CN106429742A - Locating device and implementing method for mounting elevator cage of construction elevator - Google Patents

Locating device and implementing method for mounting elevator cage of construction elevator Download PDF

Info

Publication number
CN106429742A
CN106429742A CN201610966792.7A CN201610966792A CN106429742A CN 106429742 A CN106429742 A CN 106429742A CN 201610966792 A CN201610966792 A CN 201610966792A CN 106429742 A CN106429742 A CN 106429742A
Authority
CN
China
Prior art keywords
clamping block
block
ladder cage
mounting
building hoist
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610966792.7A
Other languages
Chinese (zh)
Other versions
CN106429742B (en
Inventor
王辉
孙金桥
李迪
周勇
叶贞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN201610966792.7A priority Critical patent/CN106429742B/en
Publication of CN106429742A publication Critical patent/CN106429742A/en
Application granted granted Critical
Publication of CN106429742B publication Critical patent/CN106429742B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B11/00Main component parts of lifts in, or associated with, buildings or other structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Ladders (AREA)

Abstract

The invention provides a locating device for mounting an elevator cage of a construction elevator. The locating device comprises a support frame and a locking block, wherein the locking block is fixed to a target position of a guide rail frame, and the support frame is in detachable connection with the locking block. The invention further provides an implementing method for mounting the elevator cage of the construction elevator. The implementing method comprises the following steps: initially locating the locking block in the target position of the guide rail frame; lifting the support frame through a crane or an electric hoist or by a worker; aligning the support frame with the locking block which is well located and fixing the support frame; mounting the elevator cage, to be specific, directly mounting the elevator cage on the support frame; and mounting the driving system and the electric system of the construction elevator, and carrying out electric adjustment. By mounting the device on the guide rail frame, the elevator cage can be located at any height on the guide rail frame, and the elevator cage does not need to be placed on a main underframe or a sleeper.

Description

Building hoist ladder cage mounting and positioning device and implementation
Technical field
The present invention relates to building hoist field is and in particular to a kind of building hoist ladder cage mounting and positioning device and enforcement Method.
Background technology
In installation process, when mounted, ladder cage and driving means are lifted ladder cage current building hoist, put respectively Enter in guide rail bracket, and because now electrical system is not yet installed and debugged, ladder cage does not have stopping means on guide rail bracket, ladder cage is only Can be placed on main underframe or on chock, make ladder cage is provided with larger limitation, if in addition, ladder cage is sent out in certain altitude Raw fault and when being not easy to drop to floor pen, maintenance activity under certain altitude for the ladder cage also makes certain hidden of security presence Suffer from.
In addition, for the construction elevator of many ladder cages, the installation of ladder cage cannot place one's entire reliance upon be placed on main underframe or On person's chock, therefore design and construction elevator ladder cage mounting and positioning device is necessary.
Content of the invention
The technical problem to be solved in the present invention is:A kind of building hoist ladder cage mounting and positioning device and embodiment party are provided Method, so that ladder cage can be positioned on guide rail bracket, without being placed on main underframe or on chock.
The present invention by solving the technical scheme taken of above-mentioned technical problem is:A kind of building hoist ladder cage installs positioning Device it is characterised in that:It includes bracing frame and clamping block, and clamping block is fixed on the target location of guide rail bracket, and described props up Support is detachably connected with clamping block.
By such scheme, described bracing frame includes support beam, lower support block and bracing piece therebetween;Described Upper support beam and bracing piece between, between bracing piece and lower support block, be and be fixedly connected;
Described clamping block includes clamping block and lower clamping block, and upper clamping block is connected with described upper support beam, lower locking Block is connected with described lower support block.
By such scheme, described bracing piece is at least 2 bracing diagonals.
By such scheme, the incline direction of described bracing diagonal is from top to bottom from laterally toward intermediate, inclined.
By such scheme, described bracing frame is connected with clamping block by screw.
By such scheme, described clamping block includes 2 pieces of fixture blocks for clamp rail frame, and 2 fixture blocks pass through connector Connect.
A kind of building hoist ladder cage installation embodiment party being realized using above-mentioned building hoist ladder cage mounting and positioning device Method it is characterised in that:It comprises the following steps:
S1, by clamping block initial alignment in the target location of guide rail bracket;
S2, sling by loop wheel machine or electric block or manually lift bracing frame;
S3, bracing frame is with the locking block alignment having good positioning and fixing;
S4, installation ladder cage, ladder cage is rest directly upon on bracing frame;
S5, installation lift drive system and electrical system, and carry out electric adjustment.
As stated above, described bracing frame includes support beam, lower support block and bracing piece therebetween;Described Upper support beam and bracing piece between, between bracing piece and lower support block, be and be fixedly connected;Described clamping block includes Clamping block and lower clamping block;
Upper support beam first by upper support beam and upper locking block alignment, is fixed on upper clamping block by screw by described S3 On;Again by lower support block and lower locking block alignment, by screw, lower support block is fixed on lower clamping block.
Beneficial effects of the present invention are:
1st, pass through this device is installed on guide rail bracket, can on guide rail bracket any altitude location ladder cage, put without by ladder cage Put on main underframe or on chock;When ladder cage breaks down, this device can be installed below ladder cage it is ensured that the peace of ladder cage Quan Xing;This device is easy for installation, simple economy, improves benefit it is ensured that job safety.
2nd, for the building hoist of many ladder cages, ensure that more ladder cages are convenient on guide rail bracket and install.
3rd, by refinement further to bracing frame, on the premise of ensureing quality, bracing frame can further be reduced Complex degree of structure.
4th, arrange the bracing diagonal of eight shapes, can further improve the strength and stiffness of whole device.
Brief description
Fig. 1 is one embodiment of the invention application schematic diagram in single ladder cage.
Fig. 2 is one embodiment of the invention application schematic diagram in many ladder cages.
Fig. 3 is the Structure explosion diagram of one embodiment of the invention.
Fig. 4 is the Structure explosion diagram of clamping block in one embodiment of the invention.
In figure:1- guide rail bracket, 2- drive system, 3- ladder cage, 4- ladder cage mounting and positioning device, 5- attached wall, the upper clamping block of 6-, Support block, 12- screw under clamping block under 7- circular cone pin, the upper support beam of 8-, 9- bracing diagonal, 10-, 11-, 13- fixture block.
Specific embodiment
With reference to instantiation and accompanying drawing, the present invention will be further described.
As illustrated in figs. 1 and 2, guide rail bracket 1 is connected with attached wall 5, first ladder cage mounting and positioning device 4 is arranged on guide rail bracket On 1, then ladder cage 3 is installed so that ladder cage mounting and positioning device supports ladder cage 3, then drive system 2 is installed again.
The present invention provides a kind of building hoist ladder cage mounting and positioning device, and it includes bracing frame and clamping block, clamping block It is fixed on the target location of guide rail bracket 1, described bracing frame is detachably connected with clamping block.
As shown in Figure 3 it is preferred that described bracing frame include support beam 8, lower support block 11 and therebetween plus Strong bar;Between described upper support beam 8 and bracing piece, between bracing piece and lower support block 11, it is and is fixedly connected;Described Clamping block includes clamping block 6 and lower clamping block 10, and upper clamping block 6 is connected with described upper support beam 8, lower clamping block 10 with Described lower support block 11 connects.Upper support beam 8 is used for directly supporting the polycrystalline substance of ladder cage 3, and lower support block 11 can carry The latching force of this device high.
It is further preferred that described bracing piece is at least 2 bracing diagonals 9.In the present embodiment, described bracing diagonal 9 incline direction is from top to bottom from laterally toward intermediate, inclined.When bracing diagonal 9 is 2, as herringbone, this knot Structure can improve the strength and stiffness of whole device.
Refine further, described bracing frame is connected with clamping block by screw 12.
Further refine, as shown in figure 4, described clamping block includes 2 pieces of fixture blocks 13,2 for clamp rail frame Individual fixture block 13 is connected by connector, and in the present embodiment, connector is circular cone pin 7.
A kind of building hoist ladder cage installation embodiment party being realized using above-mentioned building hoist ladder cage mounting and positioning device Method, comprises the following steps:S1, by clamping block initial alignment in the target location of guide rail bracket 1(With two pieces of fixture blocks 13 in the present embodiment Clamp guide rail bracket, then with circular cone pin 7, two pieces of fixture blocks 13 are fixed);S2, sling by loop wheel machine or electric block or manually Lift bracing frame;S3, bracing frame is with the locking block alignment having good positioning and fixing;S4, installation ladder cage 3, ladder cage 3 is directly laid On bracing frame;S5, installation lift drive system and electrical system, and carry out electric adjustment.
Preferably, described bracing frame includes support beam 8, lower support block 11 and bracing piece therebetween;Described Upper support beam 8 and bracing piece between, between bracing piece and lower support block 11, be and be fixedly connected;Described clamping block bag Include clamping block 6 and lower clamping block 10;Upper support beam 8 is first aligned by described S3 with upper clamping block 6, will by screw 12 Upper support beam 8 is fixed on clamping block 6;Again lower support block 11 is aligned with lower clamping block 10, by screw 12 by lower Bracer 11 is fixed on lower clamping block 10.
Above example is merely to illustrate design philosophy and the feature of the present invention, its object is to make technology in the art Personnel will appreciate that present disclosure and implement according to this, protection scope of the present invention is not limited to above-described embodiment.So, all according to The equivalent variations made according to disclosed principle, mentality of designing or modification, all within protection scope of the present invention.

Claims (8)

1. a kind of building hoist ladder cage mounting and positioning device it is characterised in that:It includes bracing frame and clamping block, and clamping block is solid It is scheduled on the target location of guide rail bracket, described bracing frame is detachably connected with clamping block.
2. building hoist ladder cage mounting and positioning device according to claim 1 it is characterised in that:Described bracing frame bag Include support beam, lower support block and bracing piece therebetween;Between described upper support beam and bracing piece, bracing piece with Between lower support block, it is and is fixedly connected;
Described clamping block includes clamping block and lower clamping block, and upper clamping block is connected with described upper support beam, lower locking Block is connected with described lower support block.
3. building hoist ladder cage mounting and positioning device according to claim 2 it is characterised in that:Described bracing piece is At least 2 bracing diagonals.
4. building hoist ladder cage mounting and positioning device according to claim 3 it is characterised in that:Described bracing diagonal Incline direction be from top to bottom from laterally toward intermediate, inclined.
5. building hoist ladder cage mounting and positioning device as claimed in any of claims 1 to 4 it is characterised in that: Described bracing frame is connected with clamping block by screw.
6. building hoist ladder cage mounting and positioning device as claimed in any of claims 1 to 4 it is characterised in that: Described clamping block includes 2 pieces of fixture blocks for clamp rail frame, and 2 fixture blocks are connected by connector.
7. the building hoist ladder cage peace that the building hoist ladder cage mounting and positioning device described in a kind of utilization claim 1 is realized Dress implementation it is characterised in that:It comprises the following steps:
S1, by clamping block initial alignment in the target location of guide rail bracket;
S2, sling by loop wheel machine or electric block or manually lift bracing frame;
S3, bracing frame is with the locking block alignment having good positioning and fixing;
S4, installation ladder cage, ladder cage is rest directly upon on bracing frame;
S5, installation lift drive system and electrical system, and carry out electric adjustment.
8. building hoist ladder cage according to claim 7 implementation is installed it is characterised in that:Described bracing frame bag Include support beam, lower support block and bracing piece therebetween;Between described upper support beam and bracing piece, bracing piece with Between lower support block, it is and is fixedly connected;Described clamping block includes clamping block and lower clamping block;
Upper support beam first by upper support beam and upper locking block alignment, is fixed on upper clamping block by screw by described S3 On;Again by lower support block and lower locking block alignment, by screw, lower support block is fixed on lower clamping block.
CN201610966792.7A 2016-10-28 2016-10-28 Building hoist ladder cage mounting and positioning device and implementation method Active CN106429742B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610966792.7A CN106429742B (en) 2016-10-28 2016-10-28 Building hoist ladder cage mounting and positioning device and implementation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610966792.7A CN106429742B (en) 2016-10-28 2016-10-28 Building hoist ladder cage mounting and positioning device and implementation method

Publications (2)

Publication Number Publication Date
CN106429742A true CN106429742A (en) 2017-02-22
CN106429742B CN106429742B (en) 2019-04-16

Family

ID=58179426

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610966792.7A Active CN106429742B (en) 2016-10-28 2016-10-28 Building hoist ladder cage mounting and positioning device and implementation method

Country Status (1)

Country Link
CN (1) CN106429742B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000086113A (en) * 1998-09-10 2000-03-28 Toshiba Elevator Co Ltd Elevator, and installation method thereof
CN2467492Y (en) * 2001-02-27 2001-12-26 中国菱电股份有限公司 Construction platform for elevator mounting machine
CN201923740U (en) * 2011-01-25 2011-08-10 李贤明 Construction operation hanging basket for installing elevators
CN203795819U (en) * 2014-01-23 2014-08-27 唐继忠 Attached type lifting scaffold anti-inclination locking device
CN104163391A (en) * 2014-08-08 2014-11-26 三峡大学 Safe locking method and safe locking device for heavy-load construction of special construction lifting platform
CN204310644U (en) * 2014-12-11 2015-05-06 无锡市小天鹅建筑机械有限公司 A kind of single suspension centre cage guide installation and maintenance hanging basket
CN105986663A (en) * 2015-02-04 2016-10-05 雄宇集团无锡电梯安装技术有限公司 Elevator tooling lifting platform

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000086113A (en) * 1998-09-10 2000-03-28 Toshiba Elevator Co Ltd Elevator, and installation method thereof
CN2467492Y (en) * 2001-02-27 2001-12-26 中国菱电股份有限公司 Construction platform for elevator mounting machine
CN201923740U (en) * 2011-01-25 2011-08-10 李贤明 Construction operation hanging basket for installing elevators
CN203795819U (en) * 2014-01-23 2014-08-27 唐继忠 Attached type lifting scaffold anti-inclination locking device
CN104163391A (en) * 2014-08-08 2014-11-26 三峡大学 Safe locking method and safe locking device for heavy-load construction of special construction lifting platform
CN204310644U (en) * 2014-12-11 2015-05-06 无锡市小天鹅建筑机械有限公司 A kind of single suspension centre cage guide installation and maintenance hanging basket
CN105986663A (en) * 2015-02-04 2016-10-05 雄宇集团无锡电梯安装技术有限公司 Elevator tooling lifting platform

Also Published As

Publication number Publication date
CN106429742B (en) 2019-04-16

Similar Documents

Publication Publication Date Title
CN201821226U (en) Lifting device of large synchronous motor
CN108915272A (en) A kind of inclined-plane cell cube hanging method
CN102659043B (en) Improved dismounting device for buttress rod of tower crane
US11279593B2 (en) Compensation line storing apparatus, jump lift and the usage method thereof
CN103420281B (en) The attaching/detaching apparatus of hoisting crane and accessory structure thereof, method for dismounting and installation method
CN104153586A (en) Construction method for installing purline through suspension cable cranes
AU2219901A (en) Method for installing elevators
JP2011132012A (en) Method of installing hoisting machine of elevator
CN106429742A (en) Locating device and implementing method for mounting elevator cage of construction elevator
CN106121259A (en) The hanging apparatus of embedded integrated outer wall plate and hanging method thereof
CN103979442B (en) The method of 6400 tons of Hydraulic double-type crane lifting cost tropsch reactors
CN107458965B (en) A kind of large scale equipment hanging method
CN203959697U (en) The equalizing bar of hoisting platform truss
CN104030176B (en) The equalizer bar of hoisting platform truss and hanging method thereof
CN105253793B (en) Construction method for traction transporting and hoisting of zinc pot in zinc plating workshop
CN210485177U (en) Water pipe and bridge shared anti-seismic support
AU2016300492A1 (en) Assembly method for DC converter valve
CN203715136U (en) Tool for hoisting lifting hole cover plate in nuclear power plant
CN106365049B (en) Swing arm tower crane attachment support steel beam transporting device
CN201972391U (en) Self-stabilizing operation platform of elevator shaft
CN102121307B (en) Self-stabilizing operating platform for elevator shaft
CN105442828B (en) One kind is conveniently detached security protection screen
CN203834907U (en) Installation rack for non-scaffold elevator installation
CN217128915U (en) Hanging flower basket equipment rack
CN103225390A (en) Hollow facade pulley guide attached-type lifting scaffold

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant