CN106123872A - 一种用于竖井开挖施工的坐标传递方法 - Google Patents
一种用于竖井开挖施工的坐标传递方法 Download PDFInfo
- Publication number
- CN106123872A CN106123872A CN201610441312.5A CN201610441312A CN106123872A CN 106123872 A CN106123872 A CN 106123872A CN 201610441312 A CN201610441312 A CN 201610441312A CN 106123872 A CN106123872 A CN 106123872A
- Authority
- CN
- China
- Prior art keywords
- total powerstation
- section
- point coordinates
- point
- laser
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01C—MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
- G01C15/00—Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01C—MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
- G01C7/00—Tracing profiles
- G01C7/06—Tracing profiles of cavities, e.g. tunnels
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Radar, Positioning & Navigation (AREA)
- Remote Sensing (AREA)
- Multimedia (AREA)
- Earth Drilling (AREA)
Abstract
一种用于竖井开挖施工的坐标传递方法,包括第一全站仪和第二全站仪,在竖井的上平段上架设第一全站仪,竖井底部架设第二全站仪,通过第一全站仪检测投射在上弯段的激光点坐标,设置第二全站仪,实现坐标传递。包括以下步骤:1)在竖井的上平段以及底部上分别架设第一全站仪和第二全站仪;2)得到A点坐标值;3)得到B点坐标值;4)根据步骤A、B两点坐标,进行第二全站仪的设站;5)将第一全站仪与第二全站仪测得的C点坐标进行比对,控制在误差允许范围内,完成坐标传递;6)利用卡西欧计算器程序进行竖井的开挖轮廓线放样、超欠挖检查、断面测量,完成下弯段的转向确定。
Description
技术领域
本发明涉及竖井施工技术领域,特别是一种用于竖井开挖施工的坐标传递方法。
背景技术
在竖井施工过程中,竖井测量方法采用较多的是在竖井顶部中心位置悬挂钢丝吊放铅垂或安装激光导向仪,量取钢丝或激光导线仪发射的激光至竖井开挖边线的距离并画线,作为施工开挖的轮廓,但采用竖井顶部中心悬挂钢丝法存在钢丝因竖井***需频繁收放铅垂及钢丝在竖井开挖***作业时易被炸断,或与竖井顶部悬挂的作业吊篮缠绕等问题;采用在竖井顶部中心安装激光导向仪法存在因竖井开挖***震动,需频繁调校安装在竖井顶部的激光导向仪,竖井开挖越深,每次到竖井顶部调校激光导向仪的安全风险就越大。并且采用上述两种方法均不能解决竖井下弯的平面精确转向。
发明内容
本发明所要解决的技术问题是提供一种用于竖井开挖施工的坐标传递方法,能够,代替了传统的测量方法中悬挂钢丝或钢带尺传递坐标的繁琐工序,同时能够方便、快捷、精确的解决竖井直段的断面测量、超欠挖测量和下弯段的开挖测量放样,解决竖井下弯段的精确转向,确保与下平段的顺利贯通。
为解决上述技术问题,本发明所采用的技术方案是:一种用于竖井开挖施工的坐标传递方法,包括第一全站仪和第二全站仪,在竖井的上平段上架设第一全站仪,竖井底部架设第二全站仪,通过第一全站仪检测投射在上弯段的激光点坐标,设置第二全站仪,实现坐标传递。
优选的方案中,包括以下步骤:
1)在竖井的上平段以及底部上分别架设第一全站仪和第二全站仪;
2)利用竖井底部的第二全站仪将激光投射在上弯段上的A点,然后利用上平段上设置的第一全站仪投射激光,使第一全站仪的激光投射在A点上,得到A点坐标值;
3)利用竖井底部的第二全站仪将激光投射在上弯段上的B点,然后利用上平段上设置的第一全站仪投射激光,使第一全站仪的激光投射在B点上,得到B点坐标值;
4)根据步骤A、B两点坐标,利用自由设站法进行第二全站仪的设站;
5)第一全站仪与第二全站仪同时投射激光至上弯段上同一点C,将第一全站仪与第二全站仪测得的C点坐标进行比对,控制在误差允许范围内,完成坐标传递;
6)利用卡西欧计算器程序进行竖井的开挖轮廓线放样、超欠挖检查、断面测量,完成下弯段的转向确定。
优选的方案中,所述的第一全站仪和第二全站仪采用弯管目镜,并同时在上弯段上设置三个反射片。
优选的方案中,所述的竖井井壁的锚筋上焊接三块钢板,钢板正下方粘贴设置反射片,完成第一次坐标传递之后,利用第二全站仪测设三个反射片的三维坐标,用作后续测量放样工作的已知控制点。
本发明提供的一种用于竖井开挖施工的坐标传递方法,通过采用上述方法,与传统的悬挂钢丝吊放铅垂、安装激光导向仪来说,能够大大提升施工效率,简化施工步骤,采用悬挂钢丝吊放铅垂时,在开挖施工时需重反复收放铅垂,同时也需要时刻避免钢丝在竖井***作业时被破坏的情况,而安装激光导向仪容易受***产生的震动产生偏差,因此需要频繁进行激光导向仪的校正,而且随着竖井开挖深度的加深,校正激光导向仪的作业风险也逐渐增大,而本发明所采用的坐标传递方法则能够快速精确的对竖井坐标进行传递并解决解决竖井直段的断面测量、超欠挖测量和下弯段的开挖测量放样等问题,在简化了施工步骤,提高了施工效率的同时,也能够实现竖井下弯段的精确转向确保与下平段的顺利贯通。
附图说明
下面结合附图和实施例对本发明作进一步说明:
图1为本发明的整体结构示意图。
图中:第一全站仪1,第二全站仪2,上平段3,上弯段4,下弯段5,下平段6。
具体实施方式
实施例1:
一种用于竖井开挖施工的坐标传递方法,包括第一全站仪1和第二全站仪2,在竖井的上平段3上架设第一全站仪1,竖井底部架设第二全站仪2,通过第一全站仪1检测投射在上弯段4的激光点坐标,设置第二全站仪2,实现坐标传递。
实施例2:
在实施例1的基础上,包括以下步骤:
1)在竖井的上平段3以及底部上分别架设第一全站仪1和第二全站仪2;
2)利用竖井底部的第二全站仪2将激光投射在上弯段4上的A点,然后利用上平段3上设置的第一全站仪1投射激光,使第一全站仪1的激光投射在A点上,得到A点坐标值;
3)利用竖井底部的第二全站仪2将激光投射在上弯段4上的B点,然后利用上平段3上设置的第一全站仪1投射激光,使第一全站仪1的激光投射在B点上,得到B点坐标值;
4)根据步骤A、B两点坐标,利用自由设站法进行第二全站仪2的设站;
5)第一全站仪1与第二全站仪2同时投射激光至上弯段4上同一点C,将第一全站仪1与第二全站仪2测得的C点坐标进行比对,控制在误差允许范围内,完成坐标传递;
6)利用卡西欧计算器程序进行竖井的开挖轮廓线放样、超欠挖检查、断面测量,完成下弯段5的转向确定。
优选的方案中,所述的第一全站仪1和第二全站仪2采用弯管目镜,并同时在上弯段4上设置三个反射片。采用上述结构能够提升坐标传递或检核的精准度。
优选的方案中,所述的竖井井壁的锚筋上焊接三块钢板,钢板正下方粘贴设置反射片,完成第一次坐标传递之后,利用第二全站仪2测设三个反射片的三维坐标,用作后续测量放样工作的已知控制点。
Claims (4)
1.一种用于竖井开挖施工的坐标传递方法,包括第一全站仪(1)和第二全站仪(2),其特征是:在竖井的上平段(3)上架设第一全站仪(1),竖井底部架设第二全站仪(2),通过第一全站仪(1)检测投射在上弯段(4)的激光点坐标,设置第二全站仪(2),实现坐标传递。
2.根据权利要求1所述的一种用于竖井开挖施工的坐标传递方法,其特征是包括以下步骤:
1)在竖井的上平段(3)以及底部上分别架设第一全站仪(1)和第二全站仪(2);
2)利用竖井底部的第二全站仪(2)将激光投射在上弯段(4)上的A点,然后利用上平段(3)上设置的第一全站仪(1)投射激光,使第一全站仪(1)的激光投射在A点上,得到A点坐标值;
3)利用竖井底部的第二全站仪(2)将激光投射在上弯段(4)上的B点,然后利用上平段(3)上设置的第一全站仪(1)投射激光,使第一全站仪(1)的激光投射在B点上,得到B点坐标值;
4)根据步骤A、B两点坐标,利用自由设站法进行第二全站仪(2)的设站;
5)第一全站仪(1)与第二全站仪(2)同时投射激光至上弯段(4)上同一点C,将第一全站仪(1)与第二全站仪(2)测得的C点坐标进行比对,控制在误差允许范围内,完成坐标传递;
6)利用卡西欧计算器程序进行竖井的开挖轮廓线放样、超欠挖检查、断面测量,完成下弯段(5)的转向确定。
3.根据权利要求2所述的一种用于竖井开挖施工的坐标传递方法,其特征在于:所述的第一全站仪(1)和第二全站仪(2)采用弯管目镜,并同时在上弯段(4)上设置三个反射片。
4.根据权利要求2所述的一种用于竖井开挖施工的坐标传递方法,其特征在于:所述的竖井井壁的锚筋上焊接三块钢板,钢板正下方粘贴设置反射片,完成第一次坐标传递之后,利用第二全站仪(2)测设三个反射片的三维坐标,用作后续测量放样工作的已知控制点。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610441312.5A CN106123872A (zh) | 2016-06-20 | 2016-06-20 | 一种用于竖井开挖施工的坐标传递方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610441312.5A CN106123872A (zh) | 2016-06-20 | 2016-06-20 | 一种用于竖井开挖施工的坐标传递方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106123872A true CN106123872A (zh) | 2016-11-16 |
Family
ID=57471166
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610441312.5A Pending CN106123872A (zh) | 2016-06-20 | 2016-06-20 | 一种用于竖井开挖施工的坐标传递方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106123872A (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106971046A (zh) * | 2017-04-10 | 2017-07-21 | 中国电力工程顾问集团西南电力设计院有限公司 | 一种高位收水冷却塔中央竖井设计方法 |
CN108446473A (zh) * | 2018-03-13 | 2018-08-24 | 中国水利水电第五工程局有限公司 | 一种水电站斜井开挖和超欠挖检查方法 |
CN110823199A (zh) * | 2019-11-15 | 2020-02-21 | 安徽金寨抽水蓄能有限公司 | 竖井超欠挖快速测量结构及其应用方法 |
CN110984995A (zh) * | 2019-12-18 | 2020-04-10 | 中国水利水电第五工程局有限公司 | 一种竖井弯段开挖体型控制方法 |
CN112052498A (zh) * | 2020-09-02 | 2020-12-08 | 国家电网有限公司 | 一种斜井开挖放样检测方法及装置 |
CN117053684A (zh) * | 2023-07-03 | 2023-11-14 | 中国葛洲坝集团三峡建设工程有限公司 | 一种小转弯半径条件下隧道测量方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090171619A1 (en) * | 2006-01-10 | 2009-07-02 | Leica Geosystems Ag | Surveying procedure and system for a high-rise structure |
CN103017741A (zh) * | 2011-09-26 | 2013-04-03 | 上海久隆电力(集团)有限公司 | 一种电力电缆线路数据的测量方法 |
CN103162671A (zh) * | 2011-12-13 | 2013-06-19 | 永升建设集团有限公司 | 异型建筑物测量施工方法 |
CN104457719A (zh) * | 2014-12-28 | 2015-03-25 | 上海隧道工程股份有限公司 | 矩形盾构施工的姿态测量装置及测量方法 |
US20150219455A1 (en) * | 2012-08-08 | 2015-08-06 | Hexagon Technology Center Gmbh | Inclination sensor |
CN105628001A (zh) * | 2014-11-26 | 2016-06-01 | 中国华冶科工集团有限公司 | 一种隔离层下矿山竖井延伸测量定向方法 |
-
2016
- 2016-06-20 CN CN201610441312.5A patent/CN106123872A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090171619A1 (en) * | 2006-01-10 | 2009-07-02 | Leica Geosystems Ag | Surveying procedure and system for a high-rise structure |
CN103017741A (zh) * | 2011-09-26 | 2013-04-03 | 上海久隆电力(集团)有限公司 | 一种电力电缆线路数据的测量方法 |
CN103162671A (zh) * | 2011-12-13 | 2013-06-19 | 永升建设集团有限公司 | 异型建筑物测量施工方法 |
US20150219455A1 (en) * | 2012-08-08 | 2015-08-06 | Hexagon Technology Center Gmbh | Inclination sensor |
CN105628001A (zh) * | 2014-11-26 | 2016-06-01 | 中国华冶科工集团有限公司 | 一种隔离层下矿山竖井延伸测量定向方法 |
CN104457719A (zh) * | 2014-12-28 | 2015-03-25 | 上海隧道工程股份有限公司 | 矩形盾构施工的姿态测量装置及测量方法 |
Non-Patent Citations (1)
Title |
---|
《测绘工程》 ISTIC -2013年3期曾怀恩刘金平ZENG HUAI-ENLIU JIN-PING: "基于免棱镜全站仪的竖井高精度测量 ", 《《测绘工程》第22卷第3期》 * |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106971046A (zh) * | 2017-04-10 | 2017-07-21 | 中国电力工程顾问集团西南电力设计院有限公司 | 一种高位收水冷却塔中央竖井设计方法 |
CN106971046B (zh) * | 2017-04-10 | 2020-03-27 | 中国电力工程顾问集团西南电力设计院有限公司 | 一种高位收水冷却塔中央竖井设计方法 |
CN108446473A (zh) * | 2018-03-13 | 2018-08-24 | 中国水利水电第五工程局有限公司 | 一种水电站斜井开挖和超欠挖检查方法 |
CN108446473B (zh) * | 2018-03-13 | 2020-02-18 | 中国水利水电第五工程局有限公司 | 一种水电站斜井开挖和超欠挖检查方法 |
CN110823199A (zh) * | 2019-11-15 | 2020-02-21 | 安徽金寨抽水蓄能有限公司 | 竖井超欠挖快速测量结构及其应用方法 |
CN110984995A (zh) * | 2019-12-18 | 2020-04-10 | 中国水利水电第五工程局有限公司 | 一种竖井弯段开挖体型控制方法 |
CN112052498A (zh) * | 2020-09-02 | 2020-12-08 | 国家电网有限公司 | 一种斜井开挖放样检测方法及装置 |
CN112052498B (zh) * | 2020-09-02 | 2024-02-02 | 国家电网有限公司 | 一种斜井开挖放样检测方法及装置 |
CN117053684A (zh) * | 2023-07-03 | 2023-11-14 | 中国葛洲坝集团三峡建设工程有限公司 | 一种小转弯半径条件下隧道测量方法 |
CN117053684B (zh) * | 2023-07-03 | 2024-03-12 | 中国葛洲坝集团三峡建设工程有限公司 | 一种小转弯半径条件下隧道测量方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106123872A (zh) | 一种用于竖井开挖施工的坐标传递方法 | |
CN106679533B (zh) | 用于lng船液货舱三向板cm节点的检测工装***及检测方法 | |
CN108871266B (zh) | 一种基于中间法三角高程方法的自动化沉降监测方法 | |
CN106382121B (zh) | 一种地铁隧道盾构掘进的测量方法 | |
CN104764434B (zh) | 一种盾构姿态快速解算***及方法 | |
CN106638318B (zh) | 斜拉桥梁端锚固点的定位方法及索导管安装方法 | |
CN105865426A (zh) | 一种自动对中与测量的全站仪 | |
CN104763156A (zh) | 一种核电站钢制安全壳底封头的组装方法 | |
CN104295297A (zh) | 一种掘进机截割头定位***及方法和掘进机 | |
CN205808414U (zh) | 一种建筑施工用垂直度检测装置 | |
CN107255442B (zh) | 基于激光跟踪技术的大尺寸水轮发电机定子安装测量方法 | |
CN104074548B (zh) | 一种激光指向仪偏移实时监测装置及监测方法 | |
CN102914278A (zh) | 一种应用全站仪对船舶轴线进行照光找中定位的方法 | |
CN108592877A (zh) | 一种变尺寸穹顶半径检测方法 | |
CN105628000A (zh) | 一种矿山竖井坐标传递测量方法 | |
CN103759701A (zh) | 基于安卓平台的手机智能测距方法 | |
CN211576110U (zh) | 基于拉丝点云校正单侧站点云空间方位的辅助定向装置 | |
CN106646498B (zh) | 一种掘进机横向偏移测量方法 | |
CN102889075B (zh) | 煤矿用钻孔角度测量***及方法 | |
CN108931237A (zh) | 一种全站仪精确定位大型炉体框架柱垂直度的施工方法 | |
CN109238254A (zh) | 一种洞桩投点方法 | |
CN104215183A (zh) | 一种连铸机扇形段鞍座安装检测方法及装置 | |
CN105382491A (zh) | 弧形钢管柱的加工制作及检验方法 | |
CN205449052U (zh) | 一种激光测量建筑物倾斜角的装置 | |
CN102374861B (zh) | 产生铅垂激光束的全站仪或觇牌的点下对中操作方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161116 |