CN106761765A - One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method - Google Patents

One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method Download PDF

Info

Publication number
CN106761765A
CN106761765A CN201611211301.4A CN201611211301A CN106761765A CN 106761765 A CN106761765 A CN 106761765A CN 201611211301 A CN201611211301 A CN 201611211301A CN 106761765 A CN106761765 A CN 106761765A
Authority
CN
China
Prior art keywords
wall
shaft
freezing
hole
frozen
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611211301.4A
Other languages
Chinese (zh)
Inventor
张馨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201611211301.4A priority Critical patent/CN106761765A/en
Publication of CN106761765A publication Critical patent/CN106761765A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/10Preparation of the ground
    • E21D1/12Preparation of the ground by freezing
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/03Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method, determines major-minor well shaft center and outer according to design drawing, and indicated with lime.The data such as main round, middle round, arrangement circle footpath, hole count, the perforate spacing in anti-wall caving hole accurately determine bore position in major-minor well shaft freezing hole plane of arrangement figure.In freezing process is implemented, control brine temp and brine recycling speed, control freezing wall expansion rate, thickness and Care in method, reach and do not freeze real energy safe excavation again, main round is mainly and ensures that frost wall reaches the satisfactory requirement for handing over circle and basement rock weathering section to freeze, being undertaken together with middle round simultaneously increases Frozen wall thickness, reduces frost wall mean temperature, the effect of increase frost wall strength and stability, and middle round also acts as the effect that the well increased below anti-wall caving hole helps stability.Logical to improve shaft sinking speed, work efficiency is greatly improved, and the construction period significantly shortens, and saves expense, good economy performance.

Description

One kind is applied to Frozen Shaft safely and fast to be excavated and is applied by huge thick big expanded clay layer Work method
Technical field
The present invention relates to a kind of huge thick big expanded clay interval frozen construction new technology of vertical shaft, more particularly to one kind is applied to Frozen Shaft is safely and fast excavated by huge thick big expanded clay layer construction technique.
Background technology
Frozen Shaft is by the big expanded clay of huge thick-layer, such as Jiangsu Feng County Li Tangkuang main shafts and auxiliary shaft, argillic horizon total thickness point Not Wei 287.23m and 309.81m, account for respectively table soil freeze section 67.2% and 72.0%, particularly main shaft is in well depth -320.5 ~-422.0m, auxiliary shaft in well depth -323.2~-423.8m, its continuous clay thickness degree respectively reach 101.5m and 100.6m, clay has certain viscosity mainly in yellow, grayish green, reddish brown, aubergine of becoming rusty, and natural expansion rate is 105%~115%, is frozen 0.4~0.5MPa of expansive force, frozen-heave factor 2.09%~2.65%.Freeze control quality most important, freeze too real to construction safety It is guaranteed, but a rate of advance is too slow, and cost increases;Freeze not in place, excavate soon, but be susceptible to wall caving inbreak, potential safety hazard Greatly, in addition occur fracture of freezing pipe, cause to freeze unsuccessfully pit shaft waterflooding.The risk of freeze section driving and masonry construction is high, and difficulty is very big, right Borehole wall supporting construction and intensity requirement are high.After frost wall thaws, borehole wall stress is big, and force structure is complicated.
The content of the invention
The purpose of the present invention is that when overcoming above-mentioned expanded clay layer tunneling construction big to huge thickness in the prior art not Foot, and one kind is provided is applied to Frozen Shaft and safely and fast excavate by huge thick big expanded clay layer construction technique, the new skill Art uses the comprehensive freezing method of " main round+via hole+anti-wall caving hole ", and by Optimizing construction technique, improves and freeze to apply Work progress, shortens the duration, can play plant machinery efficiency, construction safety, economic, practical.
The technical scheme is that:One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer Construction method, the method is carried out according to the following steps:
S1 measures unwrapping wire according to design drawing, major-minor well shaft center and pit shaft outer is released, and entered with lime Rower shows.
S2 according to main round, middle round and anti-wall caving hole in the major-minor well shaft freezing hole arrangement parameter table of table 1 arrangement circle The parameters such as footpath, the depth of freezing, hole depth, perforate spacing are drilled, and whether drilling is completed, and is hole-specifically checked, sees meet the requirements.
After S3 borehole inspections meet requirement, freezing pipe is installed, be using specificationNorth expects pipe makees feed flow Manage, specification isFreezing pipe is using interior hoop weldering.
S4 controls brine temp and brine recycling speed, control freezing wall expansion rate, thickness in freezing process is implemented And Care in method, reach and do not freeze real energy safe excavation again.
S5 carries out Shaft Excavation according to design drawing, and pit shaft concreting is carried out in time.
The present invention has the advantage that and good effect:
1st, anti-wall caving hole is mainly in frozen soil tunneling process, plays a part of to prevent upper exposed famine wall flaps from helping, anti- The side hole depth of freezing becomes path position determination according to shaft excavation, and main round is mainly guarantee satisfactory friendship of frost wall arrival and encloses and base The requirement that rock weathering section is freezed, while undertaking increase Frozen wall thickness together with middle round, reducing frost wall mean temperature, increase The effect of frost wall strength and stability, middle round also acts as the effect that the well increased below anti-wall caving hole helps stability.
2nd, can be by controlling brine temp and brine recycling speed, control freezing wall expansion rate, thickness and well side temperature Degree, reaches and do not freeze real energy safe excavation again.
3rd, shaft sinking speed is improved, work efficiency is greatly improved, and the construction period significantly shortens, saves expense, good economy performance.
Brief description of the drawings
Fig. 1 is major-minor well shaft freezing hole plane of arrangement figure.
Specific embodiment
As described in Figure 1, the present invention is safely and fast excavated by huge thick big expanded clay layer for one kind is applied to Frozen Shaft Construction technique, carries out 1. determining major-minor well shaft center and outer according to design drawing, and entered with lime according to the following steps Rower shows.2. according to main round in Fig. 1 major-minor well shaft freezing hole plane of arrangement figures, middle round, the arrangement circle footpath in anti-wall caving hole, The data such as hole count, perforate spacing accurately determine bore position, with red lacquer painting circle.According to the major-minor well shaft freezing hole cloth of table 1 during drilling The depth of freezing is drilled in putting parameter designing table.3. whether drilling is completed, and is hole-specifically checked, sees meet the requirements.4. drill Check after meeting requirement, install freezing pipe (specificationFreezing pipe is using interior hoop weldering), be using specificationNorth expects pipe makees feed pipe.5. in freezing process is implemented, brine temp and brine recycling speed, control are controlled Frost wall expansion rate processed, thickness and Care in method, reach and do not freeze real energy safe excavation again.6. it is waste in tunneling process in order to reduce Wall open-assembly time, it is ensured that outer wall excavation and lining construction safety, in huge thick-bedded clay outer wall short section pick build section it is high determine H=2.0~ 2.5m, empty side time t ≯ 24h, by the control of displacement of sidewall amount in 20~50mm, it is ensured that thickness of shaft wall.7. in section is high 3 80~100mm of loop diameter, 400~600mm of depth holes are made a call in upper, middle and lower using twist drill rods by well side, while uniformly excavating 8~16 Road V-arrangement pressure relief groove, discharges the bulbs of pressure.8. bilayer 30~60mm polystyrene plastic foamboards are laid between well side and outer wall, Fixed with the bar dowel squeezed into clay using bamboo chip, slow release of pressure effect is played certain well side deflection has been reserved, improved Concrete walling curing condition, plays function of heat insulation, it is ensured that concrete solidifies, effectively prevents outer wall morning at low temperature Phase damages by pressure, it is ensured that external wall construction quality and follow-up driving and masonry construction safety.9. in order to prevent outer wall cracking chip off-falling, personnel in the pit is set It is standby to cause potential safety hazard, 10~40 sets of walling cribs first are processed on ground, walling crib is using [18a channel-section steels make, and each walling crib is by four pieces of groups Into with 2 bolt connections of Φ 18mm between every piece, connecting plate is processed using 10mm steel plates.Each walling crib processing simultaneously is straight Footpath Φ 36mm, the reverse wedge formula crab-bolt 12 of length 400mm, crab-bolt end thickness 10mm steel plates are welded and fixed walling crib.If hair Existing outer wall cracking chip off-falling, 8mm steel plates are laid in the borehole wall, and steel plate specification is length × wide=6000mm × 1500mm, and ring is placed, First steel plate is hung on reinforcing bar, after walling crib is fixed on the borehole wall, then steel plate is bolted in walling crib, walling crib and Steel plate combination is used as the external mold for pouring into a mould concrete.Pressure stubble that is vertical and laterally having 50mm, can be connected with spot welding between every block of steel plate Connect.10. the borehole wall concrete of pit shaft is poured.
Table 1 is major-minor well shaft freezing hole arrangement parameter design table
The major-minor well shaft frost wall formation and development prediction case of table 2

Claims (3)

1. one kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method, it is characterised in that: The method uses the comprehensive freezing method of " main round+via hole+anti-wall caving hole ", and by Optimizing construction technique, improves jelly Knot construction speed, shortens the duration, can play plant machinery efficiency, construction safety, economic, practical;Frozen Shaft is safely and fast Excavate by huge thick big expanded clay layer construction technique, it is characterised in that carried out according to the following steps:S1 is according to design drawing Paper, measures unwrapping wire, major-minor well shaft center and pit shaft outer is released, and indicated with lime;S2 is according to major-minor well Pit shaft freezing hole arrangement parameter table is to the arrangement circle footpath of main round, middle round and anti-wall caving hole, between the depth of freezing, hole depth, perforate Away from etc. parameter drilled, drilling complete, hole-specifically checked, see whether meet the requirements;After S3 borehole inspections meet requirement, peace If freezing pipe, specificationFreezing pipe is welded using interior hoop, be using specificationPVC the first day of the lunar month expects pipes make feed flow Pipe;S4 controls brine temp and brine recycling speed, control freezing wall expansion rate, thickness and well in freezing process is implemented Side temperature, reaches and do not freeze real energy safe excavation again;S5 carries out Shaft Excavation according to design drawing, pit shaft concrete is carried out in time and is poured Build.
2. one kind according to claim 1 is applied to Frozen Shaft and safely and fast excavates applied by huge thick big expanded clay layer Work method, it is characterised in that:Anti- wall caving hole is mainly in frozen soil tunneling process, plays the work for preventing upper exposed famine wall flaps side With the anti-wall caving hole depth of freezing becomes path position and determines according to shaft excavation, and main round is mainly guarantee frost wall and reaches satisfactory friendship The requirement that circle and basement rock weathering section are freezed, while it is average that increase Frozen wall thickness, reduction frost wall are undertaken together with middle round The effect of temperature, increase frost wall strength and stability, middle round also acts as the well increased below anti-wall caving hole and helps stability Effect.
3. one kind according to claim 1 is applied to Frozen Shaft and safely and fast excavates applied by huge thick big expanded clay layer Work method, it is characterised in that:By controlling brine temp and brine recycling speed, control freezing wall expansion rate, thickness and well Side temperature, reaches and do not freeze real energy safe excavation again.
CN201611211301.4A 2016-12-24 2016-12-24 One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method Pending CN106761765A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611211301.4A CN106761765A (en) 2016-12-24 2016-12-24 One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611211301.4A CN106761765A (en) 2016-12-24 2016-12-24 One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method

Publications (1)

Publication Number Publication Date
CN106761765A true CN106761765A (en) 2017-05-31

Family

ID=58919449

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611211301.4A Pending CN106761765A (en) 2016-12-24 2016-12-24 One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method

Country Status (1)

Country Link
CN (1) CN106761765A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104820A (en) * 2017-11-28 2018-06-01 安徽理工大学 Freeze-wellboring freezing hole method for arranging under a kind of big flow velocity groundwater effect
CN108678750A (en) * 2018-07-19 2018-10-19 淮矿西部煤矿投资管理有限公司 A kind of headframe pile foundation and freezing drill bore parallel construction system and parallel construction method
CN108843325A (en) * 2018-07-19 2018-11-20 淮矿西部煤矿投资管理有限公司 Cross parallel construction system and method are built in vertical headframe, pit shaft freezing, pick
CN108952728A (en) * 2018-07-19 2018-12-07 淮矿西部煤矿投资管理有限公司 A kind of headframe main body construction and self well digging freeze parallel construction system and method
CN110439567A (en) * 2019-09-05 2019-11-12 李功洲 Deep thick alluvium project of shaft freezing design method
CN113356858A (en) * 2021-07-13 2021-09-07 中煤第一建设有限公司 Non-equal-strength composite freezing wall freezing method
CN114382071A (en) * 2021-12-28 2022-04-22 中煤邯郸特殊凿井有限公司 Method for freezing chalk series stratum
CN114562271A (en) * 2022-03-02 2022-05-31 安徽理工大学 Design method of freezing rib-spalling-preventing hole of shaft

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000297590A (en) * 1999-04-16 2000-10-24 Chem Grouting Co Ltd Excavation wall construction method
CN1560557A (en) * 2004-03-10 2005-01-05 马芹永 Technology method of artificial frozen soil control blasting by deep surface forzen method
CN101419041A (en) * 2008-11-19 2009-04-29 中煤第一建设公司第四十九工程处 Deep hole blasting process in frost weathering bedrock segment
CN103277103A (en) * 2013-05-20 2013-09-04 陕西彬长矿业集团有限公司 None-full-depth freezing method for penetrating through ultra-thick water-rich bed rock in shaft deepening
CN104405400A (en) * 2014-10-08 2015-03-11 海南大学 Method for arranging cup-shaped horizontal freezing holes in end of large-diameter shield tunnel
CN105823387A (en) * 2016-02-25 2016-08-03 中铁十八局集团有限公司 Rapid construction method for deep hole blasting of vertical shaft frozen bedrock
CN205532600U (en) * 2016-03-31 2016-08-31 煤炭工业合肥设计研究院 A dog collar control system for during vertical construction freezing method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000297590A (en) * 1999-04-16 2000-10-24 Chem Grouting Co Ltd Excavation wall construction method
CN1560557A (en) * 2004-03-10 2005-01-05 马芹永 Technology method of artificial frozen soil control blasting by deep surface forzen method
CN101419041A (en) * 2008-11-19 2009-04-29 中煤第一建设公司第四十九工程处 Deep hole blasting process in frost weathering bedrock segment
CN103277103A (en) * 2013-05-20 2013-09-04 陕西彬长矿业集团有限公司 None-full-depth freezing method for penetrating through ultra-thick water-rich bed rock in shaft deepening
CN104405400A (en) * 2014-10-08 2015-03-11 海南大学 Method for arranging cup-shaped horizontal freezing holes in end of large-diameter shield tunnel
CN105823387A (en) * 2016-02-25 2016-08-03 中铁十八局集团有限公司 Rapid construction method for deep hole blasting of vertical shaft frozen bedrock
CN205532600U (en) * 2016-03-31 2016-08-31 煤炭工业合肥设计研究院 A dog collar control system for during vertical construction freezing method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张馨: "《深立井与隧道工程理论和实践》", 31 May 2008, 中国铁道出版社 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104820A (en) * 2017-11-28 2018-06-01 安徽理工大学 Freeze-wellboring freezing hole method for arranging under a kind of big flow velocity groundwater effect
CN108678750A (en) * 2018-07-19 2018-10-19 淮矿西部煤矿投资管理有限公司 A kind of headframe pile foundation and freezing drill bore parallel construction system and parallel construction method
CN108843325A (en) * 2018-07-19 2018-11-20 淮矿西部煤矿投资管理有限公司 Cross parallel construction system and method are built in vertical headframe, pit shaft freezing, pick
CN108952728A (en) * 2018-07-19 2018-12-07 淮矿西部煤矿投资管理有限公司 A kind of headframe main body construction and self well digging freeze parallel construction system and method
CN108952728B (en) * 2018-07-19 2019-06-25 淮矿西部煤矿投资管理有限公司 A kind of headframe main body construction and self well digging freeze parallel construction system and method
CN110439567A (en) * 2019-09-05 2019-11-12 李功洲 Deep thick alluvium project of shaft freezing design method
CN110439567B (en) * 2019-09-05 2020-11-03 李功洲 Deep punching lamination freezing scheme design method
CN113356858A (en) * 2021-07-13 2021-09-07 中煤第一建设有限公司 Non-equal-strength composite freezing wall freezing method
CN113356858B (en) * 2021-07-13 2023-02-28 中煤第一建设有限公司 Non-equal-strength composite freezing wall freezing method
CN114382071A (en) * 2021-12-28 2022-04-22 中煤邯郸特殊凿井有限公司 Method for freezing chalk series stratum
CN114382071B (en) * 2021-12-28 2024-02-06 中煤邯郸特殊凿井有限公司 Chalk-based stratum freezing method
CN114562271A (en) * 2022-03-02 2022-05-31 安徽理工大学 Design method of freezing rib-spalling-preventing hole of shaft

Similar Documents

Publication Publication Date Title
CN106761765A (en) One kind is applied to Frozen Shaft and safely and fast excavates by huge thick big expanded clay layer construction method
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN105041333B (en) It is a kind of first to fill out the method for digging method processing Tunnel Landslide afterwards
CN105351001B (en) A kind of method based on gob side entry retaining region reinforcement gas pumping
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
WO2014187171A1 (en) Method for networked reinforcement of cross boreholes of outburst coal seam
CN113137235B (en) Construction method of high-ground-stress soft rock extrusion large-deformation tunnel
CN110284885A (en) Shield inspection-pit construction method
CN110617067A (en) Low-risk construction method for full-section boundary advanced pipe shed of extremely-soft surrounding rock tunnel
CN104196014A (en) Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN113803074A (en) Construction method of tunnel structure for artificial and mechanical combined obstacle removal of water-rich sand layer
CN107100164A (en) A kind of long auger guncreting pile construction method
CN107191206B (en) A kind of six step construction method of Shallow-buried Large-span Tunnel Unit two
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN105134069B (en) One kind is related to gas vertical and passes through the anti-well method construction technology in strong rich water rock stratum
CN108547625B (en) TBM cutterhead method for dismounting in a kind of tunnel
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN105927246A (en) High-pressure tunnel lining concrete uplift failure repair method
CN105862897A (en) Original-groove casting construction method for shallow foundation of sandy mudstone foundation
CN212272234U (en) High-strength combined template for open groove section of large-section inclined shaft
CN112983467A (en) Treatment method for tunnel gate closing type large collapse
CN103147435A (en) Method for treating construction engineering foundation in gob
CN202124855U (en) Rotary drilling prefabricate composite pile
CN207177912U (en) Through the anti-skidding shearing resistance administration structure of the inter-laminar dislocation band of great burying underground chamber

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531