CN106087959A - A kind of grouting strengthening method of effective minimizing building foundation uneven settlement - Google Patents
A kind of grouting strengthening method of effective minimizing building foundation uneven settlement Download PDFInfo
- Publication number
- CN106087959A CN106087959A CN201610509519.1A CN201610509519A CN106087959A CN 106087959 A CN106087959 A CN 106087959A CN 201610509519 A CN201610509519 A CN 201610509519A CN 106087959 A CN106087959 A CN 106087959A
- Authority
- CN
- China
- Prior art keywords
- slip casting
- grouting
- strengthening
- district
- casting district
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
Description
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610509519.1A CN106087959B (en) | 2016-06-30 | 2016-06-30 | A kind of effective grouting strengthening method for reducing building foundation uneven settlement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610509519.1A CN106087959B (en) | 2016-06-30 | 2016-06-30 | A kind of effective grouting strengthening method for reducing building foundation uneven settlement |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106087959A true CN106087959A (en) | 2016-11-09 |
CN106087959B CN106087959B (en) | 2018-05-18 |
Family
ID=57211617
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610509519.1A Active CN106087959B (en) | 2016-06-30 | 2016-06-30 | A kind of effective grouting strengthening method for reducing building foundation uneven settlement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106087959B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106968689A (en) * | 2017-03-21 | 2017-07-21 | 北京市政建设集团有限责任公司 | A kind of subregion for being adapted to the construction of tunnel proximate building strong grouting strengthening method such as not |
CN112796765A (en) * | 2021-01-07 | 2021-05-14 | 中铁十九局集团第三工程有限公司 | Partitioned grouting reinforcement method for tunnel adjacent building construction |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102704937A (en) * | 2011-03-28 | 2012-10-03 | 同济大学 | Method for identifying settlement pattern during shield tunnel construction |
CN102967481A (en) * | 2012-12-13 | 2013-03-13 | 青岛理工大学 | Method for determining action relationship between ground building and underground structure |
JP5378860B2 (en) * | 2009-03-31 | 2013-12-25 | 住友林業株式会社 | Foundation structure of buildings in soft ground |
CN103628920A (en) * | 2013-11-07 | 2014-03-12 | 广州市地下铁道总公司 | Early-warning and prediction method for sedimentation nearby tunnel construction working face |
CN104965994A (en) * | 2015-07-17 | 2015-10-07 | 青岛理工大学 | Method for measuring and estimating characteristic parameters of surface subsidence caused by subway tunnel construction |
-
2016
- 2016-06-30 CN CN201610509519.1A patent/CN106087959B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5378860B2 (en) * | 2009-03-31 | 2013-12-25 | 住友林業株式会社 | Foundation structure of buildings in soft ground |
CN102704937A (en) * | 2011-03-28 | 2012-10-03 | 同济大学 | Method for identifying settlement pattern during shield tunnel construction |
CN102967481A (en) * | 2012-12-13 | 2013-03-13 | 青岛理工大学 | Method for determining action relationship between ground building and underground structure |
CN103628920A (en) * | 2013-11-07 | 2014-03-12 | 广州市地下铁道总公司 | Early-warning and prediction method for sedimentation nearby tunnel construction working face |
CN104965994A (en) * | 2015-07-17 | 2015-10-07 | 青岛理工大学 | Method for measuring and estimating characteristic parameters of surface subsidence caused by subway tunnel construction |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106968689A (en) * | 2017-03-21 | 2017-07-21 | 北京市政建设集团有限责任公司 | A kind of subregion for being adapted to the construction of tunnel proximate building strong grouting strengthening method such as not |
CN112796765A (en) * | 2021-01-07 | 2021-05-14 | 中铁十九局集团第三工程有限公司 | Partitioned grouting reinforcement method for tunnel adjacent building construction |
Also Published As
Publication number | Publication date |
---|---|
CN106087959B (en) | 2018-05-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110130936B (en) | Construction method for sudden encountering untreated karst cave or crack in shield tunneling process | |
CN104631438B (en) | Long auger guncreting uplift pile construction method | |
CN110985055B (en) | Tunnel grouting and drainage synchronous construction method for controlling surface uplift | |
CN110864162B (en) | Construction process of argillaceous sandstone geological pipe jacking | |
CN104711987B (en) | A kind of deep covering layer sleeving valve tube method controllable grouting method | |
CN103866762A (en) | Pile body longitudinal multipoint grouting device | |
CN111706337B (en) | Construction method for shield to penetrate high-speed rail | |
CN105696550A (en) | Three axes agitating pile construction method capable of assisting in grooving of reinforced underground diaphragm wall | |
CN110685272B (en) | Method for treating soft foundation settlement overrun by utilizing inclined-hole cloth bag pile | |
CN109594575A (en) | A kind of open caisson periphery grouting and reinforcing soil body construction method | |
CN109440757A (en) | A kind of foundation reinforcement method for karst region | |
CN106087959A (en) | A kind of grouting strengthening method of effective minimizing building foundation uneven settlement | |
CN105569041B (en) | Borehole wall-protection method in the deep sand-pebble layer in karst area | |
CN106592615A (en) | Deviation rectification construction method for inclined sink | |
CN103510507A (en) | Slurry protection wall construction method with holes formed in cast-in-situ bored pile sand soil layer | |
CN207959202U (en) | A kind of CFG bracing means | |
CN110344394A (en) | A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method | |
CN206233232U (en) | A kind of upper and lower part expansion type soil cement is combined pile tube | |
CN209959261U (en) | Real-time feedback grouting device for correcting horizontal deformation of subway tunnel | |
CN205778943U (en) | A kind of duct pieces of shield tunnel that is applicable to settles the lifting system transfinited | |
CN205259188U (en) | Miniature pressure -bearing stake of bag pocket type of controllable slip casting scope | |
CN211816292U (en) | Sand-flow prevention device for water-rich sand layer anchor rod construction | |
CN106948315A (en) | A kind of stone masonry dam dam grouting reinforcing structure inferior and method | |
Cui | Nondestructive controllable grouting: a novel method to correct deviation of building foundation | |
CN104727305B (en) | Boring high-pressure slip-casting uplift pile construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Lian Xinzeng Inventor after: Zhu Xu Inventor after: Wang Hongbin Inventor after: Huang Mingli Inventor after: Li Jingyun Inventor after: Wang Haitao Inventor after: Zhao Jianming Inventor after: Qian Wenbin Inventor before: Lian Xinzeng Inventor before: Zhu Xu Inventor before: Huang Mingli Inventor before: Li Jingyun Inventor before: Wang Haitao Inventor before: Zhao Jianming Inventor before: Qian Wenbin |
|
GR01 | Patent grant | ||
GR01 | Patent grant |