CN106089338A - A kind of back pressure machine association system regulating heat supply and generating and method - Google Patents

A kind of back pressure machine association system regulating heat supply and generating and method Download PDF

Info

Publication number
CN106089338A
CN106089338A CN201610385205.5A CN201610385205A CN106089338A CN 106089338 A CN106089338 A CN 106089338A CN 201610385205 A CN201610385205 A CN 201610385205A CN 106089338 A CN106089338 A CN 106089338A
Authority
CN
China
Prior art keywords
heat
water
moisturizing
boiler
back pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610385205.5A
Other languages
Chinese (zh)
Other versions
CN106089338B (en
Inventor
王祥图
许红胜
庄贺峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Original Assignee
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University filed Critical Southeast University
Priority to CN201610385205.5A priority Critical patent/CN106089338B/en
Publication of CN106089338A publication Critical patent/CN106089338A/en
Application granted granted Critical
Publication of CN106089338B publication Critical patent/CN106089338B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01KSTEAM ENGINE PLANTS; STEAM ACCUMULATORS; ENGINE PLANTS NOT OTHERWISE PROVIDED FOR; ENGINES USING SPECIAL WORKING FLUIDS OR CYCLES
    • F01K11/00Plants characterised by the engines being structurally combined with boilers or condensers
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22STEAM GENERATION
    • F22DPREHEATING, OR ACCUMULATING PREHEATED, FEED-WATER FOR STEAM GENERATION; FEED-WATER SUPPLY FOR STEAM GENERATION; CONTROLLING WATER LEVEL FOR STEAM GENERATION; AUXILIARY DEVICES FOR PROMOTING WATER CIRCULATION WITHIN STEAM BOILERS
    • F22D1/00Feed-water heaters, i.e. economisers or like preheaters
    • F22D1/50Feed-water heaters, i.e. economisers or like preheaters incorporating thermal de-aeration of feed-water
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/02Hot-water central heating systems with forced circulation, e.g. by pumps
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D2220/00Components of central heating installations excluding heat sources
    • F24D2220/10Heat storage materials, e.g. phase change materials or static water enclosed in a space

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Engine Equipment That Uses Special Cycles (AREA)

Abstract

The invention discloses a kind of back pressure machine association system regulating heat supply and generating and method, system includes that back pressure thermal power plant unit, boiler energy storage are for thermal sub-system and adiabatic compression air energy storage subsystem.When heat supply low ebb, unit oepration at full load, unnecessary heat supply after low-pressure turbine generates electricity, is first heated heat-storage medium, is reheated moisturizing energy storage in boiler;When heat supply peak, moisturizing changes the hot water in boiler into, increases external heating load;When heat demand is between 25 DEG C of rated heating capacities corresponding with 95 DEG C of moisturizing temperature, calculate and set reasonable feed temperature, regulation feedwater automatic controller so that unit oepration at full load.During low power consumption, by unnecessary electric energy compression storage, the heat produced in compression process is absorbed by moisturizing;During peak of power consumption, the air of compression absorbs the heat in heat storage can, and expansion power generation increases generated energy.The present invention can not only guarantee that unit efficient stable runs, and also can regulate generating according to need for electricity simultaneously.

Description

A kind of back pressure machine association system regulating heat supply and generating and method
Technical field
The invention belongs to heat supply and technical field of power generation, specifically relate to a kind of back pressure machine regulating heat supply and generating Association system and method.
Background technology
Along with industrial development and growth in the living standard, the production of China also gets more and more with life vapour.Steam power plant carries on the back The directly externally heat supply of press group steam discharge, in theory, the temperature-decreased pressure reducer that puts into operation when external heating load is more than back pressure machine heating load supplies Heat, and back pressure unit under-capacity operation when thermal load demands is less, but present situation is some steam power plant's back pressure unit is chronically at low Load operation operating mode so that back pressure type cogeneration of heat and power benefit is difficult to embody.
The principle of back pressure unit is electricity determining by heat, and thermic load directly determines electric load, and this just makes electric load be difficult to regulate.Add Domestic large area close down small-sized extraction and condensing unit, encourage development back pressure unit to take out solidifying thermal power plant unit with large-scale, this just makes electrical network adjust Peak energy power is more not enough.The difficulty of peak load regulation network is greatly increased, and also the utilization to other energy causes restriction, and thermoelectricity unit is such as What participates in peak regulation becomes the problem that power industry is in the urgent need to address.Run in order to ensure back pressure unit efficient stable, some heat Power plant takes such as installs the operation of rearmounted machine or the measure of energy-storage system after back pressure unit additional, it is ensured that back pressure thermal power plant unit is full Load operation, but now unit generation remains maximum generating watt, causes producing dump energy, peak of power consumption during low power consumption Time output not enough, do not mate with actual need for electricity, regulation is difficult.
Summary of the invention
In order to overcome the deficiencies in the prior art, it is an object of the invention to provide a kind of back of the body regulating heat supply and generating Press association system and method.This system ensures the long-term oepration at full load of back pressure unit, increases external heating load during with hot peak, Improve heat supply degree of amplitude modulation, reduce thermic load fluctuation regulation interval, reduce back pressure machine by adiabatic compression air energy storage subsystem Group coupled thermomechanics effect, regulates generating more neatly according to need for electricity.
For achieving the above object, present invention employs techniques below scheme: a kind of back pressure machine regulating heat supply and generating joins Assembly system, including back pressure thermal power plant unit, boiler energy storage for thermal sub-system and adiabatic compression air energy storage subsystem.
Described back pressure thermal power plant unit includes boiler, main steam turbine, main generator, oxygen-eliminating device, feed pump, temperature-decreased pressure reducer and High-pressure heater;The outfan of described boiler is divided into two branch roads, and wherein a branch road is by main steam line and main steam turbine Main inlet throttle-stop valve connects, and an other branch road is by the input of temperature-decreased pressure reducer with heat user
Connect;Described main steam turbine is connected with main generator, and described oxygen-eliminating device is connected with main steam turbine steam discharge and heats moisturizing, described High-pressure heater is connected with deaerator feedwater end by feed pump, described high-pressure heater outfan and boiler feedwater input phase Even, outfan hot water sends into boiler economizer.
Described boiler energy storage includes the first vapor-water heat exchanger, the second vapor-water heat exchanger, cold water storage cistern, hot water for thermal sub-system Case, feedwater automatic controller, water supply pump, heat-exchanger pump, low-pressure turbine, energy-reserving generator;Moisturizing conveyance conduit one tunnel and cold water The water inlet of case is connected, and another road is sequentially connected with the first vapor-water heat exchanger, the second vapor-water heat exchanger, boiler;Feedwater control automatically Device water inlet end processed is connected with cold water storage cistern, hot water tank outlet simultaneously, and described feedwater automatic controller water side intakes with oxygen-eliminating device Mouth is connected.
The heat that the moisturizing chemically come between waterwheel produces during absorbing compressed gas in the first vapor-water heat exchanger, just Step heating moisturizing in the second vapor-water heat exchanger with heating heat storage can in medium after steam discharge mixed heat transfer become 95 DEG C of heat Water is stored in boiler.
Described adiabatic compression air energy storage subsystem includes compressor, the first vapor-water heat exchanger, air accumulator, heat storage can and swollen Swollen generating equipment, the medium in described heat storage can is the high-temperature phase-change energy storage material of such as fuse salt or composite.
A kind of method regulating heat supply and the back pressure machine association system of generating, comprises the steps:
1) use heat demand low-valley interval, it is ensured that main steam turbine oepration at full load, meet power plant self and heat user heat supply need After asking, residue steam discharge first passes through low-pressure turbine generating, heats energy-accumulating medium subsequently into heat storage can, finally enters the second soda pop Heat exchanger, is mixed and heated to 95 DEG C by the moisturizing of entrance, is stored in boiler, now is controlled to enter by feedwater automatic controller The moisturizing of oxygen-eliminating device is 25 DEG C of cold water of cold water storage cistern;
2) using heat demand peak period, feedwater automatic controller controls to enter the moisturizing of oxygen-eliminating device by the 25 of cold water storage cistern DEG C of moisturizings Change 95 DEG C of hot water of boiler into, reduce oxygen-eliminating device heating steam consumption, increase external heating load;
3) it is being less than the rated heating capacity of moisturizing 95 DEG C with heat demand and is being more than the rated heating capacity period of moisturizing 25 DEG C, foundation Back pressure unit thermodynamic behaviour, sets back pressure unit oepration at full load in feedwater automatic controller and mates extraneous heating demand Feed temperature, enter the feedwater hot water of automatic controller and cool water quantity according to this set value calculation during actual motion so that supply Hot back pressure machine oepration at full load;
4) in the low power consumption period, being the most also to use heat demand low-valley interval, providing auxiliary power amount is stored up by compressor compresses air Can be in air accumulator, the heat absorption produced in air compression process is in the moisturizing by the first vapor-water heat exchanger.
5) in the peak of power consumption period, the most also it is non-heat supply low-valley interval, main steam turbine steam discharge all externally heat supply, low pressure Steam turbine is out of service, and in heat storage can, energy-accumulating medium stops heat absorption, and compressed air is after the energy-accumulating medium in heat storage can heats Becoming high temperature and high pressure gas, expansion power generation produces electricity when increasing Peak power use.
Generally electricity consumption reaches unanimity with hot peak interval of time, substantially from system work process, due to compressed air mistake Heat release in the first vapor-water heat exchanger in journey, with steam discharge heat accumulation during hot low ebb in heat storage can and boiler, boiler energy-storage system Relatively independent with adiabatic compression air energy storage systems, though therefore when electricity consumption with heat demand peak valley asynchronous time also have very well Matching.
The method of the present invention compared with the prior art, has the advantages that
(1) system that the present invention provides is ensureing unit stable operation at full capacity, is meeting external heating load, reduction thermic load fluctuation While regulation interval, it is possible to regulate electricity consumption more neatly according to electrical load requirement.
(2) system that the present invention provides can reduce back pressure unit coupled thermomechanics effect, enables heat supply cleverer with electricity consumption Regulate alively.
(3) heat absorption produced in air compression process is in moisturizing to be heated, absorbs during compressed air expansion power generation Energy-accumulating medium heat, regulates the hotspot stress of back pressure unit to a certain extent.
(4) heat supply and electrification energy storage regulation system relatively independent, electricity consumption with heat demand peak interval of time asynchronous time also have The preferably suitability.
Accompanying drawing explanation
Fig. 1 is the structural representation that the present invention regulates heat supply and the back pressure machine association system of generating;
Fig. 2 is certain steam power plant typical case in the summer day thermic load curve chart shown in embodiment 1;
Fig. 3 is the confession heat flow curve figure after the steam power plant shown in embodiment 1 uses association system;
Fig. 4 is that the steam power plant's generating shown in embodiment 1 regulates schematic diagram with need for electricity.
The explanation of Fig. 1 Main Reference Numerals: 1 boiler;2 temperature-decreased pressure reducers;3. main steam turbine;4 main generators;5 heat user; 6 low-pressure turbines;7 energy-reserving generators;8 oxygen-eliminating devices;9 feed pumps;10 high-pressure heaters;11 compressors;12 first steam-water heat exchangings Device;13 air accumulators;14 heat storage cans;15 expansion power generation equipment;16 second vapor-water heat exchangers;17 boilers;18 heat-exchanger pumps;19 feedwater Automatic controller;20 water supply pumps;21 cold water storage cisterns.
Detailed description of the invention
Below in conjunction with the accompanying drawings, by detailed description of the invention, the invention will be further described.
With reference to Fig. 1, the present invention provides a kind of back pressure machine association system regulating heat supply and generating, including back pressure heat supply machine Group, boiler energy storage are for thermal sub-system and adiabatic compression air energy storage subsystem.
Described back pressure thermal power plant unit includes that boiler 1, main steam turbine 3, main generator 4, oxygen-eliminating device 8, feed pump 9, desuperheat subtract Depressor 2 and high-pressure heater 10;The outfan of described boiler 1 is divided into two branch roads, and wherein a branch road passes through main steam line Being connected with main steam turbine 3 main inlet throttle-stop valve, an other branch road is connected with the input of heat user 5 by temperature-decreased pressure reducer 2;Described master Steam turbine 3 is connected with main generator 4, and described oxygen-eliminating device 8 is connected with main steam turbine 3 steam discharge and heats demineralized water, described hyperbaric heating Device 10 is connected to water end (W.E.) with oxygen-eliminating device 8 by feed pump 9, and described high-pressure heater 10 outfan and boiler 1 feed water input phase Even, outfan hot water sends into boiler economizer.
Described boiler energy storage includes first vapor-water heat exchanger the 12, second vapor-water heat exchanger 16, cold water storage cistern for thermal sub-system 21, boiler 17, feedwater automatic controller 19, water supply pump 20, heat-exchanger pump 18, low-pressure turbine 6, energy-reserving generator 7;Demineralized water Conveyance conduit one tunnel is connected with the water inlet of cold water storage cistern 21, and another road is sequentially connected with first vapor-water heat exchanger the 12, second soda pop and changes Hot device 16, boiler 17, feedwater automatic controller 19 water inlet end is connected with cold water storage cistern 21, boiler 17 outlet simultaneously, described Feedwater automatic controller 19 water side is connected with oxygen-eliminating device 8 water inlet.
The heat that the moisturizing chemically come between waterwheel produces during absorbing compressed gas in the first vapor-water heat exchanger 12, Preliminarily heated moisturizing in the second vapor-water heat exchanger 16 with heating heat storage can 14 in medium after steam discharge mixed heat transfer become 95 DEG C of hot water are stored in boiler 17.
Described adiabatic compression air energy storage subsystem includes compressor the 11, first vapor-water heat exchanger 12, air accumulator 13, heat accumulation Tank 14 and expansion power generation equipment 15, the high-temperature phase-change energy storage that medium is such as fuse salt or composite in described heat storage can 14 Material, this medium is only being heated by the steam discharge of low-pressure turbine 6 with hot low-valley interval, and remaining period stops heat absorption and adds hot compression Air, the compressed air of High Temperature High Pressure expands increases generated energy.
A kind of method regulating heat supply and the back pressure machine association system of generating, comprises the steps:
1) use heat demand low-valley interval, it is ensured that main steam turbine oepration at full load, meet power plant self and heat user heat supply need After asking, residue steam discharge first passes through low-pressure turbine generating, heats energy-accumulating medium subsequently into heat storage can, finally enters the second soda pop Heat exchanger, is mixed and heated to 95 DEG C by the moisturizing of entrance, is stored in boiler, now is controlled to enter by feedwater automatic controller The moisturizing of oxygen-eliminating device is 25 DEG C of cold water of cold water storage cistern;
2) using heat demand peak period, feedwater automatic controller controls to enter the moisturizing of oxygen-eliminating device by cold water storage cistern
25 DEG C of moisturizings change 95 DEG C of hot water of boiler into, reduce oxygen-eliminating device heating steam consumption, increase external heating load;
3) it is being less than the rated heating capacity of moisturizing 95 DEG C with heat demand and is being more than the rated heating capacity period of moisturizing 25 DEG C, foundation Back pressure unit thermodynamic behaviour, sets back pressure unit oepration at full load in feedwater automatic controller and mates extraneous heating demand Feed temperature, enter the feedwater hot water of automatic controller and cool water quantity according to this set value calculation during actual motion so that supply Hot back pressure machine oepration at full load;
4) in the low power consumption period, being the most also to use heat demand low-valley interval, providing auxiliary power amount is stored up by compressor compresses air Can be in air accumulator, the heat absorption produced in air compression process is in the moisturizing by the first vapor-water heat exchanger.
5) in the peak of power consumption period, the most also it is non-heat supply low-valley interval, main steam turbine steam discharge all externally heat supply, low pressure Steam turbine is out of service, and heat storage can energy-accumulating medium stops heat absorption, and compressed air becomes after the energy-accumulating medium in heat storage can heats Becoming high temperature and high pressure gas, expansion power generation produces electricity when increasing peak of power consumption.
Generally heat supply reaches unanimity, from system work process, during compressed air substantially with generating peak interval of time Heat release in the first vapor-water heat exchanger 12, with steam discharge energy storage during hot low ebb in heat storage can 14 and boiler 17, owing to boiler stores up Can system relatively independent with adiabatic compression air energy storage systems, even if therefore when electricity consumption with heat demand peak valley asynchronous time also have There is good matching.
Embodiment 1
With reference to Fig. 2, the present invention illustrates with typical case in the summer day thermic load curve of certain steam power plant, is specifically described back pressure machine association system Heat supply and generating regulation process, for other steam power plants, operation logic is identical.
Certain steam power plant's main steam turbine 3 rated generation power is 15MW, exhaust parameter be 1.27MPa, 292.7 DEG C, with heat need Ask and be 144.5t/h, minimum 82.7t/h to the maximum.When demineralized water moisturizing is 25 DEG C, external heat supply 111.4t/h;Work as demineralized water When moisturizing is 95 DEG C, external heat supply 125.6t/h.When the moisturizing of entrance oxygen-eliminating device 8 is changed into 95 DEG C of hot water by 25 DEG C of cold water, externally Heating load increases 14.2t/h.
In Fig. 2,23 when next day 6, the rated heating capacity of main steam turbine 3 when being 25 DEG C with heat demand less than moisturizing, this Time be heat supply low-valley interval.It is the desalination of 25 DEG C in cold water storage cistern 21 that feedwater automatic controller 19 controls to enter the moisturizing of oxygen-eliminating device 8 Water, it is ensured that unit oepration at full load, the unnecessary steam discharge of main steam turbine 3 enters low pressure back pressure machine 6 and generates electricity, and generated output is 2.5MW, energy-accumulating medium in low pressure back pressure machine 6 steam discharge heating heat storage can 14, finally mixes with moisturizing in the second vapor-water heat exchanger 16 Conjunction is heated to 95 DEG C and is stored in boiler 17
In.This period is also the low power consumption period, and main generator 4 and energy-reserving generator 7 generated output are 17.5MW.
In Fig. 2,6 up to 7 time, 17 up to 23 time, in this period heat demand less than moisturizing 95 DEG C rated heating capacity and More than the rated heating capacity of moisturizing 25 DEG C, the hot water that now feedwater automatic controller 19 enters according to set value calculation when running And cool water quantity, back pressure unit oepration at full load, and meet now use heat demand.
In Fig. 2,7 up to 17 time, and this period is heat supply peak period, and feedwater automatic controller 19 controls to enter oxygen-eliminating device 8 Moisturizing be the hot water of 95 DEG C in boiler 17, not enough heating load is compensated by regulating units.Low-pressure turbine 6 is in non-heat supply Low-valley interval is out of service, and in heat storage can 14, energy-accumulating medium stops heat absorption.
Fig. 3 is to use after association system typical case's day summer of main steam turbine 3 for heat flow curve, and dotted line is that peak regulation compensates and supplies Heat, before running with using association system compared with, reduce the frequent start-stop of regulating units during heat supply, peak regulation interval from 33.1t/h falls below 18.9t/h, it is ensured that the operation steady in a long-term of unit.
Fig. 4 is that the generating of typical case's day summer regulates schematic diagram with need for electricity, and curve 1 is to run adiabatic compression air energy storage System generating curve before subsystem, curve 2 is typical case in summer day electricity consumption demand curve.20 when next day 6, and this period is to use Electricity low-valley interval, main generator 4 and energy-reserving generator 7 generated output are 17.5MW, now produce electricity superfluous, enable compressed air storage Energy subsystem, compressed air is stored in air accumulator 13.6 is the peak of power consumption period up to 20 time, now compresses in air accumulator 13 Air after the energy-accumulating medium in heat storage can 14 heats, become high temperature and high pressure gas, expansion power generation produces electricity when increasing peak of power consumption Amount.
In Fig. 4, electricity consumption is to liking electricity consumer around steam power plant, and now back pressure machine association system product electricity is not surfed the Net, and meets thermoelectricity Electricity consumer demand around factory, on the spot production and marketing, it is achieved the flexible to need for electricity.For other steam power plants, when steam power plant is sent out During electricity online, running compressed-air energy storage subsystem, producing electricity has bigger regulation interval, and when Duo Jia steam power plant, back pressure unit is all adopted Run by association system mode and generate electricity online time, can increase produce electric adjustable interval, slow down electrical network electric load regulate difficulty.Figure 2 understand with Fig. 4, and heat supply peak interval of time is the most synchronize with electricity consumption peak interval of time, owing to boiler heat supply energy storage subsystem is with adiabatic Compressed-air energy storage subsystem is relatively independent, present invention shows the preferable suitability.
In implementation process of the present invention, back pressure unit remains oepration at full load, adds externally when with hot peak Heating load, reduces between heat fluctuation regulatory region;Produce dump energy, peak of power consumption when preferably reducing low power consumption simultaneously Time the not enough situation of output, regulate electricity consumption according to heat demand more flexibly, give a kind of back pressure thermal power plant unit association system Heat supply and the regulation System and method for of generating.
Heretofore described detailed description of the invention is only the preferable case study on implementation of the present invention, is not used for limiting this
Bright practical range.On the premise of without departing from the principle of the invention and content, it is also possible to make some improvement, these improve Also should be regarded as protection scope of the present invention.

Claims (5)

1. the back pressure machine association system regulating heat supply and generating, it is characterised in that: described system include back pressure thermal power plant unit, Boiler energy storage is for thermal sub-system and adiabatic compression air energy storage subsystem;
Described back pressure thermal power plant unit includes boiler, main steam turbine, main generator, oxygen-eliminating device, feed pump, temperature-decreased pressure reducer and high pressure Heater;The outfan of described boiler is divided into two branch roads, and wherein a branch road is by main steam line and the main vapour of main steam turbine Door connects, and an other branch road is connected with the input of heat user by temperature-decreased pressure reducer;Described main steam turbine and main generator Connecting, described oxygen-eliminating device is connected with main steam turbine steam discharge and heats moisturizing, and described high-pressure heater is given with oxygen-eliminating device by feed pump Water end (W.E.) is connected, and described high-pressure heater outfan is connected with boiler feedwater input, and outfan hot water sends into boiler economizer;
Described boiler energy storage for thermal sub-system include the first vapor-water heat exchanger, the second vapor-water heat exchanger, cold water storage cistern, boiler, Feedwater automatic controller, water supply pump, heat-exchanger pump, low-pressure turbine, energy-reserving generator;Moisturizing conveyance conduit one tunnel and cold water storage cistern Water inlet is connected, and another road is sequentially connected with the first vapor-water heat exchanger, the second vapor-water heat exchanger, boiler, and feed water automatic controller Water inlet end is connected with cold water storage cistern, hot water tank outlet simultaneously, described feedwater automatic controller water side and oxygen-eliminating device water inlet phase Even;
Described adiabatic compression air energy storage subsystem includes that compressor, the first vapor-water heat exchanger, air accumulator, heat storage can and expansion are sent out Electricity equipment.
Regulation heat supply the most according to claim 1 and the back pressure machine association system of generating, it is characterised in that: described boiler Energy storage is in thermal sub-system, and the moisturizing chemically come between waterwheel produces during absorbing compressed gas in the first vapor-water heat exchanger Heat, preliminarily heated moisturizing in the second vapor-water heat exchanger with heating heat storage can in medium after steam discharge mixed heat transfer become 95 DEG C of hot water are become to be stored in boiler.
Regulation heat supply the most according to claim 1 and 2 and the back pressure machine association system of generating, it is characterised in that: described storage Medium in hot tank is high-temperature phase-change energy storage material.
Regulation heat supply the most according to claim 3 and the back pressure machine association system of generating, it is characterised in that: described high-temperature-phase Change energy-storage material is fuse salt or composite.
5. control method based on the regulation heat supply described in claim 1 with the back pressure machine association system of generating, it is characterised in that: Comprise the steps:
Step (1), use heat demand low-valley interval, it is ensured that main steam turbine oepration at full load, meet power plant self and heat user After heat demand, residue steam discharge first passes through low-pressure turbine generating, heats energy-accumulating medium subsequently into heat storage can, finally enters the Two vapor-water heat exchangers, are mixed and heated to 95 DEG C by the moisturizing of entrance, are stored in boiler, now by feedwater automatic controller control System enters moisturizing is cold water storage cistern 25 DEG C of cold water of oxygen-eliminating device;
Step (2), using heat demand peak period, feedwater automatic controller controls to enter the moisturizing of oxygen-eliminating device by the 25 of cold water storage cistern DEG C moisturizing changes 95 DEG C of hot water of boiler into;
Step (3), with heat demand less than the rated heating capacity of moisturizing 95 DEG C and more than rated heating capacity period of moisturizing 25 DEG C, According to back pressure unit thermodynamic behaviour, feedwater automatic controller sets back pressure unit oepration at full load and mates extraneous heat supply The feed temperature of load, enters hot water and the cool water quantity of feedwater automatic controller, makes according to this set value calculation during actual motion Obtain heat supply back pressure machine oepration at full load;
Step (4), in the low power consumption period, be the most also to use heat demand low-valley interval, providing auxiliary power amount passes through compressor compresses The heat absorption that air energy storage produces in air accumulator, air compression process is in the moisturizing by the first vapor-water heat exchanger;
Step (5), in the peak of power consumption period, be the most also non-heat supply low-valley interval, all externally heat supplies of main steam turbine steam discharge, low Pressure steam turbine is out of service, and in heat storage can, energy-accumulating medium stops heat absorption, the storage in heat storage can of the compressed air in air accumulator Can become high temperature and high pressure gas after medium heating, expansion power generation produces electricity when increasing peak of power consumption.
CN201610385205.5A 2016-06-03 2016-06-03 A kind of back pressure machine association system and method adjusting heat supply and power generation Active CN106089338B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610385205.5A CN106089338B (en) 2016-06-03 2016-06-03 A kind of back pressure machine association system and method adjusting heat supply and power generation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610385205.5A CN106089338B (en) 2016-06-03 2016-06-03 A kind of back pressure machine association system and method adjusting heat supply and power generation

Publications (2)

Publication Number Publication Date
CN106089338A true CN106089338A (en) 2016-11-09
CN106089338B CN106089338B (en) 2018-09-14

Family

ID=57448214

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610385205.5A Active CN106089338B (en) 2016-06-03 2016-06-03 A kind of back pressure machine association system and method adjusting heat supply and power generation

Country Status (1)

Country Link
CN (1) CN106089338B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106989433A (en) * 2017-03-30 2017-07-28 德清县中能热电有限公司 A kind of tide heat reservoir and tide heat supply method
CN107504550A (en) * 2017-09-21 2017-12-22 广东电网有限责任公司电力科学研究院 A kind of hot co-feeding system of industrial park gas based on energy-storage system
CN108224535A (en) * 2018-01-18 2018-06-29 中国科学院工程热物理研究所 A kind of thermal power plant's cogeneration of heat and power and compressed-air energy storage complementation integrated system
CN108644859A (en) * 2018-07-17 2018-10-12 上海力顺燃机科技有限公司 A kind of the heat load adjustment system and its control method of gas turbine cogeneration of heat and power
CN108678819A (en) * 2018-04-23 2018-10-19 华北电力科学研究院有限责任公司 A kind of system for realizing thermoelectricity decoupling and quick peak regulation using bypass
CN109184831A (en) * 2018-10-17 2019-01-11 中国船舶重工集团公司第七0三研究所 It a kind of energy supply side can multipotency switching, the hot energy storage multipotency supply system of decoupling type
CN109307306A (en) * 2018-08-16 2019-02-05 爱能森新能源(深圳)有限公司 A kind of method and system of systems of distributed heating systems
CN110159372A (en) * 2019-06-26 2019-08-23 西安西热节能技术有限公司 A kind of system and method for realizing vapour pneumoelectric trilogy supply
CN110608073A (en) * 2019-09-30 2019-12-24 国网山东省电力公司电力科学研究院 Method for analyzing influence of back pressure on steam turbine generator unit and output space of steam turbine generator unit
CN110783961A (en) * 2019-12-06 2020-02-11 山东大学 Overwater photovoltaic system capable of reducing impact of grid connection on power grid
CN111706846A (en) * 2020-07-21 2020-09-25 宁波正源电力有限公司 System for adjusting heat supply peak valley by utilizing energy storage of high-pressure heater and operation mode
CN112460668A (en) * 2020-12-01 2021-03-09 福建晋江热电有限公司 Undisturbed heat storage system and method for peak valley filling of back pressure type heat supply unit

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11173109A (en) * 1997-12-05 1999-06-29 Pado:Kk Power generation and hot water supply system
CN104265458A (en) * 2014-07-31 2015-01-07 东南大学 Compressed air energy-storage power generation system and working mode thereof
CN104675458A (en) * 2015-02-09 2015-06-03 山东大学 Thermoelectricity combined supply type compressed air energy storage system and method for back pressure type thermoelectric unit
CN105201573A (en) * 2015-09-21 2015-12-30 东南大学建筑设计研究院有限公司 Back pressure turbine heat supply and energy storage system and heat supply and energy storage method thereof
CN105221345A (en) * 2015-09-26 2016-01-06 国网山东省电力公司济南供电公司 A kind of cogeneration type compressed-air energy-storage system and controlling method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11173109A (en) * 1997-12-05 1999-06-29 Pado:Kk Power generation and hot water supply system
CN104265458A (en) * 2014-07-31 2015-01-07 东南大学 Compressed air energy-storage power generation system and working mode thereof
CN104675458A (en) * 2015-02-09 2015-06-03 山东大学 Thermoelectricity combined supply type compressed air energy storage system and method for back pressure type thermoelectric unit
CN105201573A (en) * 2015-09-21 2015-12-30 东南大学建筑设计研究院有限公司 Back pressure turbine heat supply and energy storage system and heat supply and energy storage method thereof
CN105221345A (en) * 2015-09-26 2016-01-06 国网山东省电力公司济南供电公司 A kind of cogeneration type compressed-air energy-storage system and controlling method thereof

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106989433A (en) * 2017-03-30 2017-07-28 德清县中能热电有限公司 A kind of tide heat reservoir and tide heat supply method
CN107504550A (en) * 2017-09-21 2017-12-22 广东电网有限责任公司电力科学研究院 A kind of hot co-feeding system of industrial park gas based on energy-storage system
CN108224535A (en) * 2018-01-18 2018-06-29 中国科学院工程热物理研究所 A kind of thermal power plant's cogeneration of heat and power and compressed-air energy storage complementation integrated system
CN108224535B (en) * 2018-01-18 2020-03-24 中国科学院工程热物理研究所 Complementary integrated system of cogeneration of thermal power plant and compressed air energy storage
CN108678819A (en) * 2018-04-23 2018-10-19 华北电力科学研究院有限责任公司 A kind of system for realizing thermoelectricity decoupling and quick peak regulation using bypass
CN108678819B (en) * 2018-04-23 2024-01-26 华北电力科学研究院有限责任公司 System for realizing thermal decoupling and rapid peak shaving by utilizing bypass
CN108644859A (en) * 2018-07-17 2018-10-12 上海力顺燃机科技有限公司 A kind of the heat load adjustment system and its control method of gas turbine cogeneration of heat and power
CN109307306B (en) * 2018-08-16 2022-05-24 爱能森新能源(深圳)有限公司 Distributed heat supply method and system
CN109307306A (en) * 2018-08-16 2019-02-05 爱能森新能源(深圳)有限公司 A kind of method and system of systems of distributed heating systems
CN109184831A (en) * 2018-10-17 2019-01-11 中国船舶重工集团公司第七0三研究所 It a kind of energy supply side can multipotency switching, the hot energy storage multipotency supply system of decoupling type
CN109184831B (en) * 2018-10-17 2023-10-20 中国船舶重工集团公司第七0三研究所 Energy supply side multi-energy switching and decoupling type heat energy storage multi-energy supply system
CN110159372A (en) * 2019-06-26 2019-08-23 西安西热节能技术有限公司 A kind of system and method for realizing vapour pneumoelectric trilogy supply
CN110608073A (en) * 2019-09-30 2019-12-24 国网山东省电力公司电力科学研究院 Method for analyzing influence of back pressure on steam turbine generator unit and output space of steam turbine generator unit
CN110608073B (en) * 2019-09-30 2022-04-12 国网山东省电力公司电力科学研究院 Method for analyzing influence of back pressure on steam turbine generator unit and output space of steam turbine generator unit
CN110783961A (en) * 2019-12-06 2020-02-11 山东大学 Overwater photovoltaic system capable of reducing impact of grid connection on power grid
CN111706846A (en) * 2020-07-21 2020-09-25 宁波正源电力有限公司 System for adjusting heat supply peak valley by utilizing energy storage of high-pressure heater and operation mode
CN112460668A (en) * 2020-12-01 2021-03-09 福建晋江热电有限公司 Undisturbed heat storage system and method for peak valley filling of back pressure type heat supply unit

Also Published As

Publication number Publication date
CN106089338B (en) 2018-09-14

Similar Documents

Publication Publication Date Title
CN106089338B (en) A kind of back pressure machine association system and method adjusting heat supply and power generation
CN108224535A (en) A kind of thermal power plant's cogeneration of heat and power and compressed-air energy storage complementation integrated system
CN206845247U (en) One kind enhancing power plant flexibility therrmodynamic system
CN113202574A (en) Peak-shaving power generation system and method by coupling compressed air energy storage
CN112050177A (en) High-temperature molten salt heat storage steam storage and regulation system
CN116182138B (en) Deep peak regulation energy supply system and method for power generation by thermal-electrolytic coupling of coal-fired unit
CN108023360A (en) Avoided the peak hour and the participation peak load regulation network steam power plant of heat supply network heat accumulation and peak regulating method based on thermoelectricity
CN210483828U (en) Energy-saving power generation and utilization system utilizing exhaust steam waste heat of steam turbine of thermal power plant
WO2023226666A1 (en) Carbon dioxide energy storage system and method coupled with coal power unit
CN205400830U (en) 300MW grade fire coal is taken out combined heat and power units restriction steam extraction improvement heat supply with fixed attention and is compared system
CN109139153B (en) Heat storage type auxiliary peak shaving heat supply system and method for coal-fired generator set
CN206816307U (en) A kind of new thermoelectricity decoupling therrmodynamic system
CN209688799U (en) A kind of system that electric heat storage boiler cooperation Direct Air-cooled Unit participates in depth peak regulation
CN212319667U (en) Fused salt energy storage heat release system of thermal power plant
CN114991895A (en) Coal-fired power generating unit with coupled compressed air energy storage function and operation method thereof
CN111622814B (en) Method and system for controlling energy-saving operation of low-pressure cylinder of steam turbine based on real-time online operation data
CN208858422U (en) Thermal generation unit heat storage type assists peak regulation heating system
CN207333026U (en) A kind of comprehensive hospital energy supplying system based on gas turbine
CN215109066U (en) Natural gas distributed energy resource station based on heat accumulator
CN219366121U (en) CCPP unit cogeneration system
CN217712695U (en) Industry supplies vapour system based on fused salt energy storage
CN220151467U (en) Heat storage type water turbine and air-steam combined cycle cogeneration system
CN220750100U (en) Heating system of electrode boiler coupling screw expander
CN217055315U (en) Double-machine regenerative generator connecting system based on double-fed generator/motor
CN114718676B (en) Heat storage and release system for fused salt heated by coal-fired unit steam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant