CN106759478A - A kind of prefabricated piping lane construction method - Google Patents

A kind of prefabricated piping lane construction method Download PDF

Info

Publication number
CN106759478A
CN106759478A CN201611219825.8A CN201611219825A CN106759478A CN 106759478 A CN106759478 A CN 106759478A CN 201611219825 A CN201611219825 A CN 201611219825A CN 106759478 A CN106759478 A CN 106759478A
Authority
CN
China
Prior art keywords
base plate
lateral wall
board
connector
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611219825.8A
Other languages
Chinese (zh)
Other versions
CN106759478B (en
Inventor
马晓燕
王中和
刘銮成
陈杰
丁飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Coal No 3 Construction Group Co Ltd
Original Assignee
China Coal No 3 Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Coal No 3 Construction Group Co Ltd filed Critical China Coal No 3 Construction Group Co Ltd
Priority to CN201611219825.8A priority Critical patent/CN106759478B/en
Publication of CN106759478A publication Critical patent/CN106759478A/en
Application granted granted Critical
Publication of CN106759478B publication Critical patent/CN106759478B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of prefabricated piping lane construction method, comprise the following steps:(1) construction of prefabricated components:Prefabricated lateral wall, top board and base plate, and left end and right-hand member in the top and bottom of lateral wall, the left end of top board and right-hand member and base plate is respectively provided with connector;(2) assembly of prefabricated components:Base plate is first lifted, then lifts lateral wall, and the connector of the lower end of lateral wall is interfixed to the corresponding connector on base plate, then framework equipment is installed, finally lift top board, and the connector of the upper end of lateral wall is interfixed to the corresponding connector on top board;(3) cast-in-place shaping:Concrete is poured in the inner surface of lateral wall and the outer surface of top board.The present invention using it is prefabricated with cast-in-place combination by the way of come piping lane of constructing, operation is simple, speed is fast, and safety coefficient is high, and bulk velocity serves good structurally waterproof and act on far above integral prefabricated lift-on/lift-off system, efficiently solves waterproof problem.

Description

A kind of prefabricated piping lane construction method
Technical field
The present invention relates to a kind of prefabricated piping lane construction method, lay and safeguard for the underground utilities in city.
Background technology
The function that the underground utilities in city are responsible for the information transmission in city, energy conveying, water drainage mitigation, waste are dumped, Material base that city is depended on for existence and development, it just as " blood vessel " and " nerve " in human body, therefore, be known as city " lifeline " in city.
With the acceleration of Urbanization in China, City Buried Pipeline development is very swift and violent.Therefore, Development of Urban ground Lower pipe gallery engineering has certain " urgent " property.Pipe gallery refers to be placed in below ground, managed for accommodating various municipal administrations Line, is provided with special inspection socket, hoisting port and monitoring system, implement unified planning, the structure of design-build and management and its Affiliated facility, is one of important form of current underground space development.
At present, two kinds of conventional construction methods and its shortcoming of pipe gallery are as follows:
1st, cast in situs method:Domestic to build or built pipe gallery is generally using the construction of cast-in-place concrete method, its is excellent Point is that technique and operability are simple, it is flexible to construct, and is participated in jointly to control cost beneficial to social vast enterprise, but exist Distinct disadvantages such as " activity duration are long, airborne dust is big, influence public transport ", also solves, this side without complete prophylactico-therapeutic measures Method obtains many denouncing from society.
2nd, integral prefabricated, lift-on/lift-off system:In recent years, as foreign countries are using integral prefabricated Method for Installation construction underground pipe gallery technology Successful Application, and progressively promote, achieve obvious social benefit, the country starts to imitate, but because China has still belonged to step Section, the required mould development of prefabrication, the exploitation of piping lane Dock With Precision Position plant equipment, operative's level relatively fall behind, unfavorable It is general more using the design of light section size piping lane in native land in the development and application of the piping lane of big cross section size.Big cross section size, The piping lane of the big scale of construction needs the hoisting machineries such as configuration more than hundred tons large caterpillars, straddle trucks to aid in easily, increased and is constructed into This, also increases difficulty of construction, is unfavorable for construction safety.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of operation simply, and speed is fast, and safety coefficient is high, effectively solve The prefabricated piping lane construction method of waterproof problem.
In order to solve the above-mentioned technical problem, the present invention is adopted the following technical scheme that:A kind of prefabricated piping lane construction method, it is special Levy and be, comprise the following steps:
(1) construction of prefabricated components
Prefabricated lateral wall, top board and base plate, and at the top and bottom of lateral wall, the left end of top board and right-hand member and bottom The left end and right-hand member of plate are respectively provided with connector;
(2) assembly of prefabricated components
Base plate is first lifted, then lifts lateral wall, and by the connector of the lower end of lateral wall and the corresponding connector on base plate Interfix, then framework equipment is installed, finally lift top board, and the connector of the upper end of lateral wall is corresponding on top board Connector interfixes;
(3) cast-in-place shaping
Concrete is poured in the inner surface of lateral wall and the outer surface of top board.
Further, step (1) also includes prefabricated mid-board, and is also provided with connector in the upper end of mid-board, in base plate Inner surface setting be used for mid-board lower end insert groove;Step (2) be additionally included in lifting lateral wall after, install mould bases Mid-board is lifted before equipment, makes the lower end of mid-board insert in the groove on base plate, and after top board is lifted, by mid-board The connector of upper end interfixes with the corresponding connector on corresponding top board;Pour the upper surface that step (3) is additionally included in mid-board Build concrete.
Further, connector is provided with the bolt hole of bar shaped.
Further, the connector on the connector and base plate of the lower end of lateral wall is provided with curved bolt hole, Remaining connector is provided with the bolt hole of bar shaped.
Further, step (1) also includes, is left in the inner surface of lateral wall and the outer surface of top board and connects a batch reinforcing bar.
Further, step (1) also includes, the left side upper edge of the outer surface lower edge of lateral wall and base plate, Right side upper edge is respectively provided with elongated unfilled corner, and after cast-in-place shaping, the elongated unfilled corner on lateral wall is corresponding on base plate Elongated unfilled corner surrounds filling waterproof gasket cement in interval.
Further, step (1) also includes, pre-buried first weldment on the cell wall of the groove on base plate, and in mid-board Corresponding first weldment in lower end position at pre-buried second weldment, step (2) also includes, base plate is inserted the lower end of mid-board is being made Groove in after, the first weldment is welded and fixed with the second weldment.
Further, the cross section of the groove on base plate is in inverted trapezoidal, pre- respectively in two chute walls of the groove on base plate The first weldment is buried, the lower end of mid-board is also in inverted trapezoidal, has distinguished the second weldering pre-buried on two oblique side walls of the lower end of mid-board Part.
Further, framework equipment includes more than two door shape frames for being connected by two supporting legs and crossbeam and being constituted Frame, is connected with the singletree of more than between two supporting legs of door shape framework, two are passed through between adjacent two sub- shape frameworks Connecting rod more than root is connected.
Further, singletree is hollow tapped long nut, and interlocking has gaily decorated basket screw rod on singletree.
Beneficial effects of the present invention are embodied in:
1. the present invention using it is prefabricated with cast-in-place combination by the way of come piping lane of constructing, and it is small that piping lane is integrally split as several Component, part primary structural component is divided into prefabricated components and cast-in-place two parts, and base plate is complete prefabricated, and top board and lateral wall are half prefabricated, solution Determine and tied up public transport, large lifting equipment cost absorption, the problem of speed of application, and prefabricated components typically only need to tens Operation by ton crane, operation is simple, speed is fast, and safety coefficient is high, and bulk velocity is far above integral prefabricated lift-on/lift-off system, and this Each single prefabricated component is poured and constitutes an entirety by the last cast-in-place link of invention, serves good structure Waterproof action, efficiently solves waterproof problem.
2. the design of bolt hole of the present invention can substantially reduce the stitching error between each prefabricated components, so as to effectively keep away Exempt to splice the generation in gap and the running pulp everywhere when concrete is poured.
3. the present invention clogs waterproof gasket cement by designing elongated unfilled corner, further increases the anti-watertight between component Feng Xing, solves seepage problem present in prior art.
4. mid-board of the present invention is plugged in groove by the first weldment and being welded and fixed for the second weldment, in ensure that The firmly installing property of partition wall, compared to the mode of slip casting, faster, structure is more stable for speed of application.
Brief description of the drawings
Fig. 1 is the schematic cross-section of double storehouse rectangle piping lanes that the prefabricated piping lane construction method of one embodiment of the invention is constructed.
Fig. 2 is the structure broken away view of double storehouse rectangle piping lanes that the prefabricated piping lane construction method of one embodiment of the invention is constructed.
Fig. 3 is the knot of the prefabricated components of double storehouse rectangle piping lanes that the prefabricated piping lane construction method of one embodiment of the invention is constructed Structure broken away view.
Fig. 4 is enlarged drawing at the A of Fig. 3.
Fig. 5 is the regulation schematic diagram of the curved bolt hole in the prefabricated piping lane construction method of one embodiment of the invention.
Fig. 6 is enlarged drawing at the B of Fig. 3.
Fig. 7 is enlarged drawing at the C of Fig. 3.
The flow chart of the step of Fig. 8 to Figure 13 one embodiment of the invention prefabricated piping lane construction method (2) and (3).
Figure 14 is enlarged drawing at the D of Figure 13.
Figure 15 is the structural representation of the framework equipment in the prefabricated piping lane construction method of one embodiment of the invention.
Figure 16 is that the door shape framework of the framework equipment in the prefabricated piping lane construction method of one embodiment of the invention removes signal Figure.
In accompanying drawing the mark of each part for:1 lateral wall, 2 top boards, 3 base plates, 4 mid-boards, 5 connectors, 6 grooves, 7 first Weldment, 8 second weldments, 9 elongated unfilled corners, 10 framework equipments, 101 supporting legs, 102 crossbeams, 103 bolts, 104 singletrees, 105 connections Bar, 106 gaily decorated basket screw rods, 107 rollers.
Specific embodiment
The invention will be further described below in conjunction with the accompanying drawings:
Referring to Fig. 1, so that sectional dimension is 8m wide, 5m high, wall thickness 0.3m, the double storehouse rectangle piping lanes per sections 3m long as an example, The prefabricated piping lane construction method of one embodiment of the invention is elaborated, the structure of the double storehouse rectangle piping lanes being molded by the method is torn open Divide and see Fig. 2, be split as:Two pieces of 2, two pieces of top board, 1, one piece of lateral wall, 4, one piece of base plates 3 of mid-board, wherein concrete legend are filled Part is pre-erection, and oblique line filling part is divided into cast-in-place part.
Specifically include following steps:
(1) construction of prefabricated components, refers to Fig. 3:
Lateral wall 1 it is prefabricated:The thickness of lateral wall 1 0.15m, 4.7m high, 3m long, inner surface leaves and connects a batch reinforcing bar, and inner surface Top and bottom are respectively equipped with connector 5, and every piece of lateral wall 1 sets 4 connectors 5;
Top board 2 it is prefabricated:The thickness of top board 2 0.15m, 3.55m wide, 3m long, outer surface are left and connect a batch reinforcing bar, and left and right two ends are also divided Connector 5 is not provided with, and every piece of top board 2 sets 4 connectors 5;
Base plate 3 it is prefabricated:The thickness of base plate 3 0.3m, 8m wide, 3m long, the inner surface centre position of base plate 3 is provided with elongated inverted trapezoidal Groove 6, deep about 3 centimeters, left and right two ends are also respectively equipped with connector 5;
Mid-board 4 it is prefabricated:Thick 0.3m, 4.43m high, 3m long, the upper end of mid-board 4 also are provided with connector 5, in every piece every Wall 4 sets 2 connectors 5, and the lower end of mid-board 4 can be inserted in the groove 6 of base plate 3;
Connector 5 on above-mentioned each prefabricated components is made of steel plate, and bolt hole is provided with connector 5, so each prefabricated Component can be interconnected and fixed by through the bolt of the bolt hole on the connector 5 them;
In addition, referring to Fig. 7, the first weldment 7, the lower end of mid-board 4 are embedded with two chute walls of the groove 6 on base plate 3 In inverted trapezoidal, pre-buried second weldment 8 is distinguished on two oblique side walls of the lower end of mid-board 4, the lower end of such mid-board 4 can insert bottom After in the groove 6 of plate 3, the first weldment 7 is corresponding with the position of the second weldment 8, and the first weldment 7 and the second weldment 8 are made of steel plate, Both substantially fit;
In addition, referring to Fig. 4, the outer surface lower edge of figure lateral wall 1 and the left and right both ends of the surface upper edge of base plate 3 set respectively There are deep 2 centimeters, 1 centimeter wide of elongated unfilled corner 9, waterproof gasket cement is clogged for the later stage;
(2) assembly of prefabricated components
Positioning, unwrapping wire, slot, pour concrete bed course after, first lift base plate 3, as shown in Figure 8;
The left end and right-hand member in base plate 3 lift lateral wall 1 respectively again, and blending bolt is by the connector 5 of the lower end of lateral wall 1 Interfixed to the corresponding connector 5 on base plate 3, as shown in Figure 9;
Then mid-board 4 is lifted, makes the lower end of mid-board 4 insert in the groove 6 of base plate 3, adjust the perpendicularity of mid-board 4 Afterwards, the first weldment 7 and the second weldment 8 are welded to each other fixation, as shown in Figure 10;
Framework equipment 10 is respectively mounted in each corridor storehouse again, as shown in figure 11;
Finally lift top board 2, blending bolt is by the corresponding connection on the connector 5 of the upper end of lateral wall 1 and corresponding top board 2 Part 5 interfixes, the connector 5 of the upper end of mid-board 4 interfixes with the corresponding connector 5 on corresponding top board 2, such as Figure 12 institutes Show;
Space between two pieces of lateral walls 1 is divided into this method mid-board 4 Lang Cang of two, and a Lang Cang correspondence one There is top board 2 block top board 2, the upper end left and right sides of mid-board 4, therefore, can be by the connector 5 of the upper end of mid-board 4 and two pieces of top boards 2 On corresponding connector 5 be disposably connected, as shown in figure 12;
(3) cast-in-place shaping
The upper surface of inner surface, the outer surface of top board 2 and mid-board 4 in lateral wall 1 pours concrete, under 25 DEG C of temperature about 8 hours ensure concrete not losing fangle can the demoulding, as shown in figure 13;
(4) waterproof
In the outer surface of lateral wall 1 and the left and right both ends of the surface junction of base plate 3, namely the elongated unfilled corner 9 on lateral wall 1 Surrounded to the corresponding elongated unfilled corner 9 on base plate 3 and waterproof gasket cement clogged in interval, as shown in figure 14, the outer surface of lateral wall 1 with The guarantee of trying one's best of the left and right both ends of the surface of base plate 3 is flushed, then by design and construction outsourcing waterproof coiled material, that is, completes applying for the sections of piping lane one Work.So circulation.
During in-site installation, each prefabricated components, it cannot be guaranteed that absolute is horizontal and vertical, exist in spelling between component Certain position deviation, therefore the present embodiment design, the wherein connector on the connector 5 and base plate 3 of the lower end of lateral wall 1 Bolt hole on 5 is curved, referring to Fig. 4, so, the adjustable-angle upper deviation, for example, base plate 3 wait when mounted can not possibly be with Lateral wall 1 ensures absolute upright, but it has individual rule, refers to Fig. 5, is exactly that lateral wall 1 is the A points (under outer surface in figure Edge) rotation, therefore be that can determine that radius of turn according to the position of connector 5, arc length can determine that according to deviation range requirement;In every The bolt hole on connector 5 on wall 4 is in vertical bar shaped, preferably kidney ellipsoid, and the bolt hole on remaining connector 5 is in level Bar shaped, preferred kidney ellipsoid, as shown in fig. 6, the deviation so on adjustable horizontal, vertical direction;
Can substantially reduce the stitching error between each prefabricated components by the design with upper bolt hole, so as to effectively keep away Exempt to splice the generation in gap and the running pulp everywhere when concrete is poured.
In addition, the present invention clogs waterproof gasket cement by designing elongated unfilled corner 9, further increase anti-between component Water tightness, solves seepage problem present in prior art.
And mid-board 4 is plugged in groove 6 by the first weldment 7 and being welded and fixed for the second weldment 8, in ensure that The firmly installing property of partition wall 4, compared to the mode of slip casting, faster, structure is more stable for speed of application.
Referring to Figure 15, in the present embodiment, framework equipment 10 is passed through including two by two supporting legs 101 and a crossbeam 102 Bolt 103 is connected the door shape framework for constituting, and door shape framework can dismantle arbitrarily, two supporting legs 101 of door shape framework it Between be vertically uniformly provided with three horizontal singletrees 104, and the two ends of singletree 104 are respectively adopted hinge with two supporting legs 101 The mode of connecing is connected, and is connected by six roots of sensation connecting rod 105 between two sub- shape frameworks, and the two ends of connecting rod 105 are respectively adopted pin joint Mode is connected with two sub- shape frameworks, and certainly, as needed, door shape framework can set more, singletree and connecting rod Quantity can also increase or reduce.
In the present embodiment, singletree is hollow tapped long nut, and interlocking has gaily decorated basket screw rod 106 on singletree 104. So singletree 104 constitutes flower basket bolt with gaily decorated basket screw rod 106, by the intermediate handle for rotating gaily decorated basket screw rod, you can realize branch Leg 101 " stretches and shrinks ".
The lower section of supporting leg 101 is provided with roller 107, convenient walking.
Whether connecting rod outside can lay steel form as needed, install the cast-in-place structural template of lateral wall inner surface When, its base opening should reserve more than 2 centimeters gaps, facilitate roller to roll, and gap can be blocked using small template;This framework equipment 10 is torn open Dress is simple, is readily transported, stores, and schematic diagram is as shown in figure 16 after dismounting.
It should be noted that above is to explaining that prefabricated piping lane construction method of the invention is carried out by taking double storehouse rectangle piping lanes as an example State, only need one piece of mid-board 4, if the storehouse number demand of piping lane is more, the quantity of mid-board 4 is in two or more, certainly, groove 6 Quantity and position according to can need to be changed;
When the storehouse number requirement to piping lane is one, then mid-board 4, the inner surface of base plate 3 is not needed to set groove 6, and only need one piece of top board 2.
It should be understood that example as herein described and implementation method are not intended to limit the invention, this area only for explanation Technical staff can make various modifications or change according to it, all any modifications within the spirit and principles in the present invention, made, Equivalent, improvement etc., should be included within the scope of the present invention.

Claims (10)

1. a kind of prefabricated piping lane construction method, it is characterised in that comprise the following steps:
(1) construction of prefabricated components
Prefabricated lateral wall, top board and base plate, and in the top and bottom of lateral wall, the left end of top board and right-hand member and base plate Left end and right-hand member are respectively provided with connector;
(2) assembly of prefabricated components
Base plate is first lifted, then lifts lateral wall, and the connector of the lower end of lateral wall is mutual to the corresponding connector on base plate It is fixed, then framework equipment is installed, finally lift top board, and by the connector of the upper end of lateral wall and the corresponding connection on top board Part interfixes;
(3) cast-in-place shaping
Concrete is poured in the inner surface of lateral wall and the outer surface of top board.
2. prefabricated piping lane construction method as claimed in claim 1, it is characterised in that:Step (1) also includes prefabricated mid-board, and Connector is also provided with the upper end of mid-board, the groove that the lower end for being used for mid-board in the inner surface setting of base plate is inserted;Step (2) be additionally included in lifting lateral wall after, install framework equipment before lift mid-board, make mid-board lower end insert base plate on Groove in, it is and after top board is lifted, the connector of mid-board upper end and corresponding connector on corresponding top board is mutually solid It is fixed;The upper surface that step (3) is additionally included in mid-board pours concrete.
3. prefabricated piping lane construction method as claimed in claim 1 or 2, it is characterised in that:Connector is provided with the spiral shell of bar shaped Keyhole.
4. prefabricated piping lane construction method as claimed in claim 1 or 2, it is characterised in that:The connector of the lower end of lateral wall with And the connector on base plate is provided with curved bolt hole, remaining connector is provided with the bolt hole of bar shaped.
5. prefabricated piping lane construction method as claimed in claim 1 or 2, it is characterised in that:Step (1) also includes, in lateral wall Inner surface and the outer surface of top board leave and connect a batch reinforcing bar.
6. prefabricated piping lane construction method as claimed in claim 1 or 2, it is characterised in that:Step (1) also includes, in lateral wall Outer surface lower edge and the left side upper edge of base plate, right side upper edge be respectively provided with elongated unfilled corner, cast-in-place shaping it Afterwards, the elongated unfilled corner on lateral wall surrounds to the corresponding elongated unfilled corner on base plate and waterproof gasket cement is clogged in interval.
7. prefabricated piping lane construction method as claimed in claim 2, it is characterised in that:Step (1) also includes, recessed on base plate Pre-buried first weldment on the cell wall of groove, and pre-buried second weldment, step at the position of corresponding first weldment in lower end of mid-board (2) also include, after making in the groove of lower end insertion base plate of mid-board, the first weldment is welded and fixed with the second weldment.
8. prefabricated piping lane construction method as claimed in claim 7, it is characterised in that:The cross section of the groove on base plate is terraced in falling Shape, distinguishes pre-buried first weldment in two chute walls of the groove on base plate, the lower end of mid-board is also in inverted trapezoidal, mid-board Pre-buried second weldment is distinguished on two oblique side walls of lower end.
9. prefabricated piping lane construction method as claimed in claim 1 or 2, it is characterised in that:Framework equipment includes more than two Be connected the door shape framework for constituting by two supporting legs and crossbeam, be connected between two supporting legs of door shape framework one with On singletree, it is connected by the connecting rod of more than two between adjacent two sub- shape frameworks.
10. prefabricated piping lane construction method as claimed in claim 9, it is characterised in that:Singletree is hollow tapped length Nut, interlocking has gaily decorated basket screw rod on singletree.
CN201611219825.8A 2016-12-26 2016-12-26 A kind of prefabricated piping lane construction method Active CN106759478B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611219825.8A CN106759478B (en) 2016-12-26 2016-12-26 A kind of prefabricated piping lane construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611219825.8A CN106759478B (en) 2016-12-26 2016-12-26 A kind of prefabricated piping lane construction method

Publications (2)

Publication Number Publication Date
CN106759478A true CN106759478A (en) 2017-05-31
CN106759478B CN106759478B (en) 2019-01-04

Family

ID=58926907

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611219825.8A Active CN106759478B (en) 2016-12-26 2016-12-26 A kind of prefabricated piping lane construction method

Country Status (1)

Country Link
CN (1) CN106759478B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107653900A (en) * 2017-08-25 2018-02-02 中建科技有限公司深圳分公司 A kind of preparation method of Prefabricated pipe gallery
CN109469103A (en) * 2019-01-16 2019-03-15 上海中森建筑与工程设计顾问有限公司 A kind of environment-friendly type fabricated assembly overall pipe gallery and its assembly method
CN110130396A (en) * 2019-05-14 2019-08-16 沈阳建筑大学 A kind of assembly type variable storehouse underground pipe gallery and attaching method thereof
CN110617079A (en) * 2019-10-28 2019-12-27 中铁二院工程集团有限责任公司 Shield comprehensive pipe gallery pipeline installation shed frame system
CN112482435A (en) * 2020-12-01 2021-03-12 西安建筑科技大学 Underground excavation construction method for underground multi-cabin pipe gallery through building

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232328A (en) * 2003-01-30 2004-08-19 Taisei Corp Structure of half precast type arch culvert and its construction method
CN104674847A (en) * 2015-03-05 2015-06-03 东北大学 Novel assembling type precast concrete urban comprehensive pipe gallery and construction method thereof
CN104762993A (en) * 2015-02-11 2015-07-08 中国铁建大桥工程局集团有限公司 Splicing type construction method of urban lake-passing tunnel
CN105696622A (en) * 2016-01-18 2016-06-22 中国铁建大桥工程局集团有限公司 Prefabricated urban pipe gallery and construction method thereof
CN106245674A (en) * 2016-08-01 2016-12-21 中建五局第三建设有限公司 Hollow wallboard mixes prefabricated assembled pipe gallery and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232328A (en) * 2003-01-30 2004-08-19 Taisei Corp Structure of half precast type arch culvert and its construction method
CN104762993A (en) * 2015-02-11 2015-07-08 中国铁建大桥工程局集团有限公司 Splicing type construction method of urban lake-passing tunnel
CN104674847A (en) * 2015-03-05 2015-06-03 东北大学 Novel assembling type precast concrete urban comprehensive pipe gallery and construction method thereof
CN105696622A (en) * 2016-01-18 2016-06-22 中国铁建大桥工程局集团有限公司 Prefabricated urban pipe gallery and construction method thereof
CN106245674A (en) * 2016-08-01 2016-12-21 中建五局第三建设有限公司 Hollow wallboard mixes prefabricated assembled pipe gallery and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107653900A (en) * 2017-08-25 2018-02-02 中建科技有限公司深圳分公司 A kind of preparation method of Prefabricated pipe gallery
CN109469103A (en) * 2019-01-16 2019-03-15 上海中森建筑与工程设计顾问有限公司 A kind of environment-friendly type fabricated assembly overall pipe gallery and its assembly method
CN110130396A (en) * 2019-05-14 2019-08-16 沈阳建筑大学 A kind of assembly type variable storehouse underground pipe gallery and attaching method thereof
CN110617079A (en) * 2019-10-28 2019-12-27 中铁二院工程集团有限责任公司 Shield comprehensive pipe gallery pipeline installation shed frame system
CN112482435A (en) * 2020-12-01 2021-03-12 西安建筑科技大学 Underground excavation construction method for underground multi-cabin pipe gallery through building

Also Published As

Publication number Publication date
CN106759478B (en) 2019-01-04

Similar Documents

Publication Publication Date Title
CN106759478B (en) A kind of prefabricated piping lane construction method
CN106854873B (en) Engineering method of prefabricated spliced open caisson type parking garage and parking garage
CN105089669B (en) A kind of underground station of use prefabricated parts and its construction method
CN105756070B (en) A kind of Fabricated Structure for Support of Excavation system based on prefabricated components
CN106049530B (en) City integrated piping lane and construction method
CN107142960A (en) A kind of city piping lane construction method
CN106284412B (en) A kind of prefabricated pipe gallery and construction method
CN206971270U (en) Exterior wall formwork system in underground pipe gallery cast-in-place construction
CN207160062U (en) A kind of underground is without post overlapping wall station
CN108149706A (en) A kind of cast-in-place hidden girder and the prefabricated assembled pipe gallery and its construction method of superimposed sheet splicing
CN109184740A (en) Assembled tube coupling and preparation method thereof
CN110080295A (en) A kind of lid of assembled vault greatly across no column underground structure digs full-reverse construction method
CN109555112A (en) A kind of structure superposition formula diaphram wall and construction method
CN208486404U (en) A kind of concrete shear force wall of steel bar template integrative installation technology
CN103122642B (en) Construction method of vertical post support change
CN203795601U (en) Horizontal connection node for precast concrete members
CN208734343U (en) A kind of station tunnel excavation structure with interim middle spacer post support
CN204151835U (en) The vertical piece structure of connection of the basement wall and cast-in-place buttress
CN208235584U (en) Ring-like assembled overlaps piping lane
CN214784092U (en) Foundation ditch relief well enclosed construction
CN110847239A (en) Assembled large reinforced concrete prefabricated inspection well and construction method thereof
CN202925483U (en) Prefabricated assembly type reinforced concrete culvert opening
CN206840385U (en) A kind of prefab-form splicing frock of large volume tongue and groove box culvert
CN206220558U (en) Old City Wall door opening ruggedized construction
CN209011158U (en) Prefabricated piping lane section

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant