CN105930968A - Passenger line construction risk control and early warning system - Google Patents

Passenger line construction risk control and early warning system Download PDF

Info

Publication number
CN105930968A
CN105930968A CN201610242437.5A CN201610242437A CN105930968A CN 105930968 A CN105930968 A CN 105930968A CN 201610242437 A CN201610242437 A CN 201610242437A CN 105930968 A CN105930968 A CN 105930968A
Authority
CN
China
Prior art keywords
construction
early warning
subsystem
risk
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610242437.5A
Other languages
Chinese (zh)
Inventor
王潇潇
卢海军
刘卫
冯德定
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201610242437.5A priority Critical patent/CN105930968A/en
Publication of CN105930968A publication Critical patent/CN105930968A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention discloses a passenger line construction risk control and early warning system which comprises a detection alarm subsystem for obtaining monitoring feedback information, confirming the reliability of a construction project, adjusting a corresponding parameter, and verifying or improving a design construction scheme, a risk prediction subsystem for comparing safety project data and a set safety threshold to determine a construction risk level and generating a corresponding early warning condition, a plan configuration subsystem which is used for monitoring a dangerous source, comparing the warning condition in an accident, sending accident information, and modifying an emergency plan. According to the invention, the comprehensive, timely and accurate grasp of a construction risk prevention and control condition can be realized, the construction management level is improved, the computerization of first line construction operations, and the construction efficiency is improved.

Description

Line for Passenger Transportation construction risk controls early warning system
Technical field
The invention belongs to Construction Technology field, be specifically related to a kind of Line for Passenger Transportation construction risk Control early warning system.
Background technology
Along with the development of Environment in Railway Engineering Construction, Environment in Railway Engineering Construction quality assurance and security performance more More paid attention to, the informationization such as Radio Transmission Technology, data mining, data analysis and process The technology application in engineering construction phase and operation phase is gradually increased, and informationization is built with railway engineering It is imperative if organically blending.Engineering construction at present data handling procedure ratio is relatively decentralized, it is impossible to Unified management, it is impossible to realize risk monitoring and control, therefore, it is information-based that tissue builds Environment in Railway Engineering Construction Platform, realize the function such as Risk-warning and statistical query be engineering construction at present be badly in need of solve difficulty Topic.
Summary of the invention
The purpose of the present invention is contemplated to solve the deficiency that above-mentioned background technology exists, it is provided that a kind of Line for Passenger Transportation construction risk controls early warning system.
The technical solution used in the present invention is: a kind of Line for Passenger Transportation construction risk controls early warning system, Including
Detection alert sub-system, for according to receive with quality and security-related project data Obtain monitoring feedback information with construction parameter, the reliability of construction work is confirmed, adjusts Corresponding parameter, checking or Curve guide impeller arrangement and method for construction;
Risk prediction subsystem, for the secure threshold by project data and construction parameter with setting Compare and determine construction risk grade, generate corresponding early-warning conditions;
Prediction scheme configuration subsystem, for real-time monitor hazardous source, contrasts early warning when accident occurs Condition, sends accident information, and revises emergency preplan.
Further, described prediction scheme configuration subsystem also includes for calling existing video monitoring Monitor hazardous source in real time;When accident occurs, contrast early-warning conditions, issue according to the information of prompting Program, sends information rapidly, provides function of statistic analysis to be used for accident of assessing simultaneously and damages Lose and coverage and size, revise emergency preplan and preserve;In the restoration and reconstruction stage Carry out examination and the assessment of reconstruction model.
Further, also include follow-up investigations subsystem, for according to project data and construction ginseng Number checks construction safety in real time, and the safety problem finding safety inspection carries out closed loop and disposes complete Process management.
Further, described closed loop disposal Whole Course Management includes the rectification of safety inspection problem Dynamic tracking and closed loop control, notice and Letter of Instructions management, safety inspection information inquiry and system Meter is analyzed and safety inspection manages all kinds of statistical report forms.
Further, also include accident transaction subsystem, be used for recording or revise accident treatment mistake Accident information in journey.
Further, also include security document subsystem, for the document of internal system is entered Row encryption, arranges user's search access right simultaneously.
The present invention can realize construction risk prevention and control situation comprehensively, in time, hold accurately, carry High construction management level, it is achieved the computerization of a line construction vocational work, improves efficiency of construction, Standard construction technological process, saving scene construction evidence, realizes the supervision of workmen and pipe Reason.Meanwhile, this system automatically generates construction safety information model, it is achieved that work progress time-varying Structure and the safety analysis of support system, progress, resource, the conflict analysis of cost and prediction, And early warning mechanism and decision support accordingly.Realize the construction of Line for Passenger Transportation high-quality safely and fast, And save man power and material in a large number, the beneficially scientification of decision-making, factor of reducing risks, evade wind Danger accident, the risk management consciousness improving construction participant and risk management ability, thus reach Control risk and reduce the purpose of loss.
Accompanying drawing explanation
Fig. 1 is the system block diagram of the present invention.
Detailed description of the invention
The present invention is described in further detail with specific embodiment below in conjunction with the accompanying drawings, just In being well understood to the present invention, but they do not constitute restriction to the present invention.
As it is shown in figure 1, the present invention include monitoring, alarming subsystem 1, risk prediction subsystem 2, Prediction scheme configuration subsystem 3, follow-up investigations subsystem 4, accident transaction subsystem 5 and security document Subsystem 6.Each subsystem is separate, is related the most mutually, and risk forecast system is by monitoring Early warning system warning message carries out risk forecast and pushes, and accident transaction subsystem configures according to prediction scheme System and follow-up investigations subsystem carry out the process of accident, investigate and close, and security document system The secure file to each subsystem of uniting is encrypted management.
Monitoring, alarming subsystem 1 with collect the Real-Time Measuring report by site operation technical staff Announcement, tunnel tunnel face mapping and advance geologic prediction report, be uploaded to system platform, Understood the actual effect of construction method by monitoring, and it is carried out fitness-for-service assessment, to obtain Monitoring feedback information be foundation, the reliability of tunnel and science of bridge building is confirmed, adjust Corresponding excavation, supporting parameter etc., checking or Curve guide impeller, arrangement and method for construction.
Risk prediction subsystem 2 built-in security threshold module, for by safety engineering data with set Fixed secure threshold is compared and is determined construction risk grade, according to secure threshold by risk class It is divided into level Four: I level (especially severe), II level (seriously) III level (more serious), IV level ( As) represent by red, orange, yellow and green successively.
Prediction scheme configuration subsystem 3 includes dangerous matter sources monitoring, early warning action, information report and processes Etc..System can call the systems such as existing video monitoring, for real-time monitor hazardous source; During just in case there being accident to occur, early-warning conditions can be contrasted, according to the information release process of prompting, will Information sends rapidly.System can provide function of statistic analysis be used for assessing causality loss with And coverage and size, it is possible to amendment emergency preplan also preserves easily.Recovering weight Building the stage, utilisation system carries out examination and the assessment of reconstruction model.
Follow-up investigations subsystem 4 major function includes the safety that the safety inspection of classification finds Problem closed loop disposes Whole Course Management, dynamic tracking and the closed loop control to the rectification of safety inspection problem System, notice and Letter of Instructions management, safety inspection information inquiry and statistical analysis, safety inspection Manage all kinds of statistical report form.Safety inspection works after realistic typing, and system is according to its related service Process rule and enter different message processing flow, related personnel at different levels by writing instructions and transfer, reporting, whole Change, feed back, audit, the issue handling service link such as return safety problem is processed, and Final pin number, different accountability unit are respectively completed respective process, constitute complete safety problem Information processing overall process closed loop management and control.
In accident transaction subsystem 5, manager carries out according to accident investigating the investigation report drawn Accuse, upload the related accessories data such as investigation report accident protocol.By typing, revise, mend Record, issue, forward, report the accident information of generation, and accident information is pushed to project bears Duty people, by system platform by users at different levels according to authority query-related information.
Security document subsystem 6 is implemented by " safety management " module, by safety literary composition Document can be encrypted by group system, and users at different levels are according under authority and cipher inquiry Carry relevant documentation information.
The present invention control early warning system by Environment in Railway Engineering Construction with quality and security-related engineering Data and construction parameter are uploaded to this platform, and are analyzed data processing, it is achieved risk is pre- The functions such as police and statistical query, accomplish that quality control is known what's what.Wherein monitoring, alarming subsystem and Risk prediction subsystem, is combined into the core of monitoring system, is monitored the collection of data, place Reason, comprehensive analysis and early warning are issued.This systematic study defines the people that construction management field relates to The Resource information mode such as power, machinery, material, by setting up Resource information mode and construction meter Draw, information integration mechanism that cost and construction site information model are associated, build construction excellent Change information model analyze working sources and the dynamic relationship between the construction period and not with construction work Dynamic relationship between phase and the uncertain event impact on the duration of a project, it is achieved that rationally Working sources under the conditions of duration and the optimization in place and right under certain resource and site condition Working procedure is optimized.This system automatically generates construction safety information model, it is achieved that construction Process Time variable structure and the safety analysis of support system, progress, resource, the conflict analysis of cost And prediction, and early warning mechanism and decision support accordingly.Realize Line for Passenger Transportation the highest Quality Construction, and save man power and material in a large number.
The content not being described in detail in this specification belongs to known to professional and technical personnel in the field Prior art.

Claims (6)

1. a Line for Passenger Transportation construction risk controls early warning system, it is characterised in that: include
Detection alert sub-system, for according to receive with quality and security-related project data Obtain monitoring feedback information with construction parameter, the reliability of construction work is confirmed, adjusts Corresponding parameter, checking or Curve guide impeller arrangement and method for construction;
Risk prediction subsystem, for the secure threshold by project data and construction parameter with setting Compare and determine construction risk grade, generate corresponding early-warning conditions;
Prediction scheme configuration subsystem, for real-time monitor hazardous source, contrasts early warning when accident occurs Condition, sends accident information, and revises emergency preplan.
A kind of Line for Passenger Transportation construction risk the most according to claim 1 controls early warning system, It is characterized in that: described prediction scheme configuration subsystem also includes for calling existing video monitoring real Time monitor hazardous source;When accident occurs, contrast early-warning conditions, issue journey according to the information of prompting Sequence, sends information rapidly, provides function of statistic analysis to be used for assessing causality loss simultaneously And coverage and size, amendment emergency preplan preserving;Enter in the restoration and reconstruction stage The examination of row reconstruction model and assessment.
A kind of Line for Passenger Transportation construction risk the most according to claim 1 controls early warning system, It is characterized in that: also include follow-up investigations subsystem, for according to project data and construction parameter Check construction safety in real time, and the safety problem finding safety inspection carries out closed loop and disposes full mistake Thread management.
A kind of Line for Passenger Transportation construction risk the most according to claim 3 controls early warning system, It is characterized in that: described closed loop is disposed Whole Course Management and included moving safety inspection problem rectification State is followed the tracks of and closed loop control, notice and Letter of Instructions management, safety inspection information inquiry and statistics Analyze and safety inspection manages all kinds of statistical report forms.
A kind of Line for Passenger Transportation construction risk the most according to claim 1 controls early warning system, It is characterized in that: also include accident transaction subsystem, be used for recording or revising incident processing procedure In accident information.
A kind of Line for Passenger Transportation construction risk the most according to claim 1 controls early warning system, It is characterized in that: also include security document subsystem, for the document of internal system is added Close, user's search access right is set simultaneously.
CN201610242437.5A 2016-04-19 2016-04-19 Passenger line construction risk control and early warning system Pending CN105930968A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610242437.5A CN105930968A (en) 2016-04-19 2016-04-19 Passenger line construction risk control and early warning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610242437.5A CN105930968A (en) 2016-04-19 2016-04-19 Passenger line construction risk control and early warning system

Publications (1)

Publication Number Publication Date
CN105930968A true CN105930968A (en) 2016-09-07

Family

ID=56838375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610242437.5A Pending CN105930968A (en) 2016-04-19 2016-04-19 Passenger line construction risk control and early warning system

Country Status (1)

Country Link
CN (1) CN105930968A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108960647A (en) * 2018-07-11 2018-12-07 宿州云宏建设安装有限公司 A kind of highway construction security risk assessment system
CN113705963A (en) * 2021-07-16 2021-11-26 福建省海洋预报台 Offshore emergency method and terminal

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108960647A (en) * 2018-07-11 2018-12-07 宿州云宏建设安装有限公司 A kind of highway construction security risk assessment system
CN113705963A (en) * 2021-07-16 2021-11-26 福建省海洋预报台 Offshore emergency method and terminal

Similar Documents

Publication Publication Date Title
Wu et al. A new accident causation model based on information flow and its application in Tianjin Port fire and explosion accident
CN110505102B (en) Power information communication fusion monitoring and service standardization management platform system and method
CN104778414B (en) A kind of Vulnerability Management system and method
CN101497342A (en) System integrated supervision method and system thereof of self-movement special equipment safe operation
CN103941652A (en) Method and device suitable for security protection and security audit of various DCS production control systems
CN103257918A (en) Project test procedure management method based on software testing and evaluation platform
CN105469248A (en) Method for lean control of full life circle of subjects in power marketing inspection
CN112598368A (en) Sewage treatment online supervision platform
CN111598411A (en) Intelligent safety control system for operation site of transformer substation
CN105205624A (en) Enterprise probity risk monitoring system
CN112837195A (en) Block chain-based environment monitoring system and method
CN105184519A (en) Standardized safety operation tracing management system
CN116227918A (en) Supervision method and system for medicine safety
CN116957341A (en) Intelligent safety risk management and control system based on steel mill
CN105930968A (en) Passenger line construction risk control and early warning system
CN115239144A (en) Dual prevention mechanism information system based on regional risk management
CN109376876A (en) A kind of highway device intelligence cruising inspection system
CN108710978A (en) Enterprise management method and system and computer readable storage medium
CN117375241A (en) Visual management method and system for soft pressing plate of secondary equipment of digital substation
CN116911596A (en) Worker risk early warning method and system based on operation stability model
CN109493571B (en) Alarm system based on radiation environment monitoring data
CN111667243A (en) Business audit system based on ERP system
CN113869758A (en) Intelligent two-ticket management and operation site risk early warning system
CN115619212A (en) Intelligent chemical industry park big data analysis method based on block chain
CN110544026A (en) Railway transportation safety monitoring system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160907