CN105891101A CN201610397694.6A CN201610397694A CN105891101A CN 105891101 A CN105891101 A CN 105891101A CN 201610397694 A CN201610397694 A CN 201610397694A CN 105891101 A CN105891101 A CN 105891101A
Authority
CN
China
Prior art keywords
reinforcing bar
concrete
corrosion
test block
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610397694.6A
Other languages
Chinese (zh)
Other versions
CN105891101B (en
Inventor
曹忠露
米胜东
陈浩宇
李沛
苏忠纯
王娜
张鹏
杨建军
雷周
周晓朋
周佰祥
朱明轩
夏志远
谢丽霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
Tianjin Port Engineering Institute Ltd of CCCC Frst Harbor Engineering Co Ltd
Tianjin Harbor Engineering Quality Inspection Center Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
Tianjin Port Engineering Institute Ltd of CCCC Frst Harbor Engineering Co Ltd
Tianjin Harbor Engineering Quality Inspection Center Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, Tianjin Port Engineering Institute Ltd of CCCC Frst Harbor Engineering Co Ltd, Tianjin Harbor Engineering Quality Inspection Center Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201610397694.6A priority Critical patent/CN105891101B/en
Priority to CN201810129665.0A priority patent/CN108469410A/en
Publication of CN105891101A publication Critical patent/CN105891101A/en
Application granted granted Critical
Publication of CN105891101B publication Critical patent/CN105891101B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N17/00Investigating resistance of materials to the weather, to corrosion, or to light
    • G01N17/02Electrochemical measuring systems for weathering, corrosion or corrosion-protection measurement

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Ecology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Environmental Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Testing Resistance To Weather, Investigating Materials By Mechanical Methods (AREA)

Abstract

The invention discloses a detection device and method for steel bar macrocell corrosion in concrete. The device comprises two steel bar concrete corrosion detection units, and each steel bar concrete corrosion detection unit comprises a steel bar concrete composite structure, a pipeline and a wire, wherein the steel bar concrete composite structure comprises a concrete test block and a steel bar, the steel bar is arranged in center of the concrete test block, the portion, stretching out of the concrete test block, of the steel bar is provided with a sealing layer, one end of the steel bar is connected with the wire, hole channels are formed in the concrete test block, and the two ends of the hole channels are connected with the pipeline in a sealing mode; the two steel bar concrete corrosion detection units are arranged in a same containing vessel, water in contained in the containing vessel, and the wires of the two steel bar concrete corrosion detection units are communicated and provided with a switch. The detection device and method have the advantages that the structure is simple, operation is convenient, an analytical method is simple and clear, the microcell corrosion effect and the macrocell corrosion effect of the steel bars can be comprehensively and synthetically evaluated, and the control modes steel bar macrocell corrosion in various corrosion environments can be illustrated.

Description

The detection apparatus and method of reinforcement in concrete macro cell corrosion
Technical field
The invention belongs to reinforcement corrosion guard technology field, more particularly, it relates to the grand electricity of reinforcement in concrete The detection apparatus and method of pond corrosion.
Background technology
Reinforced Concrete Materials because of its low cost, easily construct and there is good plasticity and durability, thus It is widely used in various industrial civil building, water conservancy project or sea work structure.Generally in xoncrete structure, The high alkalinity environment that hydrated cementitious produces, can make rebar surface form one layer of ferrum oxygen that can resist reinforcement corrosion Compound protective layer.But, along with chloride ion, the nuisance such as sulfate ion and carbon dioxide is constantly from outside Carrying out of the concrete structure crack that environment causes toward infiltration and external environment condition and load in concrete, this ferrum Instability that protective oxide film gradually becomes and go to pot, and then excite the corrosion of reinforcing bar.
Research to Steel Corrosion In Concrete Structures at present, is based primarily upon micro-cell corrosion theoretical, by dividing The half-cell prtential of analysis reinforcing bar and corrosion rate evaluate its corrosion condition, seldom theoretical based on macro cell corrosion, Its corrosion condition is evaluated by analyzing the macro cell polarization characteristic of negative electrode reinforcing bar and anode reinforcing bar.Half-cell electricity The Appreciation gist of position is ASTM C876 standard, and whether this standard pin is in passive state or corrosion to reinforcing bar State, simply show a probability judgement, and this judgement suffers the impact of dry and wet environment the biggest;Secondly, This standard is only applicable to alkalescence xoncrete structure, for carbonated concrete structure inapplicable, and works as coagulation When soil structure exists macro cell corrosion, use half-cell prtential method will cause bigger erroneous judgement.By linear pole Change the Corrosion Rate of Steel that impedance method, electrochemical impedance Atlas Method or electrochemical noise method obtain, usually used as Micro-cell corrosion speed, this corrosion rate only just true rotten close to reinforcing bar when macro cell corrosion is left in the basket Erosion speed.Owing to the true corrosion rate of reinforcing bar is micro-cell corrosion speed and macro cell corrosion speed sum, again Owing to generally existing in the macro cell corrosion of active service Steel Bars in Concrete Structure, so using linear polarization Impedance method and electrochemical impedance Atlas Method will underestimate the corrosion rate of reinforcing bar, affect reinforcement corrosion protection effect Rational evaluation.Therefore theoretical based on micro-cell corrosion, by analyzing half-cell prtential and the corrosion speed of reinforcing bar It is inaccurate and insecure that degree evaluates its corrosion condition.
In micro-cell corrosion, cathode chamber and anode region coexist alternately, and corrosion is also uniform;And In the xoncrete structure of reality, cathode chamber and anode region are separate and apart from each other, and corrosion is not, This formation making it easy to cause reinforcing bar macro cell corrosion.When reinforcing bar is under macro cell corrosion state, anode The electronics of reinforcement corrosion release is transferred to negative electrode reinforcing bar and is consumed by negative electrode reinforcing bar, thus is formed from negative electrode Reinforcing bar flows to the macro cell current of anode reinforcing bar, and then causes the corrosion potential of anode reinforcing bar towards positive potential side (cloudy towards negative direction reduction to the corrosion potential increasing (the macro cell polarization of anode reinforcing bar) and negative electrode reinforcing bar The macro cell polarization of pole reinforcing bar).Therefore the corrosion evaluating Steel Bars in Concrete Structure is considered as its macro cell corrosion Polarization characteristic and control mechanism.
Summary of the invention
It is an object of the invention to overcome the deficiencies in the prior art, for the problems referred to above, be proposed for concrete The detection apparatus and method of middle reinforcing bar macro cell corrosion.Present configuration is simple, easily operated, it is possible to realize The micro-cell corrosion state of reinforcing bar and the alternate cycles change of macro cell corrosion state, analyze cathode steel intuitively Macro cell potential difference, macro cell corrosion electric current, negative electrode reinforcing bar and anode reinforcing bar between muscle and anode reinforcing bar Polarization ratio and polarization slope, can the suppression to reinforcing bar macro cell corrosion of the effectively evaluating each corrosion protection technology Effect, additionally it is possible to illustrate the control mechanism of reinforcing bar macro cell corrosion under various corrosive environment.
For realizing above-mentioned technical purpose, the present invention proposes following technical scheme:
A kind of armored concrete composite construction, including concrete test block and reinforcing bar, wherein: steel-bar arrangement is mixed The middle position of solidifying soil test block;Along concrete test block length direction, reinforcing bar runs through whole concrete test block, and Concrete test block is stretched out at reinforcing bar two ends;Arranging duct on concrete test block, described duct is uniformly arranged on one On the individual reinforcing bar the to be arranged on concrete test block middle position circumference as the center of circle, and along concrete test block length Direction, whole concrete test block is run through in duct.
In technique scheme, the quantity in duct is 26, preferably 46.
In technique scheme, a length of 160-200mm of concrete test block, width is 60-100mm, high Degree is 60-100mm.
In technique scheme, a diameter of 6-20mm in duct, the distance of duct centre distance reinforcing steel bar center For 6-20mm.
Use technique scheme, reinforcing bar and duct carried out position cooperation, simple in construction, easy to use and Can effectively simulate the corrosive environment of reinforcing bar, it is simple to the research to reinforcement corrosion.
For the armored concrete composite construction of corrosion test, including armored concrete composite construction, pipeline, Wire, wherein: armored concrete composite construction, including concrete test block and reinforcing bar, steel-bar arrangement is at coagulation The middle position of soil test block;Along concrete test block length direction, reinforcing bar runs through whole concrete test block, and steel Concrete test block is stretched out at muscle two ends;Arranging sealant at the two ends of reinforcing bar, one end of reinforcing bar is connected with wire;
Arranging duct on concrete test block, described duct is uniformly arranged on one to be arranged on concrete test block The reinforcing bar of middle position is on the circumference in the center of circle, and along concrete test block length direction, duct runs through whole mixed The test block of solidifying soil;The two ends in duct are connected with seal for pipe joints respectively;Pipeline opening straight up, and pipeline tapping Higher than concrete test block, it is full of duct realizing liquid.
In technique scheme, the quantity in duct is 26, preferably 46.
In technique scheme, a length of 160-200mm of concrete test block, width is 60-100mm, high Degree is 60-100mm.
In technique scheme, a diameter of 6-20mm in duct, the distance of duct centre distance reinforcing steel bar center For 6-20mm.
In technique scheme, arranging screw and packing ring in one end of reinforcing bar, screw is screwed into steel through packing ring Inside muscle, wire is connected with screw or packing ring, to realize the UNICOM of wire and the measurement circuit of reinforcing bar;And Wire passes sealant.
In technique scheme, sealant is polystyrene resin layer.
In technique scheme, sealant covers the two ends of the reinforcing bar stretching out concrete test block, and extends to Reinforcing bar in oversite concrete test block in concrete test block.
In technique scheme, in concrete test block, a length of 30-50mm of reinforcing bar that sealant covers.
Use technique scheme, utilize the pipeline of opening straight up to load solution (example to concrete test block Such as Chloride Solution, water, mortar etc.), and utilize law of connected vessels make in pipeline liquid level higher than concrete test block, To maintain solution diffusion in concrete test block, so the corrosion condition of follow-on test reinforcing bar, simple in construction, Easy to use and can effectively simulate the corrosive environment of reinforcing bar, it is simple to the research to reinforcement corrosion.
A kind of steel reinforced concrete erosion test cell, including armored concrete composite construction, pipeline, wire, Wherein: armored concrete composite construction, including concrete test block and reinforcing bar, steel-bar arrangement is at concrete test block Middle position;Along concrete test block length direction, reinforcing bar runs through whole concrete test block, and reinforcing bar two ends Stretch out concrete test block;Arranging sealant at the two ends of reinforcing bar, one end of reinforcing bar is connected with wire;
Arranging duct on concrete test block, described duct is uniformly arranged on one to be arranged on concrete test block The reinforcing bar of middle position is on the circumference in the center of circle, and along concrete test block length direction, duct runs through whole mixed The test block of solidifying soil;The two ends in duct are connected with seal for pipe joints respectively;Pipeline is connected with reserving liquid tank, and on pipeline Pump and effusion meter are set, to realize by the one end in duct, liquid in reserving liquid tank is entered concrete test block, another End flows out and is back to reserving liquid tank, utilizes the cooperation of pump and effusion meter, it is achieved to liquid in pipeline and hole simultaneously The control of flow velocity and adjustment in road.
In technique scheme, the quantity in duct is 26, preferably 46.
In technique scheme, a length of 160-200mm of concrete test block, width is 60-100mm, high Degree is 60-100mm.
In technique scheme, a diameter of 6-20mm in duct, the distance of duct centre distance reinforcing steel bar center For 6-20mm.
In technique scheme, arranging screw and packing ring in one end of reinforcing bar, screw is screwed into steel through packing ring Inside muscle, wire is connected with screw or packing ring, to realize the UNICOM of wire and the measurement circuit of reinforcing bar;And Wire passes sealant.
In technique scheme, sealant is polystyrene resin layer.
In technique scheme, sealant covers the two ends of the reinforcing bar stretching out concrete test block, and extends to Reinforcing bar in oversite concrete test block in concrete test block.
In technique scheme, in concrete test block, a length of 30-50mm of reinforcing bar that sealant covers.
Use technique scheme, utilize pipeline, pump and effusion meter to load solution (such as to concrete test block Chloride Solution, water, mortar etc.), and realize the direct control to flow velocity, brief introduction controls solution at concrete Diffusion in test block, and then the corrosion condition of follow-on test reinforcing bar, simple in construction, easy to use and can have The corrosive environment of effect simulation reinforcing bar, it is simple to the research to reinforcement corrosion.
The detection device of reinforcement in concrete macro cell corrosion, including two steel reinforced concrete erosion test cells, Container, two of which steel reinforced concrete erosion test cell is arranged in same container, and Container arranges water;Two steel reinforced concrete erosion test cell structures are identical, and each reinforced concrete Soil corrosion test unit, including armored concrete composite construction, pipeline and wire, two armored concrete corruption Erosion test cell selects structure or the second armored concrete of the first steel reinforced concrete erosion test cell The structure of corrosion test unit: wherein
In the structure of the first steel reinforced concrete erosion test cell, armored concrete composite construction, including Concrete test block and reinforcing bar, steel-bar arrangement is in the middle position of concrete test block;Along concrete test block length side To, reinforcing bar runs through whole concrete test block, and concrete test block is stretched out at reinforcing bar two ends;Set at the two ends of reinforcing bar Putting sealant, one end of reinforcing bar is connected with wire;Arranging duct on concrete test block, described duct is uniform Be arranged on one with on the reinforcing bar circumference as the center of circle being arranged on concrete test block middle position, and along concrete Test block length direction, whole concrete test block is run through in duct;The two ends in duct are connected with seal for pipe joints respectively; Pipeline opening straight up, and pipeline tapping is higher than concrete test block, is full of duct realizing liquid;
In the structure of the second steel reinforced concrete erosion test cell, armored concrete composite construction, including Concrete test block and reinforcing bar, steel-bar arrangement is in the middle position of concrete test block;Along concrete test block length side To, reinforcing bar runs through whole concrete test block, and concrete test block is stretched out at reinforcing bar two ends;Set at the two ends of reinforcing bar Putting sealant, one end of reinforcing bar is connected with wire;Arranging duct on concrete test block, described duct is uniform Be arranged on one with on the reinforcing bar circumference as the center of circle being arranged on concrete test block middle position, and along concrete Test block length direction, whole concrete test block is run through in duct;The two ends in duct are connected with seal for pipe joints respectively; Pipeline is connected with reserving liquid tank, and arranges pump and effusion meter on pipeline, to realize liquid in reserving liquid tank by hole The one end in road enters concrete test block, and the other end flows out and is back to reserving liquid tank, utilizes pump and effusion meter simultaneously Cooperation, it is achieved control and the adjustment to liquid flow velocity in pipeline and duct;
Switch is set between two steel reinforced concrete erosion test cells, switch respectively with two armored concrete Wire in corrosion test unit is connected.
In technique scheme, the quantity in duct is 26, preferably 46.
In technique scheme, a length of 160-200mm of concrete test block, width is 60-100mm, high Degree is 60-100mm.
In technique scheme, a diameter of 6-20mm in duct, the distance of duct centre distance reinforcing steel bar center For 6-20mm.
In technique scheme, arranging screw and packing ring in one end of reinforcing bar, screw is screwed into steel through packing ring Inside muscle, wire is connected with screw or packing ring, to realize the UNICOM of wire and the measurement circuit of reinforcing bar;And Wire passes sealant.
In technique scheme, sealant is polystyrene resin layer.
In technique scheme, sealant covers the two ends of the reinforcing bar stretching out concrete test block, and extends to Reinforcing bar in oversite concrete test block in concrete test block.
In technique scheme, in concrete test block, a length of 30-50mm of reinforcing bar that sealant covers.
The detection method of reinforcement in concrete macro cell corrosion, in a steel reinforced concrete erosion test cell Reinforcing bar is anode reinforcing bar, and the reinforcing bar in another steel reinforced concrete erosion test cell is negative electrode reinforcing bar, according to The following step is carried out:
Step 1, uses the water in flat vessel that two steel reinforced concrete erosion test cells are carried out moistening, with Make between two steel reinforced concrete erosion test cells, to form the electricity general character;
In step 1, by all or part of for concrete test block in two steel reinforced concrete erosion test cells It is immersed in the water, to simulate the macro cell corrosion of different humidity or underwater concrete, such as by two reinforced concretes In soil corrosion test unit, concrete test block is immersed in the water 3-5mm.
Step 2, by pipeline injection experiments liquid in the duct of concrete test block;
In step 2, experimental liquid is Chloride Solution or corrosion inhibitor solution.
Step 3, uses determinator to be connected with steel reinforced concrete erosion test cell;
In described step 3, determinator is corrosion diagnosis instrument or steel bar corrosion instrument or electrochemical workstation Or zero resistance galvanometer, in actual use, require to be attached according to the use of each determinator.
Step 4: disconnect the wire between negative electrode reinforcing bar and anode reinforcing bar, persistently measure the micro cell of negative electrode reinforcing bar Corrosion potential Emi-cWith micro-cell corrosion electric current density imi-c, the micro-cell corrosion current potential E of anode reinforcing barmi-aWith Micro-cell corrosion electric current density imi-a
Step 5: connect the wire between negative electrode reinforcing bar and anode reinforcing bar, the macro cell of test constantly negative electrode reinforcing bar Corrosion unit Ema-c, the macro cell corrosion current potential E of anode reinforcing barma-a, between negative electrode reinforcing bar and anode reinforcing bar flow Dynamic macro cell corrosion electric current density ima=ima-c=ima-a
Step 6: step 4 and step 5 are tried as a cycle period, repetition step 4 and step 5 Test.
In described step 4, anode reinforcing bar and cathode steel tendon breaking open state (i.e. micro-cell corrosion state) Time is 24 weeks (i.e. one week is 7 days, and every day is 24 hours), in order to negative electrode reinforcing bar and anode reinforcing bar Between the recovery of micro-cell corrosion state and stable.
In described step 5, anode reinforcing bar and the time of negative electrode reinforcing bar connection status (i.e. macro cell corrosion) It is 24 weeks (i.e. one week is 7 days, and every day is 24 hours), in order to flow through negative electrode reinforcing bar and anode steel steel Stablizing of macro cell corrosion electric current between muscle, and macro cell polarization stablize.
In described step 6, using step 4 and step 5 as a cycle period, an anode reinforcing bar and Cathode steel tendon breaking open state and an anode reinforcing bar and negative electrode reinforcing bar connection status form a cycle period, time Between be 48 weeks (i.e. one week is 7 days, and every day is 24 hours).
The present invention relative to prior art have the advantages that present configuration be simple and convenient to operate, Analysis method is simple and clear, it is possible to micro-cell corrosion effect and macro cell corrosion effect to reinforcing bar are carried out comprehensively Comprehensive evaluation, it is possible to illustrate the control model of reinforcing bar macro cell corrosion under each corrosive environment.
Accompanying drawing explanation
Fig. 1 is the structural representation (1) of the armored concrete composite construction in the present invention.
Fig. 2 is the structural representation (2) of the armored concrete composite construction in the present invention.
Fig. 3 is the structural representation of the armored concrete composite construction for corrosion test of the present invention.
Fig. 4 is the structural representation of the steel reinforced concrete erosion test cell of the present invention.
Fig. 5 is that the negative electrode reinforcing bar in the detection device of reinforcement in concrete macro cell corrosion disconnects with anode reinforcing bar Attachment structure schematic diagram.
Fig. 6 is the negative electrode reinforcing bar in the detection device of reinforcement in concrete macro cell corrosion and anode bar connecting Structural representation.
Fig. 7 is the detection method schematic diagram (1) of reinforcement in concrete macro cell corrosion.
Fig. 8 is the detection method schematic diagram (2) of reinforcement in concrete macro cell corrosion.
Wherein 1 is concrete test block, and 2 is duct, and 3 is reinforcing bar, 4 sealants, and 5 is screw, and 6 is plain cushion Circle, 7 is wire, and 8 is plastic conduit, and 9 is flat vessel, and 10 is negative electrode reinforcing bar, and 11 is anode reinforcing bar, 12 is reserving liquid tank, and 13 is pump, and 14 is effusion meter, and 15 is switch.
Detailed description of the invention
With specific embodiment, the present invention is described in further detail below in conjunction with the accompanying drawings:
As shown in figure 1 and 2, the armored concrete composite construction of the present invention, including concrete test block and steel Muscle, wherein: steel-bar arrangement is in the middle position of concrete test block;Along concrete test block length direction, reinforcing bar Run through whole concrete test block, and concrete test block is stretched out at reinforcing bar two ends;Concrete test block arranges duct, Described duct is uniformly arranged on one with the reinforcing bar circumference as the center of circle being arranged on concrete test block middle position On, and along concrete test block length direction, whole concrete test block is run through in duct.
In technique scheme, the quantity in duct is 4, lay respectively at the surface of reinforcing bar, underface, Front-left and front-right, a diameter of 6mm, the distance of duct centre distance reinforcing steel bar center is 8mm;Concrete The a length of 160mm of test block, width is 80mm, and height is 80mm.
As it is shown on figure 3, the armored concrete composite construction for corrosion test of the present invention, including such as Fig. 1 With the armored concrete composite construction shown in 2, pipeline, wire, wherein: armored concrete composite construction, Including concrete test block and reinforcing bar, steel-bar arrangement is in the middle position of concrete test block;Long along concrete test block Degree direction, reinforcing bar runs through whole concrete test block, and concrete test block is stretched out at reinforcing bar two ends;At reinforcing bar two End arranges sealant, and one end of reinforcing bar is connected with wire;
Arranging duct on concrete test block, described duct is uniformly arranged on one to be arranged on concrete test block The reinforcing bar of middle position is on the circumference in the center of circle, and along concrete test block length direction, duct runs through whole mixed The test block of solidifying soil;The two ends in duct are connected with seal for pipe joints respectively;Pipeline opening straight up, and pipeline tapping Higher than concrete test block, it is full of duct realizing liquid.
In technique scheme, the quantity in duct is 4, lay respectively at the surface of reinforcing bar, underface, Front-left and front-right, a diameter of 6mm, the distance of duct centre distance reinforcing steel bar center is 8mm;Concrete The a length of 160mm of test block, width is 80mm, and height is 80mm.
In technique scheme, arranging screw and packing ring in one end of reinforcing bar, screw is screwed into steel through packing ring Inside muscle, wire is connected with screw or packing ring, to realize the UNICOM of wire and the measurement circuit of reinforcing bar;And Wire passes sealant.
In technique scheme, sealant is polystyrene resin layer, and sealant covers and stretches out concrete examination The two ends of the reinforcing bar of block, and the reinforcing bar extended in concrete test block in oversite concrete test block.At concrete In test block, a length of 30mm of reinforcing bar that sealant covers.
As shown in Figure 4, a kind of steel reinforced concrete erosion test cell, including reinforcing bar as illustrated in fig. 1 and 2 Composite concrete structure, pipeline, wire, wherein: armored concrete composite construction, including concrete test block And reinforcing bar, steel-bar arrangement is in the middle position of concrete test block;Along concrete test block length direction, reinforcing bar passes through Wear whole concrete test block, and concrete test block is stretched out at reinforcing bar two ends;At the two ends of reinforcing bar, sealant is set, One end of reinforcing bar is connected with wire;
Arranging duct on concrete test block, described duct is uniformly arranged on one to be arranged on concrete test block The reinforcing bar of middle position is on the circumference in the center of circle, and along concrete test block length direction, duct runs through whole mixed The test block of solidifying soil;The two ends in duct are connected with seal for pipe joints respectively;Pipeline is connected with reserving liquid tank, and on pipeline Pump and effusion meter are set, to realize by the one end in duct, liquid in reserving liquid tank is entered concrete test block, another End flows out and is back to reserving liquid tank, utilizes the cooperation of pump and effusion meter, it is achieved to liquid in pipeline and hole simultaneously The control of flow velocity and adjustment in road.
In technique scheme, the quantity in duct is 4, lay respectively at the surface of reinforcing bar, underface, Front-left and front-right, a diameter of 6mm, the distance of duct centre distance reinforcing steel bar center is 8mm;Concrete The a length of 160mm of test block, width is 80mm, and height is 80mm.
In technique scheme, arranging screw and packing ring in one end of reinforcing bar, screw is screwed into steel through packing ring Inside muscle, wire is connected with screw or packing ring, to realize the UNICOM of wire and the measurement circuit of reinforcing bar;And Wire passes sealant.
In technique scheme, sealant is polystyrene resin layer, and sealant covers and stretches out concrete examination The two ends of the reinforcing bar of block, and the reinforcing bar extended in concrete test block in oversite concrete test block.At concrete In test block, a length of 30mm of reinforcing bar that sealant covers.
As shown in Fig. 16, the detection device of reinforcement in concrete macro cell corrosion, including two reinforced concretes Soil corrosion test unit, container, two of which steel reinforced concrete erosion test cell is arranged on same In container, and water is set in container;Two steel reinforced concrete erosion test cell structures are identical, And each steel reinforced concrete erosion test cell, including armored concrete composite construction, pipeline and wire, two Individual steel reinforced concrete erosion test cell selects the structure or of the first steel reinforced concrete erosion test cell The structure of two kinds of steel reinforced concrete erosion test cells: wherein
In the structure of the first steel reinforced concrete erosion test cell, armored concrete composite construction, including Concrete test block and reinforcing bar, steel-bar arrangement is in the middle position of concrete test block;Along concrete test block length side To, reinforcing bar runs through whole concrete test block, and concrete test block is stretched out at reinforcing bar two ends;Set at the two ends of reinforcing bar Putting sealant, one end of reinforcing bar is connected with wire;Arranging duct on concrete test block, described duct is uniform Be arranged on one with on the reinforcing bar circumference as the center of circle being arranged on concrete test block middle position, and along concrete Test block length direction, whole concrete test block is run through in duct;The two ends in duct are connected with seal for pipe joints respectively; Pipeline opening straight up, and pipeline tapping is higher than concrete test block, is full of duct realizing liquid;
In the structure of the second steel reinforced concrete erosion test cell, armored concrete composite construction, including Concrete test block and reinforcing bar, steel-bar arrangement is in the middle position of concrete test block;Along concrete test block length side To, reinforcing bar runs through whole concrete test block, and concrete test block is stretched out at reinforcing bar two ends;Set at the two ends of reinforcing bar Putting sealant, one end of reinforcing bar is connected with wire;Arranging duct on concrete test block, described duct is uniform Be arranged on one with on the reinforcing bar circumference as the center of circle being arranged on concrete test block middle position, and along concrete Test block length direction, whole concrete test block is run through in duct;The two ends in duct are connected with seal for pipe joints respectively; Pipeline is connected with reserving liquid tank, and arranges pump and effusion meter on pipeline, to realize liquid in reserving liquid tank by hole The one end in road enters concrete test block, and the other end flows out and is back to reserving liquid tank, utilizes pump and effusion meter simultaneously Cooperation, it is achieved control and the adjustment to liquid flow velocity in pipeline and duct;
Switch is set between two steel reinforced concrete erosion test cells, switch respectively with two armored concrete Wire in corrosion test unit is connected.
In technique scheme, the quantity in duct is 4, lay respectively at the surface of reinforcing bar, underface, Front-left and front-right, a diameter of 6mm, the distance of duct centre distance reinforcing steel bar center is 8mm;Concrete The a length of 160mm of test block, width is 80mm, and height is 80mm.
In technique scheme, arranging screw and packing ring in one end of reinforcing bar, screw is screwed into steel through packing ring Inside muscle, wire is connected with screw or packing ring, to realize the UNICOM of wire and the measurement circuit of reinforcing bar;And Wire passes sealant.
In technique scheme, sealant is polystyrene resin layer, and sealant covers and stretches out concrete examination The two ends of the reinforcing bar of block, and the reinforcing bar extended in concrete test block in oversite concrete test block.At concrete In test block, a length of 30mm of reinforcing bar that sealant covers.
The detection method of reinforcement in concrete macro cell corrosion, in a steel reinforced concrete erosion test cell Reinforcing bar is anode reinforcing bar, and the reinforcing bar in another steel reinforced concrete erosion test cell is negative electrode reinforcing bar, according to The following step is carried out:
Step 1, uses the water in flat vessel that two steel reinforced concrete erosion test cells are carried out moistening, with Make between two steel reinforced concrete erosion test cells, to form the electricity general character;
In step 1, by all or part of for concrete test block in two steel reinforced concrete erosion test cells It is immersed in the water, to simulate the macro cell corrosion of different humidity or underwater concrete, such as by two reinforced concretes In soil corrosion test unit, concrete test block is immersed in the water 3-5mm.
Step 2, by pipeline injection experiments liquid in the duct of concrete test block;
In step 2, experimental liquid is Chloride Solution or corrosion inhibitor solution.
Step 3, uses determinator to be connected with steel reinforced concrete erosion test cell;
In described step 3, determinator is corrosion diagnosis instrument or steel bar corrosion instrument or electrochemical workstation Or zero resistance galvanometer, in actual use, require to be attached according to the use of each determinator.
Step 4: disconnect the wire between negative electrode reinforcing bar and anode reinforcing bar, persistently measure the micro cell of negative electrode reinforcing bar Corrosion potential Emi-cWith micro-cell corrosion electric current density imi-c, the micro-cell corrosion current potential E of anode reinforcing barmi-aWith Micro-cell corrosion electric current density imi-a
Step 5: connect the wire between negative electrode reinforcing bar and anode reinforcing bar, the macro cell of test constantly negative electrode reinforcing bar Corrosion unit Ema-c, the macro cell corrosion current potential E of anode reinforcing barma-a, between negative electrode reinforcing bar and anode reinforcing bar flow Dynamic macro cell corrosion electric current density ima=ima-c=ima-a
Step 6: step 4 and step 5 are tried as a cycle period, repetition step 4 and step 5 Test.
In described step 4, anode reinforcing bar and cathode steel tendon breaking open state (i.e. micro-cell corrosion state) Time is 24 weeks (i.e. one week is 7 days, and every day is 24 hours), in order to negative electrode reinforcing bar and anode reinforcing bar Between the recovery of micro-cell corrosion state and stable.
In described step 5, anode reinforcing bar and the time of negative electrode reinforcing bar connection status (i.e. macro cell corrosion) It is 24 weeks (i.e. one week is 7 days, and every day is 24 hours), in order to flow through negative electrode reinforcing bar and anode steel steel Stablizing of macro cell corrosion electric current between muscle, and macro cell polarization stablize.
In described step 6, using step 4 and step 5 as a cycle period, an anode reinforcing bar and Cathode steel tendon breaking open state and an anode reinforcing bar and negative electrode reinforcing bar connection status form a cycle period, time Between be 48 weeks (i.e. one week is 7 days, and every day is 24 hours).
When detecting, corrosion potential, also commonly referred to as half-cell prtential, by corrosion diagnosis instrument or steel Muscle corrosion instrument or electrochemical workstation record.Micro-cell corrosion electric current density imi, by Stern-Geary equation meter Calculate and obtain, it may be assumed that imi=B/Rp, in formula: Rp is reinforcing bar impedance (k Ω .cm2), B is Stern-Geary constant. Reinforcing bar impedance Rp is recorded by corrosion diagnosis instrument or steel bar corrosion instrument or electrochemical workstation.Macro cell corrosion electricity Current density ima, following formula calculate and obtain: ima=Ima/Aa, in formula: ImaIt is macro cell corrosion electric current (μ A), AaIt is corroded area (generally reinforcing bar radial cross-section street, the cm of anode reinforcing bar2).Anode reinforcing bar is defined For discharging the reinforcing bar of electronics, judgement can be carried out from the flow direction of grand electric current and draw.Macro cell corrosion electric current Ima Zero resistance galvanometer is used to record.
In the off state, the micro-cell corrosion current potential E of negative electrode reinforcing bar is measuredmi-cClose with micro-cell corrosion electric current Degree imi-c, the micro-cell corrosion current potential E of anode reinforcing barmi-aWith micro-cell corrosion electric current density imi-a;Connecting shape Under state, measure macro cell corrosion unit E of negative electrode reinforcing barma-c, the macro cell corrosion current potential E of anode reinforcing barma-a、 Macro cell corrosion electric current density i of flowing between negative electrode reinforcing bar and anode reinforcing barma=ima-c=ima-a
In a cycle period or several cycle period, detection obtains above-mentioned electric current and electric potential signal is carried out point Analysis test and appraisal, the location parameter be given is as follows:
Potential difference between negative electrode reinforcing bar and anode reinforcing bar under off-state (micro-cell corrosion state) ΔEcorr1=/Emi-c-Emi-a/;
Potential difference between negative electrode reinforcing bar and anode reinforcing bar under connection status (macro cell corrosion state) ΔEcorr4=/Ema-c-Ema-a/;
The polarization potential difference of negative electrode reinforcing bar is that it in (micro cell) state of disconnection and connects (macro cell) state Under potential difference Δ Ecorr2=/Emi-c-Ema-c/;
The polarization potential difference of anode reinforcing bar is that it in (micro cell) state of disconnection and connects (macro cell) state Under potential difference Δ Ecorr3=/Ema-a-Emi-a/, and Δ Ecorr1=Δ Ecorr2+ΔEcorr3+ΔEcorr4;
The macro cell corrosion polarization ratio PR of negative electrode reinforcing barsteel-c=Δ Ecorr2/ΔEcorr1;
The macro cell corrosion polarization ratio PR of anode reinforcing barsteel-a=Δ Ecorr3/ΔEcorr1;
The macro cell corrosion polarization ratio PR of concrete impedancecon=Δ Ecorr4/ΔEcorr1, and PRsteel-c+PRsteel-a+PRcon=1;
The macro cell corrosion polarization slope β of negative electrode reinforcing barma-c=Δ Ecorr2/[log(imi-c)-log(ima-c)];
The macro cell corrosion polarization slope β of anode reinforcing barma-a=Δ Ecorr3/[log(ima-a)-log(imi-a)]。
Mensuration based on above-mentioned parameter, the control model evaluating reinforcement in concrete macro cell corrosion is as follows:
(1) negative electrode reinforcing bar control model (i.e. PRsteel-c>=60%, PRsteel-a≤ 30%, PRcon< 10%);
(2) anode reinforcing bar control model (i.e. PRsteel-c≤ 30%, PRsteel-a>=60%, PRcon< 10%);
(3) mixing control model (i.e. 30% < PRsteel-c< 60%, 30% < PRsteel-a< 60%, PRcon< 40%);
(4) concrete impedance control pattern (i.e. PRsteel-c≤ 30%, PRsteel-a≤ 30%, PRcon>=40%).
In the detection and assay of reinforcement in concrete macro cell corrosion, potential difference, is to determine macro cell One of principal element of corrosion current size, by analyzing potential difference Δ Ecorr1、ΔEcorr2、ΔEcorr3 and Δ Ecorr4 With macro cell corrosion electric current density imaRelation, it is possible to preferably evaluate negative electrode reinforcing bar, anode reinforcing bar and coagulation The soil impedance impact on macro cell corrosion electric current.Polarization ratio, is obtained by following manner, it may be assumed that with horizontal seat It is designated as Δ Ecorr1, vertical coordinate is Δ EcorrI (i=2,3,4) draws scatterplot, and is fitted with linear function, Then the slope of straight line is respectively defined as polarization ratio, the polarization ratio of anode reinforcing bar and the coagulation of negative electrode reinforcing bar The polarization ratio of soil.Polarization ratio, it is possible to evaluate negative electrode reinforcing bar, anode reinforcing bar and concrete impedance to grand electricity The Relative Contribution degree of pond corrosion;The control model of reinforcing bar macro cell corrosion under each corrosive environment can be illustrated; Reflect that anode and negative electrode reinforcing bar polarize release electronics and the energy of the consumption electronics that polarizes under macro cell corrosion state Power, it is possible to the power of corrosive power resisted under macro cell corrosion state by evaluation negative electrode reinforcing bar and anode reinforcing bar.
In being embodied as, reinforcing bar refer to regular reinforcement in xoncrete structure (such as HPB300, HRB335, HRBF335, HRB400, HRBF400, HRB500, HRBF500).The intensity etc. of described concrete Level is C20~C60.What the present embodiment was selected be HPB300 plain bar and strength grade is C30 concrete, It is embodied as follows.
What the present embodiment was selected is HPB300 plain bar, diameter 20mm, long 180mm, reinforcing bar two ends The position of portion's 40mm length all seals wrapped with polystyrene resin, and reinforcing bar is poured to be mixed in 80 × 80 × 160mm Coagulate the center position of soil test block, and surrounding is uniform-distribution with the aperture of 4 diameter 6mm.Concreting Time at the HPB300 plain bar of the preset 4 diameter 6mm of aperture position, take out before concrete coagulation hardens Go out to form aperture, after concrete test block hardens, by the aperture of test block end and plastic suction pipe polyphenyl second Olefine resin is tightly connected.
Strength grade of concrete used is C30, and its match ratio is cement: flyash: fluvial sand: rubble: additive: water =1:0.43:3.11:3.8:0.014:0.6.Negative electrode concrete test block mixes 0%Cl-and (accounts for Binder Materials matter when pouring Amount), anode concrete test block mixes 3%Cl-(accounting for Binder Materials quality) when pouring, so that negative electrode reinforcing bar With it is poor to present significant corrosion potential between anode reinforcing bar, it is simple under macro cell corrosion state, it is possible to clear Clear observes negative electrode reinforcing bar and the polarization behavior of anode reinforcing bar.
The all demouldings after pouring 1 day of negative electrode concrete test block and anode concrete test block, then proceed to be placed on 20 DEG C Thermostatic chamber in carry out in water maintenance to age.Take out afterwards, by a negative electrode test block and an anode test block Being positioned in the flat plastic ware containing a small amount of water, the water in vessel is just above the lower limb of test block About 3-5mm.Then it is placed at room temperature 2 weeks, make the humidity of test block keep phase with indoor humidity To stable.
The corrosion diagnosis device used in the present embodiment is the CM-SE1 type corrosion diagnosis of Ji Yan commercial firm of Nippon Steel exploitation Device, the zero resistance electric current of use is calculated as the HM-103A type zero resistance galvanometer of Big Dipper electrician Co., Ltd..
First, the wire of negative electrode reinforcing bar test block and the wire of anode reinforcing bar test block are first off 2 weeks, this Time negative electrode reinforcing bar and anode reinforcing bar be respectively at micro-cell corrosion state;CM-SE1 corrosion diagnosis device is used to divide Ce Liang negative electrode reinforcing bar and negative electrode reinforcing bar corrosion potential E under micro cell statemi-cAnd Emi-a, erosion resistance Rp-cAnd Rp-a, and electrical impedance R of mortar (i.e. concrete test block)con;The time interval measured is 1 day, To obtain the time varied curve of each corrosion parameter;During measurement, full water absorbent cotton is positioned over corrosion diagnosis device Between probe and concrete test block surface, to guarantee good current conductivity;Negative electrode reinforcing bar and negative electrode reinforcing bar Corrosion electric current density in the off state is referred to as micro-cell corrosion electric current density imi-cAnd imi-a, can be by Stern-Geary equation calculates and obtains, it may be assumed that imi=B/Rp, in formula, imiIt it is micro-cell corrosion electric current density (μA/cm2), RpIt is reinforcing bar impedance (k Ω .cm2), B is Stern-Geary constant, when reinforcing bar is in corrosion State be value be 26mV, when reinforcing bar is in passive state, value is 52mV.Test measurement data is shown in Table 1。
Then, the wire of negative electrode reinforcing bar test block and the wire of anode reinforcing bar test block again are at connection status 2 weeks, this Time negative electrode reinforcing bar and anode reinforcing bar be respectively at macro cell corrosion state;CM-SE1 corrosion diagnosis device is used to divide Ce Liang negative electrode reinforcing bar and negative electrode reinforcing bar corrosion potential E under macro cell statema-cAnd Ema-a;Use HM-103A type zero resistance galvanometer records the electric current flowed through between negative electrode reinforcing bar and anode reinforcing bar, the grandest electric current; Macro cell corrosion electric current density is calculated by following formula and obtains, it may be assumed that ima=ima-c=ima-a=Ima/Aa, in formula, imaIt is grand Battery corrosion electric current density (μ A/cm2), ImaIt is macro cell corrosion electric current (μ A), AaIt it is the corruption of anode reinforcing bar Erosion area (cm2);Anode reinforcing bar is defined as discharging the reinforcing bar of electronics, can enter from the flow direction of grand electric current Row judgement draws;The time interval measured is 1 day, in order to obtain the time varied curve of each corrosion parameter.
Off-state 2 weeks and connection status 2 weeks, this is defined as 1 test cycle for 4 weeks, and the present embodiment exists After carrying out 6 test cycles, in the aperture of anode test block, inject the nitrite ion solution of 8mol/L (NaNO2), then proceed by test cycle to 20 times.Test measurement data is shown in Table 1.
Calculate the potential difference between negative electrode reinforcing bar and anode reinforcing bar under (micro cell) state of disconnection ΔEcorr1=/Emi-c-Emi-a/, connect the potential difference between negative electrode reinforcing bar and anode reinforcing bar under (macro cell) state ΔEcorr4=/Ema-c-Ema-a/, the polarization potential difference of negative electrode reinforcing bar is that it is in (micro cell) state of disconnection and connection Potential difference Δ E under (macro cell) statecorr2=/Emi-c-Ema-c/, the polarization potential difference of anode reinforcing bar be it (micro cell) state of disconnection and the potential difference Δ E connected under (macro cell) statecorr3=/Ema-a-Emi-a/, cloudy The macro cell corrosion polarization ratio PR of pole reinforcing barsteel-c=Δ Ecorr2/ΔEcorr1, the macro cell corrosion pole of anode reinforcing bar Change ratio PRsteel-a=Δ Ecorr3/ΔEcorr1, the macro cell corrosion polarization ratio of concrete impedance PRcon=Δ Ecorr4/ΔEcorr1, the macro cell corrosion polarization slope β of negative electrode reinforcing barma-c=Δ Ecorr2/ [log(imi-c)-log(ima-c)], the macro cell corrosion polarization slope β of anode reinforcing barma-a=Δ Ecorr3/ [log(ima-a)-log(imi-a)].Result of calculation is shown in Table 1.
Analyze potential difference Δ Ecorr1、ΔEcorr2、ΔEcorr3 and Δ Ecorr4 with macro cell corrosion electric current density ima's Relation, evaluates negative electrode reinforcing bar, anode reinforcing bar and concrete (mortar) impedance shadow to macro cell corrosion electric current Ring.As shown in Table 1, when after the nitrite ion solution injecting 8mol/L in the aperture of anode test block, along with Macro cell potential difference is gradually reduced, and macro cell corrosion electric current density also decreases, and nitrite ion is to reinforcing bar The inhibition of macro cell corrosion is confirmed.
Analyze polarization ratio, evaluate negative electrode reinforcing bar, anode reinforcing bar and concrete (mortar) impedance rotten to macro cell The Relative Contribution degree of erosion, illustrates the control model of reinforcing bar macro cell corrosion under this corrosive environment.Can by table 1 Knowing, in the present embodiment, the polarization ratio of negative electrode reinforcing bar is relatively big, plays main contributions in macro cell corrosion, therefore this In embodiment, the macro cell corrosion control model of reinforcing bar is that negative electrode reinforcing bar controls.
Analyze polarization slope, evaluate anode reinforcing bar and negative electrode reinforcing bar polarizes under macro cell corrosion state and discharges electronics With the ability that polarization consumes electronics, evaluate negative electrode reinforcing bar and corruption resisted under macro cell corrosion state by anode reinforcing bar The power of erosion ability.As shown in Table 1, molten when the nitrite ion injecting 8mol/L in the aperture of anode test block After liquid, the polarization slope of anode reinforcing bar gradually counterclockwise increases, to the rejection ability of macro cell corrosion by Cumulative by force, the inhibition of reinforcing bar macro cell corrosion is confirmed by nitrite ion.
Table 1 embodiment data and interpretation of result
Note: the present embodiment, after carrying out 6 test cycles, injects the nitrite ion solution (NaNO of 8mol/L in the aperture of anode test block2), so After proceed test cycle to 20 times.Data Emi-c that are given in table, Emi-a, Rp-c, Rp-a, Rcon, Ema-c, Ema-a, ima, Ima-c, ima-a, be the meansigma methods of each stage surveyed data.
The above, only embodiments of the invention, it is not intended to limit protection scope of the present invention.
In addition to the implementation, the present invention can also have other embodiments.All employing equivalents or equivalence become Change the technical scheme of formation, all fall within the protection domain of application claims.

Claims (10)

1. the detection device of reinforcement in concrete macro cell corrosion, it is characterised in that: include two steel Reinforced concrete corrosion test unit, container, two of which steel reinforced concrete erosion test cell It is arranged in same container, and water is set in container;Two armored concrete corruption Erosion test cell structure is identical, and each steel reinforced concrete erosion test cell, including reinforced concrete Soil composite construction, pipeline and wire, two steel reinforced concrete erosion test cells select the first steel The structure of reinforced concrete corrosion test unit or the knot of the second steel reinforced concrete erosion test cell Structure: wherein
In the structure of the first steel reinforced concrete erosion test cell, armored concrete composite construction, Including concrete test block and reinforcing bar, steel-bar arrangement is in the middle position of concrete test block;Along concrete Test block length direction, reinforcing bar runs through whole concrete test block, and concrete test block is stretched out at reinforcing bar two ends; Arranging sealant at the two ends of reinforcing bar, one end of reinforcing bar is connected with wire;Concrete test block sets Putting duct, described duct is uniformly arranged on one with the reinforcing bar being arranged on concrete test block middle position For on the circumference in the center of circle, and along concrete test block length direction, whole concrete test block is run through in duct; The two ends in duct are connected with seal for pipe joints respectively;Pipeline opening straight up, and pipeline tapping is higher than Concrete test block, is full of duct realizing liquid;
In the structure of the second steel reinforced concrete erosion test cell, armored concrete composite construction, Including concrete test block and reinforcing bar, steel-bar arrangement is in the middle position of concrete test block;Along concrete Test block length direction, reinforcing bar runs through whole concrete test block, and concrete test block is stretched out at reinforcing bar two ends; Arranging sealant at the two ends of reinforcing bar, one end of reinforcing bar is connected with wire;Concrete test block sets Putting duct, described duct is uniformly arranged on one with the reinforcing bar being arranged on concrete test block middle position For on the circumference in the center of circle, and along concrete test block length direction, whole concrete test block is run through in duct; The two ends in duct are connected with seal for pipe joints respectively;Pipeline is connected with reserving liquid tank, and arranges on pipeline Pump and effusion meter, to realize by the one end in duct, liquid in reserving liquid tank is entered concrete test block, separately One end is flowed out and is back to reserving liquid tank, utilizes the cooperation of pump and effusion meter, it is achieved exist liquid simultaneously The control of flow velocity and adjustment in pipeline and duct;
Switch is set between two steel reinforced concrete erosion test cells, switch respectively with two reinforcing bars Wire in concrete erosion test cell is connected.
2. the detection device of reinforcement in concrete macro cell corrosion as claimed in claim 1, it is special Levying and be: the quantity in described duct is 26, a diameter of 6-20mm in duct, in duct The distance of heart distance reinforcing steel bar center is 6-20mm.
3. the detection device of reinforcement in concrete macro cell corrosion as claimed in claim 1, it is special Levying and be: a length of 160-200mm of described concrete test block, width is 60-100mm, highly For 60-100mm.
4. the detection device of reinforcement in concrete macro cell corrosion as claimed in claim 1, it is special Levying and be: arrange screw and packing ring in one end of reinforcing bar, screw is screwed into inside reinforcing bar through packing ring, Wire is connected with screw or packing ring, to realize the UNICOM of wire and the measurement circuit of reinforcing bar;And lead Line passes sealant.
5. the detection device of reinforcement in concrete macro cell corrosion as claimed in claim 1, it is special Levying and be: described sealant is polystyrene resin layer, sealant covers and stretches out concrete test block The two ends of reinforcing bar, and the reinforcing bar extended in concrete test block in oversite concrete test block, mixed In the test block of solidifying soil, a length of 30-50mm of reinforcing bar that sealant covers.
6. the detection method of reinforcement in concrete macro cell corrosion, it is characterised in that: a reinforcing bar mixes Reinforcing bar in solidifying soil corrosion test unit is anode reinforcing bar, and the test of another steel reinforced concrete erosion is single Reinforcing bar in unit is negative electrode reinforcing bar, carries out according to the following step:
Step 1, uses the water in flat vessel to moisten two steel reinforced concrete erosion test cells Wet, so that forming the electricity general character between two steel reinforced concrete erosion test cells;
Step 2, by pipeline injection experiments liquid in the duct of concrete test block;
Step 3, uses determinator to be connected with steel reinforced concrete erosion test cell;
Step 4: disconnect the wire between negative electrode reinforcing bar and anode reinforcing bar, persistently measure negative electrode reinforcing bar Micro-cell corrosion current potential Emi-cWith micro-cell corrosion electric current density imi-c, the micro cell of anode reinforcing bar is rotten Erosion current potential Emi-aWith micro-cell corrosion electric current density imi-a
Step 5: connect the wire between negative electrode reinforcing bar and anode reinforcing bar, test constantly negative electrode reinforcing bar Macro cell corrosion unit Ema-c, the macro cell corrosion current potential E of anode reinforcing barma-a, negative electrode reinforcing bar and sun Macro cell corrosion electric current density i of flowing between the reinforcing bar of polema=ima-c=ima-a
Step 6: using step 4 and step 5 as a cycle period, repeats step 4 and step 5 Test.
7. the detection method of reinforcement in concrete macro cell corrosion as claimed in claim 6, it is special Levy and be: in described step 1, concrete in two steel reinforced concrete erosion test cells is tried Block is immersed in the water in whole or in part, to simulate the macro cell corrosion of different humidity or underwater concrete, Such as concrete test block in two steel reinforced concrete erosion test cells is immersed in the water 3-5mm;Institute In the step 2 stated, experimental liquid is Chloride Solution or corrosion inhibitor solution.
8. the detection method of reinforcement in concrete macro cell corrosion as claimed in claim 6, it is special Levying and be: in described step 3, determinator is corrosion diagnosis instrument or steel bar corrosion instrument or electricity Chem workstation or zero resistance galvanometer.
9. the detection method of reinforcement in concrete macro cell corrosion as claimed in claim 6, it is special Levying and be: in described step 4, (i.e. micro cell is rotten for anode reinforcing bar and cathode steel tendon breaking open state Erosion state) time be 24 weeks, in order to micro-cell corrosion between negative electrode reinforcing bar and anode reinforcing bar The recovery of state and stable;In described step 5, anode reinforcing bar and negative electrode reinforcing bar connection status are (i.e. Macro cell corrosion) time be 24 weeks, in order to flow through between negative electrode reinforcing bar and anode steel reinforcing bar The stablizing of macro cell corrosion electric current, and the stablizing of macro cell polarization;In described step 6, will Step 4 and step 5 are as a cycle period, an anode reinforcing bar and cathode steel tendon breaking open state Forming a cycle period with an anode reinforcing bar and negative electrode reinforcing bar connection status, the time is 48 weeks.
10. the detection method of reinforcement in concrete macro cell corrosion as claimed in claim 6, it is special Levy and be: in the off state, measure the micro-cell corrosion current potential E of negative electrode reinforcing barmi-cAnd micro cell Corrosion electric current density imi-c, the micro-cell corrosion current potential E of anode reinforcing barmi-aWith micro-cell corrosion electric current Density imi-a;In connected state, macro cell corrosion unit E of negative electrode reinforcing bar is measuredma-c, anode steel The macro cell corrosion current potential E of musclema-a, between negative electrode reinforcing bar and anode reinforcing bar flowing macro cell corrosion Electric current density ima=ima-c=ima-a
In a cycle period or several cycle period, detection obtains above-mentioned electric current and electric potential signal Being analyzed test and appraisal, the location parameter be given is as follows:
Potential difference between negative electrode reinforcing bar and anode reinforcing bar under off-state (micro-cell corrosion state) ΔEcorr1=/Emi-c-Emi-a/;
Potential difference between negative electrode reinforcing bar and anode reinforcing bar under connection status (macro cell corrosion state) ΔEcorr4=/Ema-c-Ema-a/;
The polarization potential difference of negative electrode reinforcing bar is that it in (micro cell) state of disconnection and connects (macro cell) Potential difference Δ E under statecorr2=/Emi-c-Ema-c/;
The polarization potential difference of anode reinforcing bar is that it in (micro cell) state of disconnection and connects (macro cell) Potential difference Δ E under statecorr3=/Ema-a-Emi-a/, and Δ Ecorr1=Δ Ecorr2+ΔEcorr3+ΔEcorr4;
The macro cell corrosion polarization ratio PR of negative electrode reinforcing barsteel-c=Δ Ecorr2/ΔEcorr1;
The macro cell corrosion polarization ratio PR of anode reinforcing barsteel-a=Δ Ecorr3/ΔEcorr1;
The macro cell corrosion polarization ratio PR of concrete impedancecon=Δ Ecorr4/ΔEcorr1, and PRsteel-c+PRsteel-a+PRcon=1;
The macro cell corrosion polarization slope β of negative electrode reinforcing barma-c=Δ Ecorr2/[log(imi-c)-log(ima-c)];
The macro cell corrosion polarization slope β of anode reinforcing barma-a=Δ Ecorr3/[log(ima-a)-log(imi-a)];
Mensuration based on above-mentioned parameter, evaluates the control model of reinforcement in concrete macro cell corrosion As follows:
(1) negative electrode reinforcing bar control model (i.e. PRsteel-c>=60%, PRsteel-a≤ 30%, PRcon< 10%);
(2) anode reinforcing bar control model (i.e. PRsteel-c≤ 30%, PRsteel-a>=60%, PRcon< 10%);
(3) mixing control model (i.e. 30% < PRsteel-c< 60%, 30% < PRsteel-a< 60%, PRcon< 40%);
(4) concrete impedance control pattern (i.e. PRsteel-c≤ 30%, PRsteel-a≤ 30%, PRcon>=40%).
CN201610397694.6A 2016-06-05 2016-06-05 The detection device and method of reinforcement in concrete macro cell corrosion Active CN105891101B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201610397694.6A CN105891101B (en) 2016-06-05 2016-06-05 The detection device and method of reinforcement in concrete macro cell corrosion
CN201810129665.0A CN108469410A (en) 2016-06-05 2016-06-05 The detection method of reinforcement in concrete macro cell corrosion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610397694.6A CN105891101B (en) 2016-06-05 2016-06-05 The detection device and method of reinforcement in concrete macro cell corrosion

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201810129665.0A Division CN108469410A (en) 2016-06-05 2016-06-05 The detection method of reinforcement in concrete macro cell corrosion

Publications (2)

Publication Number Publication Date
CN105891101A true CN105891101A (en) 2016-08-24
CN105891101B CN105891101B (en) 2018-12-07

Family

ID=56710135

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201810129665.0A Pending CN108469410A (en) 2016-06-05 2016-06-05 The detection method of reinforcement in concrete macro cell corrosion
CN201610397694.6A Active CN105891101B (en) 2016-06-05 2016-06-05 The detection device and method of reinforcement in concrete macro cell corrosion

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201810129665.0A Pending CN108469410A (en) 2016-06-05 2016-06-05 The detection method of reinforcement in concrete macro cell corrosion

Country Status (1)

Country Link
CN (2) CN108469410A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110823983A (en) * 2019-10-08 2020-02-21 九州职业技术学院 Real-time monitoring device and detection method for reinforced bar galvanic couples in concrete
CN112540104A (en) * 2020-12-17 2021-03-23 成都龙之泉科技股份有限公司 Concrete matrix corrosion control quality detection method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110186964B (en) * 2019-04-26 2021-05-07 浙江大学 Device and method for testing corrosion macro current of steel bar in concrete
CN113252545B (en) * 2020-05-28 2022-07-19 中交天津港湾工程研究院有限公司 Method for rapidly identifying corrosion control mode of steel bar macro cell in marine concrete

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1438478A (en) * 2003-03-20 2003-08-27 上海交通大学 Method for detecting corrosion of concrete bar in reinforced concrete
CN202101924U (en) * 2011-04-25 2012-01-04 青岛理工大学 Embedded reinforcement corrosion monitoring system
US20130269283A1 (en) * 2012-04-11 2013-10-17 King Saud University Induced macro-cell corrosion prevention method
JP2014013173A (en) * 2012-07-04 2014-01-23 Sumitomo Osaka Cement Co Ltd Metal corrosion testing device and metal corrosion testing method
CN104568732A (en) * 2015-01-09 2015-04-29 南京钢铁股份有限公司 Experimental device and testing method for rapidly determining corrosion rate of reinforcing steel bars

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003107025A (en) * 2001-09-28 2003-04-09 Nobuaki Otsuki Method for calculating corrosion rate of macrocell in concrete member
CN201159716Y (en) * 2008-02-19 2008-12-03 清华大学 Device for fast assessing corrosion resistance of steel reinforced concrete
CN202486035U (en) * 2012-02-27 2012-10-10 北京建筑材料科学研究总院有限公司 Device for measuring macro current corrosion rate of steel bar in concrete
CN104374813B (en) * 2014-10-31 2017-02-08 南京钢铁股份有限公司 Method for determining concentration of critical chloride ion in concrete reinforcing bars

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1438478A (en) * 2003-03-20 2003-08-27 上海交通大学 Method for detecting corrosion of concrete bar in reinforced concrete
CN202101924U (en) * 2011-04-25 2012-01-04 青岛理工大学 Embedded reinforcement corrosion monitoring system
US20130269283A1 (en) * 2012-04-11 2013-10-17 King Saud University Induced macro-cell corrosion prevention method
JP2014013173A (en) * 2012-07-04 2014-01-23 Sumitomo Osaka Cement Co Ltd Metal corrosion testing device and metal corrosion testing method
CN104568732A (en) * 2015-01-09 2015-04-29 南京钢铁股份有限公司 Experimental device and testing method for rapidly determining corrosion rate of reinforcing steel bars

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110823983A (en) * 2019-10-08 2020-02-21 九州职业技术学院 Real-time monitoring device and detection method for reinforced bar galvanic couples in concrete
CN112540104A (en) * 2020-12-17 2021-03-23 成都龙之泉科技股份有限公司 Concrete matrix corrosion control quality detection method
CN112540104B (en) * 2020-12-17 2024-05-14 成都龙之泉科技股份有限公司 Concrete matrix corrosion control quality detection method

Also Published As

Publication number Publication date
CN108469410A (en) 2018-08-31
CN105891101B (en) 2018-12-07

Similar Documents

Publication Publication Date Title
Niu et al. Critical conditions and life prediction of reinforcement corrosion in coral aggregate concrete
Fan et al. Effect of steel fibers with galvanized coatings on corrosion of steel bars embedded in UHPC
CN105891101A (en) Detection device and method for steel bar macrocell corrosion in concrete
Ji et al. Corrosion current distribution of macrocell and microcell of steel bar in concrete exposed to chloride environments
McCarter et al. Developments in performance monitoring of concrete exposed to extreme environments
CN107843539A (en) A kind of ion penetration resistance of concrete measuring method
CN106770519B (en) A kind of device and method promoting electrochemical rehabilitation concrete efficiency
CN109959683A (en) A kind of detection method of sleeve Grouted density quality
CN109115677A (en) Constant current cycle seepage environment lower prestress anchor pole corrosion test system and its test method
CN105547988A (en) Reinforced concrete corrosion test device and test method
Ribeiro et al. Proposed criterion to assess the electrochemical behavior of carbon steel reinforcements under corrosion in carbonated concrete structures after patch repairs
CN105424578B (en) The method and experimental rig of contactless Impedance Determination concrete interconnected pore rate
CN103130467B (en) Modified cement and application thereof
Tang Corrosion of steel fibre reinforced concrete (SFRC) subjected to simulated stray direct (DC) interference
CN206281763U (en) A kind of concrete erosion electrochemical experimental device in Flow Corrosion medium
CN205826484U (en) A kind of armored concrete composite construction
CN205826488U (en) The detection device of reinforcement in concrete macro cell corrosion
CN205826489U (en) A kind of steel reinforced concrete erosion test cell
CN108254302A (en) A kind of experimental rig and method for being used to study bridge pier littoral area and splash zone chloride threshold concentration
CN103558140B (en) A kind of test unit and test method being applicable to cement-based material normal erosion
Presuel-Moreno et al. Corrosion of reinforced concrete pipes: an accelerated approach
CN205826487U (en) Armored concrete composite construction for corrosion test
Cai et al. Durability of concrete bridge structure under marine environment
CN209292487U (en) A kind of electrode measuring switch-off potential
CN209182216U (en) Constant current cycle seepage environment lower prestress anchor pole corrosion test system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant