CN106192781A - 预应力单箱三室板梁的拆除方法 - Google Patents
预应力单箱三室板梁的拆除方法 Download PDFInfo
- Publication number
- CN106192781A CN106192781A CN201610576788.XA CN201610576788A CN106192781A CN 106192781 A CN106192781 A CN 106192781A CN 201610576788 A CN201610576788 A CN 201610576788A CN 106192781 A CN106192781 A CN 106192781A
- Authority
- CN
- China
- Prior art keywords
- plate
- girder
- room
- falsework
- dismounting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种预应力单箱三室板梁的拆除方法,包括以下步骤:S1:搭设临时支架:利用桥墩作为搭设基础,沿桥墩侧部搭设临时支架,使单箱三室板梁端部承载在临时支架上;S2:纵向分条:沿单箱三室板梁中间箱室顶底板的最薄位置进行纵向切割,使单箱三室板梁沿中线分割成条;S3:横向分段:沿墩顶和临时支架之间的位置对单箱三室板梁进行横向切割,使单箱三室板梁分割成段;S4:吊放:利用吊装设备将纵横切割形成的板梁单元依次进行吊放;S5:拆卸临时支架:待板梁单元吊放完成后,对临时支架进行拆卸。该方法具有操作方便、可提高施工安全性和施工效率的优点。
Description
技术领域
本发明主要涉及般桥梁结构拆除技术,尤其涉及一种预应力单箱三室板梁的拆除方法。
背景技术
一般桥梁结构拆除大多借鉴了建筑物的拆除方法,如***法、直接破除法、机械吊拆法等;但还有一些方法则是根据桥梁特殊情况而只针对桥梁拆除的方法,如龙门吊拆除、顶推拆除、浮桥拆除等。对目前桥梁拆除方法进行归类,可分为***拆除法和机械(非***)拆除法两个大的类别,每个类别又包含了多种不同的拆除方法,均有各自的适用范围。机械拆除法是指利用机械设备对桥梁进行破碎、分割、吊运等形式进行拆除。常规的机械拆除法需要搭设支架及防护网,将桥梁结构就地破碎或吊运指定地点。
发明内容
本发明要解决的技术问题是克服现有技术的不足,提供一种操作方便、可提高施工安全性和施工效率的预应力单箱三室板梁的拆除方法。
为解决上述技术问题,本发明采用以下技术方案:
一种预应力单箱三室板梁的拆除方法,包括以下步骤:
S1:搭设临时支架:利用桥墩作为搭设基础,沿桥墩侧部搭设临时支架,使单箱三室板梁端部承载在临时支架上;
S2:纵向分条:沿单箱三室板梁中间箱室顶底板的最薄位置进行纵向切割,使单箱三室板梁沿中线分割成条;
S3:横向分段:沿墩顶和临时支架之间的位置对单箱三室板梁进行横向切割,使单箱三室板梁分割成段;
S4:吊放:利用吊装设备将纵横切割形成的板梁单元依次进行吊放;
S5:拆卸临时支架:待板梁单元吊放完成后,对临时支架进行拆卸。
作为上述技术方案的进一步改进:
在步骤S1中,在临时支架顶部设置宽度大于单箱三室板梁的分配梁。
检查单箱三室板梁的梁底是否间隙,用橡胶垫抄实间隙。
在进行步骤S2和S3之前,先将单箱三室板梁侧部的翼板进行切除吊放。
在步骤S5中,待所有板梁单元吊放完成后,对临时支架进行拆卸。
在步骤S5中,在待吊放工位与已吊放工位相距一个板梁单元时,对已吊放工位的临时支架进行拆卸。
采用绳锯进行切割。
与现有技术相比,本发明的优点在于:
本发明的预应力单箱三室板梁的拆除方法,采用该方法,临时支架起到临时承载单箱三室板梁的作用,将预应力单箱三室板梁先纵向分条、后横向分段,形成多段板梁单元简支于墩旁的临时支架上,最后采用大吨位吊机吊装拆除,局部切断预应力筋、避免整体解除梁体预应力体系,提高了施工的安全性;单箱三室板梁纵向分条、横向分段的半封闭拆除,其施工方便、效率高。
附图说明
图1是本发明预应力单箱三室板梁的拆除方法的流程图。
图2是预应力单箱三室板梁的主视图。
图3是预应力单箱三室板梁的俯视图。
图4是预应力单箱三室板梁的侧视图。
图中各标号表示。
具体实施方式
以下将结合说明书附图和具体实施例对本发明做进一步详细说明。
如图1所示,本发明预应力单箱三室板梁的拆除方法的流程图,其包括以下步骤:
S1:搭设临时支架:利用桥墩作为搭设基础,沿桥墩侧部搭设临时支架,使单箱三室板梁端部承载在临时支架上;
S2:纵向分条:沿单箱三室板梁中间箱室顶底板的最薄位置进行纵向切割,使单箱三室板梁沿中线分割成条;
S3:横向分段:沿墩顶和临时支架之间的位置对单箱三室板梁进行横向切割,使单箱三室板梁分割成段;
S4:吊放:利用吊装设备将纵横切割形成的板梁单元依次进行吊放;
S5:拆卸临时支架:待板梁单元吊放完成后,对临时支架进行拆卸。
采用该方法,临时支架起到临时承载单箱三室板梁的作用,将预应力单箱三室板梁先纵向分条、后横向分段,形成多段板梁单元简支于墩旁的临时支架上,最后采用大吨位吊机吊装拆除,局部切断预应力筋、避免整体解除梁体预应力体系,提高了施工的安全性;单箱三室板梁纵向分条、横向分段的半封闭拆除,其施工方便、效率高。
如图2至图4所示,本发明预应力单箱三室板梁的拆除方法的具体实施例,先沿桥墩1侧部搭设临时支架2,使单箱三室板梁3端部承载在临时支架2上;再沿单箱三室板梁3中间箱室顶底板的最薄位置进行纵向切割,使单箱三室板梁3沿中线分割成条;然后沿墩顶和临时支架2之间的位置对单箱三室板梁3进行横向切割,使单箱三室板梁3分割成段;再利用吊装设备将纵横切割形成的板梁单元依次进行吊放;最后待板梁单元吊放完成后,对临时支架2进行拆卸。
本实施例中,在步骤S1中,在临时支架2顶部设置宽度大于单箱三室板梁3的分配梁21,这样设置,使得在纵横切割后形成的板梁单元能稳固的承载在分配梁21上,不会跌落,进一步提高了施工的安全性。
本实施例中,检查单箱三室板梁3的梁底是否间隙,用橡胶垫抄实间隙,这样设置能保证单箱三室板梁3的平整,能提高切割的稳定性。
本实施例中,在进行步骤S2和S3之前,先将单箱三室板梁3侧部的翼板31进行切除吊放,这样设置,能保证板梁单元主体为一块规整的矩形体,便于板梁单元吊放时的受力,使吊放过程更加平稳可靠。
本实施例中,采用绳锯进行切割,采用绳锯切割方便可靠。
本实施例中,在步骤S5中,待所有板梁单元吊放完成后,对临时支架2进行拆卸,这样操作,一方面能提高施工的安全性,另一方面可减少施工现场的人员配备。
在其它实施例中,在步骤S5中,在待吊放工位与已吊放工位相距一个板梁单元时,对已吊放工位的临时支架2进行拆卸,这样操作,基本能实现吊放工作与拆卸工作同步进行,可提高施工效率。
虽然本发明已以较佳实施例揭示如上,然而并非用以限定本发明。任何熟悉本领域的技术人员,在不脱离本发明技术方案范围的情况下,都可利用上述揭示的技术内容对本发明技术方案做出许多可能的变动和修饰,或修改为等同变化的等效实施例。因此,凡是未脱离本发明技术方案的内容,依据本发明技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均应落在本发明技术方案保护的范围内。
Claims (7)
1.一种预应力单箱三室板梁的拆除方法,其特征在于:包括以下步骤:
S1:搭设临时支架:利用桥墩作为搭设基础,沿桥墩侧部搭设临时支架,使单箱三室板梁端部承载在临时支架上;
S2:纵向分条:沿单箱三室板梁中间箱室顶底板的最薄位置进行纵向切割,使单箱三室板梁沿中线分割成条;
S3:横向分段:沿墩顶和临时支架之间的位置对单箱三室板梁进行横向切割,使单箱三室板梁分割成段;
S4:吊放:利用吊装设备将纵横切割形成的板梁单元依次进行吊放;
S5:拆卸临时支架:待板梁单元吊放完成后,对临时支架进行拆卸。
2.根据权利要求1所述的预应力单箱三室板梁的拆除方法,其特征在于:在步骤S1中,在临时支架顶部设置宽度大于单箱三室板梁的分配梁。
3.根据权利要求2所述的预应力单箱三室板梁的拆除方法,其特征在于:检查单箱三室板梁的梁底是否间隙,用橡胶垫抄实间隙。
4.根据权利要求3所述的预应力单箱三室板梁的拆除方法,其特征在于:在进行步骤S2和S3之前,先将单箱三室板梁侧部的翼板进行切除吊放。
5.根据权利要求4所述的预应力单箱三室板梁的拆除方法,其特征在于:在步骤S5中,待所有板梁单元吊放完成后,对临时支架进行拆卸。
6.根据权利要求4所述的预应力单箱三室板梁的拆除方法,其特征在于:在步骤S5中,在待吊放工位与已吊放工位相距一个板梁单元时,对已吊放工位的临时支架进行拆卸。
7.根据权利要求1至6中任一项所述的预应力单箱三室板梁的拆除方法,其特征在于:采用绳锯进行切割。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610576788.XA CN106192781A (zh) | 2016-07-21 | 2016-07-21 | 预应力单箱三室板梁的拆除方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610576788.XA CN106192781A (zh) | 2016-07-21 | 2016-07-21 | 预应力单箱三室板梁的拆除方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106192781A true CN106192781A (zh) | 2016-12-07 |
Family
ID=57491993
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610576788.XA Pending CN106192781A (zh) | 2016-07-21 | 2016-07-21 | 预应力单箱三室板梁的拆除方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106192781A (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108589564A (zh) * | 2018-04-17 | 2018-09-28 | 成都西南交大研究院有限公司 | 一种基于非***的桥梁静态切割分块拆除方法 |
CN108824842A (zh) * | 2018-05-29 | 2018-11-16 | 五冶集团上海有限公司 | 一种脱硫塔拆除方法 |
CN109056557A (zh) * | 2018-08-17 | 2018-12-21 | 中铁五局集团有限公司 | 一种分解拆除既有桥梁施工方法 |
CN111172902A (zh) * | 2020-01-09 | 2020-05-19 | 南京林业大学 | 一种无支架快速拆除箱梁桥的施工方法 |
CN111560864A (zh) * | 2020-01-17 | 2020-08-21 | 广东冠粤路桥有限公司 | 一种旧桥的拆除方法 |
CN114263129A (zh) * | 2021-12-31 | 2022-04-01 | 宁波市政工程建设集团股份有限公司 | 桥梁上部结构的拆除施工方法 |
CN114541286A (zh) * | 2021-12-31 | 2022-05-27 | 宁波市政工程建设集团股份有限公司 | 现浇预应力箱梁的分段分块拆除施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103291085A (zh) * | 2013-06-07 | 2013-09-11 | 陈春来 | 混凝土静力切割拆除施工方法 |
CN103343512A (zh) * | 2013-07-03 | 2013-10-09 | 上海市机械施工集团有限公司 | 大断面混凝土箱梁的拆除方法与吊装装置 |
CN103938557A (zh) * | 2014-03-11 | 2014-07-23 | 卢耒运 | 一种跨线桥拆除方法 |
CN104131519A (zh) * | 2014-08-11 | 2014-11-05 | 浙江兴土桥梁专用装备制造有限公司 | 一种桥梁拆除施工方法及其设备 |
CN104631349A (zh) * | 2015-02-04 | 2015-05-20 | 中铁十八局集团第一工程有限公司 | 一种城市高架桥钢箱梁的拆卸与存放方法 |
-
2016
- 2016-07-21 CN CN201610576788.XA patent/CN106192781A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103291085A (zh) * | 2013-06-07 | 2013-09-11 | 陈春来 | 混凝土静力切割拆除施工方法 |
CN103343512A (zh) * | 2013-07-03 | 2013-10-09 | 上海市机械施工集团有限公司 | 大断面混凝土箱梁的拆除方法与吊装装置 |
CN103938557A (zh) * | 2014-03-11 | 2014-07-23 | 卢耒运 | 一种跨线桥拆除方法 |
CN104131519A (zh) * | 2014-08-11 | 2014-11-05 | 浙江兴土桥梁专用装备制造有限公司 | 一种桥梁拆除施工方法及其设备 |
CN104631349A (zh) * | 2015-02-04 | 2015-05-20 | 中铁十八局集团第一工程有限公司 | 一种城市高架桥钢箱梁的拆卸与存放方法 |
Non-Patent Citations (1)
Title |
---|
***: "吴淞路闸桥切割拆除施工流程", 《中国市政工程》 * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108589564A (zh) * | 2018-04-17 | 2018-09-28 | 成都西南交大研究院有限公司 | 一种基于非***的桥梁静态切割分块拆除方法 |
CN108824842A (zh) * | 2018-05-29 | 2018-11-16 | 五冶集团上海有限公司 | 一种脱硫塔拆除方法 |
CN109056557A (zh) * | 2018-08-17 | 2018-12-21 | 中铁五局集团有限公司 | 一种分解拆除既有桥梁施工方法 |
CN111172902A (zh) * | 2020-01-09 | 2020-05-19 | 南京林业大学 | 一种无支架快速拆除箱梁桥的施工方法 |
CN111560864A (zh) * | 2020-01-17 | 2020-08-21 | 广东冠粤路桥有限公司 | 一种旧桥的拆除方法 |
CN114263129A (zh) * | 2021-12-31 | 2022-04-01 | 宁波市政工程建设集团股份有限公司 | 桥梁上部结构的拆除施工方法 |
CN114541286A (zh) * | 2021-12-31 | 2022-05-27 | 宁波市政工程建设集团股份有限公司 | 现浇预应力箱梁的分段分块拆除施工方法 |
CN114541286B (zh) * | 2021-12-31 | 2023-09-05 | 宁波市政工程建设集团股份有限公司 | 现浇预应力箱梁的分段分块拆除施工方法 |
CN114263129B (zh) * | 2021-12-31 | 2023-09-05 | 宁波市政工程建设集团股份有限公司 | 桥梁上部结构的拆除施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106192781A (zh) | 预应力单箱三室板梁的拆除方法 | |
CN107268463B (zh) | 一种连续梁拆除方法 | |
CN109235290A (zh) | 桥梁安拆施工方法 | |
CN103470068B (zh) | 一种既有轧制线地下空间混凝土结构的拆除方法 | |
CN104652298B (zh) | 一种基于桥面支撑的整跨箱梁下放拆除***及其施工方法 | |
CN103790398B (zh) | 大型混凝土结构体无预支撑拆除方法 | |
CN106638336B (zh) | 跨线连续梁拆除方法及拆除用支架 | |
CN105569376A (zh) | 建筑墙体的拆除施工方法 | |
CN107217605A (zh) | 一种连续梁拆除施工方法 | |
CN104131519B (zh) | 一种桥梁拆除设备施工方法 | |
CN108560560A (zh) | 一种基坑围护结构的拆除方法 | |
CN104099872B (zh) | 一种下穿铁路大跨度箱涵纵挑横抬顶进施工方法 | |
CN109208938B (zh) | 钢筋混凝土板定向无损静力切割拆除处理方法 | |
CN110056205A (zh) | 一种采用绳锯切割砼内支撑梁的方法 | |
KR101060598B1 (ko) | 수평 이동식 업다운 동바리 장치 및 이를 이용하는 급속 교량교체공법 | |
CN202609768U (zh) | 一种吊车梁制动板专用吊装装置 | |
CN110453934A (zh) | 用于大型钢结构屋面厂房的拆除方法 | |
CN111622117A (zh) | 小净距贝雷支架拆除方法 | |
CN102828472B (zh) | 用绳锯割除连续梁桥临时支座的方法 | |
JP6873718B2 (ja) | 床版部材の解体方法 | |
CN104060832A (zh) | 一种提高卸料平台安全性的方法及装置 | |
CN105625176A (zh) | 支架预压施工工艺 | |
CN102031783A (zh) | 一种基坑钢砼支撑剪切拆除法 | |
CN202481643U (zh) | 块石搬运辅助工具 | |
JP7097203B2 (ja) | クライミング式テルハ及び建物の解体方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161207 |
|
RJ01 | Rejection of invention patent application after publication |