CN106640118A - Underground cavity arch crown structure, underground cavity and underground cavity construction method - Google Patents

Underground cavity arch crown structure, underground cavity and underground cavity construction method Download PDF

Info

Publication number
CN106640118A
CN106640118A CN201710134481.9A CN201710134481A CN106640118A CN 106640118 A CN106640118 A CN 106640118A CN 201710134481 A CN201710134481 A CN 201710134481A CN 106640118 A CN106640118 A CN 106640118A
Authority
CN
China
Prior art keywords
hole
construction
auxiliary stress
cavern
stress hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710134481.9A
Other languages
Chinese (zh)
Other versions
CN106640118B (en
Inventor
陈伟
潘江洋
冯树荣
郭云强
胡育林
钟辉亚
石青春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Zhongnan Engineering Corp Ltd
Original Assignee
PowerChina Zhongnan Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Zhongnan Engineering Corp Ltd filed Critical PowerChina Zhongnan Engineering Corp Ltd
Priority to CN201710134481.9A priority Critical patent/CN106640118B/en
Publication of CN106640118A publication Critical patent/CN106640118A/en
Application granted granted Critical
Publication of CN106640118B publication Critical patent/CN106640118B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses an underground cavity arch crown structure. The underground cavity arch crown structure comprises an arch crown part located at the top of a main cavity, construction transportation cavities formed by longitudinally digging rock mass at the two sides of the main cavity and auxiliary stress cavities arranged to be tightly attached to the upper surface of the arch crown in a crossing mode, and multiple auxiliary stress cavities are formed longitudinally and communicated with the construction transportation cavities; the auxiliary stress cavities are filled with reinforced concrete through pouring, and a prestress anchor cable stretching up into the rock mass is arranged on each auxiliary stress cavity. The underground cavity arch crown structure is convenient and fast to construct, supporting and reinforcing of the arch crown of the main cavity is completed before the main cavity is dug to form a steady arch crown structure, the effect of reinforcing in advance is achieved, the integrity of surrounding rock is improved, and own bearing capacity of the surrounding rock is effectively brought into play. Compared with the conventional construction technology, safety, reliability and stability of the whole cavity are remarkably improved, and the underground cavity arch crown structure is particularly suitable for a super-large-span underground cavity with complex geological conditions and extremely poor surrounding rock stability.

Description

A kind of underground cavern crown structure, underground chamber and Cavity Construction method
Technical field
The invention belongs to underground engineering, and in particular to a kind of underground cavern crown structure, underground chamber and underground chamber are applied Work method, is particularly suited for super-span underground chamber under complex geological condition.
Background technology
The section span of conventional underground chamber is usually no more than 40 meters, the reinforcing to underground cavern crown, conventional measure After for cavern excavation, then using the supporting type of some support.
The span of large section cavern often reaches 60-70 rice.Conventional supporting measure due to exist excavation slag tap the duration with In the supporting construction cycle, it is latter until supporting construction is completed that face explosion forms cavern, a period of time is needed during this, so as to make There is engineering safety hidden danger in a period of time interior non-support in cavitation ceiling arch.
Large section cavern under the complex geological condition such as poor for surrounding rock of chamber condition, usually due to surrounding rock of chamber condition Difference causes cavern's crown excavate molding, just caves in therewith after excavation, it is impossible to form conventional cavern.Can even excavate The geological conditions of molding, as the span of large section cavern is excessive, using conventional support form, also results in cavern's crown and encloses Rock is unstable.
The problems referred to above are being limited by various conditions, the super large being arranged in the poor stratum of complex geologic conditions, wall rock condition It is especially prominent in span underground chamber.
In addition, the direction vocabulary to being previously mentioned in this case is defined, in the art, technical staff generally assert longitudinal direction It is the direction along underground chamber depth;It is laterally the direction of underground chamber transverse section, perpendicular to underground chamber axis.
The content of the invention
For the problems referred to above, the present invention is intended to provide a kind of underground cavern crown structure of safety and firmness, supporting underground Cavern and Cavity Construction method.
The technical scheme of solve problem of the present invention is:A kind of underground cavern crown structure, including positioned at main Mass Near The Top of Underground Cavity Crown portion, be additionally included in the rock mass of main cavern both sides dig along longitudinal direction construction transportation hole, be close to crown portion upper surface across The auxiliary stress hole of setting, the auxiliary stress hole are provided with multiple along longitudinal direction, and connect with construction transportation hole;
Pour in the auxiliary stress hole and be filled with armored concrete, be equipped with each auxiliary stress hole and extend upwardly into rock mass Prestress anchorage cable.
In such scheme, bearing beam is formed after the pouring reinforcement concrete of auxiliary stress hole, is pulled by prestress anchorage cable, Ensure stablizing for crown portion.
Further, pour in the construction transportation hole and be filled with armored concrete, be filled with the solid of armored concrete Construction transportation hole is the bearing for aiding in stress hole;The construction transportation hole is externally provided with the anchoring piece for stretching into rock mass, to construction transportation Hole pulls.
Construction transportation hole forms stress bearing, can further increase the ability that load is born in auxiliary stress hole.Anchoring piece For anchor pole or anchor cable, construction transportation hole is formed by anchor pole or anchor cable and pulled, by increasing capacitance it is possible to increase the bearing capacity in construction transportation hole.
The arrangement in auxiliary stress hole has various, e.g., interval setting between the adjacent auxiliary stress hole.
Or, continuously arrange between the adjacent auxiliary stress hole.
Further, the transverse section in the auxiliary stress hole is arch or linear type.Preferably arch, domes are born Power is bigger.
Preferably, the prestress anchorage cable is radially arranged.
Meanwhile, the present invention also provides a kind of underground chamber, including main cavern, and the top of the main cavern is such scheme institute The crown structure stated.
Accordingly, the present invention also provides a kind of Cavity Construction method, comprises the steps:
a)Before the construction of main cavern excavation, in the rock mass that main cavern region both sides are excavated in design, along longitudinal excavation construction traffic Hole;
b)With the construction transportation hole of wherein side as starting point, the construction transportation hole of opposite side as terminal, be close to crown portion upper table Auxiliary stress hole is laterally excavated in face, and auxiliary stress hole is provided with multiple along longitudinal direction, and connects with construction transportation hole;In auxiliary stress hole Interior laying reinforcing bar or formed steel construction, and stress hole is aided in concreting filling is whole;
c)Construct upwards prestress anchorage cable from auxiliary stress hole, until deeply aiding in the rock mass above stress hole and fixed;
e)The excavation of main cavern is carried out, after excavating molding, auxiliary stress hole is directly becoming with the area segments that are connected of main Mass Near The Top of Underground Cavity A part for main cavern;Afterwards, carry out main cavern support construction.
In above-mentioned work progress, construction transportation hole adopts anchor pole or cable bolting.
Further, in step c)Afterwards, step e)Step d is additionally provided with before)Pouring reinforcement is mixed in the construction transportation hole Solidifying soil, makes the construction transportation hole of both sides form the bearing in auxiliary stress hole;Then it is externally provided with construction transportation hole and stretches into rock mass Anchoring piece, pulls to construction transportation hole.
Further, the arrangement form in stress hole is aided in determine after being considered according to cavern span, geological conditions, one Plant in specific scheme:
Step b)In interval setting between adjacent auxiliary stress hole;
Step c)In prestress anchorage cable on each auxiliary stress hole radially arrange.
In another kind of specific scheme:
Step b)In continuously arrange between adjacent auxiliary stress hole, the auxiliary stress hole of continuous arrangement using storehouse construction is jumped, finally Form entirety closely.
The present invention not only easy construction, quick, and the supporting in main cavern's crown portion is completed before main cavern excavation add Gu, firm crown structure is formed, the effect of prior reinforcing is achieved, be increased country rock globality, effectively play country rock itself Bearing capacity.Compared to conventional construction technology, the overall safety in cavern, reliability and stability are significantly improved, it is especially suitable In complex geologic conditions, the super-span underground chamber of surrounding rock stability extreme difference.
Description of the drawings
The invention will be further described below in conjunction with the accompanying drawings.
Fig. 1 is 1 underground chamber drawing in side sectional elevation of embodiment.
Fig. 2 is 1 underground chamber profilograph of embodiment.
Fig. 3 is 2 underground chamber drawing in side sectional elevation of embodiment.
Fig. 4 is 2 underground chamber profilograph of embodiment.
In figure:1-auxiliary stress hole, 2-construction transportation hole, 3-prestress anchorage cable, 5-main cavern, 8- anchor poles.
Specific embodiment
Embodiment 1
As shown in Fig. 1~2, a kind of underground cavern crown structure, including the crown portion at the top of main cavern 5,5 liang of main cavern The construction transportation hole 2 dug along longitudinal direction in the rock mass of side, it is close to crown portion upper surface across the auxiliary stress hole 1 for arranging.
The auxiliary stress hole 1 is longitudinally spaced to be provided with multiple, and connects with construction transportation hole 2.
Pour in the auxiliary stress hole 1 and be filled with armored concrete, each aids in being equipped with stress hole 1 and is in upwards The radial prestress anchorage cable 3 for stretching into rock mass.
Pour in the construction transportation hole 2 and be filled with armored concrete, be filled with the solid construction transportation of armored concrete Bearing of the hole 2 for auxiliary stress hole 1.The construction transportation hole 2 is externally provided with the anchor pole 8 for stretching into rock mass, and construction transportation hole 2 is led Draw.
The transverse section in the auxiliary stress hole 1 is arch.
The present embodiment also provides a kind of underground chamber, including main cavern 5, and the top of the main cavern 5 is tied for above-mentioned crown Structure.
At the same time, the present embodiment also provides a kind of Cavity Construction method, comprises the steps:
a)Before 5 excavation construction of main cavern, in the rock mass that main 5 region both sides of cavern are excavated in design, hand over along longitudinal excavation construction Logical hole 2.Construction transportation hole 2 is externally provided with the anchor pole 8 for stretching into rock mass, and construction transportation hole 2 is pulled.The length in construction transportation hole 2 is big In or be equal to main cavern's length.
b)With the construction transportation hole of wherein side 2 as starting point, the construction transportation hole 2 of opposite side as terminal, be close to crown Portion's upper surface laterally excavates auxiliary stress hole 1, and auxiliary stress hole 1 is longitudinally spaced to be provided with multiple, and connects with construction transportation hole 2 It is logical.Reinforcing bar or formed steel construction are laid in auxiliary stress hole 1, and whole auxiliary stress hole 1 are filled with concreting.
c)Radially construct upwards prestress anchorage cable 3 from auxiliary stress hole 1, until deeply aiding in above stress hole 1 It is in rock mass and fixed.
d)The pouring reinforcement concrete in the construction transportation hole 2, makes the construction transportation hole 2 of both sides form auxiliary stress hole 1 Bearing.
e)Carry out the excavation of main cavern 5, after excavating molding, aid in stress hole 1 with the top of main cavern 5 to be connected area segments straight A part for cavern 5 based on being connected into.Afterwards, carry out 5 supporting construction of main cavern.
In above-mentioned steps method, the cross dimensions in stress hole 1 is aided according to its 5 span of load and main cavern born etc. Condition is calculated and construction transportation needs comprehensive determination.
Embodiment 2
As shown in figs. 34, repeat embodiment 1, except that:For the super large of complex geologic conditions, wall rock condition extreme difference breaks Mian Zhu caverns, are continuously arranged between adjacent auxiliary stress hole 1.
Exist in its construction method following different:
Step b)In continuously arrange between adjacent auxiliary stress hole 1, the auxiliary stress hole 1 of continuous arrangement using storehouse construction is jumped, most Entirety closely is formed afterwards.

Claims (11)

1. a kind of underground cavern crown structure, including positioned at main cavern(5)The crown portion at top, it is characterised in that:It is additionally included in Main cavern(5)The construction transportation hole dug along longitudinal direction in the rock mass of both sides(2), be close to crown portion upper surface across arrange auxiliary Stress hole(1), the auxiliary stress hole(1)Along longitudinal direction is provided with multiple, and with construction transportation hole(2)Connection;
The auxiliary stress hole(1)Inside pour and be filled with armored concrete, each auxiliary stress hole(1)On be equipped with and stretch upwards Enter the prestress anchorage cable of rock mass(3).
2. underground cavern crown structure according to claim 1, it is characterised in that:The construction transportation hole(2)Inside pour Armored concrete is filled with, the solid construction transportation hole of armored concrete is filled with(2)To aid in stress hole(1)Bearing;Institute State construction transportation hole(2)The anchoring piece for stretching into rock mass is externally provided with, to construction transportation hole(2)Drawing.
3. underground cavern crown structure according to claim 1, it is characterised in that:The adjacent auxiliary stress hole(1)It Between interval setting.
4. underground cavern crown structure according to claim 1, it is characterised in that:The adjacent auxiliary stress hole(1)It Between continuously arrange.
5. underground cavern crown structure according to claim 1, it is characterised in that:The auxiliary stress hole(1)It is cross-section Face is arch.
6. underground cavern crown structure according to claim 1, it is characterised in that:The prestress anchorage cable(3)It is in spoke Penetrate shape arrangement.
7. a kind of underground chamber, including main cavern(5), it is characterised in that:The main cavern(5)Top be the claims Crown structure described in 1~6 any one.
8. a kind of Cavity Construction method, it is characterised in that comprise the steps:
a)In main cavern(5)Before excavation construction, main cavern is excavated in design(5)In the rock mass of region both sides, along longitudinal direction, excavation is applied Work access tunnel(2);
b)With the construction transportation hole of wherein side(2)For starting point, the construction transportation hole of opposite side(2)For terminal, it is close to crown Portion's upper surface laterally excavates auxiliary stress hole(1), auxiliary stress hole(1)Along longitudinal direction is provided with multiple, and with construction transportation hole(2)Even It is logical;In auxiliary stress hole(1)Interior laying reinforcing bar or formed steel construction, and stress hole is aided in concreting filling is whole(1);
c)From auxiliary stress hole(1)Construct upwards prestress anchorage cable(3), until deeply aiding in stress hole(1)In the rock mass of top And it is fixed;
e)Carry out main cavern(5)Excavation, after excavating molding, aid in stress hole(1)With main cavern(5)The linking area segments at top It is directly becoming main cavern(5)A part;Afterwards, carry out main cavern(5)Supporting construction.
9. Cavity Construction method according to claim 8, it is characterised in that:In step c)Afterwards, step e)Before It is additionally provided with step d)In construction transportation hole(2)Interior pouring reinforcement concrete, makes the construction transportation hole of both sides(2)Form auxiliary stress Hole(1)Bearing;Then in construction transportation hole(2)The anchoring piece for stretching into rock mass is externally provided with, to construction transportation hole(2)Drawing.
10. Cavity Construction method according to claim 8, it is characterised in that:Step b)In adjacent auxiliary stress hole (1)Between interval setting;
Step c)In each auxiliary stress hole(1)On prestress anchorage cable(3)Radially arrange.
11. underground cavern crown structures according to claim 8, it is characterised in that:Step b)In adjacent auxiliary stress hole (1)Between continuously arrange, the auxiliary stress hole of continuous arrangement(1)Using storehouse construction is jumped, entirety closely is eventually formed.
CN201710134481.9A 2017-03-08 2017-03-08 A kind of underground cavern crown structure, underground chamber and Cavity Construction method Active CN106640118B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710134481.9A CN106640118B (en) 2017-03-08 2017-03-08 A kind of underground cavern crown structure, underground chamber and Cavity Construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710134481.9A CN106640118B (en) 2017-03-08 2017-03-08 A kind of underground cavern crown structure, underground chamber and Cavity Construction method

Publications (2)

Publication Number Publication Date
CN106640118A true CN106640118A (en) 2017-05-10
CN106640118B CN106640118B (en) 2019-02-19

Family

ID=58848186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710134481.9A Active CN106640118B (en) 2017-03-08 2017-03-08 A kind of underground cavern crown structure, underground chamber and Cavity Construction method

Country Status (1)

Country Link
CN (1) CN106640118B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107355233A (en) * 2017-08-30 2017-11-17 中国电建集团中南勘测设计研究院有限公司 A kind of underground chamber and Cavity Construction method
CN109404019A (en) * 2018-12-25 2019-03-01 中国电建集团成都勘测设计研究院有限公司 Surrounding rock of chamber pays protecting system and cavern's structure in advance

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11193689A (en) * 1998-01-05 1999-07-21 Shimizu Corp Underground cavity construction method and underground cavity construction thereby
JP2000120398A (en) * 1998-10-16 2000-04-25 Daiho Constr Co Ltd Construction method for tunnel having arc-shaped cross section and underground excavator
CN102226403A (en) * 2011-03-30 2011-10-26 中铁一局集团有限公司 Construction method of large-span subway station main body by using arched cover method and station main body structure
CN102536273A (en) * 2012-03-30 2012-07-04 中建市政建设有限公司 One-step forming construction method for 26m large-span space
CN102654055A (en) * 2012-05-21 2012-09-05 乐贵平 Construction method for compound construction of large-scale underground space structure by holes, groove and piles
CN103306682A (en) * 2013-06-26 2013-09-18 中国水电顾问集团中南勘测设计研究院 Long-span and high-side-wall underground space building and excavation support method thereof
CN103306248A (en) * 2013-07-01 2013-09-18 中国水电顾问集团中南勘测设计研究院 High dam spillway foundation drainage system and excavation method
CN203559432U (en) * 2013-10-25 2014-04-23 中国水电顾问集团中南勘测设计研究院有限公司 Underground powerhouse vault
CN204646268U (en) * 2015-05-26 2015-09-16 中国电建集团中南勘测设计研究院有限公司 A kind of underground construction steel arch-shelf composite supporting construction
CN206722841U (en) * 2017-03-08 2017-12-08 中国电建集团中南勘测设计研究院有限公司 A kind of underground cavern crown structure and its underground chamber

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11193689A (en) * 1998-01-05 1999-07-21 Shimizu Corp Underground cavity construction method and underground cavity construction thereby
JP2000120398A (en) * 1998-10-16 2000-04-25 Daiho Constr Co Ltd Construction method for tunnel having arc-shaped cross section and underground excavator
CN102226403A (en) * 2011-03-30 2011-10-26 中铁一局集团有限公司 Construction method of large-span subway station main body by using arched cover method and station main body structure
CN102536273A (en) * 2012-03-30 2012-07-04 中建市政建设有限公司 One-step forming construction method for 26m large-span space
CN102654055A (en) * 2012-05-21 2012-09-05 乐贵平 Construction method for compound construction of large-scale underground space structure by holes, groove and piles
CN103306682A (en) * 2013-06-26 2013-09-18 中国水电顾问集团中南勘测设计研究院 Long-span and high-side-wall underground space building and excavation support method thereof
CN103306248A (en) * 2013-07-01 2013-09-18 中国水电顾问集团中南勘测设计研究院 High dam spillway foundation drainage system and excavation method
CN203559432U (en) * 2013-10-25 2014-04-23 中国水电顾问集团中南勘测设计研究院有限公司 Underground powerhouse vault
CN204646268U (en) * 2015-05-26 2015-09-16 中国电建集团中南勘测设计研究院有限公司 A kind of underground construction steel arch-shelf composite supporting construction
CN206722841U (en) * 2017-03-08 2017-12-08 中国电建集团中南勘测设计研究院有限公司 A kind of underground cavern crown structure and its underground chamber

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107355233A (en) * 2017-08-30 2017-11-17 中国电建集团中南勘测设计研究院有限公司 A kind of underground chamber and Cavity Construction method
CN107355233B (en) * 2017-08-30 2019-03-22 中国电建集团中南勘测设计研究院有限公司 A kind of underground chamber and Cavity Construction method
CN109404019A (en) * 2018-12-25 2019-03-01 中国电建集团成都勘测设计研究院有限公司 Surrounding rock of chamber pays protecting system and cavern's structure in advance
CN109404019B (en) * 2018-12-25 2024-02-27 中国电建集团成都勘测设计研究院有限公司 Cave surrounding rock pre-supporting system and cave structure

Also Published As

Publication number Publication date
CN106640118B (en) 2019-02-19

Similar Documents

Publication Publication Date Title
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN101775988B (en) Construction method for inclined shaft to main tunnel of weak surrounding rock
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN107725068A (en) A kind of assembled supporting construction and its construction method based on outside steel arch-shelf and inner side concrete slab
CN104533446A (en) Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel
CN103775092A (en) Tunnel shallow-buried excavation reserved core soil improved CRD construction method
CN103628885A (en) Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN110629671A (en) Suspension bridge anchorage and construction method thereof
CN107060774A (en) A kind of anti-tunnel portal wall damage device and construction method
CN203782684U (en) Anti-skid pile provided with crossbeam
CN103362513A (en) Transformation and construction method for existing cavity in underground excavation region
CN109853399B (en) Large-section inclined tunnel type arch support structure for arch bridge and construction method thereof
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN205895242U (en) Low -angle crossing tunnel structure
CN206530341U (en) A kind of underground cavern crown structure and its underground chamber
CN109973122A (en) A kind of tunnel reinforcement control method of wall rock loosening or soft rock large deformation
CN105156114A (en) Enlarging repair and reinforcement method of roadways at crossing
CN103939115A (en) Semi-subsurface excavation method construction shed tunnel method and structure
CN107191206B (en) A kind of six step construction method of Shallow-buried Large-span Tunnel Unit two
CN106640117B (en) A kind of underground cavern crown structure, underground chamber and Cavity Construction method
CN106640118A (en) Underground cavity arch crown structure, underground cavity and underground cavity construction method
CN204311456U (en) Foundation ditch strengthening structure
CN207484290U (en) The hollow clump of piles anchorage of super-large diameter

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant