CN106091101A - A kind of hydraulically balanced adjustment method and system - Google Patents

A kind of hydraulically balanced adjustment method and system Download PDF

Info

Publication number
CN106091101A
CN106091101A CN201610393224.2A CN201610393224A CN106091101A CN 106091101 A CN106091101 A CN 106091101A CN 201610393224 A CN201610393224 A CN 201610393224A CN 106091101 A CN106091101 A CN 106091101A
Authority
CN
China
Prior art keywords
debugging
hydraulic jacking
jacking tests
tests
flow rate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610393224.2A
Other languages
Chinese (zh)
Inventor
黄维
付南南
刘柏林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Huare Technology Development Co Ltd
Original Assignee
Beijing Huare Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Huare Technology Development Co Ltd filed Critical Beijing Huare Technology Development Co Ltd
Priority to CN201610393224.2A priority Critical patent/CN106091101A/en
Publication of CN106091101A publication Critical patent/CN106091101A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D19/00Details
    • F24D19/10Arrangement or mounting of control or safety devices
    • F24D19/1006Arrangement or mounting of control or safety devices for water heating systems
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/02Hot-water central heating systems with forced circulation, e.g. by pumps

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)

Abstract

This application discloses a kind of hydraulically balanced adjustment method and system, determine the product identification of hydraulic jacking tests to be debugged, from the data base pre-set, obtain the valve parameter curve corresponding with described product identification;Obtain the valve opening of described hydraulic jacking tests, determine the discharge coefficient corresponding with described valve opening according to described valve parameter curve;Obtain the pressure difference at described hydraulic jacking tests two ends, calculate the present flow rate flowing through described hydraulic jacking tests according to described pressure difference and described discharge coefficient.Visible, the application is by obtaining the valve parameter curve corresponding with the product identification of hydraulic jacking tests to be debugged from the data base pre-set, it is assured that the discharge coefficient corresponding with the valve opening of hydraulic jacking tests, the pressure difference obtained in conjunction with measurement, just can calculate the present flow rate flowing through described hydraulic jacking tests, such that it is able to release debugging instrument can only restriction matching used with hydraulic jacking tests, reduce hydraulically balanced debugging difficulty.

Description

A kind of hydraulically balanced adjustment method and system
Technical field
The application relates to the debugging technique field of heating and air-conditioner water system, particularly relates to a kind of hydraulically balanced debugging Method and system.
Background technology
Hydraulic equilibrium technology is the important technology in heating and air-conditioner water system, directly influences the use effect of heating air conditioning Fruit and energy saving of system.And hydraulic misadjustment is the obstinate disease in heating and air-conditioner water system, hydraulic misadjustment phenomenon can cause heating and sky Adjusting system hot and cold water flow is the most uneven.
As a example by heating system, in design calculates, every building all calculates and is assigned with fixing hot water circulating flow, presses Flow hot-water supply like this, building room temperature just can reach to design requirement, and due to construction adjustment, engineering matter in practical operation A lot of engineering practical factor such as amount and products application, the flow that most buildings actually obtain substantially deviates from design load, common Be the distance near building hot water circulating flow of thermal source beyond several times, the remote building circular flow of distance thermal source only less than half, The overheated needs of building room temperature causing distance thermal source near are windowed, and do not reach design requirement apart from the building room temperature that thermal source is remote. Hydraulic misadjustment is the most common within air-conditioning systems, and run unit is typically to strengthen low-temperature receiver and pump equipment puts into, and sacrifices more Energy meets use requirement, and this can waste big energy.Generally speaking, heating of today and air-conditioner water system, the most mostly There is serious hydraulic misadjustment problem in number, does not obtain correct solution.
Along with the requirement of energy-conserving and environment-protective improves, hydraulic misadjustment is increasingly paid close attention to by industry, in order to solve this problem, common Way be in heating and air-conditioner water system Specification Design calculate and install hydraulic jacking tests.Hydraulic jacking tests is a kind of permissible Manually regulation, be furnished with flow debugging instrument, can the valve of in-site measurement flow, its valve opening and discharge coefficient exist Relation one to one, has recorded its valve parameter curve (valve opening and the corresponding relation of discharge coefficient when design Curve), as long as measure the pressure difference at hydraulic jacking tests two ends at engineering site differential manometer, find the stream of now hydraulic jacking tests Coefficient of discharge, just can calculate the flow now by hydraulic jacking tests further according to flow formula.In other words, every hydraulic jacking tests Meter specially can be reached by and measure flow at the scene, and meter specially can be used at the scene to every hydraulic jacking tests Flow carry out the debugging that quantifies, make each end obtain due suitable flow.
But, due to the valve parameter existence difference of the debugging instrument inside solidification that different manufacturers produces, therefore debugging instrument Table can only use with supporting hydraulic jacking tests collocation, then cannot be carried out accurately in debugging instrument and hydraulic jacking tests when not matching Debugging, this makes hydraulically balanced debugging difficulty the biggest.
Summary of the invention
In view of this, the embodiment of the present application provides a kind of hydraulically balanced adjustment method and system, to reduce hydraulic equilibrium Debugging difficulty.
To achieve these goals, the technical scheme that the embodiment of the present application provides is as follows:
A kind of hydraulically balanced adjustment method, including:
Determine the product identification of hydraulic jacking tests to be debugged, obtain and described product mark from the data base pre-set The valve parameter curve of sensible correspondence;
Obtain the valve opening of described hydraulic jacking tests, determine and described valve opening phase according to described valve parameter curve Corresponding discharge coefficient;
Obtain the pressure difference at described hydraulic jacking tests two ends, calculate according to described pressure difference and described discharge coefficient and flow through institute State the present flow rate of hydraulic jacking tests.
Preferably, also include:
Receive on-site parameters investigation records;Described on-site parameters investigation records includes area of heat-supply service parameter, pump operating condition The position of each described hydraulic jacking tests in parameter, heating effect parameter, the pipeline parameter of heating network and described heating network Put parameter and number parameter;
Debugging plan is formulated according to described on-site parameters investigation records;Described debugging plan includes debugging wheel number and Often taking turns in debugging the target flow for each described hydraulic jacking tests distribution in described heating network.
Preferably, also include:
According to the debugging plan pre-established, send the target flow corresponding with described hydraulic jacking tests to operator, So that described operator judges whether described present flow rate matches with described target flow, and in described present flow rate with described When target flow does not mates, the described valve opening of described hydraulic jacking tests is debugged, until described present flow rate and institute State target flow to match.
Preferably, also include:
Receive the target flow corresponding with described hydraulic jacking tests;
Judge whether described present flow rate matches with described target flow;
If described present flow rate is not mated with described target flow, then send debugging instruction to operator;Described debugging Instruction is for indicating described operator to debug the described valve opening of described hydraulic jacking tests, so that described present flow rate Match with described target flow.
Preferably, also include:
Record debugging process, generates debugging report according to described debugging process;Described debugging report includes operator ground Reason location information and the data modification information of described hydraulic jacking tests;
Described debugging report is sent in server, in order to inquire about, revise and call.
A kind of hydraulically balanced debugging system, including:
Acquisition module, for determining the product identification of hydraulic jacking tests to be debugged, obtains from the data base pre-set Take the valve parameter curve corresponding with described product identification;
Determine module, for obtaining the valve opening of described hydraulic jacking tests, according to described valve parameter curve determine with The discharge coefficient that described valve opening is corresponding;
Computing module, for obtaining the pressure difference at described hydraulic jacking tests two ends, according to described pressure difference and described flow Coefficient calculations flows through the present flow rate of described hydraulic jacking tests.
Preferably, also include:
Logging modle, is used for receiving on-site parameters investigation records;Described on-site parameters investigation records includes area of heat-supply service Each described water in parameter, pump operating condition parameter, heating effect parameter, the pipeline parameter of heating network and described heating network The location parameter of dynamic balance valve and number parameter;
Formulate module, for formulating debugging plan according to described on-site parameters investigation records;Described debugging plan comprises There is debugging wheel number and often taking turns in debugging the target flow for each described hydraulic jacking tests distribution in described heating network.
Preferably, also include:
Sending module, for according to the debugging plan pre-established, sending relative with described hydraulic jacking tests to operator The target flow answered, so that described operator judges whether described present flow rate matches with described target flow, and described When present flow rate is not mated with described target flow, the described valve opening of described hydraulic jacking tests is debugged, until institute State present flow rate to match with described target flow.
Preferably, also include:
Receiver module, for receiving the target flow corresponding with described hydraulic jacking tests;
Judge module, is used for judging whether described present flow rate matches with described target flow;
Debugging module, if do not mated with described target flow for described present flow rate, then sends debugging to operator Instruction;Described debugging instruction is used for indicating described operator to debug the described valve opening of described hydraulic jacking tests, with Described present flow rate is made to match with described target flow.
Preferably, also include:
Generation module, is used for recording debugging process, generates debugging report according to described debugging process;In described debugging report Data modification information including operator's geo-localisation information and described hydraulic jacking tests;
Reporting modules, for being sent to described debugging report in server, in order to inquire about, revise and call.
The technical scheme provided from above the embodiment of the present application, relative to prior art, the application has to be had as follows Benefit effect:
The hydraulically balanced adjustment method of application the application offer and system, determine the product of hydraulic jacking tests to be debugged Mark, obtains the valve parameter curve corresponding with described product identification from the data base pre-set;Obtain described waterpower The valve opening of balanced valve, determines the discharge coefficient corresponding with described valve opening according to described valve parameter curve;Obtain The pressure difference at described hydraulic jacking tests two ends, calculates according to described pressure difference and described discharge coefficient and flows through described hydraulic jacking tests Present flow rate.Visible, the embodiment of the present application is by obtaining and hydraulic jacking tests to be debugged from the data base pre-set The corresponding valve parameter curve of product identification, it is possible to determine the flow system corresponding with the valve opening of hydraulic jacking tests Number, the pressure difference obtained in conjunction with measurement, it is possible to calculate the present flow rate flowing through described hydraulic jacking tests, such that it is able to release Debugging instrument can only restriction matching used with hydraulic jacking tests, reduce hydraulically balanced debugging difficulty.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present application or technical scheme of the prior art, below will be to embodiment or existing In having technology to describe, the required accompanying drawing used is briefly described, it should be apparent that, the accompanying drawing in describing below is only this Some embodiments described in application, for those of ordinary skill in the art, on the premise of not paying creative work, Other accompanying drawing can also be obtained according to these accompanying drawings.
The flow chart of the hydraulically balanced adjustment method that Fig. 1 provides for one embodiment of the application;
The flow chart of the hydraulically balanced adjustment method that Fig. 2 provides for another embodiment of the application;
The structure chart of the hydraulically balanced debugging system that Fig. 3 provides for one embodiment of the application;
The structure chart of the hydraulically balanced debugging system that Fig. 4 provides for another embodiment of the application.
Detailed description of the invention
For making the purpose of the embodiment of the present invention, technical scheme and advantage clearer, below in conjunction with the embodiment of the present invention In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is The a part of embodiment of the present invention rather than whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art The every other embodiment obtained under not making creative work premise, broadly falls into the scope of protection of the invention.
The flow chart of the hydraulically balanced adjustment method that Fig. 1 provides for one embodiment of the application.
Shown in reference Fig. 1, the hydraulically balanced adjustment method that the application provides, including:
S101: determine the product identification of hydraulic jacking tests to be debugged, obtains with described from the data base pre-set The valve parameter curve that product identification is corresponding;
In the embodiment of the present application, it is possible to use intelligent terminal combines APP technological development and goes out hydraulically balanced debugging system Working software, can realize balanced valve debugging instrument function, can inquire about and water from the local data base pre-set The valve parameter curve that the product identification of dynamic balance valve is corresponding, it is also possible to internet interview cloud database obtains and hydraulic equilibrium The valve parameter curve that the product identification of valve is corresponding.
In the embodiment of the present application, described valve parameter curve includes discharge coefficient and the valve of described hydraulic jacking tests The corresponding relation of aperture.
The data base of the embodiment of the present application can include product identification and the valve of the hydraulic jacking tests of all China and foreign countries brand The corresponding relation of door parameter curve, such that it is able to realize debugging stand-alone service.As long as the curve which kind of balanced valve data base has (can Obtain to arrange from enterprise's sample or examining report), just can measure the on-the-spot flow of which kind of balanced valve, it is possible to compatible all Hydraulic jacking tests product, it is achieved on-the-spot test and debugging.
Further, the data base using the embodiment of the present application to provide, can debug instrument by hydraulic equilibrium and waterpower is put down The relation of Heng Fa manufacturing enterprise is peeled off, and balance adjustment service is worked as professional service, even if having in a water system pipe network Many hydraulic jacking tests products (produce as the engineering department of different bid sections employs different hydraulic jacking tests in same heating system Product, Late reformation have changed hydraulic jacking tests product, owner oneself has changed hydraulic jacking tests product etc., cannot in prior art Solve many enterprises and debug the problem worked in coordination simultaneously), it is also possible to the most unified debugging.
S102: obtain the valve opening of described hydraulic jacking tests, determines and described valve according to described valve parameter curve The discharge coefficient that aperture is corresponding;
In the embodiment of the present application, after obtaining valve parameter curve, i.e. can determine that the valve opening phase with hydraulic jacking tests Corresponding discharge coefficient.
S103: obtain the pressure difference at described hydraulic jacking tests two ends, calculates according to described pressure difference and described discharge coefficient Flow through the present flow rate of described hydraulic jacking tests.
In the embodiment of the present application, determining the valve opening of hydraulic jacking tests, and finding corresponding with valve opening After discharge coefficient, can by means of the pressure difference at the instrument measurement hydraulic jacking tests two ends of simple on-the-spot test pressure reduction, according to Described pressure difference and described discharge coefficient calculate the present flow rate Q=Kv* △ P flowing through described hydraulic jacking tests0.5, wherein, Kv is Discharge coefficient, △ P is pressure difference.In other words, every hydraulic jacking tests can be reached by pressure test instrument and surveys at the scene The pressure difference gone out calculates present flow rate, and the debugging that can quantify present flow rate, changes current a lot of enterprise and puts down Weighing apparatus valve product does not debug the present situation of instrument.
The technical scheme that the embodiment of the present application provides, it is only necessary to the idiographic flow of above-mentioned test job is solidificated in waterpower and puts down Among debugging system APP of weighing apparatus, using the mode of dialog box, instruction operator log in from personnel step by step, instrument prepares, valve Door block clearing, vendor name model input (product identification input), valve opening input, pressure difference measurement etc. operate step by step, After can be calculated scene present flow rate.
Further, the embodiment of the present application can also receive the target flow corresponding with described hydraulic jacking tests, at meter After calculating present flow rate, it is judged that whether described present flow rate matches with described target flow, if described present flow rate and institute State target flow not mate, then send debugging instruction to operator;Described debugging instruction is used for indicating described operator to described The described valve opening of hydraulic jacking tests is debugged, so that described present flow rate matches with described target flow.
Certainly, after debugging valve opening, the pressure difference at hydraulic jacking tests two ends is likely to become therewith Change, therefore after valve opening is debugged, the embodiment of the present application be according to debugging after valve opening and debugging after Pressure difference carries out what whether the present flow rate after calculating debugging matched with target flow.
It is understood that the embodiment of the present application can also record debugging process, generate debugging according to described debugging process Report;Described debugging report includes the data modification information of operator's geo-localisation information and described hydraulic jacking tests;Will Described debugging report is sent in server, in order to inquires about, revise and calls.Such that it is able to stop false debugging and debugging inferior Effect so that effect depends on artificial work originally, is changed into dependence standard, refinement flow process, result controlled.And owner in the future When oneself wanting that changing certain valve operating mode finely tunes or think again to debug, conventional record is the most documented.
The hydraulically balanced adjustment method that application the application provides, determines the product identification of hydraulic jacking tests to be debugged, The valve parameter curve corresponding with described product identification is obtained from the data base pre-set;Obtain described hydraulic jacking tests Valve opening, determine the discharge coefficient corresponding with described valve opening according to described valve parameter curve;Obtain described water The pressure difference at dynamic balance valve two ends, calculates according to described pressure difference and described discharge coefficient and flows through the current of described hydraulic jacking tests Flow.Visible, the embodiment of the present application is by obtaining and the product of hydraulic jacking tests to be debugged from the data base pre-set Identify corresponding valve parameter curve, it is possible to determine the discharge coefficient corresponding with the valve opening of hydraulic jacking tests, then The pressure difference obtained in conjunction with measurement, it is possible to calculate the present flow rate flowing through described hydraulic jacking tests, such that it is able to release debugging Instrument can only restriction matching used with hydraulic jacking tests, reduce hydraulically balanced debugging difficulty.
The flow chart of the hydraulically balanced adjustment method that Fig. 2 provides for another embodiment of the application.
Shown in reference Fig. 2, the hydraulically balanced adjustment method that the application provides, including:
S201: determine the product identification of hydraulic jacking tests to be debugged, obtains with described from the data base pre-set The valve parameter curve that product identification is corresponding;
S202: obtain the valve opening of described hydraulic jacking tests, determines and described valve according to described valve parameter curve The discharge coefficient that aperture is corresponding;
S203: obtain the pressure difference at described hydraulic jacking tests two ends, calculates according to described pressure difference and described discharge coefficient Flow through the present flow rate of described hydraulic jacking tests;
S204: receive on-site parameters investigation records;
Described on-site parameters investigation records includes area of heat-supply service parameter, pump operating condition parameter, heating effect parameter, heat supply The location parameter of each described hydraulic jacking tests in the pipeline parameter of pipe network and described heating network and number parameter;
S205: formulate debugging plan according to described on-site parameters investigation records;
Described debugging plan includes debugging wheel number and is often taking turns in debugging as each institute in described heating network State the target flow of hydraulic jacking tests distribution;
In the embodiment of the present application, it is also possible to the experimental technology of hydraulic equilibrium system debug is integrated in hydraulically balanced tune Among test system APP software, according to on-site parameters investigation records (area of heat-supply service, pump operating condition, heating effect etc. that specialty is loaded down with trivial details Deng) carrying out Conversion of measurement unit, tabulation calculating, formulation debugging order, debugging wheel number (such as carry out initial adjustment, middle tune, accurate adjustment three rotation Examination), and often taking turns in debugging as each described hydraulic jacking tests distribution target flow in described heating network, it is possible to by this A little all formation dialog form and flow processs, conclude on-site parameters investigation loaded down with trivial details for specialty among formula questionnaire, operator When using hydraulically balanced debugging system APP software, cannot be proceeded to next step if any omitting.Various data can be stored in High in the clouds, conveniently records, inquires about, revises and calls in the future.
S206: according to the debugging plan pre-established, send the target corresponding with described hydraulic jacking tests to operator Flow, so that described operator judges whether described present flow rate matches with described target flow, and in described present flow rate When not mating with described target flow, the described valve opening of described hydraulic jacking tests is debugged, until described current stream Amount matches with described target flow.
Tubing in heating and air-conditioner water system is extremely complex, is merely capable of on-the-spot measurement amount or inadequate, is The regulation in hydraulic equilibrium is debugged of each hydraulic jacking tests in system can interfere, and needing that debugging is repeated several times could assist The flow of each hydraulic jacking tests in adjusting system, such as us the Flow-rate adjustment of a building to after design load, then goes regulation The when of other balanced valve, this flow mixed up will change, and wants to be transferred to all buildings and reaches design discharge, not only needs Commissioning experience is wanted to enrich, in addition it is also necessary to many tune are the most repeatedly.And debug each hydraulic jacking tests will look for place, offer sb. a chance to remedy a fault gracefully, The preparation of taking time such as joining two pipes together, add that engineering site problem is complicated, environment is poor, each hydraulic jacking tests of system is in hydraulic equilibrium Interfering in debugging, all of hydraulic jacking tests is adjusted and repeatedly be will take for plenty of time and manpower, causes debugging rework rate high, Repeated work is many, and debugging efficiency is low, and debugging effect is undesirable.
In the prior art, debugging senior skilled worker and normal operations work regardless of, be responsible for calculate check, investigation problem, formulation The senior engineer of the work such as debugging plan also to go balanced valve one by one to go into the well debugging operations, wastes time and cost.
In the embodiment of the present application, hydraulically balanced debugging system APP software can also be with commander and communication function, energy Enough systematically command several operator to debug the flow of multiple hydraulic jacking tests rapidly and orderly, complete the most anti-at short notice Polyphony tries, it is achieved optimum efficiency.
The embodiment of the present application can distinguish cammander (senior skilled worker) and operator's (ordinary skilled artisan), by cammander one people Leading 5~10 human operators to carry out the work, cammander is responsible for early stage contact, solution formulation, debugging commander, by hydraulically balanced The target flow calculated and debugging instruction are issued on the intelligent terminal of operator by the auxiliary of debugging system APP software In hydraulically balanced debugging system APP, as long as operator's reception order is done simple operations and just can be got through one's task with great speed, it is possible to system Ground is coordinated many people and is debugged the flow of each hydraulic jacking tests rapidly and orderly, and do so can complete the most at short notice Debugging, it is achieved optimum efficiency, effectively distribute human resources, be greatly improved work efficiency, have a quality complete debugging efforts.With biography Tracking one people of examination repeatedly regulates and compares, although employment is more, but debugging is quick, and effect is accurate, more proficient service, energy Enough expedite the emergence of debugging services industry.
It is emphasized that although technical scheme is set forth by the embodiment of the present application with the form of step, but this Shen Please each step in embodiment may be along hold execution, it is also possible to performing, the embodiment of the present application does not limit the most each simultaneously The execution sequence of individual step.
The structure chart of the hydraulically balanced debugging system that Fig. 3 provides for one embodiment of the application.
Shown in reference Fig. 3, the hydraulically balanced debugging system that the application provides, including:
Acquisition module 1, for determining the product identification of hydraulic jacking tests to be debugged, obtains from the data base pre-set Take the valve parameter curve corresponding with described product identification;
Determine module 2, for obtaining the valve opening of described hydraulic jacking tests, according to described valve parameter curve determine with The discharge coefficient that described valve opening is corresponding;
Computing module 3, for obtaining the pressure difference at described hydraulic jacking tests two ends, according to described pressure difference and described flow Coefficient calculations flows through the present flow rate of described hydraulic jacking tests.
Preferably, it is also possible to including:
Receiver module, for receiving the target flow corresponding with described hydraulic jacking tests;
Judge module, is used for judging whether described present flow rate matches with described target flow;
Debugging module, if do not mated with described target flow for described present flow rate, then sends debugging to operator Instruction;Described debugging instruction is used for indicating described operator to debug the described valve opening of described hydraulic jacking tests, with Described present flow rate is made to match with described target flow.
Preferably, it is also possible to including:
Generation module, is used for recording debugging process, generates debugging report according to described debugging process;In described debugging report Data modification information including operator's geo-localisation information and described hydraulic jacking tests;
Reporting modules, for being sent to described debugging report in server, in order to inquire about, revise and call.
The hydraulically balanced debugging system that the embodiment of the present application provides, can use the waterpower in said method embodiment to put down The adjustment method of weighing apparatus, the step that concrete function is referred in any of the above-described embodiment of the method describes, and here is omitted.
The structure chart of the hydraulically balanced debugging system that Fig. 4 provides for another embodiment of the application.
Shown in reference Fig. 4, the hydraulically balanced debugging system that the application provides, including:
Acquisition module 1, for determining the product identification of hydraulic jacking tests to be debugged, obtains from the data base pre-set Take the valve parameter curve corresponding with described product identification;
Determine module 2, for obtaining the valve opening of described hydraulic jacking tests, according to described valve parameter curve determine with The discharge coefficient that described valve opening is corresponding;
Computing module 3, for obtaining the pressure difference at described hydraulic jacking tests two ends, according to described pressure difference and described flow Coefficient calculations flows through the present flow rate of described hydraulic jacking tests;
Logging modle 4, is used for receiving on-site parameters investigation records;Described on-site parameters investigation records includes area of heat-supply service Each described water in parameter, pump operating condition parameter, heating effect parameter, the pipeline parameter of heating network and described heating network The location parameter of dynamic balance valve and number parameter;
Formulate module 5, for formulating debugging plan according to described on-site parameters investigation records;Described debugging plan comprises There is debugging wheel number and often taking turns in debugging the target flow for each described hydraulic jacking tests distribution in described heating network;
Sending module 6, for according to the debugging plan pre-established, sending relative with described hydraulic jacking tests to operator The target flow answered, so that described operator judges whether described present flow rate matches with described target flow, and described When present flow rate is not mated with described target flow, the described valve opening of described hydraulic jacking tests is debugged, until institute State present flow rate to match with described target flow.
The hydraulically balanced debugging system that the embodiment of the present application provides, can use the waterpower in said method embodiment to put down The adjustment method of weighing apparatus, the step that concrete function is referred in any of the above-described embodiment of the method describes, and here is omitted.
The technical scheme provided from above the embodiment of the present application, relative to prior art, the application has to be had as follows Benefit effect:
The hydraulically balanced adjustment method of application the application offer and system, determine the product of hydraulic jacking tests to be debugged Mark, obtains the valve parameter curve corresponding with described product identification from the data base pre-set;Obtain described waterpower The valve opening of balanced valve, determines the discharge coefficient corresponding with described valve opening according to described valve parameter curve;Obtain The pressure difference at described hydraulic jacking tests two ends, calculates according to described pressure difference and described discharge coefficient and flows through described hydraulic jacking tests Present flow rate.Visible, the embodiment of the present application is by obtaining and hydraulic jacking tests to be debugged from the data base pre-set The corresponding valve parameter curve of product identification, it is possible to determine the flow system corresponding with the valve opening of hydraulic jacking tests Number, the pressure difference obtained in conjunction with measurement, it is possible to calculate the present flow rate flowing through described hydraulic jacking tests, such that it is able to release Debugging instrument can only restriction matching used with hydraulic jacking tests, reduce hydraulically balanced debugging difficulty.
For convenience of description, it is divided into various unit to be respectively described with function when describing apparatus above.Certainly, this is being implemented The function of each unit can be realized in same or multiple softwares and/or hardware during application.
Each embodiment in this specification all uses the mode gone forward one by one to describe, identical similar portion between each embodiment Dividing and see mutually, what each embodiment stressed is the difference with other embodiments.Especially for device or For system embodiment, owing to it is substantially similar to embodiment of the method, so describing fairly simple, relevant part sees method The part of embodiment illustrates.
Apparatus and system embodiment described above is only schematically, wherein said illustrates as separating component Unit can be or may not be physically separate, and the parts shown as unit can be or may not be thing Reason unit, i.e. may be located at a place, or can also be distributed on multiple NE.Can select according to the actual needs Select some or all of module therein to realize the purpose of the present embodiment scheme.Those of ordinary skill in the art are not paying wound In the case of the property made work, i.e. it is appreciated that and implements.
Professional further appreciates that, in conjunction with the unit of each example that the embodiments described herein describes And algorithm steps, it is possible to electronic hardware, computer software or the two be implemented in combination in, in order to clearly demonstrate hardware and The interchangeability of software, the most generally describes composition and the step of each example according to function.These Function performs with hardware or software mode actually, depends on application-specific and the design constraint of technical scheme.Specialty Technical staff specifically should can be used for using different methods to realize described function to each, but this realization should not Think beyond the scope of this invention.
The method described in conjunction with the embodiments described herein or the step of algorithm can direct hardware, processor be held The software module of row, or the combination of the two implements.Software module can be placed in random access memory (RAM), internal memory, read-only deposit Reservoir (ROM), electrically programmable ROM, electrically erasable ROM, depositor, hard disk, moveable magnetic disc, CD-ROM or technology In any other form of storage medium well known in field.
Described above to the disclosed embodiments, makes professional and technical personnel in the field be capable of or uses the present invention. Multiple amendment to these embodiments will be apparent from for those skilled in the art, as defined herein General Principle can realize without departing from the spirit or scope of the present invention in other embodiments.Therefore, the present invention It is not intended to be limited to the embodiments shown herein, and is to fit to and principles disclosed herein and features of novelty phase one The widest scope caused.

Claims (10)

1. a hydraulically balanced adjustment method, it is characterised in that including:
Determine the product identification of hydraulic jacking tests to be debugged, obtain and described product identification phase from the data base pre-set Corresponding valve parameter curve;
Obtain the valve opening of described hydraulic jacking tests, determine corresponding with described valve opening according to described valve parameter curve Discharge coefficient;
Obtain the pressure difference at described hydraulic jacking tests two ends, calculate according to described pressure difference and described discharge coefficient and flow through described water The present flow rate of dynamic balance valve.
Adjustment method the most according to claim 1, it is characterised in that also include:
Receive on-site parameters investigation records;Described on-site parameters investigation records include area of heat-supply service parameter, pump operating condition parameter, The location parameter of each described hydraulic jacking tests in heating effect parameter, the pipeline parameter of heating network and described heating network And number parameter;
Debugging plan is formulated according to described on-site parameters investigation records;Described debugging plan includes debugging wheel number and often Wheel is the target flow of each described hydraulic jacking tests distribution in described heating network in debugging.
Adjustment method the most according to claim 1, it is characterised in that also include:
According to the debugging plan pre-established, send the target flow corresponding with described hydraulic jacking tests to operator, so that Described operator judges whether described present flow rate matches with described target flow, and in described present flow rate and described target When flow does not mates, the described valve opening of described hydraulic jacking tests is debugged, until described present flow rate and described mesh Mark flows match.
Adjustment method the most according to claim 1, it is characterised in that also include:
Receive the target flow corresponding with described hydraulic jacking tests;
Judge whether described present flow rate matches with described target flow;
If described present flow rate is not mated with described target flow, then send debugging instruction to operator;Described debugging instruction For indicating described operator that the described valve opening of described hydraulic jacking tests is debugged, so that described present flow rate and institute State target flow to match.
5. according to the adjustment method described in any one in claim 1-4, it is characterised in that also include:
Record debugging process, generates debugging report according to described debugging process;Described debugging report includes that operator's geography is fixed Position information and the data modification information of described hydraulic jacking tests;
Described debugging report is sent in server, in order to inquire about, revise and call.
6. a hydraulically balanced debugging system, it is characterised in that including:
Acquisition module, for determining the product identification of hydraulic jacking tests to be debugged, obtain from the data base pre-set with The valve parameter curve that described product identification is corresponding;
Determine module, for obtaining the valve opening of described hydraulic jacking tests, determine with described according to described valve parameter curve The discharge coefficient that valve opening is corresponding;
Computing module, for obtaining the pressure difference at described hydraulic jacking tests two ends, according to described pressure difference and described discharge coefficient Calculate the present flow rate flowing through described hydraulic jacking tests.
Debugging system the most according to claim 6, it is characterised in that also include:
Logging modle, is used for receiving on-site parameters investigation records;Described on-site parameters investigation records include area of heat-supply service parameter, Each described waterpower in pump operating condition parameter, heating effect parameter, the pipeline parameter of heating network and described heating network is put down The location parameter of weighing apparatus valve and number parameter;
Formulate module, for formulating debugging plan according to described on-site parameters investigation records;Described debugging plan includes tune Examination wheel number and often taking turns in debugging the target flow for each described hydraulic jacking tests distribution in described heating network.
Debugging system the most according to claim 6, it is characterised in that also include:
Sending module, for according to the debugging plan pre-established, sending corresponding with described hydraulic jacking tests to operator Target flow so that described operator judges whether described present flow rate matches with described target flow, and described currently When flow does not mates with described target flow, the described valve opening of described hydraulic jacking tests is debugged, work as until described Front flow matches with described target flow.
Debugging system the most according to claim 6, it is characterised in that also include:
Receiver module, for receiving the target flow corresponding with described hydraulic jacking tests;
Judge module, is used for judging whether described present flow rate matches with described target flow;
Debugging module, if do not mated with described target flow for described present flow rate, then sends debugging instruction to operator; Described debugging instruction is used for indicating described operator to debug the described valve opening of described hydraulic jacking tests, so that described Present flow rate matches with described target flow.
10. according to the debugging system described in any one in claim 6-9, it is characterised in that also include:
Generation module, is used for recording debugging process, generates debugging report according to described debugging process;Described debugging report includes The data modification information of operator's geo-localisation information and described hydraulic jacking tests;
Reporting modules, for being sent to described debugging report in server, in order to inquire about, revise and call.
CN201610393224.2A 2016-06-06 2016-06-06 A kind of hydraulically balanced adjustment method and system Pending CN106091101A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610393224.2A CN106091101A (en) 2016-06-06 2016-06-06 A kind of hydraulically balanced adjustment method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610393224.2A CN106091101A (en) 2016-06-06 2016-06-06 A kind of hydraulically balanced adjustment method and system

Publications (1)

Publication Number Publication Date
CN106091101A true CN106091101A (en) 2016-11-09

Family

ID=57447541

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610393224.2A Pending CN106091101A (en) 2016-06-06 2016-06-06 A kind of hydraulically balanced adjustment method and system

Country Status (1)

Country Link
CN (1) CN106091101A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107166407A (en) * 2017-05-22 2017-09-15 中国科学院力学研究所 A kind of valve opening adjusting method of waste incinerator
CN107940537A (en) * 2017-11-06 2018-04-20 珠海格力电器股份有限公司 Method and device for debugging floor heating system of water system
CN109724218A (en) * 2019-01-04 2019-05-07 青岛海信日立空调***有限公司 A kind of multi-gang air-conditioner ground heating system and control method
CN111928335A (en) * 2020-08-13 2020-11-13 大连海心信息工程有限公司 Secondary network hydraulic balance method based on intelligent valve

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102147623A (en) * 2011-05-29 2011-08-10 杭州哲达科技股份有限公司 Debugging method for static balance valve of hydraulic system
WO2011104419A1 (en) * 2010-02-26 2011-09-01 Metso Automation Oy Performance monitoring of a pump-valve system
CN103076048A (en) * 2012-12-29 2013-05-01 卓旦春 Method for measuring flow of valve
CN103092223A (en) * 2013-01-09 2013-05-08 卓旦春 Water power balancing debugging method of pipeline system
CN203223626U (en) * 2013-03-09 2013-10-02 卓旦春 Debugging system of valve
CN103486655A (en) * 2013-10-14 2014-01-01 卓旦春 Hydraulic equilibrium debugging device of heating and ventilating system and debugging method thereof
CN204345767U (en) * 2014-12-10 2015-05-20 成都声立德克技术有限公司 The hot distribution system of a kind of flow temperature method
CN204853661U (en) * 2015-06-25 2015-12-09 邹城市海玺商贸有限公司 Dynamic control system of heat supply network intelligence

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011104419A1 (en) * 2010-02-26 2011-09-01 Metso Automation Oy Performance monitoring of a pump-valve system
CN102147623A (en) * 2011-05-29 2011-08-10 杭州哲达科技股份有限公司 Debugging method for static balance valve of hydraulic system
CN103076048A (en) * 2012-12-29 2013-05-01 卓旦春 Method for measuring flow of valve
CN103092223A (en) * 2013-01-09 2013-05-08 卓旦春 Water power balancing debugging method of pipeline system
CN203223626U (en) * 2013-03-09 2013-10-02 卓旦春 Debugging system of valve
CN103486655A (en) * 2013-10-14 2014-01-01 卓旦春 Hydraulic equilibrium debugging device of heating and ventilating system and debugging method thereof
CN204345767U (en) * 2014-12-10 2015-05-20 成都声立德克技术有限公司 The hot distribution system of a kind of flow temperature method
CN204853661U (en) * 2015-06-25 2015-12-09 邹城市海玺商贸有限公司 Dynamic control system of heat supply network intelligence

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107166407A (en) * 2017-05-22 2017-09-15 中国科学院力学研究所 A kind of valve opening adjusting method of waste incinerator
CN107940537A (en) * 2017-11-06 2018-04-20 珠海格力电器股份有限公司 Method and device for debugging floor heating system of water system
CN107940537B (en) * 2017-11-06 2019-11-26 珠海格力电器股份有限公司 Method and device for debugging floor heating system of water system
CN109724218A (en) * 2019-01-04 2019-05-07 青岛海信日立空调***有限公司 A kind of multi-gang air-conditioner ground heating system and control method
CN111928335A (en) * 2020-08-13 2020-11-13 大连海心信息工程有限公司 Secondary network hydraulic balance method based on intelligent valve

Similar Documents

Publication Publication Date Title
CN106091101A (en) A kind of hydraulically balanced adjustment method and system
JP2021192292A (en) Computer systems and computer-implemented methods utilizing sensor-driven dynamically adjustable feedback loops to manage equipment-based risk on asset-specific level of energy data usage
CN103942726A (en) Intelligent inspection method for condition evaluation work of power grid equipment
KR102213710B1 (en) System for monitoring and sharing service of house management information
CN105184601A (en) Non-toxic decoration system and method
CN109800833A (en) A kind of material tracing and positioning management control system based on B/S framework
CN103455000A (en) SCADA system device modeling method for forming control logic automatically
CN106603344A (en) Household gateway bandwidth monitoring system and method
Markoska et al. Towards smart buildings performance testing as a service
JP6830784B2 (en) Information information system
US11888676B2 (en) Building management system with control framework
CN203980439U (en) Heat measuring system auto hydraulic balance control device
Shields et al. Revenue recovery through meter replacement
Butzbaugh et al. Automatic Fault Detection & Diagnostics: Residential Market Analysis
Sipilä et al. The building level substation–the innovation of district heating system
TW200634594A (en) Automobile inspection and repairs system
EP2508808A2 (en) Method for constructing a heating and/or drinking water heating assembly
CN205721934U (en) A kind of furniture enterprise quality control platform
Bernal Heredia et al. Case study: Field evaluation of a low-cost circuit-level electrical submetering system
KR20150121648A (en) Device requesting repair and method of the same
Heredia et al. Case Study: Laboratory and Field Evaluation of Circuit-Level Electrical Submetering with Wireless Current Transformers
Cadafalch et al. The OmniluS project
Hayden Choosing a heating system that saves energy
US20240258827A1 (en) Auto-scalable, resilient cloud-based power quality analysis engine
Marshall et al. The Ottawa Hospital Energy Management Program

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109