CN106629361A - 电梯曳引装置、对重架及对重架组装方法 - Google Patents

电梯曳引装置、对重架及对重架组装方法 Download PDF

Info

Publication number
CN106629361A
CN106629361A CN201610993215.7A CN201610993215A CN106629361A CN 106629361 A CN106629361 A CN 106629361A CN 201610993215 A CN201610993215 A CN 201610993215A CN 106629361 A CN106629361 A CN 106629361A
Authority
CN
China
Prior art keywords
column
crossbeam
counterweight frame
falcon
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610993215.7A
Other languages
English (en)
Inventor
刘威
陈涛
高起鹏
冯浩聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XJ Schindler Xuchang Elevator Co Ltd
XJ Elevator Co Ltd
Original Assignee
XJ Elevator Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XJ Elevator Co Ltd filed Critical XJ Elevator Co Ltd
Priority to CN201610993215.7A priority Critical patent/CN106629361A/zh
Publication of CN106629361A publication Critical patent/CN106629361A/zh
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B17/00Hoistway equipment
    • B66B17/12Counterpoises

Landscapes

  • Cage And Drive Apparatuses For Elevators (AREA)

Abstract

本发明涉及一种电梯曳引装置、对重架及对重架组装方法。对重架包括上下间隔的两根横梁和左右间隔的两根立柱,两横梁各自的两端分别通过隼接结构连接在对应的立柱上,并且在横梁和立柱的隼接部位设有焊接结构。本发明中横梁在立柱上采用先隼接后焊接的连接方式,以通过隼接结构来增大横梁和立柱的接触面积,一方面能够通过隼接结构承担部分负重载荷,另一方面使得横梁和立柱的焊接结构的焊缝延长、焊接强度提高,也就使得横梁在立柱上的连接可靠性提高,因而本发明中对重架具有结构稳定性好的优点。

Description

电梯曳引装置、对重架及对重架组装方法
技术领域
本发明涉及一种电梯曳引装置、对重架及对重架组装方法。
背景技术
对重属于电梯八大***之一,是曳引电梯不可缺少的部分,其安装在轿厢的另一侧,用于平衡轿厢的重量和部分电梯负载重量,保证电梯曳引***的正常运行,降低能耗,减少电机功率的损耗。如图1和图2所示,现有对重的对重架包括上下间隔的两根横梁11和左右间隔的两根立柱12,两横梁11各自的两端搭设焊接在立柱12上,以组成矩形框状的架体。通常的对重架在焊接时,对重架的两根横梁11焊接在立柱12的外侧,所以横梁11的支撑力全由焊缝的强度保证。但焊接结构必然存在焊接缺陷,并且该焊接缺陷的检测较为困难,如果缺陷超过允许范围的话,横梁11和立柱12之前的焊缝强度将不足以提供足够的支撑力,因而该对重架上存在横梁11从立柱12上脱落的安全隐患,危机电梯内搭乘的人员的人身安全。
发明内容
本发明旨在提供一种稳定性好的对重架,同时还提供了一种使用该对重架的电梯曳引装置及专用于该对重架的对重架组装方法。
为解决上述技术问题,本发明中对重架的技术方案如下:
对重架,包括上下间隔的两根横梁和左右间隔的两根立柱,两横梁各自的两端分别通过隼接结构连接在对应的立柱上,并且在横梁和立柱的隼接部位设有焊接结构。
所述隼接结构包括立柱上设置的插槽或孔,横梁的端部插接在所述插槽或孔中。
立柱上设置有插孔,插孔为沿左右方向贯穿立柱的穿孔,横梁的端部从所述插孔中穿出,所述焊接结构处于横梁的穿出部位和插孔的孔沿之间。
立柱为C型钢,所述插孔位于C型钢的棱边上。
插槽或孔的长度小于横梁的宽度,横梁的端部设有吻合插配在所述插槽或孔中的隼头。
本发明中对重架组装方法的技术方案如下:
对重架组装方法,包括如下步骤:
步骤一,将横梁与立柱相互隼接;
步骤二,在横梁和立柱的隼接部位焊接。
本发明中电梯曳引装置的技术方案如下:
电梯曳引装置,包括对重架及其内固定的对重块,对重架包括上下间隔的两根横梁和左右间隔的两根立柱,两横梁各自的两端分别通过隼接结构连接在对应的立柱上,并且在横梁和立柱的隼接部位设有焊接结构。
所述隼接结构包括立柱上设置的插槽或孔,横梁的端部插接在所述插槽或孔中。
立柱上设置有插孔,插孔为沿左右方向贯穿立柱的穿孔,横梁的端部从所述插孔中穿出,所述焊接结构处于横梁的穿出部位和插孔的孔沿之间。
立柱为C型钢,所述插孔位于C型钢的棱边上。
本发明中横梁在立柱上采用先隼接后焊接的连接方式,以通过隼接结构来增大横梁和立柱的接触面积,一方面能够通过隼接结构承担部分负重载荷,另一方面使得横梁和立柱的焊接结构的焊缝延长、焊接强度提高,也就使得横梁在立柱上的连接可靠性提高,因而本发明中对重架具有结构稳定性好的优点。
附图说明
图1是现有技术中对重架的结构示意图;
图2是图1中A处的局部放大图;
图3是本发明中曳引装置的结构示意图;
图4是图3中对重架的结构示意图;
图5是图4中B处的局部放大图。
具体实施方式
本发明中电梯曳引装置的实施例:如图3所示,该曳引装置包括对重架及其内固定的对重块,对重架的顶部设置有绳头滑轮23、底部设置有缓冲器碰块24。
如图4和图5所示,对重架主要由上下间隔的两根横梁21和左右间隔的两根立柱22组成,两横梁21各自的两端分别通过隼接结构连接在对应的立柱22上,并且在横梁21和立柱22的隼接部位设有焊接结构。隼接结构包括立柱22上设置的插孔26,横梁21的端部插接在插孔26中。插孔26为沿左右方向贯穿立柱22的穿孔,横梁21的端部从所述插孔26中穿出,焊接结构处于横梁21的穿出部位和插孔26的孔沿之间。
立柱22为C型钢,插孔26位于C型钢的棱边上。每根横梁21均是由前后平行的两根承重梁组成,两承重梁各自的两端隼接在立柱22上对应的插孔26中。插孔26的长度小于横梁21的宽度,横梁21的端部设有吻合插配在插孔26中的隼头25,隼头25为在承重梁的端部开设止口后留下的凸出头。
本实施例中对重架上下两侧的横梁21端部均有凸出头,焊接时,首先把横梁21的凸出头***立柱22的隼接孔中,最后把横梁21与立柱22的接触面焊接牢固。这样即使焊缝完全失效,立柱22自身仍可依靠隼接结构向横梁21提供支撑力而不会脱落,从而利用隼接的方法,为对重架的横梁21的牢固性提供了双重保障。
本发明中电梯曳引装置的其他实施例:该隼接结构也可以是处于横梁上的插槽或孔与处于立柱上的隼接头配合。
本发明中对重架的实施例:本实施例中对重架的结构与上述实施例中对重架的结构相同,因此不再赘述。
本发明中对重架组装方法的实施例:该方法包括如下步骤:
1,将横梁与立柱相互隼接;
2,在横梁和立柱的隼接部位焊接。
本实施例中对重架的横梁和立柱经过先隼接后焊接的方式进行连接,隼接一方面可保证横梁在立柱上的预定位,提高焊接精度;另一方面隼接会加强横梁和立柱之间的连接强度,使得焊接结构出现损伤的情况下,横梁仍然会可靠稳定的连接在立柱上。

Claims (10)

1.对重架,包括上下间隔的两根横梁和左右间隔的两根立柱,其特征在于,两横梁各自的两端分别通过隼接结构连接在对应的立柱上,并且在横梁和立柱的隼接部位设有焊接结构。
2.根据权利要求1所述的对重架,其特征在于,所述隼接结构包括立柱上设置的插槽或孔,横梁的端部插接在所述插槽或孔中。
3.根据权利要求2所述的对重架,其特征在于,立柱上设置有插孔,插孔为沿左右方向贯穿立柱的穿孔,横梁的端部从所述插孔中穿出,所述焊接结构处于横梁的穿出部位和插孔的孔沿之间。
4.根据权利要求3所述的对重架,其特征在于,立柱为C型钢,所述插孔位于C型钢的棱边上。
5.根据权利要求2所述的对重架,其特征在于,插槽或孔的长度小于横梁的宽度,横梁的端部设有吻合插配在所述插槽或孔中的隼头。
6.对重架组装方法,其特征在于,包括如下步骤:
步骤一,将横梁与立柱相互隼接;
步骤二,在横梁和立柱的隼接部位焊接。
7.电梯曳引装置,包括对重架及其内固定的对重块,对重架包括上下间隔的两根横梁和左右间隔的两根立柱,其特征在于,两横梁各自的两端分别通过隼接结构连接在对应的立柱上,并且在横梁和立柱的隼接部位设有焊接结构。
8.根据权利要求7所述的电梯曳引装置,其特征在于,所述隼接结构包括立柱上设置的插槽或孔,横梁的端部插接在所述插槽或孔中。
9.根据权利要求8所述的电梯曳引装置,其特征在于,立柱上设置有插孔,插孔为沿左右方向贯穿立柱的穿孔,横梁的端部从所述插孔中穿出,所述焊接结构处于横梁的穿出部位和插孔的孔沿之间。
10.根据权利要求9所述的电梯曳引装置,其特征在于,立柱为C型钢,所述插孔位于C型钢的棱边上。
CN201610993215.7A 2016-11-11 2016-11-11 电梯曳引装置、对重架及对重架组装方法 Pending CN106629361A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610993215.7A CN106629361A (zh) 2016-11-11 2016-11-11 电梯曳引装置、对重架及对重架组装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610993215.7A CN106629361A (zh) 2016-11-11 2016-11-11 电梯曳引装置、对重架及对重架组装方法

Publications (1)

Publication Number Publication Date
CN106629361A true CN106629361A (zh) 2017-05-10

Family

ID=58805589

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610993215.7A Pending CN106629361A (zh) 2016-11-11 2016-11-11 电梯曳引装置、对重架及对重架组装方法

Country Status (1)

Country Link
CN (1) CN106629361A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115783943A (zh) * 2022-11-17 2023-03-14 东台创跃机电有限公司 一种便于进行组装的电梯轿厢

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001122560A (ja) * 1999-10-28 2001-05-08 Toshiba Elevator Co Ltd エレベーター用釣合い重り
CN201650966U (zh) * 2010-02-08 2010-11-24 徐孝立 组合式钢床的柱梁连接装置
US20110100763A1 (en) * 2009-09-15 2011-05-05 Tom Wiacek Interlocking Elevator Cab Assembly
CN202186819U (zh) * 2011-07-27 2012-04-11 浙江诺比克电梯有限公司 电梯用对重装置
CN202373865U (zh) * 2011-12-27 2012-08-08 广东正超电气有限公司 低压开关柜框架连接结构
CN103771228A (zh) * 2014-01-08 2014-05-07 日立电梯(中国)有限公司 无焊接轿底架以及无焊接轿底
CN205603020U (zh) * 2016-04-15 2016-09-28 西继迅达(许昌)电梯有限公司 一种电梯对重装置
CN206553030U (zh) * 2016-11-11 2017-10-13 西继迅达(许昌)电梯有限公司 一种电梯曳引装置及其对重架

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001122560A (ja) * 1999-10-28 2001-05-08 Toshiba Elevator Co Ltd エレベーター用釣合い重り
US20110100763A1 (en) * 2009-09-15 2011-05-05 Tom Wiacek Interlocking Elevator Cab Assembly
CN201650966U (zh) * 2010-02-08 2010-11-24 徐孝立 组合式钢床的柱梁连接装置
CN202186819U (zh) * 2011-07-27 2012-04-11 浙江诺比克电梯有限公司 电梯用对重装置
CN202373865U (zh) * 2011-12-27 2012-08-08 广东正超电气有限公司 低压开关柜框架连接结构
CN103771228A (zh) * 2014-01-08 2014-05-07 日立电梯(中国)有限公司 无焊接轿底架以及无焊接轿底
CN205603020U (zh) * 2016-04-15 2016-09-28 西继迅达(许昌)电梯有限公司 一种电梯对重装置
CN206553030U (zh) * 2016-11-11 2017-10-13 西继迅达(许昌)电梯有限公司 一种电梯曳引装置及其对重架

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115783943A (zh) * 2022-11-17 2023-03-14 东台创跃机电有限公司 一种便于进行组装的电梯轿厢

Similar Documents

Publication Publication Date Title
CN103832446A (zh) 一种轨道车辆车体底架结构
CN102912721A (zh) 桥梁钢箱主梁双挑式索梁锚固结构
CN103802849A (zh) 一种b型地铁车辆车体结构
CN104787072B (zh) 一种低地板轨道车辆底架结构
CN104213501A (zh) 一种斜拉式可弯折开启栈桥结构及其施工方法
CN106624631A (zh) 门式起重机主梁轨道安装精度控制方法
CN105015571A (zh) 一种低地板拖车车体底架
CN106629361A (zh) 电梯曳引装置、对重架及对重架组装方法
CN206553030U (zh) 一种电梯曳引装置及其对重架
CN211645914U (zh) 支撑结构、支撑模块及钢箱梁
CN108867345B (zh) 一种节省城市桥梁下空间的钢桥梁隐形盖梁结构及其施工方法
CN209163043U (zh) 一种方中空夹层钢管混凝土柱与钢梁连接节点
CN201634994U (zh) 栓焊组合构件
CN106948262B (zh) 一种带有横向系梁的正交异性钢桥面板结构
CN202186815U (zh) 电梯轿厢架
CN102285569B (zh) 电梯轿厢的绳头架
CN202279597U (zh) 电梯轿厢的绳头架
CN205472121U (zh) 一种无机房电梯的轿厢绳头架
CN205222516U (zh) 组装式维修间的立柱和轨道横梁连接结构
CN204847834U (zh) 一种过跨单梁起重机
CN203486401U (zh) 集装箱底架及集装箱的鹅颈槽结构
CN209176695U (zh) 一种空轨货车的动车底架
CN206107346U (zh) 一种汽车门框加强结构及汽车
CN104960627A (zh) 用于船舶上层建筑的托架
CN206204784U (zh) 钢锚梁

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 461000 south section of Yanan Road, Xuchang economic and Technological Development Zone, Henan

Applicant after: Xiji Xunda Elevator Co., Ltd

Address before: 461000 south section of Yanan Road, Xuchang economic and Technological Development Zone, Henan

Applicant before: XJ SCHINDLER (XUCHANG) ELEVATOR Co.,Ltd.

CB02 Change of applicant information