CN106223151A - Severe cold area large area wing square stone material is mated formation prevention and cure of crack method - Google Patents

Severe cold area large area wing square stone material is mated formation prevention and cure of crack method Download PDF

Info

Publication number
CN106223151A
CN106223151A CN201610581952.6A CN201610581952A CN106223151A CN 106223151 A CN106223151 A CN 106223151A CN 201610581952 A CN201610581952 A CN 201610581952A CN 106223151 A CN106223151 A CN 106223151A
Authority
CN
China
Prior art keywords
expansion joint
concrete
stone material
joint
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610581952.6A
Other languages
Chinese (zh)
Other versions
CN106223151B (en
Inventor
宋陈明
李�杰
钱跃东
陈超
陈栋梁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Bajian Construction Group Co Ltd
Original Assignee
Nantong Bajian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Bajian Construction Group Co Ltd filed Critical Nantong Bajian Construction Group Co Ltd
Priority to CN201610581952.6A priority Critical patent/CN106223151B/en
Priority to CN201810272525.9A priority patent/CN108486978A/en
Priority to CN201810271448.5A priority patent/CN108396607A/en
Publication of CN106223151A publication Critical patent/CN106223151A/en
Application granted granted Critical
Publication of CN106223151B publication Critical patent/CN106223151B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/02Pavings made of prefabricated single units made of natural stones, e.g. sett stones
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C2201/00Paving elements
    • E01C2201/06Sets of paving elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • Road Repair (AREA)

Abstract

The invention discloses a kind of large area wing square, severe cold area stone material to mat formation prevention and cure of crack method, determine including granite face typesetting and expansion joint position, the step such as substrate concrete construction, the construction of surface layer paving control line, granite face are mated formation, filleting.Easy construction of the present invention, effective.Save maintenance cost.

Description

Severe cold area large area wing square stone material is mated formation prevention and cure of crack method
Technical field
The present invention relates to a kind of large area wing square, severe cold area stone material mat formation prevention and cure of crack method.
Background technology
The severe cold area winter summer temperature difference reaches to spend 100 more, and the square stone material surface layer that some have built up, due to summer in winter huge temperature Difference deformation, by drawing crack, breaks, have impact on the use on square, how to prevent the generation of wing square stone material top-crack, be one Important topic.
Summary of the invention
It is an object of the invention to provide a kind of easy construction, effective severe cold area large area wing square stone material paving Dress prevention and cure of crack method.
The technical solution of the present invention is:
A kind of large area wing square, severe cold area stone material is mated formation prevention and cure of crack method, it is characterized in that: comprise the following steps:
(1) granite face typesetting, expansion joint position determine
Use cad technique to carry out row's plate of granite face abnormity slabstone, determine between size and the stone material of every block of trapezoidal stone material Gap size, it is ensured that effect of mating formation, adjusts substrate concrete expansion joint (E.J.) spacing simultaneously in the range of 15~20m, adjusts in the range of 3~4m Integral basis layer concrete contracting kerf spacing, it is ensured that substrate concrete expansion joint (E.J.) is corresponding with facing expansion joint position with the position of contracting seam;Root Determining every piece of trapezoidal stone material size according to desk-top publishing figure, factory process is also numbered, and prevents on-the-spot with mixed;
(2) substrate concrete construction
Substrate concrete thickness is 200, uses C25 commerical ready-mixed concrete, and ground transport pump, Manual, machinery vibrate, three roll shafts Evener leveling, grooving machine joint-cutting;
Construction technology: inspection basic unit → surveying setting-out → installation form → concrete pumping → pave → flatten → plucking that vibrates → Joint-cutting → health preserving;
Substrate concrete construction formwork uses the channel-section steel that rigidity is enough, and side sets stayed mast and inserts hole;The height of steel form is base Layer concrete design thickness, template length is 3~5m, supporting adn fixing device at every meter of template-setup 1, mold plate verticality chock Wedge method adjusts, and construction joint indwelling is at expansion joint (E.J.);
According to predetermined stretching, contract seam position, when xoncrete structure base layer construction, first bury upper 25 thickness according to expansion joint (E.J.) position Soaking the Pinus koraiensis expansion joint plate of Colophonium, centre sets Φ 16mm dowel steel, spacing 200;
When concrete is unhardened, reject the concrete on expansion joint plate top, embed the batten of 20 × 20, flattened faces, expansion joint (E.J.) Plate should continuous through whole substrate concrete, expansion joint plate is vertical with Lu Zhizheng line, and slotted wall is vertical;
Dowel steel employing Φ 16mm reinforcing bar, spacing 200, a length of 700, the surface of more than half length should be coated with anti-stick Layer, end should be worn movable cap bag, be overlapped cap material and use Φ 20mm plastic tube, end employing asphalt felt to seal blocking, dowel steel steel Muscle processing should be sawed-off, cut-out must not be extruded, fracture should vertically, light justify, fall burr with grinder buffing, and be processed into 2~3 roundings Angle;
All vertical, horizontal contracting seam all uses the construction of joint-cutting method, and the joint-cutting degree of depth is 6, and width is 10, first arrives with thin saw blade sawing Require the degree of depth, re-use 6~8 thick saw blades or overlapping saw blade widens joint filling groove;
With the covering wet curing such as gunnysack, straw screen or mat and sprinkle water in time, keep concrete surface to be in dampness, basic unit all the time At the concrete curing initial stage, forbidding pedestrian, vehicle pass-through, after reaching design strength 40%, pedestrian can pass through;
(3) surface layer paving control line construction
According to stone material surface layer every block of trapezoidal stone material of CAD typesetting figure and gap size, every section of circle and the center of circle of circular arc, use total powerstation Orient the radial direction control line of each every block of stone material of section, use chord off-set method to survey the broadwise control line setting every block of stone material, and By the radial direction of every block of trapezoidal stone material and broadwise control line line of ink marker bullet on concrete base layer, as depending on of every piece of stone material paving According to;
(4) granite face is mated formation
Granite panel of mating formation is 40 thick fired slab floor file, and on C25 concrete base layer, first brush plain-water slurry one time, then adopts With 20 thick 1:2.5 cement mortar screedings, panel and basic unit use 50 thick 1:2.5 dry cement mortar binder courses, fired slab 5 thick plain-water slurry tack coats are scraped in bottom surface;
Granite face all stays at substrate concrete expansion joint (E.J.) and expansion joint and sets 10 wide expansion joints;
Using and expansion joint plate equal thickness when surface layer is mated formation, height is embedded at expansion joint plate with the batten of binder course uniform thickness of mating formation, With paving with dragging, it is ensured that without mortar between expansion joint plate and surface layer, gap-filling glue after having mated formation, is used to fill up;
(5) filleting
Expansion joint of mating formation uses PVC cement, first uses grooving machine to remove in seam sandstone, the mortar etc. of condensation being mingled with, Re-use the pressure press water more than 0.5Mpa and compressed air thoroughly removes the dust in seam and other pollutant, it is ensured that seam Wall and cleaning inside, it is dried.Slotted wall is checked can not wipe dust for cementation of fissures standard;
Crack pouring depth is at 15~20 mm, and the most shallow 15 mm that cannot be less than, first extruding embeds diameter 9~12 mm sponge plastics Backing strip, then cementation of fissures cementation of fissures end face should flush with plate face;Necessary full, uniform, the consistency of thickness of joint filling is the most through, joint sealing material Must not lack, ftracture and seep water
Stone material surface layer except expansion joint is with in addition to PVC cement filleting, other all gaps the most not filletings, drop in gap The foreign material such as cement mortar to clean out.
Easy construction of the present invention, effective.Save maintenance cost.
Below in conjunction with embodiment, the invention will be further described.
Detailed description of the invention
A kind of large area wing square, severe cold area stone material is mated formation prevention and cure of crack method, comprises the following steps:
(1) granite face typesetting, expansion joint position determine
Use cad technique to carry out row's plate of granite face abnormity slabstone, determine between size and the stone material of every block of trapezoidal stone material Gap size, it is ensured that effect of mating formation, simultaneously at 15~20m(examples 10m, 15m, 20m) in the range of adjust between substrate concrete expansion joint (E.J.) Away from, 3~4m(examples 3m, 3.5m, 4m) in the range of adjust substrate concrete contracting kerf spacing, it is ensured that substrate concrete expansion joint (E.J.) and contracting stitch Position is corresponding with facing expansion joint position;Determining every piece of trapezoidal stone material size according to desk-top publishing figure, factory process is also numbered, Prevent on-the-spot with mixed;
(2) substrate concrete construction
Substrate concrete thickness is 200, uses C25 commerical ready-mixed concrete, and ground transport pump, Manual, machinery vibrate, three roll shafts Evener leveling, grooving machine joint-cutting;
Construction technology: inspection basic unit → surveying setting-out → installation form → concrete pumping → pave → flatten → plucking that vibrates → Joint-cutting → health preserving;
Substrate concrete construction formwork uses the channel-section steel that rigidity is enough, and side sets stayed mast and inserts hole;The height of steel form is base Layer concrete design thickness, template length is 3~5m, supporting adn fixing device at every meter of template-setup 1, mold plate verticality chock Wedge method adjusts, and construction joint indwelling is at expansion joint (E.J.);
According to predetermined stretching, contract seam position, when xoncrete structure base layer construction, according to expansion joint (E.J.) position first bury upper 25 or 29mm thickness soaked the Pinus koraiensis expansion joint plate of Colophonium, and centre sets Φ 16mm dowel steel, spacing 200;
When concrete is unhardened, reject the concrete on expansion joint plate top, embed the batten of 20 × 20 (or 22 × 22mm), whole Flat surface, expansion joint plate should continuous through whole substrate concrete, expansion joint plate is vertical with Lu Zhizheng line, and slotted wall is vertical;
Dowel steel employing Φ 16mm reinforcing bar, spacing 200, a length of 700, the surface of more than half length should be coated with anti-stick Layer, end should be worn movable cap bag, be overlapped cap material and use Φ 20mm plastic tube, end employing asphalt felt to seal blocking, dowel steel steel Muscle processing should be sawed-off, cut-out must not be extruded, fracture should vertically, light justify, fall burr with grinder buffing, and be processed into 2~3 (examples 2mm, 2.5mm, 3mm) rounding;
All vertical, horizontal contracting seam all uses the construction of joint-cutting method, and the joint-cutting degree of depth is 6, and width is 10, first arrives with thin saw blade sawing Require the degree of depth, re-use 6~8 (example 6mm, 7mm, 8mm) thick saw blade or overlapping saw blade widens joint filling groove;
With the covering wet curing such as gunnysack, straw screen or mat and sprinkle water in time, keep concrete surface to be in dampness, basic unit all the time At the concrete curing initial stage, forbidding pedestrian, vehicle pass-through, after reaching design strength 40%, pedestrian can pass through;
(3) surface layer paving control line construction
According to stone material surface layer every block of trapezoidal stone material of CAD typesetting figure and gap size, every section of circle and the center of circle of circular arc, use total powerstation Orient the radial direction control line of each every block of stone material of section, use chord off-set method to survey the broadwise control line setting every block of stone material, and By the radial direction of every block of trapezoidal stone material and broadwise control line line of ink marker bullet on concrete base layer, as depending on of every piece of stone material paving According to;
(4) granite face is mated formation
Granite panel of mating formation is 40 thick fired slab floor file, and on C25 concrete base layer, first brush plain-water slurry one time, then adopts With 20 thick 1:2.5 cement mortar screedings, panel and basic unit use 50 thick 1:2.5 dry cement mortar binder courses, fired slab 5 thick plain-water slurry tack coats are scraped in bottom surface;
Granite face all stays at substrate concrete expansion joint (E.J.) and expansion joint and sets 10 wide expansion joints;
Using and expansion joint plate equal thickness when surface layer is mated formation, height is embedded at expansion joint plate with the batten of binder course uniform thickness of mating formation, With paving with dragging, it is ensured that without mortar between expansion joint plate and surface layer, gap-filling glue after having mated formation, is used to fill up;
(5) filleting
Expansion joint of mating formation uses PVC cement, first uses grooving machine to remove in seam sandstone, the mortar etc. of condensation being mingled with, Re-use the pressure press water more than 0.5Mpa and compressed air thoroughly removes the dust in seam and other pollutant, it is ensured that seam Wall and cleaning inside, it is dried.Slotted wall is checked can not wipe dust for cementation of fissures standard;
Crack pouring depth is at 15~20 mm(examples 15mm, 18mm, 20mm), the most shallow 15 mm that cannot be less than, first extruding embed diameter 9~ 12 mm(examples 9mm, 10mm, 12mm) sponge plastics backing strip, then cementation of fissures cementation of fissures end face should flush with plate face;Joint filling is necessary Full, uniform, consistency of thickness is the most through, and joint sealing material must not lack, ftractures and seep water
Stone material surface layer except expansion joint is with in addition to PVC cement filleting, other all gaps the most not filletings, drop in gap The foreign material such as cement mortar to clean out.

Claims (1)

1. severe cold area large area wing square stone material is mated formation a prevention and cure of crack method, it is characterized in that: comprise the following steps:
(1) granite face typesetting, expansion joint position determine
Use cad technique to carry out row's plate of granite face abnormity slabstone, determine between size and the stone material of every block of trapezoidal stone material Gap size, it is ensured that effect of mating formation, adjusts substrate concrete expansion joint (E.J.) spacing simultaneously in the range of 15~20m, adjusts in the range of 3~4m Integral basis layer concrete contracting kerf spacing, it is ensured that substrate concrete expansion joint (E.J.) is corresponding with facing expansion joint position with the position of contracting seam;Root Determining every piece of trapezoidal stone material size according to desk-top publishing figure, factory process is also numbered, and prevents on-the-spot with mixed;
(2) substrate concrete construction
Substrate concrete thickness is 200, uses C25 commerical ready-mixed concrete, and ground transport pump, Manual, machinery vibrate, three roll shafts Evener leveling, grooving machine joint-cutting;
Construction technology: inspection basic unit → surveying setting-out → installation form → concrete pumping → pave → flatten → plucking that vibrates → Joint-cutting → health preserving;
Substrate concrete construction formwork uses the channel-section steel that rigidity is enough, and side sets stayed mast and inserts hole;The height of steel form is base Layer concrete design thickness, template length is 3~5m, supporting adn fixing device at every meter of template-setup 1, mold plate verticality chock Wedge method adjusts, and construction joint indwelling is at expansion joint (E.J.);
According to predetermined stretching, contract seam position, when xoncrete structure base layer construction, first bury upper 25 thickness according to expansion joint (E.J.) position Soaking the Pinus koraiensis expansion joint plate of Colophonium, centre sets Φ 16mm dowel steel, spacing 200;
When concrete is unhardened, reject the concrete on expansion joint plate top, embed the batten of 20 × 20, flattened faces, expansion joint (E.J.) Plate should continuous through whole substrate concrete, expansion joint plate is vertical with Lu Zhizheng line, and slotted wall is vertical;
Dowel steel employing Φ 16mm reinforcing bar, spacing 200, a length of 700, the surface of more than half length should be coated with anti-stick Layer, end should be worn movable cap bag, be overlapped cap material and use Φ 20mm plastic tube, end employing asphalt felt to seal blocking, dowel steel steel Muscle processing should be sawed-off, cut-out must not be extruded, fracture should vertically, light justify, fall burr with grinder buffing, and be processed into 2~3 roundings Angle;
All vertical, horizontal contracting seam all uses the construction of joint-cutting method, and the joint-cutting degree of depth is 6, and width is 10, first arrives with thin saw blade sawing Require the degree of depth, re-use 6~8 thick saw blades or overlapping saw blade widens joint filling groove;
With the covering wet curing such as gunnysack, straw screen or mat and sprinkle water in time, keep concrete surface to be in dampness, basic unit all the time At the concrete curing initial stage, forbidding pedestrian, vehicle pass-through, after reaching design strength 40%, pedestrian can pass through;
(3) surface layer paving control line construction
According to stone material surface layer every block of trapezoidal stone material of CAD typesetting figure and gap size, every section of circle and the center of circle of circular arc, use total powerstation Orient the radial direction control line of each every block of stone material of section, use chord off-set method to survey the broadwise control line setting every block of stone material, and By the radial direction of every block of trapezoidal stone material and broadwise control line line of ink marker bullet on concrete base layer, as depending on of every piece of stone material paving According to;
(4) granite face is mated formation
Granite panel of mating formation is 40 thick fired slab floor file, and on C25 concrete base layer, first brush plain-water slurry one time, then adopts With 20 thick 1:2.5 cement mortar screedings, panel and basic unit use 50 thick 1:2.5 dry cement mortar binder courses, fired slab 5 thick plain-water slurry tack coats are scraped in bottom surface;
Granite face all stays at substrate concrete expansion joint (E.J.) and expansion joint and sets 10 wide expansion joints;
Using and expansion joint plate equal thickness when surface layer is mated formation, height is embedded at expansion joint plate with the batten of binder course uniform thickness of mating formation, With paving with dragging, it is ensured that without mortar between expansion joint plate and surface layer, gap-filling glue after having mated formation, is used to fill up;
(5) filleting
Expansion joint of mating formation uses PVC cement, first uses grooving machine to remove in seam sandstone, the mortar etc. of condensation being mingled with, Re-use the pressure press water more than 0.5Mpa and compressed air thoroughly removes the dust in seam and other pollutant, it is ensured that seam Wall and cleaning inside, it is dried;Slotted wall is checked can not wipe dust for cementation of fissures standard;
Crack pouring depth is at 15~20 mm, and the most shallow 15 mm that cannot be less than, first extruding embeds diameter 9~12 mm sponge plastics Backing strip, then cementation of fissures cementation of fissures end face should flush with plate face;Necessary full, uniform, the consistency of thickness of joint filling is the most through, joint sealing material Must not lack, ftracture and seep water
Stone material surface layer except expansion joint is with in addition to PVC cement filleting, other all gaps the most not filletings, drop in gap The foreign material such as cement mortar to clean out.
CN201610581952.6A 2016-07-22 2016-07-22 Large area wing square stone material in severe cold area is mated formation prevention and cure of crack method Active CN106223151B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201610581952.6A CN106223151B (en) 2016-07-22 2016-07-22 Large area wing square stone material in severe cold area is mated formation prevention and cure of crack method
CN201810272525.9A CN108486978A (en) 2016-07-22 2016-07-22 The wing square stone material of the good severe cold area large area of effect is mated formation prevention and cure of crack method
CN201810271448.5A CN108396607A (en) 2016-07-22 2016-07-22 The wing square stone material of severe cold area large area easy for construction is mated formation prevention and cure of crack method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610581952.6A CN106223151B (en) 2016-07-22 2016-07-22 Large area wing square stone material in severe cold area is mated formation prevention and cure of crack method

Related Child Applications (2)

Application Number Title Priority Date Filing Date
CN201810272525.9A Division CN108486978A (en) 2016-07-22 2016-07-22 The wing square stone material of the good severe cold area large area of effect is mated formation prevention and cure of crack method
CN201810271448.5A Division CN108396607A (en) 2016-07-22 2016-07-22 The wing square stone material of severe cold area large area easy for construction is mated formation prevention and cure of crack method

Publications (2)

Publication Number Publication Date
CN106223151A true CN106223151A (en) 2016-12-14
CN106223151B CN106223151B (en) 2018-05-15

Family

ID=57531322

Family Applications (3)

Application Number Title Priority Date Filing Date
CN201610581952.6A Active CN106223151B (en) 2016-07-22 2016-07-22 Large area wing square stone material in severe cold area is mated formation prevention and cure of crack method
CN201810271448.5A Pending CN108396607A (en) 2016-07-22 2016-07-22 The wing square stone material of severe cold area large area easy for construction is mated formation prevention and cure of crack method
CN201810272525.9A Pending CN108486978A (en) 2016-07-22 2016-07-22 The wing square stone material of the good severe cold area large area of effect is mated formation prevention and cure of crack method

Family Applications After (2)

Application Number Title Priority Date Filing Date
CN201810271448.5A Pending CN108396607A (en) 2016-07-22 2016-07-22 The wing square stone material of severe cold area large area easy for construction is mated formation prevention and cure of crack method
CN201810272525.9A Pending CN108486978A (en) 2016-07-22 2016-07-22 The wing square stone material of the good severe cold area large area of effect is mated formation prevention and cure of crack method

Country Status (1)

Country Link
CN (3) CN106223151B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610764A (en) * 2018-11-19 2019-04-12 中国电建集团江西省电力建设有限公司 A kind of granite facade paving construction technique
CN113279305A (en) * 2021-05-29 2021-08-20 浙江浩诚建设股份有限公司 Paving method of landscape footpath granite surface layer
CN114685885A (en) * 2022-05-06 2022-07-01 北京中景橙石科技股份有限公司 Elastic expansion joint plate and preparation method thereof
CN114856136A (en) * 2022-05-25 2022-08-05 南通大学 Graphene-based MS sealant construction process and MS sealant

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0220102A1 (en) * 1985-10-09 1987-04-29 BENDIX France Electrically operated control valve
EP0263001A1 (en) * 1986-09-10 1988-04-06 La Generale Du Granit Method for making grooves and bulgings for constructions, in particular for funeral monuments
CN1410933A (en) * 2001-08-27 2003-04-16 日本世纪洋服株式会社 Equipment for use from ordering goods to cut out in making clothes and producing method thereof
CN101949215A (en) * 2010-11-05 2011-01-19 中国建筑第八工程局有限公司 Mounting construction method of steel structure support seat
CN102828600A (en) * 2012-09-07 2012-12-19 华鼎建筑装饰工程有限公司 Method for laying floor artificial stones
CN102912945A (en) * 2012-11-13 2013-02-06 江苏江中集团有限公司 Roof compound seepage-proofing steam exhausting hole detail treatment technology
CN103590294A (en) * 2013-11-19 2014-02-19 苏州金螳螂园林绿化景观有限公司 Production and paving method of ice crack road surface pacing templates with different widths
CN103615110A (en) * 2013-08-21 2014-03-05 广西建工集团第一建筑工程有限责任公司 Irregular oblique-crossing web-shaped grillage beam hyperbolic roof structure construction method
CN103669788A (en) * 2013-12-20 2014-03-26 广东省第四建筑工程公司 Paving method for polished face brick wall

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101619558B (en) * 2009-07-28 2011-07-20 朱奎 Air entraining vacuum concrete roadway and constructing method thereof
CN202208877U (en) * 2011-07-01 2012-05-02 江苏南通六建建设集团有限公司 Ground pavement expansion joint structure on concrete cushion layer expansion joints
KR20130067957A (en) * 2011-12-15 2013-06-25 주식회사 데코페이브 Permeable block with water storage and process of construction
CN104294729A (en) * 2014-08-25 2015-01-21 四川金锋建设有限公司 Method for constructing concrete pavement
CN105256692A (en) * 2015-09-10 2016-01-20 重庆建工住宅建设有限公司 Color and pervious concrete pavement structure and construction technology therefor
CN105178559A (en) * 2015-10-08 2015-12-23 哈尔滨世纪天诚装饰工程有限公司 Novel construction method for granite ground
CN105781064A (en) * 2016-03-04 2016-07-20 上海宝冶集团有限公司 Floor tile laying construction method based on building information modeling (BIM)

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0220102A1 (en) * 1985-10-09 1987-04-29 BENDIX France Electrically operated control valve
EP0263001A1 (en) * 1986-09-10 1988-04-06 La Generale Du Granit Method for making grooves and bulgings for constructions, in particular for funeral monuments
CN1410933A (en) * 2001-08-27 2003-04-16 日本世纪洋服株式会社 Equipment for use from ordering goods to cut out in making clothes and producing method thereof
CN101949215A (en) * 2010-11-05 2011-01-19 中国建筑第八工程局有限公司 Mounting construction method of steel structure support seat
CN102828600A (en) * 2012-09-07 2012-12-19 华鼎建筑装饰工程有限公司 Method for laying floor artificial stones
CN102912945A (en) * 2012-11-13 2013-02-06 江苏江中集团有限公司 Roof compound seepage-proofing steam exhausting hole detail treatment technology
CN103615110A (en) * 2013-08-21 2014-03-05 广西建工集团第一建筑工程有限责任公司 Irregular oblique-crossing web-shaped grillage beam hyperbolic roof structure construction method
CN103590294A (en) * 2013-11-19 2014-02-19 苏州金螳螂园林绿化景观有限公司 Production and paving method of ice crack road surface pacing templates with different widths
CN103669788A (en) * 2013-12-20 2014-03-26 广东省第四建筑工程公司 Paving method for polished face brick wall

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610764A (en) * 2018-11-19 2019-04-12 中国电建集团江西省电力建设有限公司 A kind of granite facade paving construction technique
CN109610764B (en) * 2018-11-19 2024-04-16 中国电建集团江西省电力建设有限公司 Granite facade paving construction technology
CN113279305A (en) * 2021-05-29 2021-08-20 浙江浩诚建设股份有限公司 Paving method of landscape footpath granite surface layer
CN114685885A (en) * 2022-05-06 2022-07-01 北京中景橙石科技股份有限公司 Elastic expansion joint plate and preparation method thereof
CN114685885B (en) * 2022-05-06 2023-11-24 北京中景橙石科技股份有限公司 Elastic expansion joint plate and preparation method thereof
CN114856136A (en) * 2022-05-25 2022-08-05 南通大学 Graphene-based MS sealant construction process and MS sealant

Also Published As

Publication number Publication date
CN106223151B (en) 2018-05-15
CN108396607A (en) 2018-08-14
CN108486978A (en) 2018-09-04

Similar Documents

Publication Publication Date Title
CN106223151A (en) Severe cold area large area wing square stone material is mated formation prevention and cure of crack method
CN105587102B (en) A kind of wet construction method to the wet type high abrasion terrace that paves
CN104294729A (en) Method for constructing concrete pavement
CN102535296B (en) Construction method of superheavy-load reinforcement-free large-area seamless epoxy self-leveling terrace
CN110805455A (en) Tunnel disease comprehensive treatment method
CN106381980B (en) A kind of ground tile paving technique
CN104131512B (en) Cement concrete bridge deck thermal jet polymer modified asphalt water-proof tack coat paving structure and construction method
CN105003087A (en) Ground hollow detection and repair method based on infrared imaging
CN113323440A (en) Concrete gap repairing and anti-seepage treatment method
CN110629800A (en) Deformation joint treatment method and deformation joint waterproof structure
CN110644318A (en) Concrete construction method for field road pavement
CN104927759B (en) A kind of interface adhesive material and black overlay structure and its construction technology of changing in vain based on the material
CN204492022U (en) The waterproof construction of parapet high-low bay deformation joint
CN104179078B (en) A kind of hydrophobic processing method of CRTS II plate-type track structure gap
KR20080000440A (en) Repair method for joint of pavement
CN111021186A (en) Method for repairing large-space joint of concrete pavement slab
CN110735493A (en) Compound waterproof system of kind of flat roofing antiseep
JP6512908B2 (en) Construction method of floor slab structure
CN206071011U (en) A kind of spreading device for floor tile paving
CN104343137B (en) Underground waterproof engineering construction method
CN204162963U (en) Gravel polymer imitates stone terrace
CN209742297U (en) Terrace coating structure of carborundum wear-resistant paint for garage
CN106436517A (en) Construction method of soft soil anti-collapse concrete road surface
TWI624578B (en) Acrylic wear-resistant waterproof layer structure and construction method
JP2017057687A (en) Concrete pavement structure and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant