CN106013435B CN201610562471.0A CN201610562471A CN106013435B CN 106013435 B CN106013435 B CN 106013435B CN 201610562471 A CN201610562471 A CN 201610562471A CN 106013435 B CN106013435 B CN 106013435B
Authority
CN
China
Prior art keywords
precast beam
support frame
steel
prefabricated post
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610562471.0A
Other languages
Chinese (zh)
Other versions
CN106013435A (en
Inventor
高路恒
徐卫星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Huazheng Innovation Technology Research Institute Co ltd
Original Assignee
Nantong Textile Vocational Technology College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Textile Vocational Technology College filed Critical Nantong Textile Vocational Technology College
Priority to CN201610562471.0A priority Critical patent/CN106013435B/en
Publication of CN106013435A publication Critical patent/CN106013435A/en
Application granted granted Critical
Publication of CN106013435B publication Critical patent/CN106013435B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of prefabricated construction end bean column node fixed structure and installation methods, including prefabricated post and precast beam, the longitudinal prefabricated post muscle with outward extension of the prefabricated post, the precast beam is transversely provided with precast beam muscle, the end of the precast beam muscle is equipped with column and reserves side mode, unilateral tie support frame is additionally provided at the node of the handover of the prefabricated post and precast beam, the unilateral tie support frame includes the steel angle brace and steel column hoop being connected as one, the steel angle brace is used to support the support in place when precast beam lifting, steel column hoop is mounted in prefabricated post, carrying fulcrum as support frame.Structure of the invention is reasonable, and precast beam installation precision in place is high, and construction hoisting speed is fast, and tie support frame can be used in turn, and beam bottom support use compares, and traditional hanging method is many less, and saving Construction Cost has good economic benefit.

Description

A kind of prefabricated construction end bean column node fixed structure and installation method
Technical field
The present invention relates to a kind of bean column node fixed setting methods, and in particular to a kind of prefabricated construction end beam column Node fixed setting method.
Background technique
In recent years, prefabricated assembled continuous development and progress with new building technology and material, prefabrication It is widely used.In the country of many building industrialization prosperities, prefabrication experienced long-term experiment and Using, the prefabrication product of modernization can highly integrated building various functions, and the form built It is very exquisite with component.China's construction demand amount is big, construction speed is fast, it is necessary to develop prefabrication, then right Prefabricated construction joint structure requires and hoisting is also higher and higher.Traditional prefabricated construction hoisting cost compared with Height, lifting speed is low with precision, this brings very big difficulty to construction, and the adjustment of hoisting process error occupies largely Duration of a project, therefore, prefabrication lifting also need hanging method further to innovate and grind to realize industry modernization Study carefully.
Summary of the invention
Goal of the invention: the purpose of the present invention is to solve deficiency in the prior art, provide it is a kind of reasonable in design, Precast beam installs precision height in place, and construction hoisting speed is fast, and tie support frame can be used in turn, and beam bottom support use compares Traditional hanging method is many less, save Construction Cost a kind of prefabricated construction end beam-column node structure and its Fixed setting method.
Technical solution: a kind of prefabricated construction end bean column node fixed structure of the present invention, including it is prefabricated Column and precast beam, longitudinally prefabricated post muscle with outward extension, the precast beam are transversely provided with precast beam muscle, institute to the prefabricated post The end for stating precast beam muscle is equipped with column and reserves side mode, is additionally provided with unilateral tie at the node of the handover of the prefabricated post and precast beam Support frame, the unilateral tie support frame include the steel angle brace and steel column hoop being connected as one, and the steel angle brace is for branch The support in place when precast beam lifting is supportted, steel column hoop is mounted in prefabricated post, the carrying fulcrum as support frame.
Further, the closed triangular prism that the steel angle brace is made of 5 blocks of steel plates, steel column hoop are by 4 pieces of steel plate groups At upper and lower opening quadrangular, and steel angle brace and steel column hoop share one block of steel plate.
Further, the thickness of the steel plate is not less than 40mm.
Further, in a pre-installation, bullet has got well installation control line to the unilateral tie support frame on shaft.
Further, the unilateral tie support frame can be torn open when node strength reaches the 50% of concrete design strength It removes.
The invention also discloses a kind of above-mentioned installation method of prefabricated construction end bean column node fixed structure, packets Include following steps:
(1) prefabricated post lifts: prefabricated post lifting answers strict control column to lift quality, and Horizontal position errors are no more than 5mm, hangs down Straight error is no more than 3mm;
(2) play precast beam and lift absolute altitude control line: prefabricated post lifting fixation finishes, and lifts absolute altitude in shaft pop-up precast beam Control line, under special circumstances it is also contemplated that error transfer factor value;
(3) tie support frame and the installation of beam bottom bracket: precast beam is carried out according to shaft control line, error transfer factor value size and is hung Dress work in place;
(4) precast beam lifts, is fixed;
(5) precast beam Hoisting Position is reviewed, is adjusted;
(6) bean column node formwork erection;
(7) bean column node concreting, maintenance;
(8) tie support frame is removed, is had enough to meet the need.
The utility model has the advantages that structure of the invention is reasonable, precast beam installs precision height in place, and construction hoisting speed is fast, tie support Frame can be used in turn, and beam bottom support use traditional hanging method that compares is many less, save Construction Cost, with compared with Good economic benefit.
Detailed description of the invention
Fig. 1 is the overall schematic of node structure of the present invention;
Fig. 2 is the unilateral tie support frame structure diagram of the present invention.
Specific embodiment
A kind of prefabricated construction end bean column node fixed structure as depicted in figs. 1 and 2, including 5 He of prefabricated post Precast beam 3, the longitudinal prefabricated post muscle 6 with outward extension of the prefabricated post 5, the precast beam 3 are transversely provided with precast beam muscle 4, The end of the precast beam muscle 4 is equipped with column and reserves side mode 7, is additionally provided with list at the node of the handover of the prefabricated post 5 and precast beam 3 Side column hoop support frame, the unilateral tie support frame include the steel angle brace 1 being connected as one and steel column hoop (2), the steel Angle brace 1 is used to support the support in place when precast beam 3 lifts, and steel column hoop 2 is mounted in prefabricated post 5, the carrying as support frame Fulcrum.
The closed triangular prism that the steel angle brace 1 is made of 5 blocks of steel plates, steel column hoop 2 are made of upper and lower 4 blocks of steel plates The quadrangular of opening, two arms of angle can freely be unfolded, and steel angle brace 1 and steel column hoop 2 share one block of steel plate.
In a pre-installation, bullet has got well installation control line to the unilateral tie support frame on shaft, after guaranteeing beam lifting Precision in place.
The unilateral tie support frame rigidity is larger, and installation error adjusted value is easy to control, installation error general control Within 5mm.
The unilateral tie support frame turnaround speed is fast, (generally takes Concrete Design when node strength reaches preset value The 50% of intensity), it can first retain part conventional steel bracket, unilateral tie support frame, that is, dismountable realizes early removing system mesh Mark.
The invention also discloses a kind of above-mentioned installation method of prefabricated construction end bean column node fixed structure, packets Include following steps:
(1) prefabricated post lifts: prefabricated post lifting answers strict control column to lift quality, and Horizontal position errors are no more than 5mm, hangs down Straight error is no more than 3mm;
(2) play precast beam and lift absolute altitude control line: prefabricated post lifting fixation finishes, and lifts absolute altitude in shaft pop-up precast beam Control line, under special circumstances it is also contemplated that error transfer factor value;
(3) tie support frame and the installation of beam bottom bracket: precast beam is carried out according to shaft control line, error transfer factor value size and is hung Dress work in place;
(4) precast beam lifts, is fixed;
(5) precast beam Hoisting Position is reviewed, is adjusted;
(6) bean column node formwork erection;
(7) bean column node concreting, maintenance;
(8) tie support frame is removed, is had enough to meet the need.
Structure of the invention is reasonable, and precast beam installs precision height in place, and construction hoisting speed is fast, and tie support frame can have enough to meet the need It uses, beam bottom support use compares, and traditional hanging method is many less, and saving Construction Cost has good economic effect Benefit.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, though So the present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any technology people for being familiar with this profession Member, without departing from the scope of the present invention, when the technology contents using the disclosure above make a little change or modification For the equivalent embodiment of equivalent variations, but anything that does not depart from the technical scheme of the invention content, according to the technical essence of the invention Any simple modification, equivalent change and modification to the above embodiments, all of which are still within the scope of the technical scheme of the invention.

Claims (4)

1. a kind of prefabricated construction end bean column node fixed structure, it is characterised in that: including prefabricated post (5) and precast beam (3), the longitudinal prefabricated post muscle (6) with outward extension of the prefabricated post (5), the precast beam (3) are transversely provided with precast beam muscle (4), the end of the precast beam muscle (4) is equipped with column and reserves side mode (7), the section of the handover of the prefabricated post (5) and precast beam (3) It is additionally provided with unilateral tie support frame at point, the unilateral tie support frame includes the steel angle brace (1) and steel being connected as one Tie (2), the steel angle brace (1) are used to support the support in place when precast beam (3) lifting, and steel column hoop (2) is mounted on prefabricated post (5) the carrying fulcrum on, as support frame;
The closed triangular prism that the steel angle brace (1) is made of 5 blocks of steel plates, steel column hoop (2) are made of upper and lower 4 blocks of steel plates The quadrangular of opening, and steel angle brace (1) and steel column hoop (2) share one block of steel plate;
A kind of installation method of prefabricated construction end bean column node fixed structure, includes the following steps:
(1) prefabricated post lifts: prefabricated post lifting answers strict control column to lift quality, and Horizontal position errors are no more than 5mm, vertically accidentally Difference is no more than 3mm;
(2) play precast beam and lift absolute altitude control line: prefabricated post lifting fixation finishes, in shaft pop-up precast beam lifting absolute altitude control Line;
(3) precast beam lifting tie support frame and the installation of beam bottom bracket: is carried out just according to shaft control line, error transfer factor value size Position work;
(4) precast beam lifts, is fixed;
(5) precast beam Hoisting Position is reviewed, is adjusted;
(6) bean column node formwork erection;
(7) bean column node concreting, maintenance;
(8) tie support frame is removed, is had enough to meet the need.
2. a kind of prefabricated construction end bean column node fixed structure according to claim 1, it is characterised in that: institute The thickness of steel plate is stated not less than 40mm.
3. a kind of prefabricated construction end bean column node fixed structure according to claim 1, it is characterised in that: institute In a pre-installation, bullet has got well installation control line to the unilateral tie support frame stated on shaft.
4. a kind of prefabricated construction end bean column node fixed structure according to claim 1 or 3, feature exist In: the unilateral tie support frame can be removed when node strength reaches the 50% of concrete design strength.
CN201610562471.0A 2016-07-18 2016-07-18 A kind of prefabricated construction end bean column node fixed structure and installation method Active CN106013435B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610562471.0A CN106013435B (en) 2016-07-18 2016-07-18 A kind of prefabricated construction end bean column node fixed structure and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610562471.0A CN106013435B (en) 2016-07-18 2016-07-18 A kind of prefabricated construction end bean column node fixed structure and installation method

Publications (2)

Publication Number Publication Date
CN106013435A CN106013435A (en) 2016-10-12
CN106013435B true CN106013435B (en) 2019-01-08

Family

ID=57118139

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610562471.0A Active CN106013435B (en) 2016-07-18 2016-07-18 A kind of prefabricated construction end bean column node fixed structure and installation method

Country Status (1)

Country Link
CN (1) CN106013435B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107034989B (en) * 2016-12-05 2018-03-27 浙江省建工集团有限责任公司 A kind of prefabrication prefabricated components exempt to support installation method
CN106759880A (en) * 2016-12-29 2017-05-31 上海建工五建集团有限公司 Prefabricated superposed beam quickly positions adjustment frock and method with prefabricated post junction
CN106760572A (en) * 2016-12-29 2017-05-31 上海建工五建集团有限公司 Predetermined level component quickly positions adjustment frock and method with composite beam junction
CN106869308B (en) * 2017-03-13 2019-06-11 同济大学 A kind of quick turnover method of assembled architecture support system based on BIM
CN108622198B (en) * 2018-06-26 2024-02-20 青岛康泰镁业有限公司 Carriage bottom structure with triangular supporting structure
CN109296070A (en) * 2018-10-25 2019-02-01 安徽建筑大学 Novel assembled concrete frame beam column connected node
CN110644624A (en) * 2019-09-16 2020-01-03 佛山建装建筑科技有限公司 Building connection node and construction method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691412A (en) * 2012-06-05 2012-09-26 中国十七冶集团有限公司 Prefabricated frame structure connection supporting template with adjustable vertical height
CN104727440A (en) * 2014-11-17 2015-06-24 马恒忠 Novel industrialized production efficiently-assembled type building frame column beam and manufacturing method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100526573C (en) * 2008-08-28 2009-08-12 温州建设集团公司 Construction method of structure conversion layer concrete girder steel bracket formwork support
JP2010242390A (en) * 2009-04-07 2010-10-28 Toda Constr Co Ltd Joining method and structure of column-beam joint part having steel brace
CN202969586U (en) * 2012-12-10 2013-06-05 谌丹 Prefabricated concrete beam-column anchor welding combined structure
CN203603253U (en) * 2013-11-15 2014-05-21 华汇建设集团有限公司 Detachable steel corbel structure on reinforced concrete column
CN205894292U (en) * 2016-07-18 2017-01-18 江苏工程职业技术学院 Prefabricated assembly structure tip beam column node fixed knot constructs

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691412A (en) * 2012-06-05 2012-09-26 中国十七冶集团有限公司 Prefabricated frame structure connection supporting template with adjustable vertical height
CN104727440A (en) * 2014-11-17 2015-06-24 马恒忠 Novel industrialized production efficiently-assembled type building frame column beam and manufacturing method

Also Published As

Publication number Publication date
CN106013435A (en) 2016-10-12

Similar Documents

Publication Publication Date Title
CN106013435B (en) A kind of prefabricated construction end bean column node fixed structure and installation method
CN106013434B (en) Bean column node fixed structure and installation method among a kind of prefabricated construction
CN101619630B (en) Mounting method of steel chimney and implementary jacking device
CN104695337B (en) Self-lifting sliding and turnover construction system and construction method
CN208087078U (en) A kind of boom hoisting of large span steel reinforced concrete combination beam Bridge Erector
CN203878965U (en) Device for construction of elevator shaft
CN105926929A (en) Pouring construction method of straight wall concrete
CN105317205B (en) The construction method and equipment therefor of a kind of elevator
CN202544854U (en) Lining trolley for subway station
CN208618274U (en) A kind of assembled steel reinforced binding moulding bed group suitable for different size Precast T-Beams
CN103485574B (en) A kind of granulation tower tower top structure of reinforced concrete method
CN204781927U (en) Elevartor shaft formwork and elevartor shaft concrete placement operation platform
CN106381814A (en) Cast-in-cantilever structure of movable crane formwork of zigzag-form steel web continuous box beam and construction method of cast-in-cantilever structure
CN205894292U (en) Prefabricated assembly structure tip beam column node fixed knot constructs
CN202064281U (en) Slip form frame
CN102425140A (en) Special mobile support frame for high-altitude arch closing and construction method thereof
CN206233120U (en) Folding shape steel web continuous box girder jenny mould bases cantilever structure
CN206784172U (en) Overpass anti-collision wall formwork hoisting conveyance
CN202401753U (en) Sliding die device
CN203200664U (en) Slip-form construction device for variable cross-section hollow high pier
CN205894293U (en) Beam column node fixed knot constructs in middle of prefabricated assembly structure
CN201972099U (en) Through type hanging basket in bridge construction
CN107152112A (en) A kind of modularization Prefabricated stacking floor and its construction method for being used to drop plate region
CN115110765B (en) Construction method and device for shear wall at deformation joint
CN208543605U (en) Precast prestressed concrete composite beam production mould and production equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191220

Address after: 030000 No. 3, No. 24, 2nd floor, 15 Yam Shi Street, Xinghualing District, Taiyuan City, Shanxi Province

Patentee after: Ye Ling

Address before: 226000 Jiangsu Province, Nantong City Chongchuan District Youth Road No. 105

Patentee before: JIANGSU College OF ENGINEERING AND TECHNOLOGY

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221104

Address after: 030000 Room 415, Comprehensive Office Building, Phase II, Small and Micro Enterprise Park, Jinxiu Street, Taiyuan Yangqu Park, Taiyuan Demonstration Area, Shanxi Province

Patentee after: Shanxi Huazheng Innovation Technology Research Institute Co.,Ltd.

Address before: 030000 No. 3, No. 24, 2nd floor, 15 Yam Shi Street, Xinghualing District, Taiyuan City, Shanxi Province

Patentee before: Ye Ling

TR01 Transfer of patent right