682630U (en) Prefabricated interior wall structure of integration convenient to electromechanical pipeline house-entry
CN214280815U (en) Wiring structure with separated electrical pipelines
CN209025350U (en) A kind of modular assembly formula building water-electricity integrated modularization arrangement
CN219960040U (en) Integrative device of pre-buried high tensile couple line box
CN221263231U (en) Layered assembled composite cable bridge
CN201297478Y (en) Plastic-steel rectangular sheath pipe for insulation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 200050 Changning District, Wuyi Road, No. 150,

Applicant after: Shanghai construction design and Research Institute Co Ltd

Applicant after: Shanghai Mechanized Construction Group Co., Ltd.

Address before: 200050 Changning District, Wuyi Road, No. 150,

Applicant before: Shanghai Construction Group Design Institute Co., Ltd.

Applicant before: Shanghai Mechanized Construction Group Co., Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant