CN105844399A - Post evaluation method of power distribution network energy-saving reconstruction project - Google Patents

Post evaluation method of power distribution network energy-saving reconstruction project Download PDF

Info

Publication number
CN105844399A
CN105844399A CN201610164466.4A CN201610164466A CN105844399A CN 105844399 A CN105844399 A CN 105844399A CN 201610164466 A CN201610164466 A CN 201610164466A CN 105844399 A CN105844399 A CN 105844399A
Authority
CN
China
Prior art keywords
index
evaluation
level
saving
energy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610164466.4A
Other languages
Chinese (zh)
Inventor
田学亮
吕志来
李海
喻宜
王云鹏
张东
王德金
刘鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Beijing Xuji Electric Co Ltd
Original Assignee
State Grid Corp of China SGCC
Beijing Xuji Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Beijing Xuji Electric Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610164466.4A priority Critical patent/CN105844399A/en
Publication of CN105844399A publication Critical patent/CN105844399A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning
    • Y02P90/82Energy audits or management systems therefor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Marketing (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a post evaluation method of a power distribution network energy-saving reconstruction project. The objective of the invention is to eliminate defects in the prior art. The method includes the following steps that: S1, a power distribution network energy-saving project post evaluation system is built; S2, a hierarchical evaluation analysis model is built; S3, the weights of indexes in various evaluation systems are acquired; and S4, an evaluation result can be obtained through model analysis. According to the post evaluation method of the invention adopted, in the post evaluation process of the power distribution network energy-saving reconstruction project, the content options of bottom-layer indexes are subdivided, so that index data can be standardized, and therefore, the accuracy of the evaluation results can be ensured; the characteristics of power distribution network energy-saving reconstruction, such as adaptability and coordination, are highlighted; and the power distribution network energy-saving project post evaluation system, the evaluation model, evaluation criteria, and the weights of the evaluation indexes are built and analyzed, and the current energy-saving reconstruction level of a power distribution network can be reflected quantitatively from a plurality of angles.

Description

A kind of post evaluation method of power distribution network reducing energy consumption project
Technical field
The present invention relates to distribution network transform evaluation areas, being specifically related to is a kind of power distribution network reducing energy consumption project Post evaluation method.
Background technology
Along with distribution reducing energy consumption project has successfully been carried out in multiple provinces, explored adaptation locality power supply and The construction mode of energy saving requirement, promotes local power supply capacity and the quality of power supply and serves positive promotion Effect.In the science of research power distribution network reducing energy consumption project, the quality of quantitatively evaluating power grid construction scheme Time need power distribution network is carried out reducing energy consumption post-evaluation.One rationally, science, effectively, distribution accurately It is right that net reducing energy consumption Post-assessment Method needs: how program evaluation result;Construction scheme is the most reasonable;As The aspects such as the implementation result of what quantificational description electrical network reducing energy consumption measure carry out research and probe.
Traditional power distribution network appraisal mainly includes the individual event assessments such as reliability, safety, power supply quality. But traditional appraisal procedure lacks electrical network and the assessment of energy consumption level after transformation, still can not effective evaluation electricity Net recent energy-saving effect and remain the practical problems such as energy-conservation nargin.Therefore, one it is badly in need of more comprehensive, complete Face, the post evaluation method of reducing energy consumption project accurately.
Summary of the invention
The present invention solves the deficiencies in the prior art, propose the later evaluation of a kind of power distribution network reducing energy consumption project Method, comprises the following steps:
S1. power distribution network Energy-saving Projects later evaluation system is set up.
Described power distribution network Energy-saving Projects later evaluation system of setting up comprises the following steps:
1) determination of subsystem: by the saving quantity of electricity in power distribution network synthesis quantitative appraisement model, Project in Operation situation, equipment level, operation maintenance work, project affect and combine various electrical network economize on electricity energy The distribution situation of power, sets and evaluates subsystem.
2) determination of pointer type: with cost type, profit evaluation model, moderate type index sorting technique for depending on According to, according to step 1) selected evaluation subsystem selects one-level evaluation index.
3) determination of lower floor's index: according to step 2) selected one-level evaluation index determines that remaining lower floor refers to Mark.
Described power distribution network Energy-saving Projects later evaluation system, comprises some evaluation subsystems and level index.
Preferably, the subsystem of power distribution network Energy-saving Projects later evaluation system includes: life cycle management evaluates son System, energy-saving effect evaluate subsystem, energy-conservation nargin evaluate subsystem, evaluation of economic benefit subsystem, Subsystem is evaluated in impact.
Further, it is the whole implementation process of project that life cycle management evaluates subsystem scope, including before Phase decision-making, design preparation, construction, operational management one-level evaluation index.
Further, the main purpose of energy-saving effect evaluation be science evaluation electric network reconstruction after energy consumption level And equipment, determine and affect the key of electrical network Energy Conservation " crux " place, promote electrical network science Reduce energy consumption, including service ability, equipment one-level evaluation index.
Further, energy-conservation nargin evaluates subsystem assessment needs to adapt to load development according to power supply capacity Situation, system loss and load development judge the dynamics of investment of electrical network.With dynamics of investment for evaluating The factor, sets up the energy-conservation nargin evaluation model towards dynamics of investment, reflects electrical network by energy-conservation nargin evaluation The science of investment decision, reasonability, refer to including load growth, power supply capacity, power saving capability one-level evaluation Mark.
Further, evaluation of economic benefit subsystem by evaluation of economic benefit by benefit evaluation and electric power network technique Performance evaluation combines, and the comprehensive function effect of indices is embodied in different classes of benefit, logical Cross the level of profitability of expense effect reaction electrical network.The economic indicator timesharing intersexuality index of technical economic analysis, Value index, than forthright index.Become by general item investment income approach, period of investment recovery, income Ben Bifa is from time index, value index, objective evaluation electrical network reducing energy consumption item more comprehensive than forthright index Mesh.
Further, the subsystem assessment angle from the most beneficially social development, Quan Mianfen are evaluated in impact Analysis assessment item build with enforcement on relevant social factor, the impact of environmental factors, i.e. carry out society, Environmental evaluation.
Preferably, Pre-Stage Decision-Making one-level evaluation index includes: can compile carefully situation processed, amount of electricity saving prediction accurately Rate, construction project regulation two-level appraisement index;Design prepares one-level evaluation index and includes: planning and designing Situation, bidding management situation two-level appraisement index;Construction one-level evaluation index includes: construct into Degree administrative situation, Safety Management situation, construction quality administrative situation two-level appraisement index;Operation pipe Reason one-level evaluation index includes: local System Construction situation, energy-saving equipment defect elimination rate, energy consumption platform use Situation, energy-saving equipment put into operation situation two-level appraisement index;Service ability one-level evaluation index includes: line loss Situation, power factor (PF), three-phase imbalance rate, rate of qualified voltage, power supply capacity lifting values two-level appraisement refer to Mark;Equipment one-level evaluation index includes: energy saver ratio, basic routing line length compliance rate, line Cross section, road compliance rate, extended active duty equipment ratio, circuit attaching capacity two-level appraisement index;Power supply capacity One-level evaluation index includes: electrical network power supply capacity two-level appraisement index in the project cycle;Load growth one-level Evaluation index includes: electrical network prediction load two-level appraisement index in the project cycle;Power saving capability one-level is evaluated Index includes: electric network synthetic loss two-level appraisement index in the project cycle;Cost effectiveness (CE) one-level evaluation index Including: returns of investment ratio, investment payback time, rate of return on total investment two-level appraisement index;Returns of investment ratio, Investment payback time, rate of return on total investment two-level appraisement index include: increase delivery benefit, energy-saving efficiency three Level evaluation index;Increase three grades of evaluation indexes of delivery benefit to include: increase-volume dilatation increases delivery, reliability Promote and increase delivery benefit level Four evaluation index;Social influence's one-level evaluation index includes: low-voltage user Ratio, product electricity ratio, regional economy promotion rate, power-saving technology utilization rate two-level index;Environmental effect one Level evaluation index includes: ten thousand yuan of output value comprehensive energy consumption rates of descent, nuisances reduce discharging situation, non-renewable energy Situation two-level index is saved in source.
S2. level evaluation analysis model is set up.
Stepwise level evaluation analysis model is passed in employing, and this model uses linear analysis function equal to indexs at different levels Give weighted value;Upper strata index is considered respective weights value superposition gained by lower floor's index;Indexs at different levels are layer by layer Recursion obtains final comprehensive score.
Preferably, power distribution network reducing energy consumption evaluation score uses linear relationship formula to be calculated:
P1=A1×X1+A2×X2+…+An×Xn
Wherein (X1, X2..., Xn) it is index set, (A1, A2..., An) it is each index weights.
Preferably, life cycle management evaluates subsystem and each level evaluation index score all uses linear relationship Formula is calculated:
P1=a1×l1+a2×l2+…+an×ln
Wherein (l1, l2..., ln) it is index set, (a1, a2..., an) it is each index weights.
Preferably, energy-saving effect evaluates subsystem and each level evaluation index score all uses linear relationship public Formula is calculated:
P2=b1×m1+b2×m2+…+bn×mn
Wherein (m1,m2,…,mn) it is index set, (b1,b2,…,bn) it is each index weights.
Preferably, energy-conservation nargin evaluates subsystem and each level evaluation index score all uses linear relationship public Formula is calculated:
P3=c1×n1+c2×n2+…+cn×nn
Wherein (n1,n2,…,nn) it is index set, (c1,c2,…,cn) it is each index weights.
Preferably, evaluation of economic benefit subsystem and each level evaluation index score all use linear relationship public Formula is calculated:
P4=d1×o1+d2×o2+…+dn×on
Wherein (o1,o2,…,on) it is index set, (d1,d2,…,dn) it is each index weights.
Preferably, subsystem is evaluated in impact and each level evaluation index score all uses linear relationship formula meter Obtain:
P5=e1×p1+e2×p2+…+en×pn
Wherein (p1, p2..., pn) it is index set, (e1, e2..., en) it is each index weights.
S3. the weight of each index in evaluation system is obtained.
In conjunction with typical distribution net comprehensive Quantified Evaluation model and with reference to code, directive/guide and expertise, obtain The weight of each level evaluation index.
Preferably, Delphi method is used to obtain the weight of evaluation indexes at different levels.
S4. assessment result is obtained by model analysis.
Analyze model and the weighted value of step S3 acquisition according to what step S2 obtained, be calculated power distribution network The later evaluation value that Energy-saving Projects is final.
Preferably, described obtained assessment result by model analysis method be: first by evaluation system The most each desired value of subordinate's index is converted to score value;Then obtain according to analysis model computational analysis layer by layer Other score values at different levels;Power distribution network Energy-saving Projects is made comprehensively by the score values at different levels finally according to system Evaluate.
Preferably, calculating scoring is used to obtain the score value of subordinate's index.
The beneficial effects of the present invention is:
1. the present invention is during carrying out power distribution network reducing energy consumption project control software, is referred to by segmentation bottom Target content options, so that achievement data regulation and standardization, it is ensured that the accuracy of assessment result.
Index system the most proposed by the invention contains life cycle management process, energy-saving effect, energy-conservation abundant The index of the multinomial power distribution network Energy efficiency evaluations such as degree, economic benefit and combined influence, highlights that power distribution network is energy-conservation to be changed The features such as the adaptability made, harmony;Analyze and set up power distribution network reducing energy consumption appraisement system, evaluation Model, evaluation criterion and evaluation criterion weight, it is possible to from the joint that multiple angle quantitative response power distribution networks are current Level can be transformed.
3. the present invention had both considered the professional experiences of industry specialists, and the subjectivity that turn avoid deviation bigger is sentenced Disconnected so that index weights is more accurate.
Accompanying drawing explanation
Fig. 1 is the post evaluation method schematic diagram of power distribution network reducing energy consumption project;
Fig. 2 is that power distribution network reducing energy consumption post evaluation method analyzes model structure figure;
Fig. 3 is life cycle management process evaluation subsystem structure chart;
Fig. 4 is that energy-saving effect evaluates subsystem structure chart;
Fig. 5 is that energy-conservation nargin evaluates subsystem structure chart;
Fig. 6 is evaluation of economic benefit subsystem structure chart;
Fig. 7 is that subsystem structure chart is evaluated in impact.
Specific embodiment
In order to make the purpose of the present invention, technical scheme and advantage clearer, below in conjunction with accompanying drawing, The present invention is described in more detail.Should be appreciated that specific embodiment described herein is only in order to solve Release the present invention, be not intended to limit the present invention.
Below in conjunction with the accompanying drawings and the method for later evaluation is further illustrated by embodiments of the invention.
As it is shown in figure 1, the post evaluation method of power distribution network reducing energy consumption project of the present invention at least includes four Individual step:
S1. power distribution network Energy-saving Projects later evaluation system is set up.
Described power distribution network Energy-saving Projects later evaluation system of setting up comprises the following steps:
1) determination of subsystem: by the machine operation in power distribution network synthesis quantitative appraisement model, Equipment, the project implementation process, traffic-operating period, affect and combine the distribution feelings of power distribution network power saving capability Condition, sets and evaluates subsystem.
Fig. 2 show one embodiment of the present of invention, and power distribution network Energy-saving Projects later evaluation system includes: complete Life cycle evaluates subsystem, energy-saving effect evaluates subsystem, energy-conservation nargin evaluates subsystem, economic effect Benefit evaluates subsystem, subsystem is evaluated in impact.
2) determination of pointer type: with cost type, profit evaluation model, moderate type index sorting technique for depending on According to, according to step 1) selected evaluation subsystem selects then one-level evaluation index.
3) determination of lower floor's index: according to step 2) selected one-level evaluation index determines that other lower floors refer to Mark.
Fig. 3 show one embodiment of the present of invention, and it is project that life cycle management evaluates subsystem scope Whole implementation process, refers to including Pre-Stage Decision-Making, design preparation, construction, operational management one-level evaluation Mark.Wherein, Pre-Stage Decision-Making one-level evaluation index includes: can compile carefully situation processed, amount of electricity saving predictablity rate, Construction project regulation two-level appraisement index;Design prepares one-level evaluation index and includes: planning and designing situation, Bidding management situation two-level appraisement index;Construction one-level evaluation index includes: construction project time management Situation, Safety Management situation, construction quality administrative situation two-level appraisement index;Operation management one-level Evaluation index includes: local System Construction situation, energy-saving equipment defect elimination rate, energy consumption platform service condition, Energy-saving equipment puts into operation situation two-level appraisement index.
Fig. 4 show one embodiment of the present of invention, and the main purpose of energy-saving effect evaluation is commenting of science Energy consumption level and equipment after valency electric network reconstruction, determine and affect the key of electrical network Energy Conservation " crux " Place, promotes reducing energy consumption of electrical network science, refers to including service ability, equipment one-level evaluation Mark.Wherein: service ability one-level evaluation index includes: line loss situation, power factor (PF), three-phase imbalance Rate, rate of qualified voltage, power supply capacity lifting values two-level appraisement index;Equipment one-level evaluation index bag Include: energy saver ratio, basic routing line length compliance rate, circuit section compliance rate, extended active duty equipment Ratio, circuit attaching capacity two-level appraisement index.
Fig. 5 show one embodiment of the present of invention, and energy-conservation nargin evaluates subsystem assessment to be needed according to confession Power adapts to the situation of load development, system loss and load development and judges the investment power of electrical network Degree.With dynamics of investment as evaluation points, set up the energy-conservation nargin evaluation model towards dynamics of investment, pass through Energy-conservation nargin evaluation reflection the science of electric grid investment decision-making, reasonability, including load growth, power supply capacity, Power saving capability one-level evaluation index.Wherein: power supply capacity one-level evaluation index includes: electricity in the project cycle Net power supply capacity two-level appraisement index;Load growth one-level evaluation index includes: in the project cycle, electrical network is pre- Survey load two-level appraisement index;Power saving capability one-level evaluation index includes: in the project cycle, electric network synthetic damages Consumption two-level appraisement index.
Fig. 6 show one embodiment of the present of invention, and evaluation of economic benefit subsystem is by evaluation of economic benefit Benefit evaluation is combined with electric power network technique performance evaluation, the comprehensive function effect of indices is embodied in In different classes of benefit, by the level of profitability of cost effectiveness (CE) reaction electrical network.Received by general item investment Benefit method, period of investment recovery, benefit cost ratio method are from time index, value index, more complete than forthright index Orientation objective evaluation electrical network reducing energy consumption project.Wherein: cost effectiveness (CE) one-level evaluation index includes: investment Benefit ratio, investment payback time, rate of return on total investment two-level appraisement index;Returns of investment ratio, investment are reclaimed Phase, rate of return on total investment two-level appraisement index include: increase delivery benefit, three grades of evaluations of energy-saving efficiency refer to Mark;Increase three grades of evaluation indexes of delivery benefit to include: increase-volume dilatation increases delivery, reliability promotes to increase and supplies Utility of Energy level Four evaluation index.
Fig. 7 show one embodiment of the present of invention, and impact evaluates subsystem assessment from whether being conducive to society The angle that can develop, the construction of comprehensive assay project to implement to relevant social factor, environmental factors Impact.Wherein: social influence's one-level evaluation index includes: the electric ratio of low-voltage user's ratio, product, District's economic promotion rate, power-saving technology utilization rate two-level index;Environmental effect one-level evaluation index includes: Ten thousand yuan of output value comprehensive energy consumption rates of descent, nuisance reduction of discharging situation, non-renewable energy resources are saved situation two grades and are referred to Mark.
S2. level evaluation analysis model is set up.
Stepwise level evaluation analysis model is passed in employing, and this model uses linear analysis function equal to indexs at different levels Give weighted value;Upper strata index is considered respective weights value superposition gained by lower floor's index;Indexs at different levels are layer by layer Recursion obtains final comprehensive score.
Power distribution network reducing energy consumption is evaluated score and is used linear relationship formula to be calculated:
P1=A1×X1+A2×X2+…+An×Xn
Wherein (X1, X2..., Xn) it is index set, (A1, A2..., An) it is each index weights.
Life cycle management evaluates subsystem and each level evaluation index score all uses linear relationship formula meter Obtain:
P1=a1×l1+a2×l2+…+an×ln
Wherein (l1, l2..., ln) it is index set, (a1, a2..., an) it is each index weights.
Energy-saving effect evaluates subsystem and each level evaluation index score all uses linear relationship formula to calculate Obtain:
P2=b1×m1+b2×m2+…+bn×mn
Wherein (m1,m2,…,mn) it is index set, (b1,b2,…,bn) it is each index weights.
Energy-conservation nargin evaluates subsystem and each level evaluation index score all uses linear relationship formula to calculate Obtain:
P3=c1×n1+c2×n2+…+cn×nn
Wherein (n1,n2,…,nn) it is index set, (c1,c2,…,cn) it is each index weights.
Evaluation of economic benefit subsystem and each level evaluation index score all use linear relationship formula to calculate Obtain:
P4=d1×o1+d2×o2+…+dn×on
Wherein (o1,o2,…,on) it is index set, (d1,d2,…,dn) it is each index weights.
Subsystem is evaluated in impact and each level evaluation index score all uses linear relationship formula to be calculated:
P5=e1×p1+e2×p2+…+en×pn
Wherein (p1, p2..., pn) it is index set, (e1, e2..., en) it is each index weights.
S3. the weight of each index in evaluation system is obtained.
Delphi method is used to obtain the weight of indexs at different levels.
S4. assessment result is obtained by model analysis.
First evaluation system Zhong subordinate index being carried out calculates scoring and obtains bottom index score value;Then Other score values at different levels are obtained according to analyzing model computational analysis layer by layer;At different levels finally according to system comment Power distribution network Energy-saving Projects is made overall merit by score value.
It should be noted that and understand, in the feelings without departing from the spirit and scope required by the claims in the present invention Under condition, it is possible to the present invention of foregoing detailed description is made various modifications and improvements.It is therefore desirable to protection The scope of technical scheme do not limited by given any specific exemplary teachings.

Claims (9)

1. the post evaluation method of a power distribution network reducing energy consumption project, it is characterised in that include following step Rapid:
S1. power distribution network Energy-saving Projects later evaluation system is set up;
S2. level evaluation analysis model is set up;
S3. the weight of each index in evaluation system is obtained;
S4. assessment result is obtained by model analysis.
Power distribution network Energy-saving Projects post evaluation method the most according to claim 1, it is characterised in that: Set up power distribution network Energy-saving Projects later evaluation system described in step S1 to comprise the following steps:
1) determination of subsystem: by the machine operation in power distribution network synthesis quantitative appraisement model, Equipment, the project implementation process, traffic-operating period, affect and combine the distribution feelings of power distribution network power saving capability Condition, sets and evaluates subsystem;
2) determination of pointer type: with cost type, profit evaluation model, moderate type index sorting technique for depending on According to, according to step 1) selected evaluation subsystem selects one-level evaluation index;
3) determination of lower floor's index: according to step 2) selected sub-one-level evaluation index determines remaining lower floor Index.
Power distribution network Energy-saving Projects post evaluation method the most according to claim 2, it is characterised in that: Described evaluation subsystem can include that life cycle management evaluates subsystem, energy-saving effect evaluates subsystem, joint Nargin can evaluate subsystem, evaluation of economic benefit subsystem and impact evaluation subsystem.
Power distribution network Energy-saving Projects post evaluation method the most according to claim 3, it is characterised in that: Described each evaluation subsystem includes at least one one-level evaluation index, wherein: life cycle management evaluates daughter System includes Pre-Stage Decision-Making, design preparation, construction, operational management one-level evaluation index;Energy-saving effect Evaluate subsystem and include service ability, equipment one-level evaluation index;Energy-conservation nargin evaluates subsystem bag Include load growth, power supply capacity, power saving capability one-level evaluation index;Evaluation of economic benefit subsystem includes Cost effectiveness (CE) one-level evaluation index;Impact is evaluated subsystem and is included environmental effect, social influence's one-level evaluation Index.
Power distribution network Energy-saving Projects post evaluation method the most according to claim 4, it is characterised in that: Described Pre-Stage Decision-Making one-level evaluation index includes: can compile carefully situation processed, amount of electricity saving predictablity rate, construction Engineering regulation two-level appraisement index;Design prepares one-level evaluation index and includes: planning and designing situation, trick Bidding management situation two-level appraisement index;Construction one-level evaluation index includes: construction project time management feelings Condition, Safety Management situation, construction quality administrative situation two-level appraisement index;Operation management one-level is commented Valency index includes: local System Construction situation, energy-saving equipment defect elimination rate, energy consumption platform service condition, joint Can putting equipment in service situation two-level appraisement index;Service ability one-level evaluation index includes: line loss situation, merit Rate factor, three-phase imbalance rate, rate of qualified voltage, power supply capacity lifting values two-level appraisement index;Equipment Horizontal one-level evaluation index includes: energy saver ratio, basic routing line length compliance rate, circuit section reach Mark rate, extended active duty equipment ratio, circuit attaching capacity two-level appraisement index;Power supply capacity one-level is evaluated Index includes: electrical network power supply capacity two-level appraisement index in the project cycle;Load growth one-level evaluation index Including: electrical network prediction load two-level appraisement index in the project cycle;Power saving capability one-level evaluation index includes: Electric network synthetic loss two-level appraisement index in the project cycle;Cost effectiveness (CE) one-level evaluation index includes: investment Benefit ratio, investment payback time, rate of return on total investment two-level appraisement index;Returns of investment ratio, investment are reclaimed Phase, rate of return on total investment two-level appraisement index include: increase delivery benefit, three grades of evaluations of energy-saving efficiency refer to Mark;Increase three grades of evaluation indexes of delivery benefit to include: increase-volume dilatation increases delivery, reliability promotes to increase and supplies Utility of Energy level Four evaluation index;Social influence's one-level evaluation index includes: low-voltage user's ratio, product Electricity ratio, regional economy promotion rate, power-saving technology utilization rate two-level index;Environmental effect one-level evaluation refers to Mark includes: ten thousand yuan of output value comprehensive energy consumption rates of descent, nuisances reduce discharging situation, non-renewable energy resources saving feelings Condition two-level index.
Power distribution network Energy-saving Projects post evaluation method the most according to claim 1, it is characterised in that: Level evaluation analysis model described in step S2 is for passing stepwise level evaluation analysis model, and this model uses line Property analytic function all gives weighted value to indexs at different levels;Upper strata index is considered respective weights value by lower floor's index Superposition gained;Indexs at different levels recursion layer by layer obtains final comprehensive score.
Power distribution network Energy-saving Projects post evaluation method the most according to claim 1, it is characterised in that: The method of the weight of each index in evaluation system that obtains described in step S3 is: combine typical distribution net comprehensive Quantitative appraisement model reference code, directive/guide and expertise, obtain the weight of each level evaluation index.
Power distribution network Energy-saving Projects post evaluation method the most according to claim 7, it is characterised in that: Delphi method is used to obtain the weight of indexs at different levels.
Power distribution network Energy-saving Projects post evaluation method the most according to claim 1, it is characterised in that: Obtaining the method for assessment result by model analysis described in step S4 is: first by evaluation system under Each desired value of level index is converted to score value;Then other are obtained according to analysis model computational analysis layer by layer Score value at different levels;Power distribution network Energy-saving Projects is made overall merit by the score values at different levels finally according to system.
CN201610164466.4A 2016-03-22 2016-03-22 Post evaluation method of power distribution network energy-saving reconstruction project Pending CN105844399A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610164466.4A CN105844399A (en) 2016-03-22 2016-03-22 Post evaluation method of power distribution network energy-saving reconstruction project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610164466.4A CN105844399A (en) 2016-03-22 2016-03-22 Post evaluation method of power distribution network energy-saving reconstruction project

Publications (1)

Publication Number Publication Date
CN105844399A true CN105844399A (en) 2016-08-10

Family

ID=56587739

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610164466.4A Pending CN105844399A (en) 2016-03-22 2016-03-22 Post evaluation method of power distribution network energy-saving reconstruction project

Country Status (1)

Country Link
CN (1) CN105844399A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106651151A (en) * 2016-12-05 2017-05-10 国网山东省电力公司日照供电公司 Post-evaluation method for electric energy substitute item
CN107103415A (en) * 2017-04-17 2017-08-29 中国南方电网有限责任公司 Power distribution network resource allocation method and system
CN107392445A (en) * 2017-07-03 2017-11-24 中国联合网络通信集团有限公司 A kind of appraisal procedure and device of base station energy-saving project
CN107909290A (en) * 2017-12-07 2018-04-13 北京能源集团有限责任公司 Study of Project Evaluation and system are specialized in a kind of technological transformation
CN108305017A (en) * 2018-03-06 2018-07-20 国网陕西省电力公司经济技术研究院 A kind of analysis method of 35kV power distribution networks development model
CN108663574A (en) * 2017-09-30 2018-10-16 国网上海市电力公司 A kind of evaluation method of low-voltage platform area drop damage ability
CN109003010A (en) * 2018-10-17 2018-12-14 国网湖南省电力有限公司 The evaluation method of power grid project investment benefit
CN109711750A (en) * 2019-01-09 2019-05-03 国网宁夏电力有限公司 A kind of power grid investment benefit Whole Process Simulation method and system

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106651151A (en) * 2016-12-05 2017-05-10 国网山东省电力公司日照供电公司 Post-evaluation method for electric energy substitute item
CN107103415A (en) * 2017-04-17 2017-08-29 中国南方电网有限责任公司 Power distribution network resource allocation method and system
CN107392445A (en) * 2017-07-03 2017-11-24 中国联合网络通信集团有限公司 A kind of appraisal procedure and device of base station energy-saving project
CN108663574A (en) * 2017-09-30 2018-10-16 国网上海市电力公司 A kind of evaluation method of low-voltage platform area drop damage ability
CN107909290A (en) * 2017-12-07 2018-04-13 北京能源集团有限责任公司 Study of Project Evaluation and system are specialized in a kind of technological transformation
CN108305017A (en) * 2018-03-06 2018-07-20 国网陕西省电力公司经济技术研究院 A kind of analysis method of 35kV power distribution networks development model
CN109003010A (en) * 2018-10-17 2018-12-14 国网湖南省电力有限公司 The evaluation method of power grid project investment benefit
CN109711750A (en) * 2019-01-09 2019-05-03 国网宁夏电力有限公司 A kind of power grid investment benefit Whole Process Simulation method and system

Similar Documents

Publication Publication Date Title
CN105844399A (en) Post evaluation method of power distribution network energy-saving reconstruction project
CN105389636A (en) Low-voltage area KFCM-SVR reasonable line loss prediction method
Yang et al. Benefit evaluation of East Route Project of South to North Water Transfer based on trapezoid cloud model
CN105046591A (en) Method for evaluating electricity utilization energy efficiency of power consumer
CN103198139B (en) The energy analysis method of custom power data
CN111401732B (en) Hierarchical identification method for water resource supply and demand situation
CN102402726A (en) Method for predicting electric quantity of large-scale distribution network based on regional load analysis
Wu et al. A DEA-based improvement of China's green development from the perspective of resource reallocation
CN111967721A (en) Comprehensive energy system greening level evaluation method and system
CN106056290A (en) Power transmission network operating efficiency and benefit detection method considering new energy access
CN107145707A (en) It is a kind of to count and photovoltaic is exerted oneself the power distribution network transformer planing method of uncertain and overall life cycle cost
CN106651151A (en) Post-evaluation method for electric energy substitute item
CN109784755A (en) A kind of smart grid level evaluation method based on analytic hierarchy process (AHP)
CN108364238A (en) A kind of diversified powering mode selection method based on power supply area grade classification
CN109345090A (en) A kind of rack evaluation method promoted based on distribution network reliability
Ma et al. Economic operation evaluation of active distribution network based on fuzzy Borda method
Chen et al. A BP neural network-based hierarchical investment risk evaluation method considering the uncertainty and coupling for the power grid
Liu et al. Emergy-based urban dynamic modeling of long-run resource consumption, economic growth and environmental impact: conceptual considerations and calibration
CN101246566A (en) Building continuous design method based on full life cycle cost estimation
CN101685964B (en) Online scheduling aid decision method and system based on large-scale parallel processing
CN104299167A (en) Energy consumption analysis method for user power data of intelligent energy consumption system
CN106056245A (en) Provincial level low-carbon energy program analysis method
CN109492874A (en) A kind of decision-making technique of three levels power distribution network investment decision system
CN105117859A (en) Electric power development level general evaluation method based on IOWA operator
CN115907539A (en) Method, system and device for constructing new energy utilization evaluation index system in power market

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160810