CN106640027B - The construction method of fracture-pore reservoir underground river type karst Reservoir Body space structure well pattern - Google Patents

The construction method of fracture-pore reservoir underground river type karst Reservoir Body space structure well pattern Download PDF

Info

Publication number
CN106640027B
CN106640027B CN201610861752.6A CN201610861752A CN106640027B CN 106640027 B CN106640027 B CN 106640027B CN 201610861752 A CN201610861752 A CN 201610861752A CN 106640027 B CN106640027 B CN 106640027B
Authority
CN
China
Prior art keywords
well
reservoir body
reservoir
construction method
situation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610861752.6A
Other languages
Chinese (zh)
Other versions
CN106640027A (en
Inventor
李阳
康志江
郑松青
薛兆杰
刘中春
张允�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
Sinopec Exploration and Production Research Institute
Original Assignee
China Petroleum and Chemical Corp
Sinopec Exploration and Production Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Chemical Corp, Sinopec Exploration and Production Research Institute filed Critical China Petroleum and Chemical Corp
Priority to CN201610861752.6A priority Critical patent/CN106640027B/en
Publication of CN106640027A publication Critical patent/CN106640027A/en
Application granted granted Critical
Publication of CN106640027B publication Critical patent/CN106640027B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/30Specific pattern of wells, e.g. optimising the spacing of wells

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of construction methods of fracture-pore reservoir underground river karst Reservoir Body space structure well pattern.This method is first according to underground river type karst Reservoir Body type, development characteristics and connection model, determine well net deployment principle, to ensure that water drive direction is vertical with advantage communication direction in plane, vertical upper realization seperated layer water injection, then Reservoir Body type, Reservoir Body spatial position and interwell communication situation are met according to the production status of well, brill to determine injection-production well, to ensure that low note height is adopted, it adopts in seam note hole, new well is finally disposed according to remaining oil and well control situation, to realize producing well, water injection well, Reservoir Body distributing rationally on space structure.

Description

The construction method of fracture-pore reservoir underground river type karst Reservoir Body space structure well pattern
Technical field
The present invention relates to oil reservoir development technical field more particularly to a kind of fracture-pore reservoir underground river type karst Reservoir Body spaces The construction method of structure well pattern.
Background technique
Fracture-pore reservoir is a kind of Carbonate Reservoir for acting on and being formed through more phase tectonic movements and karst superimposed reformation. In general, the difference of fracture-pore reservoir and sandrock-type oil reservoir is concentrated mainly on the following aspects:
One, the Reservoir Body space type of fracture-pore reservoir is more, and different scale is big, and wherein corrosion hole is main Reservoir Body Space, crack are main flow channels, and the contribution that basement rock seeps storage is small;The Reservoir Body space of sandrock-type oil reservoir be hole and Pore throat, different scale are small.
Two, the Reservoir Body space of fracture-pore reservoir is in a discrete distribution, and heterogeneity is strong;The Reservoir Body space of sandrock-type oil reservoir In continuously distributed, heterogeneity is weaker.
Three, fracture-pore reservoir is " block " shape oil reservoir, and sandstone oil reservoir is " layer " shape oil reservoir.
It is very big that these above-mentioned differences cause the development technique of fracture-pore reservoir and the development technique of sandrock-type oil reservoir to exist Difference, therefore the plane well pattern construction method of existing hierarchical-development is not suitable for fracture-pore reservoir.
In addition, the well pattern research for fracture-pore reservoir, Li Xinhua, flourish marshal etc. propose " irregular structure well pattern " Concept.Wherein, the building of well pattern needs to comprehensively consider the Reservoir Body class where inter well connectivity, longitudinal fine and close interval, injection-production well Factor (the Carbonate Rocks In Tahe Oilfield fracture hole type such as Rong Yuanshuai, Li Xinhua, Liu Xueli at the height position of type, injection-production well etc. More well fracture-cavity units waterflooding extraction mode [J] the oil-gas geologies of oil reservoir and recovery ratio, 2013,20 (2): 58-61;Li Xinhua, Rong Yuan Handsome fracture-karst caved carbonate reservoir of Tahe oil field Reasonable Injection adopts well net optimization research [J] drilling technique, 2013,36 (5): 47- 51).Based on interwell communication, using the well to communicate with each other as an injection-production well group, to longitudinal well group for developing fine and close interval Implement subsection water injection, the setting of injection-production well follow " it is low note height adopt, stitch infuse hole adopt " principle.
However, the above method does not account for the factor of geologic setting.Three kinds of geologic settings of fracture-pore reservoir major developmental: table Layer weathering crust type karst, underground river type karst and disconnected solution type karst.Under different geologic settings, the development models of fracture hole are not Together, the distribution characteristics in Reservoir Body space and connection model are also different, therefore the building mode of well pattern is also different.However, existing at present Some well network design methods, the connection situation being based primarily upon between well, water drive direction is consistent with advantage communication direction, although water filling is shown in Effect is fast, but is easy to cause water breakthrough, and it to be not optimal technical solution that there are certain hidden danger.
Summary of the invention
In view of the above technical problems, the invention proposes a kind of new to be suitable for fracture-pore reservoir underground river type karst Reservoir Body Space structure well construction method.Method includes the following steps:
S10 determines well net deployment principle according to underground river type karst Reservoir Body development characteristics and connection model;
S20 determines the production status of well, bores the Reservoir Body type met and Reservoir Body spatial position and interwell communication shape Condition;
S30 according to the production status of well, bores the Reservoir Body type met and Reservoir Body spatial position and interwell communication situation To determine injector-producer pair relationship;
S40 disposes new water injection well according to well control situation and remaining oil distribution situation, thus construct producing well, water injection well, The space structure well pattern that Reservoir Body is distributed rationally on space structure.
According to an embodiment of the invention, the well net deployment principle mainly includes plane top set in above-mentioned steps S10 River and/or the water filling of trunk river edge, trunk river are recovered the oil.
Further, for vertical upper development multilayer Reservoir Body the case where, the well net deployment principle can also include vertical Upward multilayer braiding water filling.
According to an embodiment of the invention, in above-mentioned steps S20:
The production status of the well includes production capacity situation and water status;
It includes slit formation Reservoir Body, corrosion hole type Reservoir Body and Caves Reservoir Body that the brill, which meets Reservoir Body type,;
The Reservoir Body spatial position refers to the depth for boring the Reservoir Body pay interval met.
In addition, according to an embodiment of the invention, in above-mentioned steps S20, according to injection test data, tracer test data And/or geologic setting data determines the interwell communication situation.Wherein it is preferred to:
If there is injection test data determines the interwell communication situation with injection test data for main foundation;
If there is no injection test data, with tracer test data for main foundation, the interwell communication situation is determined;
If, with geologic setting data for main foundation, determining the well without injection test data and tracer test data Between be connected to situation.
Further, the geologic setting data is primarily referred to as underground river karst connection model.
According to an embodiment of the invention, determining injector-producer pair relationship in above-mentioned steps S30 comprising selection, which bores to meet, to be split Seam Reservoir Body or Reservoir Body are located at the inefficient well of lower curtate position or high water-cut well is converted production well, and selection can connect with converted production well Well that is logical, boring chance Caves Reservoir Body is producing well.
According to an embodiment of the invention, in above-mentioned steps S40, the region low to well control degree, potentiality of remaining oil is big, New water injection well is disposed in its lower curtate position.
According to an embodiment of the invention, other than disposing new water injection well, can also be disposed in above-mentioned steps S40 New producing well.
Compared with prior art, one or more embodiments of the invention can have following advantage:
The present invention determines well net deployment principle according to the development characteristics of underground river type karst Reservoir Body and connection model first, Then the Reservoir Body type and Reservoir Body spatial position and interwell communication situation met according to the production status of well, brill are infused to determine Well is adopted, so that it is guaranteed that water injection well, producing well, Reservoir Body realize the configuration of optimization on space structure, effectively promotion note, which is adopted, is set The validity and water-flooding performance and waterflooding development effect of meter.
Other features and advantages of the present invention will be illustrated in the following description, also, partly becomes from specification It obtains it is clear that understand through the implementation of the invention.The objectives and other advantages of the invention can be by specification, right Specifically noted structure is achieved and obtained in claim and attached drawing.
Detailed description of the invention
Attached drawing is used to provide further understanding of the present invention, and constitutes part of specification, with reality of the invention It applies example and is used together to explain the present invention, be not construed as limiting the invention.In the accompanying drawings:
Fig. 1 is the flow chart that the method for space structure well pattern is constructed in the embodiment of the present invention;
Fig. 2 is the schematic diagram of the existing basic well pattern in target area in the embodiment of the present invention;
Fig. 3 is showing for the space structure well pattern distributed rationally constructed by target area of the method according to the invention to Fig. 2 It is intended to.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with drawings and examples to the present invention It is described in further detail.
Fig. 1 is the flow chart that the method for space structure well pattern is constructed in the embodiment of the present invention.In detail below with reference to Fig. 1 Illustrate each step and its principle.
Step S10 determines well net deployment principle according to underground river type karst Reservoir Body development characteristics and connection model.
It is advantage communication direction along river direction along river spread in the type karst Reservoir Body plane of underground river, and vertical river Direction is secondary communication direction;Vertical upper development single-layer or multi-layer Reservoir Body.In this regard, the present invention proposes a kind of new well net deployment Principle: plane top set river and trunk river edge note, trunk river are adopted, and water drive direction is vertical with advantage communication direction, from And guarantee employing for different quality Reservoir Body in plane;And if developing multilayer river on longitudinal direction, implement seperated layer water injection, from And guarantee employing for different intervals on vertical.
Step S20 determines the production status of well, bores Reservoir Body type, Reservoir Body spatial position and the interwell communication shape met Condition.
In this step: the production status of well generally includes production capacity situation and water status;Reservoir Body type mainly includes Slit formation Reservoir Body, corrosion hole type Reservoir Body and Caves Reservoir Body;It is raw that the spatial position of Reservoir Body refers to that brill meets Reservoir Body The depth of payzone section;And the determination of interwell communication situation is mainly according to one of following three kinds of data or a variety of: injection test data, Tracer test data and geologic setting data.Specifically, if there is injection test data, then with injection test data for main judgement It is main judgment basis with tracer test data if there is no injection test data according to interwell communication situation is determined Interwell communication situation is determined, if sentenced without injection test data and tracer test data with geologic setting data to be main Disconnected foundation determines interwell communication situation.Herein, geologic setting data is primarily referred to as underground river karst connection model.
Step S30 according to the production status of well and bores Reservoir Body type, Reservoir Body spatial position and the interwell communication met Situation determines injector-producer pair relationship.
The basic well pattern of fracture-pore reservoir natural energy development phase is the irregular well pattern for the purpose of controlling Reservoir Body, And the well network design of waterflood stage must carry out on the basis of basic well pattern, usually based on oil well to injection, to bore water Supplemented by well.Specifically, it is necessary to connect according between the production status of well, the Reservoir Body type for boring chance, Reservoir Body spatial position and well Logical situation determines metaideophone oil well.In this embodiment, it is preferred that the principle based on " seam note hole is adopted, low note height is adopted ", selection storage Collective is located at lower curtate position or bores the inefficient well for meeting crack Reservoir Body or high water-cut well as converted production well, and selects Reservoir Body opposite It is higher and can be connected to converted production well, bore meet Caves Reservoir Body well as producing well, form injector-producer pair each other.
Step S40 disposes new water injection well according to well control situation and remaining oil distribution situation.To construct producing well, note The space structure well pattern that well, Reservoir Body are distributed rationally on space structure.
It, in this step, can also be according to well control situation in addition to the water injection well formed in step s 30 by oil well to injection New water injection well is drilled with remaining oil distribution situation.Region that is low especially for well control degree and having remaining oil distribution, at it New well water injection well is bored in lower curtate position, adopts to reach low note height, promotes the purpose of water-flooding performance and waterflooding development effect.
Certainly, it is also not excluded for a possibility that further disposing new producing well as needed in this step.
It should be noted here that about " lower curtate position " used herein, " inefficient well " and " high water-cut well " etc. Concept is usually the range met certain condition determined by practical condition.Specifically, " lower curtate position " be relative to For " high-order bit ", such as the case where B is adopted is infused for A, A well will be in lower position (abbreviation lower curtate position) relative to B well, with Meet the low high principle adopted of note.For " inefficient well " and " high water-cut well " is generally be directed to the economic validity of well.In general, " inefficient well " and " high water-cut well " refers to that the oily amount of adopting is very low or even cannot collect the well of oil.Therefore, these above-mentioned concepts exist It is not specifically limited herein.
Specific embodiment
Below by taking oil field at home block as an example, fracture-pore reservoir underground river karst Reservoir Body space structure well is further described The building process of net.
First, in accordance with abovementioned steps S10, well net deployment principle is determined according to geologic setting.Due to underground river karst well net deployment Principle is that branch channel or trunk river edge fill the water, and trunk river recovers the oil, therefore selects branch river to target area shown in Fig. 2 The well metaideophone in road or trunk river edge.
Then it according to abovementioned steps S20 and S30, determines the production status of well, bore the type and space bit of the Reservoir Body met It sets and interwell communication situation, and thereby determines that injection-production well.Currently, having 10 mouthfuls of wells, the life of each well in target area shown in Fig. 2 Occurrence condition bores the Reservoir Body type met and oil well to injection determining therefrom and to be formed by new injection-production relation as follows Shown in table table 1.
1 hole condition of table and metaideophone situation list
The position for disposing new water injection well is finally determined according to well control situation and remaining oil distribution situation.As shown in figure 3, In target area west side, although river where W5, W6 well is not trunk river, their production status are good, and without water filling Well forms injector-producer pair therewith, therefore can dispose new water injection well I1 between this two mouthfuls of wells, is respectively formed it with W5, W6 New injector-producer pair.
Experienced above-mentioned oil well to injection, new well deployment process after, be formed the present invention to be constructed producing well, The space structure well pattern that water injection well, Reservoir Body are distributed rationally on space structure, injection-production relation therein are detailed in Fig. 3 Carefully show.
The above, specific implementation case only of the invention, scope of protection of the present invention is not limited thereto, any ripe Those skilled in the art are known in technical specification of the present invention, modifications of the present invention or replacement all should be in the present invention Protection scope within.

Claims (8)

1. a kind of construction method of fracture-pore reservoir underground river type karst Reservoir Body space structure well pattern, comprising the following steps:
S10 determines well net deployment principle according to underground river type karst Reservoir Body development characteristics and connection model, including plane Top set river and/or the water filling of trunk river edge, trunk river are recovered the oil;
S20 determines the production status of well, bores the Reservoir Body type met and Reservoir Body spatial position and interwell communication situation;
S30 according to the production status of well, bores the Reservoir Body type met and Reservoir Body spatial position and interwell communication situation come really Determine injector-producer pair relationship;
S40 disposes new water injection well according to well control situation and remaining oil distribution situation, to construct producing well, water injection well, preserve The space structure well pattern that body is distributed rationally on space structure;
Wherein, in step s 30, it determines injector-producer pair relationship, selects Reservoir Body to be located at the inefficient well of lower curtate position or bore and meet crack The inefficient well of Reservoir Body is converted production well, and selecting to be connected to converted production well, bore the well of chance Caves Reservoir Body is producing well.
2. construction method according to claim 1, it is characterised in that:
The case where for vertical upper development multilayer Reservoir Body, the well net deployment principle further include longitudinal upper multilayer braiding note Water.
3. construction method according to claim 1, which is characterized in that in step S20:
The production status of the well includes production capacity situation and water status;
The Reservoir Body type met of boring includes slit formation Reservoir Body, corrosion hole type Reservoir Body and Caves Reservoir Body;
The Reservoir Body spatial position refers to the depth for boring the Reservoir Body pay interval met.
4. construction method according to claim 1, it is characterised in that:
In step S20, is determined according to injection test data, tracer test data and/or geologic setting data and connected between the well Logical situation.
5. construction method according to claim 4, it is characterised in that:
If there is injection test data determines the interwell communication situation with injection test data for main foundation;
If there is no injection test data, with tracer test data for main foundation, the interwell communication situation is determined;
If, with geologic setting data for main foundation, determining and connecting between the well without injection test data and tracer test data Logical situation.
6. construction method according to claim 5, it is characterised in that:
The geologic setting data refers to underground river karst connection model.
7. construction method as claimed in any of claims 1 to 6, it is characterised in that:
In step s 40, new water injection well is disposed in its lower curtate position in the region low to well control degree, potentiality of remaining oil is big.
8. construction method according to claim 1, it is characterised in that:
In step s 40, other than disposing new water injection well, new producing well is also disposed.
CN201610861752.6A 2016-09-28 2016-09-28 The construction method of fracture-pore reservoir underground river type karst Reservoir Body space structure well pattern Active CN106640027B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610861752.6A CN106640027B (en) 2016-09-28 2016-09-28 The construction method of fracture-pore reservoir underground river type karst Reservoir Body space structure well pattern

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610861752.6A CN106640027B (en) 2016-09-28 2016-09-28 The construction method of fracture-pore reservoir underground river type karst Reservoir Body space structure well pattern

Publications (2)

Publication Number Publication Date
CN106640027A CN106640027A (en) 2017-05-10
CN106640027B true CN106640027B (en) 2019-05-07

Family

ID=58854712

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610861752.6A Active CN106640027B (en) 2016-09-28 2016-09-28 The construction method of fracture-pore reservoir underground river type karst Reservoir Body space structure well pattern

Country Status (1)

Country Link
CN (1) CN106640027B (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107083939A (en) * 2017-06-26 2017-08-22 中国石油化工股份有限公司 Three-dimensional development method for the disconnected solution oil reservoir of carbonate rock
CN107191175A (en) * 2017-07-11 2017-09-22 中国石油化工股份有限公司 Flooding pattern construction method for the disconnected solution oil reservoir of carbonate rock
CN107178357B (en) * 2017-07-24 2019-10-18 中国石油化工股份有限公司 Fracture and vug carbonate reservoir water and oil control method
CN107272065A (en) * 2017-08-04 2017-10-20 中国石油化工股份有限公司 The disconnected solution profile testing method of carbonate rock
CN107387042B (en) * 2017-09-14 2019-09-17 中国石油化工股份有限公司 Carbonate Reservoir two adopts the method for the middle and later periods improving recovery ratio
CN107701167B (en) * 2017-11-28 2019-06-14 中国海洋石油集团有限公司 Dispositions method based on equilibrium displacement offshore oilfield well pattern
CN110273672B (en) * 2018-03-14 2022-05-03 中国石油化工股份有限公司 Fracture-cavity type oil reservoir space structure well pattern design method based on variation coefficient
CN110273673B (en) * 2018-03-14 2022-03-01 中国石油化工股份有限公司 Injection-production well pattern optimization design method for fracture-cavity type oil reservoir space structure
CN110761754A (en) * 2018-07-26 2020-02-07 中国石油天然气股份有限公司 Water injection method for fracture-cave type carbonate reservoir well group unit
CN110905484B (en) * 2018-09-14 2023-04-07 中国石油化工股份有限公司 Method for calculating communication degree between wells of fracture-cave type carbonate reservoir
CN111663926B (en) * 2019-03-07 2022-06-17 中国石油化工股份有限公司 Design method for fracture-cavity carbonate reservoir targeted water flooding
CN112483064B (en) * 2019-09-12 2023-04-07 中国石油天然气股份有限公司 Method, device and equipment for determining well arrangement mode of condensate gas reservoir and storage medium
CN112901117A (en) * 2019-12-03 2021-06-04 中国石油化工股份有限公司 Deployment method, device and medium for fracture-cavity type oil reservoir injection and production well
CN113313610B (en) * 2020-02-26 2024-02-13 中国石油化工股份有限公司 Method for adjusting flow passage of water injection well of broken solution oil reservoir
CN113309500B (en) * 2020-02-26 2022-10-04 中国石油化工股份有限公司 Tahe carbonate reservoir water injection well group flow channel adjusting method
CN113309485B (en) * 2020-02-26 2022-08-26 中国石油化工股份有限公司 Adjustment method for flow channel of water injection well of underground river karst reservoir
CN113605875B (en) * 2021-08-31 2022-09-09 中国石油大学(北京) Well pattern construction method, device and medium for fracture-cavity oil reservoir

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BRPI0919207B1 (en) * 2008-09-19 2020-08-18 Chevron U.S.A. I.N.C computer implemented method and system for use in modeling a geomechanical reservoir system, and computer implemented method for use in modeling a fracture
CN103670350B (en) * 2013-12-13 2015-12-02 中国石油化工股份有限公司石油勘探开发研究院 A kind of variable intensity water injection exploitation method for carbonate fracture-cavity oil reservoir
CN203685173U (en) * 2014-01-17 2014-07-02 中国石油化工股份有限公司石油勘探开发研究院 Seam cave type carbonate reservoir three-dimensional macro simulation and physical simulation experiment device
CN104747180B (en) * 2014-02-26 2016-09-14 中国石油化工股份有限公司 A kind of fracture-pore reservoir for waterflooding extraction analyzes method and application thereof
CN104153766B (en) * 2014-08-06 2017-02-15 西南石油大学 Manufacturing and application method of rock seam hole type oil deposit tracer-agent-injection injection-production model
CN104632205B (en) * 2015-01-23 2021-10-12 江杰 Fracture-cavity carbonate reservoir storage type distinguishing method
CN104790926B (en) * 2015-03-20 2017-12-26 中国石油大学(北京) A kind of fracture-pore reservoir waterflooding development effect evaluation method
CN105719097A (en) * 2016-01-27 2016-06-29 中国石油化工股份有限公司 Dynamic analysis and waterflooding management system of fractured-vuggy type reservoir

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
塔河油田缝洞型碳酸盐岩油藏合理注采井网优化研究;李新华等;《钻采工艺》;20130930;第36卷(第5期);47-50

Also Published As

Publication number Publication date
CN106640027A (en) 2017-05-10

Similar Documents

Publication Publication Date Title
CN106640027B (en) The construction method of fracture-pore reservoir underground river type karst Reservoir Body space structure well pattern
CN104141481B (en) A kind of ultra-low penetration compact oil reservoir horizontal well well-arranging procedure
Jinhu et al. Discussion on effective development techniques for continental tight oil in China
CN102146788A (en) Method for enhancing recovery ratio through three-dimensional streamline regulation of water drive reservoir
CN101818620B (en) Mining method for maximum reservoir contact well
CN103590799B (en) A kind of Sandstone Gas Reservoir horizontal well three-dimensional fracturing design method
CN105822269B (en) Remaining oil distribution pattern and modification scenario method after stratified reservoir binary is driven
CN104278980A (en) Method for optimizing tight oil horizontal well crack network parameters through transformation volume
CN106979001A (en) Thick-layer glutenite horizontal well solid seam net fracturing optimizing method
CN106050234A (en) Construction technique for protecting underground water in coal mining process
CN105822284B (en) Triangle horizontal well patterns well-arranging procedure
CN107191175A (en) Flooding pattern construction method for the disconnected solution oil reservoir of carbonate rock
CN104033137B (en) Oilfield sewage is utilized to improve fault block oil reservoir recovery ratio method
CN110306965A (en) A kind of method for increasing for coal bed gas low yield wellblock
CN201763308U (en) Fishbone well type structure
CN107387042B (en) Carbonate Reservoir two adopts the method for the middle and later periods improving recovery ratio
CN204252974U (en) A kind of horizontal well well structure for the block fractured reservoir exploitation of deep layer
CN108756745A (en) Platform cluster well boring method
CN103628848B (en) Multidirectional interlayer displacement in flooding oil production method and system
CN104533371A (en) Asymmetrical three-dimensional fracturing method for horizontal well
CN209742871U (en) Coal-based gas multilayer co-production well type structure
CN102913203B (en) Method for developing low-permeability gas reservoir
CN112282725B (en) Staggered seam-laying design method for horizontal well
CN205936553U (en) Raising output is transformed and novel coal seam gas well of formation to old well
CN110273672A (en) A kind of fracture-pore reservoir space structure well network design method based on the coefficient of variation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant