CN106639207A - 一种基于bim的复杂共享空间装配化建筑装饰施工方法 - Google Patents
一种基于bim的复杂共享空间装配化建筑装饰施工方法 Download PDFInfo
- Publication number
- CN106639207A CN106639207A CN201610935522.XA CN201610935522A CN106639207A CN 106639207 A CN106639207 A CN 106639207A CN 201610935522 A CN201610935522 A CN 201610935522A CN 106639207 A CN106639207 A CN 106639207A
- Authority
- CN
- China
- Prior art keywords
- model
- decoration
- method based
- construction method
- bim
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Instructional Devices (AREA)
Abstract
本发明提供了一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其包括以下步骤:(1)对施工现场进行三维扫描,采集施工现场的三维数据;(2)根据三维数据得到三维模型;(3)根据图纸建立装饰模型;(4)将装饰模型匹配到三维模型中进行模拟安装,并进行碰撞试验,找出装饰模型和三维模型之间不符的区域和尺寸偏差,得到碰撞结果;(5)根据碰撞结果对装饰模型进行调整;(6)在完成的装饰模型中提取坐标安装点位信息,将点位信息导入全站仪,放出后期安装完成面线。本发明可以解决现有技术中建筑装饰施工误差调整麻烦、施工效率和施工质量低的技术问题。
Description
技术领域
本发明涉及一种建筑装饰施工方法,具体而言,涉及一种基于BIM的复杂共享空间装配化建筑装饰施工方法。
背景技术
建筑信息模型(Building Information Modeling),一般简称BIM,其是以建筑工程项目的各项相关信息数据作为模型的基础,进行建筑模型的建立,通过数字信息仿真模拟建筑物所具有的真实信息。BIM具有信息完备性、信息关联性、信息一致性、可视化、协调性、模拟性、优化性和可出图性八大特点。
随着现代建筑对建筑装饰在效率、精度等方面提出了更高的要求,现在的建筑装饰基于BIM已经逐步向着数字化的方向进行发展。但是,目前的数字化建筑装饰仅限于进行模型的设计和建立,而实际建筑装饰施工过程中,时常会遇到施工误差的问题,遇到问题后,只能在后期完成施工后再重新进行调整,操作上不仅麻烦,也比较影响整体的施工效率和施工质量。
发明内容
鉴于此,本发明提供了一种基于BIM的复杂共享空间装配化建筑装饰施工方法,旨在解决现有技术中建筑装饰施工误差调整麻烦、施工效率和施工质量低的技术问题。
为此,本发明提供了一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其包括以下步骤:
(1)对施工现场进行三维扫描,采集施工现场的三维数据;
(2)根据三维数据得到三维模型;
(3)根据图纸建立装饰模型;
(4)将装饰模型匹配到三维模型中进行模拟安装,并进行碰撞试验,找出装饰模型和三维模型之间不符的区域和尺寸偏差,得到碰撞结果;
(5)根据碰撞结果对装饰模型进行调整;
(6)在完成的装饰模型中提取坐标安装点位信息,将点位信息导入全站仪,放出后期安装完成面线。
进一步地,上述步骤(1)中,具体对施工现场进行三维点云扫描,采集施工现场的三维点云数据。
进一步地,上述三维模型为点云模型。
进一步地,上述步骤(2)中,三维数据具体导入SENS软件得到三维模型。
进一步地,上述基于BIM的复杂共享空间装配化建筑装饰施工方法还包括二次碰撞步骤(7),其用于对现场钢架进行调整。
进一步地,上述二次碰撞步骤(7)包括:
(71)对施工现场的钢架结构进行三维扫描,得到钢架模型;
(72)将钢架模型导入到装饰模型中进行碰撞试验,找出装饰模型和钢架模型之间不符的区域和尺寸偏差,得到碰撞结果;
(73)根据碰撞结果对钢架模型进行调整。
进一步地,上述基于BIM的复杂共享空间装配化建筑装饰施工方法还包括三次碰撞步骤(8),对完成的现成进行三维扫描,得到完成模型,将完成模型与装饰模型进行碰撞检核。
进一步地,上述基于BIM的复杂共享空间装配化建筑装饰施工方法还包括材料扫描步骤:对进场材料进行三维扫描,与图纸数据进行对比检查,剔除不符要求的材料。
进一步地,上述步骤(4)中,将装饰模型和三维模型转成二维线条图,设定线条长度,通过提取模块提取出装饰模型和三维模型的第一框架和第二框架,第一框架为去除掉短于线条长度的线条的框架,然后将装饰模型和三维模型的第一框架进行对比。
进一步地,上述基于BIM的复杂共享空间装配化建筑装饰施工方法还设有线条加粗模块,提取模块提取出第二框架后,第二框架通过线条加粗模块进行加粗处理,然后将装饰模型和三维模型的第二框架进行对比。
本发明所提供的一种基于BIM的复杂共享空间装配化建筑装饰施工方法相较于现有技术具有以下优点:
1)数字化施工模拟:利用现场采集的精准数据结合三维可视化原理,在计算机里对施工过程进行仿真模拟,将现场问题消除在策划阶段,实现后期零返工;
2)数字化放线:对现场进行取点和放点,实现三维模型中的点位坐标与施工现场的位置的精确转换,达到图纸尺寸与现场的高度一致,为后期的精细化施工打好基础;
3)数字化下单:通过数字化施工策划,生成高精度的电子文档交付厂家下单,取代现场测量制作模板等传统下单方式,实现下单过程数字化,在保证精度的基础上节省大量人力物力;
4)数字化施工:在施工策划结束后即可进行材料下单,整个下单过程不放线和基层施工同步甚至提前,这为主材质量及成本的把控提供充足的时间,同时可以大大节约中庭部位的施工工期。
因此,本发明可以有效地解决现有技术中建筑装饰施工误差调整麻烦、施工效率和施工质量低的技术问题。
附图说明
通过阅读下文优选实施方式的详细描述,各种其他的优点和益处对于本领域普通技术人员将变得清楚明了。附图仅用于示出优选实施方式的目的,而并不认为是对本发明的限制。而且在整个附图中,用相同的参考符号表示相同的部件。在附图中:
图1为本发明实施例提供的一种基于BIM的复杂共享空间装配化建筑装饰施工方法的流程示意图。
具体实施方式
下面将参照附图更详细地描述本公开的示例性实施例。虽然附图中显示了本公开的示例性实施例,然而应当理解,可以以各种形式实现本公开而不应被这里阐述的实施例所限制。相反,提供这些实施例是为了能够更透彻地理解本公开,并且能够将本公开的范围完整的传达给本领域的技术人员。
参见图1,图中示出了本发明实施例提供的一种基于BIM的复杂共享空间装配化建筑装饰施工方法。该基于BIM的复杂共享空间装配化建筑装饰施工方法包括以下步骤:
S1:对施工现场进行三维扫描,采集施工现场的三维数据;
S2:根据三维数据得到三维模型;
S3:根据图纸建立装饰模型;
S4:将装饰模型匹配到三维模型中进行模拟安装,并进行碰撞试验,找出装饰模型和三维模型之间不符的区域和尺寸偏差,得到碰撞结果;
S5:根据碰撞结果对装饰模型进行调整;
S6:在完成的装饰模型中提取坐标安装点位信息,将点位信息导入全站仪,放出后期安装完成面线。
其中,步骤S1中,具体对施工现场进行三维点云扫描,采集施工现场的三维点云数据。三维模型具体可以为点云模型。步骤S2中,三维数据具体导入SENS软件得到三维模型。
参见图1,上述基于BIM的复杂共享空间装配化建筑装饰施工方法还包括二次碰撞步骤S7,其用于对现场钢架进行调整。该二次碰撞步骤S7包括:
S71:对施工现场的钢架结构进行三维扫描,得到钢架模型;
S72:将钢架模型导入到装饰模型中进行碰撞试验,找出装饰模型和钢架模型之间不符的区域和尺寸偏差,得到碰撞结果;
S73:根据碰撞结果对钢架模型进行调整。
参见图1,上述基于BIM的复杂共享空间装配化建筑装饰施工方法还包括三次碰撞步骤S8,对完成的现成进行三维扫描,得到完成模型,将完成模型与装饰模型进行碰撞检核。
参见图1,上述基于BIM的复杂共享空间装配化建筑装饰施工方法还包括材料扫描步骤S0:对进场材料进行三维扫描,与图纸数据进行对比检查,剔除不符要求的材料。
参见图1,步骤S4中,将装饰模型和三维模型转成二维线条图,设定线条长度,通过提取模块提取出装饰模型和三维模型的第一框架和第二框架,第一框架为去除掉短于线条长度的线条的框架,然后将装饰模型和三维模型的第一框架进行对比。由于模型中一些部分并不是一定需要调整的,例如幕墙的内部等,如果每个位置都扫描及调整就会浪费大量的时间,且使得计算机中的存储空间占用非常大,十分浪费效率,而利用此技术手段,便可以使得调整不会将模型的每个角落都实施,由此使得效率大幅度提高,节省计算机的存储空间。
参见图1,步骤S4中,还设有线条加粗模块,提取模块提取出第二框架后,第二框架通过线条加粗模块进行加粗处理,然后将装饰模型和三维模型的第二框架进行对比。此技术手段是为了防止一些位置被遗漏掉而没有调整,因此将其加粗后可以便于识别和对比,由此在上述效率提高的基础上也可以提高调整的精度,保证施工质量。
显然,本领域的技术人员可以对本发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包含这些改动和变型在内。
Claims (10)
1.一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,包括以下步骤:
(1)对施工现场进行三维扫描,采集所述施工现场的三维数据;
(2)根据所述三维数据得到三维模型;
(3)根据图纸建立装饰模型;
(4)将所述装饰模型匹配到所述三维模型中进行模拟安装,并进行碰撞试验,找出所述装饰模型和所述三维模型之间不符的区域和尺寸偏差,得到碰撞结果;
(5)根据所述碰撞结果对所述装饰模型进行调整;
(6)在完成的所述装饰模型中提取坐标安装点位信息,将所述点位信息导入全站仪,放出后期安装完成面线。
2.根据权利要求1所述的一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,所述步骤(1)中,具体对施工现场进行三维点云扫描,采集所述施工现场的三维点云数据。
3.根据权利要求1或2所述的一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,所述三维模型为点云模型。
4.根据权利要求1所述的一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,所述步骤(2)中,所述三维数据具体导入SENS软件得到三维模型。
5.根据权利要求1所述的一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,还包括二次碰撞步骤(7),其用于对现场钢架进行调整。
6.根据权利要求5所述的一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,所述二次碰撞步骤(7)包括:
(71)对施工现场的钢架结构进行三维扫描,得到钢架模型;
(72)将所述钢架模型导入到所述装饰模型中进行碰撞试验,找出所述装饰模型和所述钢架模型之间不符的区域和尺寸偏差,得到碰撞结果;
(73)根据所述碰撞结果对所述钢架模型进行调整。
7.根据权利要求5或6所述的一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,还包括三次碰撞步骤(8),对完成的现成进行三维扫描,得到完成模型,将所述完成模型与所述装饰模型进行碰撞检核。
8.根据权利要求1所述的一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,还包括材料扫描步骤:对进场材料进行三维扫描,与图纸数据进行对比检查,剔除不符要求的材料。
9.根据权利要求1所述的一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,所述步骤(4)中,将所述装饰模型和所述三维模型转成二维线条图,设定线条长度,通过提取模块提取出所述装饰模型和所述三维模型的第一框架和第二框架,所述第一框架为去除掉短于线条长度的线条的框架,然后将所述所述装饰模型和所述三维模型的第一框架进行对比。
10.根据权利要求9所述的一种基于BIM的复杂共享空间装配化建筑装饰施工方法,其特征在于,还设有线条加粗模块,所述提取模块提取出所述第二框架后,所述第二框架通过所述线条加粗模块进行加粗处理,然后将所述装饰模型和所述三维模型的第二框架进行对比。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610935522.XA CN106639207A (zh) | 2016-11-01 | 2016-11-01 | 一种基于bim的复杂共享空间装配化建筑装饰施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610935522.XA CN106639207A (zh) | 2016-11-01 | 2016-11-01 | 一种基于bim的复杂共享空间装配化建筑装饰施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106639207A true CN106639207A (zh) | 2017-05-10 |
Family
ID=58821176
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610935522.XA Pending CN106639207A (zh) | 2016-11-01 | 2016-11-01 | 一种基于bim的复杂共享空间装配化建筑装饰施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106639207A (zh) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107103151A (zh) * | 2017-05-15 | 2017-08-29 | 贵州精正检测有限公司 | 一种基于bim的装配式结构的方法和装置 |
CN107423523A (zh) * | 2017-08-14 | 2017-12-01 | 郭宇光 | 一种基于bim的复杂共享空间装配化建筑装饰施工方法 |
CN107610169A (zh) * | 2017-10-06 | 2018-01-19 | 湖北聚注通用技术研究有限公司 | 一种装修施工现场三维成像*** |
CN107702662A (zh) * | 2017-09-27 | 2018-02-16 | 深圳拎得清软件有限公司 | 基于激光扫描仪和bim的逆向监控方法及其*** |
CN107806176A (zh) * | 2017-12-01 | 2018-03-16 | 贵州精正检测有限公司 | 钢结构装配式建筑及其基于bim的施工方法 |
CN108005409A (zh) * | 2017-12-01 | 2018-05-08 | 贵州精正检测有限公司 | 分层装配式楼房及其基于bim的施工方法 |
CN108171786A (zh) * | 2017-12-12 | 2018-06-15 | 上海爱优威软件开发有限公司 | 一种终端模拟设计方法及*** |
CN108363860A (zh) * | 2018-02-07 | 2018-08-03 | 中交公局第二工程有限公司 | 一种基于bim技术的三维异形桥梁模板拼装测设方法 |
CN108765545A (zh) * | 2018-04-18 | 2018-11-06 | 山东聊建集团有限公司 | 一种基于bim技术的厨卫阳房间装饰深化设计方法 |
CN109858172A (zh) * | 2019-02-18 | 2019-06-07 | 中国铁路设计集团有限公司 | 快速建立型钢钢架bim模型的设计方法 |
CN110130659A (zh) * | 2019-04-18 | 2019-08-16 | 滁州职业技术学院 | 一种基于三维扫描的装配式建筑施工方法和*** |
CN111062069A (zh) * | 2019-11-14 | 2020-04-24 | 上海市建筑装饰工程集团有限公司 | 适用于建筑装饰工程复杂多曲构件的数字化建造辅助施工方法 |
CN111444570A (zh) * | 2020-04-16 | 2020-07-24 | 福建汇川物联网技术科技股份有限公司 | 一种施工误差信息的获取方法及装置 |
CN112663885A (zh) * | 2020-12-10 | 2021-04-16 | 深圳中安建工程建设有限公司 | 一种室内装饰预制组件的装修方法 |
CN113190904A (zh) * | 2021-05-08 | 2021-07-30 | 成都亲生命科技有限公司 | 基于点云测量的一体化数据采集可对接工厂生产的下单*** |
CN114491756A (zh) * | 2022-01-25 | 2022-05-13 | 安徽富煌钢构股份有限公司 | 一种基于bim技术的钢结构单元安装误差控制方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002342386A (ja) * | 2001-05-17 | 2002-11-29 | Sumitomo Forestry Co Ltd | 定型部材総数算出方法 |
CN103198195A (zh) * | 2013-04-16 | 2013-07-10 | 上海上安机电设计事务所有限公司 | 一种基于bim的建筑工程模型碰撞检测方法 |
CN104318610A (zh) * | 2014-10-24 | 2015-01-28 | 苏州金螳螂建筑装饰股份有限公司 | 大空间三维实体放线方法 |
CN104850709A (zh) * | 2015-05-25 | 2015-08-19 | 苏州金螳螂建筑装饰股份有限公司 | 建筑装饰工程施工三维模拟方法 |
CN105888248A (zh) * | 2016-04-27 | 2016-08-24 | 河北建筑工程学院 | 一种基于bim技术指导信息化预制构件的施工方法 |
CN106055839A (zh) * | 2016-06-30 | 2016-10-26 | 上海宝冶集团有限公司 | 基于bim的三维扫描技术在建筑工程中的应用方法 |
-
2016
- 2016-11-01 CN CN201610935522.XA patent/CN106639207A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002342386A (ja) * | 2001-05-17 | 2002-11-29 | Sumitomo Forestry Co Ltd | 定型部材総数算出方法 |
CN103198195A (zh) * | 2013-04-16 | 2013-07-10 | 上海上安机电设计事务所有限公司 | 一种基于bim的建筑工程模型碰撞检测方法 |
CN104318610A (zh) * | 2014-10-24 | 2015-01-28 | 苏州金螳螂建筑装饰股份有限公司 | 大空间三维实体放线方法 |
CN104850709A (zh) * | 2015-05-25 | 2015-08-19 | 苏州金螳螂建筑装饰股份有限公司 | 建筑装饰工程施工三维模拟方法 |
CN105888248A (zh) * | 2016-04-27 | 2016-08-24 | 河北建筑工程学院 | 一种基于bim技术指导信息化预制构件的施工方法 |
CN106055839A (zh) * | 2016-06-30 | 2016-10-26 | 上海宝冶集团有限公司 | 基于bim的三维扫描技术在建筑工程中的应用方法 |
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107103151A (zh) * | 2017-05-15 | 2017-08-29 | 贵州精正检测有限公司 | 一种基于bim的装配式结构的方法和装置 |
CN107423523A (zh) * | 2017-08-14 | 2017-12-01 | 郭宇光 | 一种基于bim的复杂共享空间装配化建筑装饰施工方法 |
CN107423523B (zh) * | 2017-08-14 | 2020-11-17 | 郭宇光 | 一种基于bim的复杂共享空间装配化建筑装饰施工方法 |
CN107702662B (zh) * | 2017-09-27 | 2020-01-21 | 深圳拎得清软件有限公司 | 基于激光扫描仪和bim的逆向监控方法及其*** |
CN107702662A (zh) * | 2017-09-27 | 2018-02-16 | 深圳拎得清软件有限公司 | 基于激光扫描仪和bim的逆向监控方法及其*** |
CN107610169A (zh) * | 2017-10-06 | 2018-01-19 | 湖北聚注通用技术研究有限公司 | 一种装修施工现场三维成像*** |
CN107806176A (zh) * | 2017-12-01 | 2018-03-16 | 贵州精正检测有限公司 | 钢结构装配式建筑及其基于bim的施工方法 |
CN108005409A (zh) * | 2017-12-01 | 2018-05-08 | 贵州精正检测有限公司 | 分层装配式楼房及其基于bim的施工方法 |
CN108171786A (zh) * | 2017-12-12 | 2018-06-15 | 上海爱优威软件开发有限公司 | 一种终端模拟设计方法及*** |
CN108363860A (zh) * | 2018-02-07 | 2018-08-03 | 中交公局第二工程有限公司 | 一种基于bim技术的三维异形桥梁模板拼装测设方法 |
CN108765545A (zh) * | 2018-04-18 | 2018-11-06 | 山东聊建集团有限公司 | 一种基于bim技术的厨卫阳房间装饰深化设计方法 |
CN108765545B (zh) * | 2018-04-18 | 2022-05-03 | 山东聊建集团有限公司 | 一种基于bim技术的厨卫阳房间装饰深化设计方法 |
CN109858172A (zh) * | 2019-02-18 | 2019-06-07 | 中国铁路设计集团有限公司 | 快速建立型钢钢架bim模型的设计方法 |
CN110130659A (zh) * | 2019-04-18 | 2019-08-16 | 滁州职业技术学院 | 一种基于三维扫描的装配式建筑施工方法和*** |
CN111062069A (zh) * | 2019-11-14 | 2020-04-24 | 上海市建筑装饰工程集团有限公司 | 适用于建筑装饰工程复杂多曲构件的数字化建造辅助施工方法 |
CN111444570A (zh) * | 2020-04-16 | 2020-07-24 | 福建汇川物联网技术科技股份有限公司 | 一种施工误差信息的获取方法及装置 |
CN112663885A (zh) * | 2020-12-10 | 2021-04-16 | 深圳中安建工程建设有限公司 | 一种室内装饰预制组件的装修方法 |
CN113190904A (zh) * | 2021-05-08 | 2021-07-30 | 成都亲生命科技有限公司 | 基于点云测量的一体化数据采集可对接工厂生产的下单*** |
CN114491756A (zh) * | 2022-01-25 | 2022-05-13 | 安徽富煌钢构股份有限公司 | 一种基于bim技术的钢结构单元安装误差控制方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106639207A (zh) | 一种基于bim的复杂共享空间装配化建筑装饰施工方法 | |
CN106600690B (zh) | 基于点云数据的复杂建筑体三维建模方法 | |
CN105547151B (zh) | 三维激光扫描点云数据采集与处理的方法及*** | |
CN105888248B (zh) | 一种基于bim技术指导信息化预制构件的施工方法 | |
CN105045950B (zh) | 一种基于三维激光扫描的桥梁安全评估*** | |
CN109800536A (zh) | 一种基于Revit与Dynamo参数化隧道模型快速建模方法 | |
CN107093206A (zh) | 利用3d激光扫描技术快速bim建模的方法 | |
CN105549548B (zh) | 三维装配工艺生成方法和生成装置 | |
KR101425576B1 (ko) | 정밀한 광역 축척 모형 제작을 위한 3차원 데이터 획득 및 가공 방법 | |
CN104850709B (zh) | 建筑装饰工程施工三维模拟方法 | |
CN107515991A (zh) | 一种基于bim技术的户型全装修模拟展示方法及展示*** | |
CN108763685A (zh) | 一种空间异形曲面幕墙***的施工方法 | |
KR100609786B1 (ko) | 도화원도를 이용한 3차원 건물 모델링 방법 | |
CN110633518B (zh) | 基于bim的简易参数化单元式幕墙材质分类统计方法 | |
CN109583033A (zh) | Bim自适应模型在异型幕墙施工中的应用方法及*** | |
CN108121873A (zh) | 一种建筑模型在幕墙施工中的应用方法 | |
CN112182718B (zh) | 基于bim与3d技术的构件设计方法、装置及存储介质 | |
CN106777779B (zh) | 一种基于bim的铁路涵洞设计方法 | |
CN104077446A (zh) | 从数字化三维模型中提取二维电气施工图的方法及*** | |
CN105550428A (zh) | 一种基于tls技术的桥梁安全评估方法 | |
CN111046459A (zh) | 一种基于3d软件的建筑模型图像设计方法 | |
CN113779670B (zh) | 一种基于Dynamo实现Revit桩基双控建模的方法及*** | |
Rashidi et al. | Video to BrIM: Automated 3D as-built documentation of bridges | |
CN109903382A (zh) | 点云数据的融合方法及装置 | |
CN112598786A (zh) | 一种参数化的墙体切割方法及装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170510 |
|
RJ01 | Rejection of invention patent application after publication |