CN106049971B - The installation method of the towering contactless suspender of noble metal tower mast - Google Patents

The installation method of the towering contactless suspender of noble metal tower mast Download PDF

Info

Publication number
CN106049971B
CN106049971B CN201610191760.4A CN201610191760A CN106049971B CN 106049971 B CN106049971 B CN 106049971B CN 201610191760 A CN201610191760 A CN 201610191760A CN 106049971 B CN106049971 B CN 106049971B
Authority
CN
China
Prior art keywords
contactless
noble metal
tower mast
metal tower
towering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610191760.4A
Other languages
Chinese (zh)
Other versions
CN106049971A (en
Inventor
王辉平
邓惠根
连珍
刘淳
江旖旎
周漪芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Building Decoration Engineering Group Co Ltd
Original Assignee
Shanghai Building Decoration Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Building Decoration Engineering Group Co Ltd filed Critical Shanghai Building Decoration Engineering Group Co Ltd
Priority to CN201610191760.4A priority Critical patent/CN106049971B/en
Publication of CN106049971A publication Critical patent/CN106049971A/en
Application granted granted Critical
Publication of CN106049971B publication Critical patent/CN106049971B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/22Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
    • B66C1/28Duplicate, e.g. pivoted, members engaging the loads from two sides

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention provides a kind of installation methods of the towering contactless suspender of noble metal tower mast, rod piece, contactless insurance support, the lower part hoop of four vertical expandable types by opening contactless suspender;The claw-like plug-in type overhanging stress levers support of contactless suspender is inserted into the preformed hole of towering noble metal tower mast lower part;Lower part hoop is connected to the rod piece of four vertical expandable types;Contactless insurance support is extended in place, it is fixed to support towering noble metal tower mast;After contactless suspender is lifted into position to be installed with crane; contactless suspender is removed from towering noble metal tower mast; the present invention can accomplish the lossless towering noble metal tower mast of lifting; it can support, towering noble metal tower mast is protected not damaged by external force friction; it is set there are enough safeties in hoisting process; can be achieved it is lossless under the conditions of towering noble metal tower mast horizontal and vertical movement, precisely installation is primary in place, the dismounting of suspender high-altitude is quick and easy, realize that primary lifting is completed.

Description

The installation method of the towering contactless suspender of noble metal tower mast
Technical field
The present invention relates to a kind of installation methods of the towering contactless suspender of noble metal tower mast.
Background technology
Frequently encountered in architectural engineering can not by the mechanical equipments such as tower crane to tower mast carry out mechanical erection, live tower crane without The problems such as local attached wall, often through dead man by lifting component, splicing, the spies such as that there are difficulty of construction coefficients is big, danger coefficient is high Point.On the other hand, tower mast rod piece is more, assembled complicated.Its technological requirement is also higher, more particularly to the towering tower mast knot of noble metal Structure, the more common tower mast of artistic component composition is increasingly complex, and the requirement for semi-finished product protection is more harsh, and on-site hoisting is necessary Accomplish lossless lifting.
The hoisting technology in China also has variation with rapid changepl. never-ending changes and improvements with the emergence of architectural engineering, can substantially be summarized as profit With mast lifting, crane hanging component, grid lifting, auxiliary device lifting, traction armed lever and traction rope lifting etc. modes, but no matter All there is following technology drawback in the hoisting technology of which kind of form:
1, it needs to lift by crane after carrying out banding fixed to component, different degrees of damage can be had to hanging piece surface, currently, also There is no a kind of lifting device of suitable touchless, lossless formula;
2, component need to be split into multiple unit multiple bearings, installation speed is slow;
3, upper air installing need to set up the mating scaffold equipment of 50m or more;
4, can not an integral hoisting, need that component is transported to eminence, difficulty of construction in advance using vertical transport equipment It increases;
5, high-altitude dismounting is inconvenient, and safety is insufficient.
So above-mentioned existing hoisting technology cannot be satisfied the lifting demand of noble metal tower mast, to ensure that surface is gilded layer And exquisite carve is injury-free during integral hoisting, cannot be lifted using traditional binding mode, and therefore, mesh It is preceding that there is an urgent need for the mating suspenders of design specialized noble metal tower mast non-contact type integral hoisting.
Invention content
The purpose of the present invention is to provide a kind of installation method of the towering contactless suspender of noble metal tower mast, can realize pair The non-contact type integral hoisting of towering noble metal tower mast.
To solve the above problems, the present invention provides a kind of installation method of the towering contactless suspender of noble metal tower mast, including:
Open rod piece, contactless insurance support, the lower part hoop of four vertical expandable types of contactless suspender;
The claw-like plug-in type overhanging stress levers support of contactless suspender is inserted into the reserved of towering noble metal tower mast lower part Kong Zhong;
Lower part hoop is connected to the rod piece of four vertical expandable types;
Contactless insurance support is extended in place, it is fixed to support towering noble metal tower mast;
After contactless suspender is lifted into position to be installed with crane, contactless suspender is torn open from towering noble metal tower mast It removes.
Further, in the installation method of the above-mentioned towering contactless suspender of noble metal tower mast, contactless insurance is supported Extend in place, after fixed the step of supporting towering noble metal tower mast, further includes:
Tower mast bolt claw-like plug-in type overhanging stress levers support is connected and fixed with towering noble metal tower mast.
Further, in the installation method of the above-mentioned towering contactless suspender of noble metal tower mast, the contactless insurance branch Support is the contactless insurance support of driven type or the contactless insurance support of rod-pulling type.
Further, in the installation method of the above-mentioned towering contactless suspender of noble metal tower mast, when the contactless insurance When support is that the contactless insurance of driven type supports, contactless insurance support is extended in place, including:
The flexible of the balancing pole that stretches is controlled by transmission device, and latch is made to engage with the tooth socket of corresponding position.
Further, in the installation method of the above-mentioned towering contactless suspender of noble metal tower mast, when the contactless insurance When support is that the contactless insurance of rod-pulling type supports, contactless insurance support is extended in place, including:
Movable cross bar is stretched and positioned by steel wire rope, telescopic device and pulley structure.
Further, in the installation method of the above-mentioned towering contactless suspender of noble metal tower mast, the tight flange plate bolt of bolt will After the step of contactless suspender is removed from towering noble metal tower mast, further include:
Upper cover plate is installed at the preformed hole position of the lower part of towering noble metal tower mast.
Further, in the installation method of the above-mentioned towering contactless suspender of noble metal tower mast, when every it is vertical deployable It is respectively set on the rod piece of formula there are one when L-shaped angle bar, lower part hoop is connected to the rod piece of four vertical expandable types, wrapped It includes:
Two free ends of each L-shaped angle bar are connect by bolt with a transverse bar member respectively.
Compared with prior art, the present invention is connect by the rod piece of four vertical expandable types of the contactless suspender of opening, nothing Touch insurance support, lower part hoop;The claw-like plug-in type overhanging stress levers support of contactless suspender is inserted into towering noble metal tower In the preformed hole of mast lower part;Lower part hoop is connected to the rod piece of four vertical expandable types;Contactless insurance is supported and is extended In place, fixed to support towering noble metal tower mast;After contactless suspender is lifted into position to be installed with crane, by contactless suspender from It is removed on towering noble metal tower mast, the present invention can accomplish the lossless towering noble metal tower mast of lifting, can support, protect towering noble metal Tower mast is not damaged by external force friction, so that it is had enough safeties in hoisting process, it can be achieved that towering expensive under the conditions of lossless The horizontal and vertical movement of metal tower mast, precisely installation are primary in place, the dismounting of suspender high-altitude is quick and easy, realize primary lifting It completes, reduces towering noble metal tower mast in high-altitude vertical transport and assembling operation time, improve the safety of its high-altitude application Property, the present invention integrally can lift by crane towering noble metal tower mast using contactless suspender and lifting rope, and working at height is avoided to endanger Danger, it is safe without setting up more than 50 meters high scaffolds.
Description of the drawings
Fig. 1 is the structure chart of the towering contactless sling system of noble metal tower mast of one embodiment of the invention;
Fig. 2 is that the blind of one embodiment of the invention wears installation guide frame figure;
Fig. 3 is the structure chart of the antitorque hanging dish-type hoop of cross of one embodiment of the invention;
Fig. 4 is the connection of the antitorque hanging dish-type hoop of cross of one embodiment of the invention and the rod piece of four vertical expandable types Schematic diagram;
Fig. 5 is the structure chart of the contactless insurance support of the driven type of one embodiment of the invention;
Fig. 6 is the structure chart of the contactless insurance support of the rod-pulling type of one embodiment of the invention;
Fig. 7 is the closure schematic diagram of the lower part hoop of one embodiment of the invention;
Fig. 8 is the dismounting schematic diagram of the lower part hoop of one embodiment of the invention;
Fig. 9 is the structure chart of the claw-like plug-in type overhanging stress levers support of one embodiment of the invention;
Figure 10 is the structure chart into formula double flange that covers of one embodiment of the invention;
Figure 11 is that the assembling tower mast on ground of one embodiment of the invention finishes upper contactless suspender schematic diagram in place;
Figure 12 is that claw-like plug-in type overhanging stress levers support is inserted into towering noble metal tower mast by one embodiment of the invention Schematic diagram in the preformed hole of lower part;
Figure 13 is the schematic diagram of the rod piece that lower part hoop is connected to four vertical expandable types of one embodiment of the invention;
Figure 14 is the schematic diagram extended contactless insurance support in place of one embodiment of the invention;
Figure 15 is the schematic diagram that contactless suspender is lifted into position to be installed with crane of one embodiment of the invention;
Figure 16 is the schematic diagram for removing contactless suspender from towering noble metal tower mast of one embodiment of the invention;
Figure 17 is that upper cover plate is installed at the preformed hole position in the lower part of towering noble metal tower mast of one embodiment of the invention Schematic diagram;
Figure 18 is that the guide rod of one embodiment of the invention and flange bolt dismantle schematic diagram.
Specific implementation mode
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, below in conjunction with the accompanying drawings and specific real Applying mode, the present invention is described in further detail.
As illustrated in fig. 1 and 2, the present invention provides a kind of towering contactless sling system of noble metal tower mast, including:
Contactless suspender, the contactless suspender includes the antitorque hanging dish-type hoop 3 of cross for being set to top, with described ten The rod piece 5 for four vertical expandable types that the antitorque hanging dish-type hoop 1 of word connects, connect contactless with 5 middle and upper part of the rod piece Insure support 2, the lower part hoop 3 being connect with 5 middle and lower part of the rod piece, and the claw-like plug-in type being connect with 5 bottom of the rod piece Overhang stress levers support 4, wherein the contactless insurance support 2, for the middle and upper part to the towering noble metal tower mast 6 Carry out contactless support, the claw-like plug-in type overhanging stress levers support 4, for the towering noble metal tower mast 6 Lower part is supported;Here, the antitorque hanging dish-type hoop of the cross at top 1 with lower loop hoop 3 is integral encircles system, ensure nothing The contactless insurance of contact suspender overall stability, middle and upper part supports 2, the lower part hoop 3 of middle and lower part and the claw-like of bottom to be inserted into Formula overhangs stress levers support 4 and forms three-point support trimming moment, ensures the safety of hoisting process, by contactless suspender, It can accomplish the lossless towering noble metal tower mast 6 of lifting, can support, towering noble metal tower mast 6 is protected not damaged by external force friction, make it Have enough safeties in hoisting process, it can be achieved that the horizontal and vertical movement of towering noble metal tower mast under the conditions of lossless, Precisely primary in place, the suspender high-altitude of installation dismounts quick and easy, realizes that primary lifting is completed, reduces towering noble metal tower mast Vertical transport and assembling operation time in high-altitude, the safety of its high-altitude application is improved, the present invention can utilize contactless hang Tool and lifting rope integrally lift by crane towering noble metal tower mast, avoid working at height dangerous, without setting up more than 50 meters high foot hand Frame, it is safe,
Blind to wear installation guide frame, the blind installation guide frame of wearing includes the bottom for being set to towering noble metal tower mast 6 Upper flange plate 7, be set to the lower flange 8 at position to be installed, wherein corresponded to respectively on the upper flange plate 7 and lower flange 8 It is provided with bolt hole 9, internal thread is provided in the bolt hole 9, ring flange is installed in the bolt hole 9 of the lower flange 8 Bolt 10 is provided with external screw thread on the flange plate bolt 10, is used for and the bolt on the upper flange plate 7 and lower flange 8 The separate screw cap end of the screw-internal thread fit in hole 9, the flange plate bolt 10 is connected with guide rod 11.Here, guide rod is convenient for blind When wearing, upper flange plate hole location is detected, upper flange plate docking location can be detected in hoisting process using guide rod, blind By lower flange integrally asymptotic movement during wearing, when touching upper flange plate hole location, forms upper and lower two-way ring flange, leads Couple to the entirety of bar, and effectively prevents bolt deflection direction in hoisting process and cause the spy of upper flange perforation difficulty Point is realized guide rod centrum principle smoothly importing upper flange plate, you can passes through external screw thread on bolt and the upper flange plate With the bolt hole screw-internal thread fit on lower flange, the tight flange plate bolt of bolt carries out dismounting guide rod.By towering noble metal tower mast It is fixed on position to be installed, accomplishes the disposable location and installation of towering noble metal tower mast, operation is by numerous change letter, efficiently, quickly, surely It is fixed.
Preferably, as shown in figure 3, the antitorque hanging dish-type hoop of the cross 1 includes:
Cross hang 12 is formed by two cross angle steel interconnections;
With the top hoop 13 of the support connection.Here, the antitorque hanging dish-type hoop design of cross can be effective against and hang The torque of dress process acts on, and plays antitorque effect.
Preferably, as shown in figure 3, the shape of the top hoop 13 is square, to ensure the antitorque hanging dish-type ring of cross The torsional strength of hoop.
Preferably, as shown in figure 3, one of each angle of the top hoop 13 of the square and the cross hang from It is connected by end, to be further ensured that the torsional strength of the antitorque hanging dish-type hoop of cross.
Preferably, as shown in figure 3, being additionally provided with lifting rope hole 14 in the cross hang, lifting rope is worn when facilitating lifting.
Preferably, as shown in figure 3, the rod piece 5 of every vertical expandable type, respectively with one of the cross hang 12 from It is connected by end, ensures the torsional strength of contactless suspender, can not reverse.
Preferably, as shown in figure 4, the rod piece 5 of every vertical expandable type passes through adjustable code part 15 and the cross-shaped The free end connection of support 12, facilitates freely being unfolded and being closed for the rod piece of every vertical expandable type.
Preferably, the contactless insurance support is the contactless insurance support of driven type or the contactless insurance branch of rod-pulling type Support.
Preferably, as shown in figure 5, it includes being set to the vertical expandable type that the contactless insurance of the driven type, which supports 2, Rod piece 5 on transmission device 21, four flexible balancing poles 22 being connect with the transmission device 21, four latches 23, each Latch 23 and every flexible balancing pole 22 are set on the rod piece 5 of a vertical expandable type, every flexible balancing pole 22 On be provided with the tooth socket coordinated with one of latch, the free end setting of every flexible balancing pole 22 is closed there are one a quarter Cyclization 24 is provided with rubber ring in each a quarter close ring 24.Here, controlling stretching for the balancing pole that stretches by transmission device Contracting, makes latch engage with the tooth socket of corresponding position, to adjust four flexible balancing pole collapsing lengths, the freedom of four balancing poles End forms close ring, and close ring most inner side uses rubber ring, can be fixed on the middle and upper part of towering noble metal tower mast described In close ring, realizes the contactless insurance clamping to towering noble metal tower mast, accomplish lossless fixation, prevent tower mast from lifting Lateral tilt, collision due to shaking is excessive in journey.
Preferably, as shown in fig. 6, it includes being respectively arranged at vertical expandable type that the contactless insurance of the rod-pulling type, which supports 2, Rod piece 5 on pulley 25, four movable cross bars 26, the telescopic device 27 being set on movable cross bar 26, with the flexible dress Set the steel wire rope 28 of 27 and the connection of pulley 25, wherein 5 activity of rod piece of every movable cross bar 26 and a vertical expandable type is even It connects, a quarter close ring 24 that there are one the free end settings of every movable cross bar 26, is set in each a quarter close ring 24 It is equipped with rubber ring.Here, movable cross bar is stretched and is positioned by steel wire rope, telescopic device and pulley structure, to adjust The free end of the collapsing length of the movable cross bar of four, section, four cross bars forms close ring, and close ring most inner side uses rubber The middle and upper part of towering noble metal tower mast, can be fixed in the close ring by circle, and realization connects the nothing of towering noble metal tower mast Insurance clamping is touched, accomplishes lossless fixation, prevents tower mast lateral tilt, collision due to shaking is excessive in hoisting process.
Preferably, as shown in fig. 7, the lower part hoop 3 includes four transverse directions being connect with the rod piece of vertical expandable type 5 Rod piece 31 encircles design up and down to be formed with top hoop 13, is formed whole.
Preferably, as shown in fig. 7, being respectively set on the rod piece 5 of every vertical expandable type there are one L-shaped angle bar 32, often Two free ends of a L-shaped angle bar 32 are connect with a transverse bar member 31 respectively, to ensure the rod piece of vertical expandable type with The bonding strength of transverse bar member.
Preferably, two free ends of each L-shaped angle bar 32 are connect by bolt 33 with a transverse bar member 31 respectively, from And realize and conveniently as shown in Figure 8 remove lower part hoop completely in the towering noble metal tower mast of fixation your towering gold fixed Lower part hoop is loaded onto again after belonging to tower mast, then is lifted by crane.
Preferably, as shown in figure 9, claw-like plug-in type overhangs stress levers support 4, including four claw-like support levers 41, Every claw-like support lever 41 is connect with the rod piece 5 of a vertical expandable type, reserved for extending into towering noble metal tower mast 6 Kong Zhong.
Preferably, the 5 extensible connection of rod piece of every claw-like support lever 41 and a vertical expandable type, facilitates every Support lever is extend into towering noble metal tower mast preformed hole.
Preferably, it is additionally provided with bolt hole in every claw-like support lever 41, facilitates every support lever to extend into towering After in noble metal tower mast preformed hole, by the cooperation of tower mast bolt and the bolt hole, every support lever is fixed on towering On noble metal tower mast.
Preferably, as shown in figs. 2 and 10, the shape of the guide rod 11 be it is cone-shaped, top point lower part is thick, i.e., with it is described The connecting pin of flange bolt 10 is thicker, and the free end far from the flange bolt 10 is thinner, and it is accurate and primary in place to meet it It is required that.
Preferably, as shown in figure 18, dismountable two components are made with the flange bolt 10 in the guide rod 11, with Guide rod is removed in the tight flange plate bolt of bolt.
Preferably, as shown in Figure 10, the system also includes be set to the blind of the towering noble metal tower mast bottom 6 to wear peace Fill the outer cover 61 outside guide frame, for accommodate it is blind wear installation guide frame, here, not destroy the aesthetics of tower mast moulding, Ad hoc meter is a kind of to be covered into formula double flange, can upper flange plate and lower flange be hidden in tower mast bottom completely.
The present invention also provides a kind of installation method of the towering contactless suspender of noble metal tower mast is as follows:
The first step:As shown in figure 11, the rod piece 5 of four vertical expandable types of contactless suspender, contactless insurance are opened Support 2, lower part hoop 3;At this point, the claw-like plug-in type overhanging stress levers support 4 of contactless suspender vertically may be used also with four The expansion of the rod piece of expansion and open;
Second step:As shown in figure 12, the claw-like plug-in type of contactless suspender overhanging stress levers support is inserted into towering expensive In the preformed hole 62 of 6 lower part of metal tower mast, to form lower part overhanging stress support, contactless suspender and towering noble metal tower Mast forms entirety, it is preferred that tower mast bolt claw-like plug-in type is overhang stress levers support and is connect admittedly with towering noble metal tower mast It is fixed, to improve support effect;
Third walks:As shown in figure 13, lower part hoop 3 is connected to the rod piece 5 of four vertical expandable types;Preferably, when It is respectively set on the rod piece of every vertical expandable type there are one when L-shaped angle bar, lower part hoop, which is connected to four vertically, to be opened up The rod piece of open type, including:Two free ends of each L-shaped angle bar are connect by bolt with a transverse bar member respectively;
4th step:As shown in figure 14, contactless insurance support 2 is extended in place, it is fixed to support towering noble metal tower mast 6, To prevent its lateral tilt, collision, it is preferred that contactless insurance support provides the selective use of two schemes, can be that nothing connects Insurance support is touched, can also be rod-pulling type contactless insurance support, here, when the contactless insurance supports as driven type without connecing When touching insurance support, contactless insurance support is extended in place, including:The flexible of the balancing pole that stretches is controlled by transmission device, Latch is set to engage with the tooth socket of corresponding position;When the contactless insurance support is that the contactless insurance of rod-pulling type supports, by nothing Contact insurance support extends in place, including:Movable cross bar is stretched and determined by steel wire rope, telescopic device and pulley structure Position.
5th step:As shown in figure 15, contactless suspender is lifted into position to be installed with crane;
6th step:As shown in Fig. 2 and 15, using the guide rod 11 on flange plate bolt by the upper of towering noble metal tower mast 6 After ring flange 7 is aligned with the bolt hole 9 of the lower flange 8 at position to be installed, as shown in figure 16 by contactless suspender from your towering gold Belong to and being removed on tower mast 6, to accomplish the disposable location and installation of towering noble metal tower mast, operation is simple by numerous change, efficient, quick, Stablize;It preferably, will be under the upper flange plate of towering noble metal tower mast and position to be installed using the guide rod on flange plate bolt The bolt hole of ring flange is aligned, including:Upper flange plate hole location is detected using the guide rod on lower flange, journey is passed through blind It is middle by lower flange integrally asymptotic movement, when guide rod touches the hole location of upper flange plate, guide rod is inserted into upper method Blue disk.
7th step:The tight flange plate bolt 10 of bolt, upper flange plate 7 and lower flange 8 are connected, and are realized towering noble metal Tower mast is fixed on position to be installed.
Preferably, further include the 8th step after above-mentioned 6th step or the 7th step:As shown in figure 17, in towering noble metal tower mast Upper cover plate 63 is installed at 62 position of preformed hole of 6 lower part, with cover it is blind wear installation guide frame, achieve the effect that it is overall beautiful, To complete the lifting of tower mast.
In conclusion the present invention opens the rod piece of four vertical expandable types of contactless suspender, contactless insurance supports, Lower part hoop;The claw-like plug-in type overhanging stress levers support of contactless suspender is inserted into the reserved of towering noble metal tower mast lower part Kong Zhong;Lower part hoop is connected to the rod piece of four vertical expandable types;Contactless insurance support is extended in place, fixed support Towering noble metal tower mast;After contactless suspender is lifted into position to be installed with crane, by contactless suspender from towering noble metal tower It is removed on mast, the present invention can accomplish the lossless towering noble metal tower mast of lifting, can support, protect towering noble metal tower mast not by external force Friction damage, so that it is had enough safeties in hoisting process, it can be achieved that towering noble metal tower mast under the conditions of lossless water It is gentle vertically move, precisely installation is primary in place, the dismounting of suspender high-altitude is quick and easy, realize that primary lifting is completed, reduce height Noble metal tower mast is alarmmed in high-altitude vertical transport and assembling operation time, improves the safety of its high-altitude application, and the present invention can be with Integrally towering noble metal tower mast is lifted by crane using contactless suspender and lifting rope, avoids working at height dangerous, it is super without setting up 50 meters of high scaffolds are crossed, it is safe.
Each embodiment is described by the way of progressive in this specification, the highlights of each of the examples are with other The difference of embodiment, just to refer each other for identical similar portion between each embodiment.
Obviously, those skilled in the art can carry out invention spirit of the various modification and variations without departing from the present invention And range.If in this way, these modifications and changes of the present invention belong to the claims in the present invention and its equivalent technologies range it Interior, then the present invention is also intended to including these modification and variations.

Claims (4)

1. a kind of installation method of the towering contactless suspender of noble metal tower mast, which is characterized in that including:
Open rod piece, contactless insurance support, the lower part hoop of four vertical expandable types of contactless suspender;
The claw-like plug-in type overhanging stress levers support of contactless suspender is inserted into the preformed hole of towering noble metal tower mast lower part;
Lower part hoop is connected to the rod piece of four vertical expandable types;
Contactless insurance support is extended in place, it is fixed to support towering noble metal tower mast, wherein the contactless insurance, which supports, is The contactless insurance support of driven type or the contactless insurance support of rod-pulling type, when the contactless insurance support is that driven type is contactless When insurance support, contactless insurance support is extended in place, including:The flexible of the balancing pole that stretches is controlled by transmission device, is made Latch engages with the tooth socket of corresponding position, to adjust four flexible balancing pole collapsing lengths, the free end shape of four balancing poles At close ring, close ring most inner side uses rubber ring, the middle and upper part of towering noble metal tower mast is fixed on the closure In annulus, the contactless insurance clamping to towering noble metal tower mast is realized;When the contactless insurance support is rod-pulling type without connecing When touching insurance support, contactless insurance support is extended in place, including:It will be lived by steel wire rope, telescopic device and pulley structure Dynamic cross bar is stretched and is positioned, and to adjust the collapsing length of four movable cross bars, the free end of four cross bars, which is formed, to be closed Annulus, close ring most inner side use rubber ring, the middle and upper part of towering noble metal tower mast are fixed in the close ring, Realize the contactless insurance clamping to towering noble metal tower mast;
After contactless suspender is lifted into position to be installed with crane, contactless suspender is removed from towering noble metal tower mast.
2. the installation method of the towering contactless suspender of noble metal tower mast as described in claim 1, which is characterized in that will be contactless Insurance support extends in place, after fixed the step of supporting towering noble metal tower mast, further includes:
Tower mast bolt claw-like plug-in type overhanging stress levers support is connected and fixed with towering noble metal tower mast.
3. the installation method of the towering contactless suspender of noble metal tower mast as described in claim 1, which is characterized in that will be contactless After the step of suspender is removed from towering noble metal tower mast, further include:
Upper cover plate is installed at the preformed hole position of the lower part of towering noble metal tower mast.
4. the installation method of the towering contactless suspender of noble metal tower mast as described in claim 1, which is characterized in that erected when every It is respectively set on the rod piece of expandable type there are one when L-shaped angle bar, lower part hoop is connected to four vertical expandable types Rod piece, including:
Two free ends of each L-shaped angle bar are connect by bolt with a transverse bar member respectively.
CN201610191760.4A 2016-03-30 2016-03-30 The installation method of the towering contactless suspender of noble metal tower mast Active CN106049971B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610191760.4A CN106049971B (en) 2016-03-30 2016-03-30 The installation method of the towering contactless suspender of noble metal tower mast

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610191760.4A CN106049971B (en) 2016-03-30 2016-03-30 The installation method of the towering contactless suspender of noble metal tower mast

Publications (2)

Publication Number Publication Date
CN106049971A CN106049971A (en) 2016-10-26
CN106049971B true CN106049971B (en) 2018-08-17

Family

ID=57484274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610191760.4A Active CN106049971B (en) 2016-03-30 2016-03-30 The installation method of the towering contactless suspender of noble metal tower mast

Country Status (1)

Country Link
CN (1) CN106049971B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107985323A (en) * 2017-12-07 2018-05-04 上海宇航***工程研究所 A kind of carrier rocket entrucking and railway transportation method
CN110469097B (en) * 2019-07-15 2024-06-04 上海市建筑装饰工程集团有限公司 Lifting inner and outer frame of tower mast structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CS275842B6 (en) * 1988-06-28 1992-03-18 Montas Equipment for steel chimneys dismantling
CN202414958U (en) * 2012-01-05 2012-09-05 湖南南方搏云新材料有限责任公司 Multifunctional lifting appliance
CN203319499U (en) * 2013-05-08 2013-12-04 中国海洋石油总公司 Shaft tube hoisting device
CN103626022A (en) * 2013-12-09 2014-03-12 天津市金万方钢结构有限公司 Steel coil hoisting tool
CN204096903U (en) * 2014-08-12 2015-01-14 中国南方电网有限责任公司超高压输电公司天生桥局 A kind of change of current becomes winding hoisting structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CS275842B6 (en) * 1988-06-28 1992-03-18 Montas Equipment for steel chimneys dismantling
CN202414958U (en) * 2012-01-05 2012-09-05 湖南南方搏云新材料有限责任公司 Multifunctional lifting appliance
CN203319499U (en) * 2013-05-08 2013-12-04 中国海洋石油总公司 Shaft tube hoisting device
CN103626022A (en) * 2013-12-09 2014-03-12 天津市金万方钢结构有限公司 Steel coil hoisting tool
CN204096903U (en) * 2014-08-12 2015-01-14 中国南方电网有限责任公司超高压输电公司天生桥局 A kind of change of current becomes winding hoisting structure

Also Published As

Publication number Publication date
CN106049971A (en) 2016-10-26

Similar Documents

Publication Publication Date Title
CN106044564B (en) The blind installation method for wearing installation guide frame
CN203760934U (en) Pulley device for cable laying
CN106049971B (en) The installation method of the towering contactless suspender of noble metal tower mast
CN108657969A (en) A kind of fulcrum type hoisting machine
CN205114843U (en) Prefabricated post hoist device with unhook function
CN106049970B (en) The installation method of the towering contactless sling system of noble metal tower mast
CN106044544B (en) The installation method of towering noble metal tower mast sling system
CN105822132A (en) Unit type assembly and erection method of extra-high-voltage power transmission iron pylon
CN207684728U (en) Towering noble metal tower mast sling system
CN204474202U (en) Large-tonnage steel member integrated hoisting fixture
CN106049969B (en) The towering contactless suspender of noble metal tower mast
CN208135719U (en) Claw-like plug-in type overhangs stress lever support structure
CN206569893U (en) Contactless insurance supporting construction
CN205855781U (en) The lower flange of guide
CN208218200U (en) Towering noble metal tower mast sling system
CN205857889U (en) The towering contactless suspender of noble metal tower mast
CN106044542B (en) Towering noble metal tower mast sling system
CN206544866U (en) It is blind to wear installation guide frame
CN106044549B (en) It covers and wears installation guide frame into formula double flange bolt is blind
CN207684735U (en) It covers and wears installation guide frame into formula double flange bolt is blind
CN106044543B (en) The towering contactless sling system of noble metal tower mast
CN206014235U (en) Three point supporting balance structure
CN205348817U (en) Safety belt pendant
CN208792732U (en) A kind of limited block for building
KR200486390Y1 (en) A folding hoist

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant