CN106296456B - Intelligent substation secondary maintenance safety measure support system and construction method - Google Patents

Intelligent substation secondary maintenance safety measure support system and construction method Download PDF

Info

Publication number
CN106296456B
CN106296456B CN201610654677.6A CN201610654677A CN106296456B CN 106296456 B CN106296456 B CN 106296456B CN 201610654677 A CN201610654677 A CN 201610654677A CN 106296456 B CN106296456 B CN 106296456B
Authority
CN
China
Prior art keywords
secondary maintenance
maintenance safety
safety measure
measures standard
intelligent substation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610654677.6A
Other languages
Chinese (zh)
Other versions
CN106296456A (en
Inventor
朱维钧
刘海峰
陈宏�
徐宇新
潘伟
霍思敏
欧阳帆
李辉
敖非
许立强
梁文武
沈杨
臧欣
刘宇
徐浩
王优优
陈鑫
唐志翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG ROOF NEW INFORMATION TECHNOLOGY Co Ltd
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Original Assignee
SHANDONG ROOF NEW INFORMATION TECHNOLOGY Co Ltd
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG ROOF NEW INFORMATION TECHNOLOGY Co Ltd, State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd, State Grid Hunan Electric Power Co Ltd filed Critical SHANDONG ROOF NEW INFORMATION TECHNOLOGY Co Ltd
Priority to CN201610654677.6A priority Critical patent/CN106296456B/en
Publication of CN106296456A publication Critical patent/CN106296456A/en
Application granted granted Critical
Publication of CN106296456B publication Critical patent/CN106296456B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to technical field of power systems more particularly to a kind of intelligent substation secondary maintenance safety measure support systems and construction method.The present invention provides a kind of construction methods of intelligent substation secondary maintenance safety measure, comprising: step 1, the secondary maintenance safety measure implementation principle according to acquisition generate secondary maintenance safety Measures Standard database;Step 2 searches the secondary maintenance safety Measures Standard for obtaining and matching according to the column information carried in the secondary maintenance safety measure ticket of acquisition from standard database;Step 3 obtains the corresponding keyword of intelligent substation default operational factor, if judgement knows that keyword is present in secondary maintenance safety Measures Standard data, obtains manual control instruction;According to the secondary maintenance safety Measures Standard data of optimization, secondary maintenance safety measure is obtained.By above-mentioned construction method, service personnel can complete, intuitive and accurate positioning isolated subject and determine quarantine measures, work out it is high-efficient, workload is small.

Description

Intelligent substation secondary maintenance safety measure support system and construction method
Technical field
The present invention relates to technical field of power systems more particularly to a kind of intelligent substation secondary maintenance safety measure to support System and construction method, and in particular to a kind of establishment efficiency that can effectively improve intelligent substation secondary maintenance safety measure mentions Height maintenance integrity degree, the support system and construction method that operator's workload is greatly decreased simultaneously.
Background technique
Intelligent substation uses modern communications and digital modeling technique, and relatively conventional station has occurred on Form of Technique The variation of essence.For the influence of secondary maintenance safety measure, it is mainly reflected in secondary maintenance safety measure Operation object and the observability of secondary safety measure implementation effect basic change has occurred.Wherein, the change of operation object Change includes: 1, empty circuit instead of the hardwire in normal station;2, soft pressing plate is instead of original hard pressing plate;3, maintenance is introduced Pressing plate;The observability variation of implementation effect then includes: that 1, circuit is no longer intuitive;2, pressing plate and being associated with for circuit are no longer intuitive. Above-mentioned variation leads to the establishment of secondary maintenance safety measure, has the following problems in implementation procedure:
1) service personnel not only needs to be grasped station relevant knowledge, while needing to be familiar with IEC61850 correlation and knowing Know or even other professional knowledges, such as communication speciality, Automation Specialty, this to be familiar with the O&M service personnel of traditional substation with Carry out huge challenge, while also proposing new challenge to the reliability of secondary safety measure.
2) the maintenance regulation executed at present and the secondary maintenance safety measure implementation principle in operations specification or typical case two Secondary safety measure is all general rule, and technical staff is needed manually to convert thereof into a certain of some specific intelligent substation Secondary safety measure.Conversion work not only needs deep to understand compilation principles or typical secondary safety measure, it is also necessary to completely Understand that intelligent substation secondary model even device software logic, and workload more demanding to technical staff are huge.
3) device can operational capacity have differences because of the difference of manufacturer or device version, maintenance regulation and operation Implementation principle in specification or typical secondary safety measure and the reality of device can operational capacity there are unmatched situations, return Road and the invisible of soft pressing plate cause these non-matching phenomenons to be not easy to be found.
Summary of the invention
(1) technical problems to be solved
The object of the present invention is to provide a kind of establishment effects that can effectively improve intelligent substation secondary maintenance safety measure Rate, the support system and construction method for improving maintenance integrity degree, operator's workload being greatly decreased simultaneously, it is existing to solve Intelligent substation secondary maintenance is complete to the more demanding of service personnel, service personnel's heavy workload, establishment inefficient and maintenance Spend low problem.
(2) technical solution
In order to solve the above-mentioned technical problems, the present invention provides a kind of buildings of intelligent substation secondary maintenance safety measure Method comprising following operating procedure:
Step 1, the safety measure implementation principle for obtaining secondary maintenance generate secondary according to the safety measure implementation principle Maintenance safety Measures Standard database;
Step 2 obtains secondary maintenance safety measure ticket, is believed according to the column carried in the secondary maintenance safety measure ticket The secondary maintenance for searching from the secondary maintenance safety Measures Standard database and obtaining and matching with the column information is ceased to pacify Full Measures Standard data;
Step 3 obtains the corresponding keyword of the intelligent substation default operational factor, if the keyword is known in judgement It is present in the secondary maintenance safety Measures Standard data, then obtains manual control instruction, the manual control instruction is root It is generated according to the real-time running data of the intelligent substation;According to secondary maintenance safety described in the manual control optimization Measures Standard data, to obtain secondary maintenance safety measure.
Wherein, step 1 specifically includes:
Step 1.1 obtains pre-established classification chart, and the classification chart includes that multiple classification items and each classification item are corresponding Categorical data;
Step 1.2 classifies multiple secondary maintenance safety measure tickets according to the classification chart, obtains each secondary maintenance The type of safety measure ticket;
Circuit and operation object classification item are corresponding in step 1.3, the same type of secondary maintenance safety measure ticket of extraction Keyword, formalization processing is carried out to circuit and the corresponding keyword of operation object classification item according to default mapping ruler, Obtain secondary maintenance safety Measures Standard database.
Wherein, the column information includes the type of Awaiting Overhaul equipment, the mode of connection of the intelligent substation, Yi Jiyu The operation conditions of the associated primary equipment of Awaiting Overhaul equipment;
Correspondingly, described to be pacified according to the column information carried in the secondary maintenance safety measure ticket from the secondary maintenance The step for obtaining the secondary maintenance safety Measures Standard data to match with the column information is searched in full Measures Standard database Suddenly it specifically includes:
It is closed according to the type of the Awaiting Overhaul equipment, the mode of connection of the intelligent substation, and with Awaiting Overhaul equipment The primary equipment operation conditions of connection carries out instantiation processing to the predetermined keyword in conjunction with the default mapping ruler, with from The secondary maintenance safety Measures Standard data to match are obtained in the secondary maintenance safety Measures Standard database.
Wherein, the keyword includes: circuit, soft pressing plate and empty circuit;
Correspondingly, the judgement knows that the keyword is present in the secondary maintenance safety Measures Standard data, then The step of obtaining manual control instruction specifically includes:
If judgement knows that circuit and soft pressing plate in the secondary maintenance safety Measures Standard data exist in the intelligence Empty circuit in the SCD file of substation and in the SCD file exists in the secondary maintenance safety Measures Standard data, Obtain the manual control instruction.
Wherein, the maintenance safety Measures Standard data secondary according to the manual control optimization obtain two The step of secondary maintenance safety measure, specifically includes:
According to the increase/deletion control instruction carried in manual control instruction, increase/deletion secondary maintenance peace Full Measures Standard data;
Or,
According to the timing adjustment instruction carried in manual control instruction, the secondary maintenance safety Measures Standard is adjusted What data corresponded to step executes sequence, obtains secondary maintenance safety measure.
The present invention also provides a kind of intelligent substation secondary maintenance safety measure support systems comprising:
First module, for obtaining the safety measure implementation principle of secondary maintenance, according to the safety measure implementation principle Generate secondary maintenance safety Measures Standard database;
Second module is carried for obtaining secondary maintenance safety measure ticket according in the secondary maintenance safety measure ticket Column information searched from the secondary maintenance safety Measures Standard database obtain with the column information match two Secondary maintenance safety Measures Standard data;
Third module, for obtaining the corresponding keyword of the intelligent substation default operational factor, if institute is known in judgement It states keyword to be present in the secondary maintenance safety Measures Standard data, then obtains manual control instruction, the manual control Instruction is to be generated according to the real-time running data of the intelligent substation;It is secondary according to the manual control optimization Maintenance safety Measures Standard data, to obtain secondary maintenance safety measure.
Wherein, first module includes first processing units, the second processing unit and third processing unit:
The first processing units, for obtaining pre-established classification chart, the classification chart include multiple classification items and The corresponding categorical data of each classification item;
Described the second processing unit, for multiple secondary maintenance safety measure tickets to be classified according to the classification chart, Obtain the type of each secondary maintenance safety measure ticket;
The third processing unit extracts circuit and operation object classification in same type of secondary maintenance safety measure ticket The corresponding keyword of project carries out form to circuit and the corresponding keyword of operation object classification item according to default mapping ruler Change processing, obtains secondary maintenance safety Measures Standard database.
Wherein, the column information includes the type of Awaiting Overhaul equipment, the mode of connection of the intelligent substation, Yi Jiyu The operation conditions of the associated primary equipment of Awaiting Overhaul equipment;
Second module includes fourth processing unit, and the fourth processing unit is used for according to the Awaiting Overhaul equipment The mode of connection of type, the intelligent substation, and with the associated primary equipment operation conditions of Awaiting Overhaul equipment, in conjunction with described Default mapping ruler, carries out instantiation processing to the predetermined keyword, with from the secondary maintenance safety Measures Standard data The secondary maintenance safety Measures Standard data to match are obtained in library.
Wherein, the keyword includes: circuit, soft pressing plate and empty circuit;
The third module includes the 5th processing unit, if the 5th processing unit knows the secondary inspection for judging It repairs circuit in safety measure normal data and soft pressing plate exists in the SCD file of the intelligent substation and SCD text Empty circuit in part exists in the secondary maintenance safety Measures Standard data, obtains the manual control instruction.
Wherein, the third module further includes the 6th processing unit, and the 6th processing unit is used for according to described artificial The increase carried in control instruction/deletion control instruction, increase/deletion secondary maintenance safety Measures Standard data;
Or,
According to the timing adjustment instruction carried in manual control instruction, the secondary maintenance safety Measures Standard is adjusted What data corresponded to step executes sequence, obtains secondary maintenance safety measure.
(3) beneficial effect
Above-mentioned technical proposal of the invention has the advantages that the present invention provides a kind of maintenance of intelligent substation secondary to pacify The construction method of full measure, including following operating procedure: step 1, the safety measure implementation principle for obtaining secondary maintenance, according to peace Full measure implementation principle generates secondary maintenance safety Measures Standard database;Step 2 obtains secondary maintenance safety measure ticket, root Searched from secondary maintenance safety Measures Standard database according to the column information carried in secondary maintenance safety measure ticket acquisition with The secondary maintenance safety Measures Standard data that column information matches;Step 3, acquisition intelligent substation default operational factor are corresponding Keyword, if judgement know keyword exist in secondary maintenance safety Measures Standard data, obtain manual control instruction, Manual control instruction is to be generated according to the real-time running data of intelligent substation;According to the secondary maintenance of manual control optimization Safety measure normal data, to obtain secondary maintenance safety measure.Realization of the application by above-mentioned construction method, service personnel Can be in the reorganization and expansion of intelligent substation, O&M and maintenance process, complete, intuitive and accurate positioning isolated subject and determination Quarantine measures, the establishment efficiency of secondary safety measure not only can be improved in this, while workload can also be greatly decreased, at the scene work There is very strong universality and practicability in work.
Detailed description of the invention
Fig. 1 is a kind of concrete operations process of intelligent substation secondary maintenance safety measure construction method of the embodiment of the present invention Figure.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiments of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill people Member's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
As shown in Figure 1, the embodiment of the invention provides a kind of construction method of intelligent substation secondary maintenance safety measure, It includes following operating procedure:
Step 1, the safety measure implementation principle for obtaining secondary maintenance generate secondary maintenance according to safety measure implementation principle Safety measure standard database;In the present embodiment, the safety measure implementation principle of secondary maintenance includes maintenance regulation or operation Secondary maintenance safety measure implementation principle in regulation;And safety measure implementation principle is compiled as by computer by edit tool The secondary maintenance safety Measures Standard database that software can identify;
Step 2 obtains secondary maintenance safety measure ticket, according to the column information carried in secondary maintenance safety measure ticket from The secondary maintenance safety Measures Standard number for obtaining and matching with column information is searched in secondary maintenance safety Measures Standard database According to;Specifically, column information may include the mode of connection of the affiliated substation of equipment to be checked, the type of equipment to be checked, job category, Primary equipment blackout condition obtains the secondary maintenance safety Measures Standard data to match according to above-mentioned column information searching;
Step 3 obtains the corresponding keyword of intelligent substation default operational factor, if judgement knows that keyword exists two In secondary maintenance safety Measures Standard data, then manual control instruction is obtained, manual control instruction is according to the reality of intelligent substation When operation data generate;According to the secondary maintenance safety Measures Standard data of manual control optimization, to obtain secondary maintenance Safety measure.Wherein, optimization refers to being instructed according to manual control, graphically increases or delete secondary maintenance safety Measures Standard What data, the secondary maintenance safety Measures Standard data of adjustment corresponded to step executes sequence, when secondary maintenance safety Measures Standard number When according to needing to increase secondary safety measure newly, by manually being increased, finally realize that the secondary maintenance safety measure of all dimensions is complete Whole generation.
Specifically, the application is by the realization of above-mentioned construction method, service personnel can intelligent substation reorganization and expansion, In O&M and maintenance process, complete, intuitive and accurate positioning isolated subject and determining quarantine measures, this not only can be improved two The establishment efficiency of secondary safety measure, while workload can also be greatly decreased, work at the scene in there is very strong universality and reality The property used.
In the present embodiment, step 1 specifically includes:
Step 1.1 obtains pre-established classification chart, and classification chart includes multiple classification items and the corresponding class of each classification item Type data;Specifically, in the present embodiment, classification item includes device type, primary equipment scope of power outage and maintenance type etc.; Device type includes busbar protective device, line protective devices, main transformer protection, combining unit, intelligent terminal, prepared auto restart etc.;One Secondary device scope of power outage includes that whole station has a power failure, voltage class has a power failure, interval has a power failure, do not have a power failure;Overhauling type includes first inspection, routine Test, defect elimination upgrading;
Step 1.2 classifies multiple secondary maintenance safety measure tickets according to classification chart, obtains each secondary maintenance safety The type of measure ticket;Table 1 is by taking route protection in the 220kV substation of double female modes of connection as an example, and classification chart is as follows:
Route protection classification chart in 1 220kV substation of table
Circuit and operation object classification item are corresponding in step 1.3, the same type of secondary maintenance safety measure ticket of extraction Keyword, formalization processing is carried out to circuit and the corresponding keyword of operation object classification item according to default mapping ruler, Obtain secondary maintenance safety Measures Standard database.In the present embodiment, with route in the 220kV substation of double female modes of connection For protecting the first inspection work when line segregation has a power failure, the pass of secondary maintenance exemplary secure measure ticket PL-BAYPF-FM is extracted Key word (is only listed and opens failure circuit), specific as shown in table 2:
The keyword of table 2 two times maintenance exemplary secure measure ticket PL-BAYPF-FM
Wherein, circuit form turns to: [space from start type] [starting type of device] to [purpose interval type] [purpose dress Set type] for [loop-type].By taking the 220kV substation of double female modes of connection as an example, the starting of route protection to bus protection Failure circuit form turns to: [LINE] [PRO] to [BUS] [PRO] for [STARTFAILURE];Safety measure formalization are as follows: [action type] [operating interval] [operating device] [operation object].
Default mapping ruler: according to national standard " IEC61850 relay protection engineer application model specification " to virtual terminator and The semanteme of soft pressing plate defines the search rule of empty circuit and soft pressing plate;And for use general semantics (such as: logical node for GGIO, DO SPCS) the empty circuit that defines and soft pressing plate, its search rule is defined using the fuzzy match mode of desc.This reality Example is applied by taking the 220kV substation of double female modes of connection as an example, the start failure protection circuit of route protection to bus protection can be established such as Lower search rule, specific as shown in table 3:
The start failure protection loop map of 3 route protection of table to bus protection is regular
Specifically, in the present embodiment, column information includes the wiring side of the type of Awaiting Overhaul equipment, intelligent substation Formula, and the operation conditions with the associated primary equipment of Awaiting Overhaul equipment;Correspondingly, it is taken according in secondary maintenance safety measure ticket The column information of band searches the secondary maintenance for obtaining and matching with column information from secondary maintenance safety Measures Standard database The step of safety measure normal data, specifically includes: according to the type of Awaiting Overhaul equipment, the mode of connection of intelligent substation, and Predetermined keyword is carried out at instantiation in conjunction with default mapping ruler with the associated primary equipment operation conditions of Awaiting Overhaul equipment Reason, to obtain the secondary maintenance safety Measures Standard data to match from secondary maintenance safety Measures Standard database.
Specifically, the corresponding keyword of intelligent substation default operational factor includes: circuit, soft pressing plate and empty circuit;Phase The step of Ying Di, judgement knows that keyword exists in secondary maintenance safety Measures Standard data, then obtains manual control instruction It specifically includes: if judgement knows that circuit and soft pressing plate in secondary maintenance safety Measures Standard data exist in intelligent substation Empty circuit in SCD file and in SCD file exists in secondary maintenance safety Measures Standard data, obtains manual control and refers to It enables, wherein manual control instruction is to be generated according to the real-time running data of intelligent substation.
Wherein, it according to the secondary maintenance safety Measures Standard data of manual control optimization, obtains secondary maintenance safety and arranges The step of applying specifically includes: according to manual control instruct in increase/deletion control instruction for carrying, the secondary maintenance of increase/deletion Safety measure normal data;Or, according to manual control instruct in the timing adjustment instruction that carries, adjust secondary maintenance safety measure What normal data corresponded to step executes sequence, obtains secondary maintenance safety measure.Specifically, in the present embodiment, secondary maintenance The optimization of safety measure normal data is broadly divided into two parts, i.e. integrity check and timing is checked.
Integrity check is in two kinds of situation: circuit present in first and second safety measure ticket or soft pressing plate are in SCD file In cannot find.Two, void circuit present in SCD file is not present in secondary safety measure ticket.For both of these case point Prompt is not provided, with checking on site.
Timing refer to violate secondary equipment of intelligent converting station relay protective scheme, trouble free service regulation etc. specification, require Operation order.When timing mistake occurs in secondary safety measure, provides alarm prompt and manually adjusted.
In the present embodiment, all secondary devices are parsed from the SCD file in intelligent substation first;Secondly it selects Equipment to be checked is selected, according to the mode of connection of the affiliated substation of equipment to be checked, the type of equipment to be checked, job category, primary equipment It is corresponding and through formalization treated secondary maintenance safety measure ticket to find out this maintenance for blackout condition;Furthermore according to through shape Optical fiber, maintenance pressing plate, secondary circuit in formulaization treated secondary maintenance safety measure the ticket keywords such as in flakes, carry out example Change processing, obtains: " extracting on XXXX line protective devices, the straight daylighting for connecting XXXX route combining unit is fine " or " by XXXX The maintenance pressing plate of route is set point " pattern;Furthermore according to the lookup of above-mentioned keyword and empty circuit, soft pressing plate in SCD file Mapping ruler, and then empty circuit and soft pressing plate are subjected to instantiation processing;Finally, prompt to uninstantiated successful empty circuit and Soft pressing plate is adjusted and is checked according to real time data progress integrality and timing, and according to circuit corresponding optical fiber (typical ticket Middle description), provide back-up safety measure;Wherein, for the describing mode of secondary safety measure can not be changed, such as: using and " extract On XX line protective devices, the straight daylighting for connecting XX route combining unit is fine " substitution is " on extraction line protective devices port x X Optical fiber ", can be by control terminal automatically by the secondary safety measure instantiation (only needing to instantiate in device) in this part, to guarantee The integrality of secondary safety measure.
The present invention also provides a kind of intelligent substation secondary maintenance safety measure support systems comprising:
First module is generated for obtaining the safety measure implementation principle of secondary maintenance according to safety measure implementation principle Secondary maintenance safety Measures Standard database;Wherein, the safety measure implementation principle of secondary maintenance includes maintenance regulation or operation Secondary maintenance safety measure implementation principle in regulation;
Second module, for obtaining secondary maintenance safety measure ticket, according to the column carried in secondary maintenance safety measure ticket Mesh information is searched acquisition from secondary maintenance safety Measures Standard database and is arranged with the secondary maintenance safety that column information matches Apply normal data;
Wherein, matching way includes two kinds of situations:
It is excavated based on the depth to grammatical and semantic in the SCD file model in intelligent substation and is described based on isolated subject Method of Fuzzy Matching, take empty circuit, soft pressing plate, physical port Auto-matching mode, realize non-object in secondary safety measure Manage the automatic identification and isolation of isolated subject;
The secondary device information supplement alternative solution of non-standard model or missing.According to state's net icd standard library and general set Meter standard, model nonstandard in SCD file or missing information itself are supplemented it is complete, model that part of standards is not directed to and circuit according to According to relationship, the relationship of function pressing plate and defencive function of soft pressing plate and empty circuit, secondary safety measure instantiation degree is reduced To device level, to realize that the secondary maintenance safety measure of all dimensions completely generates.
Third module, for obtaining the corresponding keyword of intelligent substation default operational factor, if keyword is known in judgement In the presence of manual control instruction in secondary maintenance safety Measures Standard data, is then obtained, manual control instruction is according to intelligent change What the real-time running data in power station generated;According to the secondary maintenance safety Measures Standard data of manual control optimization, to obtain Secondary maintenance safety measure.Wherein, optimization refers to being instructed according to manual control, graphically increases or delete secondary maintenance safety What Measures Standard data, the secondary maintenance safety Measures Standard data of adjustment corresponded to step executes sequence, when secondary maintenance safety is arranged When applying normal data and needing to increase secondary safety measure newly, by manually being increased, the secondary maintenance peace of all dimensions is finally realized Full measure completely generates.
Specifically, in the present embodiment, the first module includes that first processing units, the second processing unit and third processing are single Member:
First processing units, for obtaining pre-established classification chart, classification chart includes multiple classification items and each sorting item The corresponding categorical data of mesh;Wherein, classification item includes device type, primary equipment scope of power outage and maintenance type etc.;Equipment Type includes busbar protective device, line protective devices, main transformer protection, combining unit, intelligent terminal, prepared auto restart etc.;Once set Standby scope of power outage includes that whole station has a power failure, voltage class has a power failure, interval has a power failure, do not have a power failure;Overhauling type includes first inspection, customary examination It tests, defect elimination upgrading;
The second processing unit obtains each two for multiple secondary maintenance safety measure tickets to be classified according to classification chart The type of secondary maintenance safety measure ticket;
Third processing unit extracts circuit and operation object classification item in same type of secondary maintenance safety measure ticket Corresponding keyword carries out at formalization circuit and the corresponding keyword of operation object classification item according to default mapping ruler Reason, obtains secondary maintenance safety Measures Standard database.
Wherein, column information includes the type of Awaiting Overhaul equipment, the mode of connection of intelligent substation, and is set with Awaiting Overhaul The operation conditions of standby associated primary equipment;
Specifically, the second module includes fourth processing unit, fourth processing unit be used for the type according to Awaiting Overhaul equipment, The mode of connection of intelligent substation, and with the associated primary equipment operation conditions of Awaiting Overhaul equipment, in conjunction with default mapping ruler, Instantiation processing is carried out to predetermined keyword, to obtain the secondary inspection to match from secondary maintenance safety Measures Standard database Repair safety measure normal data.
Wherein, keyword includes: circuit, soft pressing plate and empty circuit;
Third module includes the 5th processing unit, if the 5th processing unit knows secondary maintenance safety measure mark for judging There is the empty circuit in the SCD file of intelligent substation and in SCD file and exist two in circuit and soft pressing plate in quasi- data In secondary maintenance safety Measures Standard data, manual control instruction is obtained.
Further, third module further includes the 6th processing unit, and the 6th processing unit according to manual control for instructing The increase of middle carrying/deletion control instruction, the secondary maintenance safety Measures Standard data of increase/deletion;Or, being referred to according to manual control The timing adjustment instruction carried in order adjusts the sequence that executes that secondary maintenance safety Measures Standard data correspond to step, obtains two Secondary maintenance safety measure.Wherein, or refer to that increase/deletion control instruction and timing adjustment instruction both respectively can be carried out independently, It can also carry out simultaneously, corresponding adjustment instruction is selected according to specific implementation principle condition.
In conclusion the present invention provides a kind of construction methods of intelligent substation secondary maintenance safety measure, including such as Lower operating procedure: step 1, the safety measure implementation principle for obtaining secondary maintenance generate secondary according to safety measure implementation principle Maintenance safety Measures Standard database;Step 2 obtains secondary maintenance safety measure ticket, according in secondary maintenance safety measure ticket The column information of carrying searches the secondary inspection for obtaining and matching with column information from secondary maintenance safety Measures Standard database Repair safety measure normal data;Step 3 obtains the corresponding keyword of intelligent substation default operational factor, if pass is known in judgement Keyword exists in secondary maintenance safety Measures Standard data, then obtains manual control instruction, manual control instruction is according to intelligence What the real-time running data of energy substation generated;According to the secondary maintenance safety Measures Standard data of manual control optimization, with Obtain secondary maintenance safety measure.For the application by the realization of above-mentioned construction method, service personnel can be in intelligent substation In reorganization and expansion, O&M and maintenance process, complete, intuitive and accurate positioning isolated subject and quarantine measures are determined, this not only can be with Improve the establishment efficiency of secondary safety measure, while workload can also be greatly decreased, work at the scene in have it is very strong pervasive Property and practicability.
Finally, it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although Present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: it still may be used To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features; And these are modified or replaceed, technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution spirit and Range.

Claims (8)

1. a kind of construction method of intelligent substation secondary maintenance safety measure, which is characterized in that including following operating procedure:
Step 1, the safety measure implementation principle for obtaining secondary maintenance generate secondary maintenance according to the safety measure implementation principle Safety measure standard database;
Step 2 obtains secondary maintenance safety measure ticket, according to the column information carried in the secondary maintenance safety measure ticket from The secondary maintenance safety for obtaining and matching with the column information is searched in the secondary maintenance safety Measures Standard database to arrange Apply normal data;
Step 3 obtains the corresponding keyword of the intelligent substation default operational factor, if judgement knows that the keyword exists In the secondary maintenance safety Measures Standard data, then manual control instruction is obtained, the manual control instruction is according to institute State the real-time running data generation of intelligent substation;The secondary maintenance safety measure according to the manual control optimization Normal data, to obtain secondary maintenance safety measure;
Wherein, step 1 specifically includes:
Step 1.1 obtains pre-established classification chart, and the classification chart includes multiple classification items and the corresponding class of each classification item Type data;
Step 1.2 classifies multiple secondary maintenance safety measure tickets according to the classification chart, obtains each secondary maintenance safety The type of measure ticket;
Step 1.3 extracts circuit and the corresponding pass of operation object classification item in same type of secondary maintenance safety measure ticket Key word carries out formalization processing to circuit and the corresponding keyword of operation object classification item according to default mapping ruler, obtains Secondary maintenance safety Measures Standard database.
2. method according to claim 1, which is characterized in that the column information includes the type, described of Awaiting Overhaul equipment The mode of connection of intelligent substation, and the operation conditions with the associated primary equipment of Awaiting Overhaul equipment;
Correspondingly, described to be arranged according to the column information carried in the secondary maintenance safety measure ticket from the secondary maintenance safety It applies and searches the step of obtaining the secondary maintenance safety Measures Standard data to match with the column information tool in standard database Body includes:
According to the type of the Awaiting Overhaul equipment, the mode of connection of the intelligent substation, and it is associated with Awaiting Overhaul equipment Primary equipment operation conditions carries out instantiation processing to predetermined keyword in conjunction with the default mapping ruler, with from described secondary The secondary maintenance safety Measures Standard data to match are obtained in maintenance safety Measures Standard database.
3. method according to claim 1, which is characterized in that the keyword includes: circuit, soft pressing plate and empty circuit;
Correspondingly, the judgement knows that the keyword is present in the secondary maintenance safety Measures Standard data, then obtains The step of manual control instructs specifically includes:
If judgement knows that circuit and soft pressing plate in the secondary maintenance safety Measures Standard data exist in the intelligent power transformation Empty circuit in the SCD file stood and in the SCD file exists in the secondary maintenance safety Measures Standard data, obtains The manual control instruction.
4. method according to claim 1, which is characterized in that the secondary inspection according to the manual control optimization The step of repairing safety measure normal data, obtaining secondary maintenance safety measure specifically includes:
According to the increase/deletion control instruction carried in manual control instruction, increase/deletion secondary maintenance safety is arranged Apply normal data;
Or,
According to the timing adjustment instruction carried in manual control instruction, the secondary maintenance safety Measures Standard data are adjusted Corresponding step executes sequence, obtains secondary maintenance safety measure.
5. a kind of intelligent substation secondary maintenance safety measure support system characterized by comprising
First module is generated for obtaining the safety measure implementation principle of secondary maintenance according to the safety measure implementation principle Secondary maintenance safety Measures Standard database;
Second module, for obtaining secondary maintenance safety measure ticket, according to the column carried in the secondary maintenance safety measure ticket Mesh information searches the secondary inspection for obtaining and matching with the column information from the secondary maintenance safety Measures Standard database Repair safety measure normal data;
Third module, for obtaining the corresponding keyword of the intelligent substation default operational factor, if the pass is known in judgement Keyword is present in the secondary maintenance safety Measures Standard data, then obtains manual control instruction, the manual control instruction For what is generated according to the real-time running data of the intelligent substation;According to secondary maintenance described in the manual control optimization Safety measure normal data, to obtain secondary maintenance safety measure;
Wherein, first module includes first processing units, the second processing unit and third processing unit:
The first processing units, for obtaining pre-established classification chart, the classification chart includes multiple classification items and each point The corresponding categorical data of intermediate item;
Described the second processing unit is obtained for multiple secondary maintenance safety measure tickets to be classified according to the classification chart The type of each secondary maintenance safety measure ticket;
The third processing unit extracts circuit and operation object classification item in same type of secondary maintenance safety measure ticket Corresponding keyword carries out at formalization circuit and the corresponding keyword of operation object classification item according to default mapping ruler Reason, obtains secondary maintenance safety Measures Standard database.
6. system according to claim 5, which is characterized in that the column information includes the type, described of Awaiting Overhaul equipment The mode of connection of intelligent substation, and the operation conditions with the associated primary equipment of Awaiting Overhaul equipment;
Second module includes fourth processing unit, and the fourth processing unit is used for the class according to the Awaiting Overhaul equipment The mode of connection of type, the intelligent substation, and with the associated primary equipment operation conditions of Awaiting Overhaul equipment, in conjunction with described pre- If mapping ruler, instantiation processing is carried out to predetermined keyword, to obtain from the secondary maintenance safety Measures Standard database Take the secondary maintenance safety Measures Standard data to match.
7. system according to claim 5, which is characterized in that the keyword includes: circuit, soft pressing plate and empty circuit;
The third module includes the 5th processing unit, if the 5th processing unit knows the secondary maintenance peace for judging Circuit and soft pressing plate in full Measures Standard data exist in the SCD file of the intelligent substation and in the SCD file Empty circuit exist in the secondary maintenance safety Measures Standard data, obtain manual control instruction.
8. system according to claim 5, which is characterized in that the third module further includes the 6th processing unit, and described Six processing units are used for according to the increase/deletion control instruction carried in manual control instruction, and increase/deletion is described secondary Maintenance safety Measures Standard data;
Or,
According to the timing adjustment instruction carried in manual control instruction, the secondary maintenance safety Measures Standard data are adjusted Corresponding step executes sequence, obtains secondary maintenance safety measure.
CN201610654677.6A 2016-08-10 2016-08-10 Intelligent substation secondary maintenance safety measure support system and construction method Active CN106296456B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610654677.6A CN106296456B (en) 2016-08-10 2016-08-10 Intelligent substation secondary maintenance safety measure support system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610654677.6A CN106296456B (en) 2016-08-10 2016-08-10 Intelligent substation secondary maintenance safety measure support system and construction method

Publications (2)

Publication Number Publication Date
CN106296456A CN106296456A (en) 2017-01-04
CN106296456B true CN106296456B (en) 2019-05-24

Family

ID=57669612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610654677.6A Active CN106296456B (en) 2016-08-10 2016-08-10 Intelligent substation secondary maintenance safety measure support system and construction method

Country Status (1)

Country Link
CN (1) CN106296456B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107133883A (en) * 2017-04-28 2017-09-05 国网黑龙江省电力有限公司电力科学研究院 Based on the intelligent substation safety measure automatic generation method and device that safety measure is semantic
CN107153946A (en) * 2017-04-28 2017-09-12 国家电网公司 Intelligent station is secondary to pacify automatic generation method and the system of arranging
CN107563520A (en) * 2017-07-26 2018-01-09 国网安徽省电力公司 A kind of intelligent substation secondary safety measure method for visualizing
CN110930122A (en) * 2019-11-29 2020-03-27 国网宁夏电力有限公司检修公司 Method for executing and testing automatic safety measures of relay protection of intelligent station

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2203754B1 (en) * 2007-10-25 2017-09-27 ABB Research Ltd. Operating a substation automation system
CN103729805A (en) * 2014-01-04 2014-04-16 国家电网公司 500kV intelligent substation security arrangement ticket expert system
CN105429027B (en) * 2015-11-12 2017-08-18 国网宁夏电力公司 Secondary safety measure supports system and construction method in the maintenance of intelligent substation O&M
CN105490387B (en) * 2015-12-29 2018-02-02 武汉凯默电气有限公司 The online capacity checking device of intelligent substation relay protection device safety measure and method

Also Published As

Publication number Publication date
CN106296456A (en) 2017-01-04

Similar Documents

Publication Publication Date Title
CN106296456B (en) Intelligent substation secondary maintenance safety measure support system and construction method
CN103218398B (en) Intelligent substation SCL (substation configuration description language) file difference comparison method
CN107045663B (en) Visual online checking system and method for secondary safety measure operation ticket
CN108549650B (en) Intelligent substation anti-misoperation lockout logic rule source end configuration method and system
CN110674282B (en) Expert knowledge rule base-based one-key sequential control operation order intelligent simulation method
CN108241771A (en) Secondary device modeling method based on electromagnetic transient simulation platform
CN107153946A (en) Intelligent station is secondary to pacify automatic generation method and the system of arranging
CN106600457B (en) Microcomputer five-prevention main wiring diagram analysis system of transformer substation
CN103730894B (en) EMS image checking mehtod and device
CN110059402A (en) A kind of intelligent substation method for optimizing configuration based on semantic modeling
CN106355305A (en) Decoupling method and device for smart substation SCD model information section
CN108490282B (en) Method and system for presetting alarm test data of intelligent substation
CN104091289A (en) Large-scale power distribution network N-1 rapid verification method based on wiring mode rules
CN107067081A (en) Substation secondary maintenance safety measure generation method based on many object models
CN115599750A (en) Intelligent substation virtual circuit checking method, system, equipment and storage medium
CN111832977A (en) Maintenance application automatic ticketing method based on natural language parsing
CN111708817A (en) Intelligent disposal method for transformer substation monitoring information
CN103529709B (en) Electric power system fault Union Switch Device model implementation method and system thereof
CN113095059B (en) Method, device, equipment and storage medium for verifying substation configuration description file
CN107871176A (en) The safety-optimized method and system of secondary device applied to IEC61850 information modelings
CN103001318B (en) A kind of based on 61850 the anti-implementation method of intelligent transformer substation topology five
CN108304947A (en) The safety-optimized method and system of secondary device based on SCD file object model
CN107871030B (en) Substation secondary maintenance safety measure generation method based on SCD file object model
CN114692245A (en) Fuzzy recognition-based automatic connection method for virtual terminal logic loop
CN107871168A (en) Intelligent substation secondary maintenance safety measure generation method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant