CN105782576B - Fluted tube line guard method is excavated below interim pipeline - Google Patents
Fluted tube line guard method is excavated below interim pipeline Download PDFInfo
- Publication number
- CN105782576B CN105782576B CN201610251939.4A CN201610251939A CN105782576B CN 105782576 B CN105782576 B CN 105782576B CN 201610251939 A CN201610251939 A CN 201610251939A CN 105782576 B CN105782576 B CN 105782576B
- Authority
- CN
- China
- Prior art keywords
- bracket
- cross bar
- vertical rod
- guan liang
- foundation ditch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/08—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing
- F16L3/10—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two or more members engaging the pipe, cable or protective tubing
- F16L3/11—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two or more members engaging the pipe, cable or protective tubing and hanging from a pendant
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/08—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing
- F16L3/10—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two or more members engaging the pipe, cable or protective tubing
- F16L3/1066—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two or more members engaging the pipe, cable or protective tubing with three or more members surrounding the pipe
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Supports For Pipes And Cables (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Fluted tube line guard method, ceiling mount bracket are excavated below interim pipeline:Vertical rod and suspension rod are vertically set on the both ends of cross bar, and vertical rod is welded with cross bar, and the upper end of suspension rod is connected with cross bar nut thread, lower end and bracket are detachably connected, and diagonal brace is arranged between cross bar and vertical rod.Method:First, two ceiling mount brackets are arranged in the both ends of longitudinal direction at the top of foundation ditch Guan Liang, and threshold value of the vertical rod away from foundation ditch Guan Liang is 4m~6m;2nd, using expansion bolt by Guan Liang top Interal fixation in foundation ditch Guan Liang;3rd, vertical rod and cross bar full weld connect;4th, lower plate is put in a groove, burning line and water supply line are respectively positioned in the framework of bracket, are assembled lower plate and two round steel, are tightened suspension bracket nut, bracket is connected with suspension rod;5th, after foundation ditch is dug, when near pipe network channel excavation to bracket of moving back, the suspension bracket nut on bracket need to be added stubborn half-turn by groove construction side again.Before the present invention is used for municipal works excavation, the protection of interim pipeline.
Description
Technical field
The present invention relates to one kind to be used for underground utilities ceiling mount bracket and pipeline protection method, and in particular to a kind of interim pipeline
Lower section ceiling mount bracket and excavation fluted tube line guard method.
Background technology
At present, municipal works (including water-supply line, communication pipeline, rainwater pipeline, sewer line, power pipeline) foundation ditch is opened
Change to above foundation ditch (i.e. above earth's surface), it is necessary to will move existing burning line and water supply line temporarily before excavation construction, so
It is the normal use for not influenceing combustion gas and supplying water to do purpose.When burning line and water supply line are moved back, progress groove of moving back is opened
Just interim the burning line changed is moved existing, below water supply line in the region of digging.Due to it is pressed for time, narrow field, it is impossible to
Secondary move is carried out to burning line and water supply line to change, and when digging foundation ditch, very strict is required to burning line and water supply line, combustion
Gas pipeline and water supply line must not move, and must not settle substantially, be needed with reference to the safety guarantee of field condition and burning line, be needed
There is supporting ceiling mount bracket to protect burning line and water supply line, make its immovable and settle.
The content of the invention
The present invention can not carry out secondary moving the feelings changed to solve live excavation to burning line and water supply line
Under condition, it is ensured that burning line and water supply line must not move, and must not settle the problem of obvious, and provide below a kind of interim pipeline
Excavate fluted tube line guard method.
Below a kind of interim pipeline of the present invention ceiling mount bracket include cross bar, vertical rod, suspension rod, diagonal brace, bracket, connecting plate and
Cross bar nut, vertical rod and suspension rod are vertically set on the both ends of cross bar, and vertical rod is located at the lower end of cross bar and welded with cross bar, suspension rod
Upper end is connected through cross bar and connecting plate with cross bar nut thread, and lower end and the bracket of suspension rod are detachably connected, and diagonal brace is arranged on
Between cross bar and vertical rod, one end of diagonal brace is connected with cross bar, and the other end of diagonal brace is connected with vertical rod.
Fluted tube line guard method is excavated below a kind of interim pipeline of the present invention, methods described is through the following steps that reality
Existing:
Step 1: two ceiling mount brackets are arranged in the both ends of longitudinal direction at the top of foundation ditch Guan Liang, on each ceiling mount bracket
Vertical rod is 4m~6m apart from the threshold value of foundation ditch Guan Liang;
Step 2: Guan Liang top steel plate is arranged between vertical rod and foundation ditch Guan Liang, Guan Liang top steel plate is consolidated using expansion bolt
It is scheduled in foundation ditch Guan Liang;
Step 3: vertical rod is connected with cross bar full weld;
Step 4: digging groove below water supply line, lower plate is put in a groove, burning line and water supply line are respectively positioned on
In the framework of bracket, lower plate and two round steel are assembled, tighten suspension bracket nut, bracket is connected with suspension rod;
Step 5: after foundation ditch is dug, when near pipe network channel excavation to bracket of moving back, groove construction side need to again by
Suspension bracket nut on bracket adds stubborn half-turn.
Technical scheme has the advantages that:
First, ceiling mount bracket can be effectively protected to pipeline below interim pipeline of the invention, it is ensured that be excavated
When, pipeline does not move, indeformable.The method of the present invention effectively solves the problems, such as pipeline robust, to ensure that pipeline is moved back work
It is smoothed out providing effective guarantee.
2nd, cross construction can be carried out using ceiling mount bracket below the interim pipeline of the present invention, i.e., after lifting terminates, so that it may
To carry out the work such as channel excavation, not schedule delays.
3rd, the inventive method construction is simple, conveniently, ceiling mount bracket can be carried out in advance prefabricated.
Brief description of the drawings
Fig. 1 is the overall structure diagram of ceiling mount bracket below the interim pipeline of the present invention;
Fig. 2 is Fig. 1 Section A-A view;
Fig. 3 is Fig. 1 section B-B view;
Fig. 4 is Fig. 1 C-C section views;
Two vertical rods 2 are arranged in the position view in foundation ditch Guan Liang 10 in the step of Fig. 5 is embodiment six one.
Embodiment
Embodiment one:Illustrate present embodiment with reference to Fig. 1~Fig. 4, present embodiment include cross bar 1, vertical rod 2,
Suspension rod 3, diagonal brace 4, bracket 5, connecting plate 6 and cross bar nut 7, vertical rod 2 and suspension rod 3 are vertically set on the both ends of cross bar 1, vertical rod 2
Welded positioned at the lower end of cross bar 1 and with cross bar 1, the upper end of suspension rod 3 connects through cross bar 1 and connecting plate 6 with the screw thread of cross bar nut 7
Connect, lower end and the bracket 5 of suspension rod 3 are detachably connected, and diagonal brace 4 is arranged between cross bar 1 and vertical rod 2, one end of diagonal brace 4 and cross bar
1 connection, the other end of diagonal brace 4 are connected with vertical rod 2.Using #83 angle steel as diagonal brace.
Embodiment two:Illustrate present embodiment with reference to Fig. 1, the cross bar 1 of present embodiment is by two channel-section steel butt welding
It is rectangular, strengthened in position while welding using batten plate 8, vertical rod 2 is rectangular by two channel-section steel butt welding, and batten plate 8 is used in position while welding
Strengthen.Channel-section steel uses #10 channel-section steels.Other compositions and annexation are identical with embodiment one.
Embodiment three:Illustrate present embodiment with reference to Fig. 1, the bracket 5 of present embodiment include upper plate 5-1, under
Plate 5-2, two round steel 5-3 and four suspension brackets nut 5-4, upper plate 5-1 and lower plate 5-2 are be arranged in parallel up and down, and two round steel 5-3 are put down
Row is set, and upper plate 5-1, lower plate 5-2 and two round steel 5-3 form framework, and each round steel 5-3 upper end passes through upper plate 5-1 and one
Individual suspension bracket nut 5-4 threaded connections, each round steel 5-3 lower end is threadedly coupled through lower plate 5-2 with a suspension bracket nut 5-4.
Upper plate 5-1 and lower plate 5-2 size is:Long 350mm, wide 100mm, thick 20mm.Round steel 5-3 diameters 20mm.It is other composition and
Annexation is identical with embodiment one or two.
Embodiment four:Illustrate present embodiment with reference to Fig. 1, on the upper plate 5-1 and lower plate 5-2 of present embodiment
Round steel hole 5-5 is elongated hole, so sets convenient connection, fine setting.Other compositions and annexation are identical with embodiment three.
Embodiment five:Illustrate present embodiment with reference to Fig. 1, present embodiment is different from embodiment four
It is that it also increases and there are two backing plates 9, a backing plate 9 is set between diagonal brace 4 and cross bar 1, one is set between diagonal brace 4 and vertical rod 2
Backing plate 9, the thickness of backing plate 9 is 5mm.Other compositions and annexation are identical with embodiment four.
Embodiment six:Illustrate present embodiment with reference to Fig. 1 and Fig. 5, present embodiment is through the following steps that reality
Existing:
Step 1: two ceiling mount brackets are arranged in the both ends of the top of foundation ditch Guan Liang 10 longitudinal direction, on each ceiling mount bracket
Vertical rod 2 apart from the threshold value W of foundation ditch Guan Liang 10 be 4m~6m;
Step 2: Guan Liang top steel plate 11 is arranged between vertical rod 2 and foundation ditch Guan Liang 10, using expansion bolt 12 by Guan Liang top
Steel plate 11 is fixed in foundation ditch Guan Liang 10, Guan Liang top 11 basis as vertical rod 2 of steel plate;
Step 3: vertical rod 2 is connected with the full weld of cross bar 1, to ensure the globality of vertical rod 2, the length of vertical rod 2 need to be real according to pipeline
Border highly adjusts;Because the edge of foundation ditch Guan Liang 10 is away from pipe center distance, the length of cross bar 1 need to be true according to on-site actual situations
It is fixed;
Step 4: digging groove 15 below water supply line 13, lower plate 5-2 is placed in groove 15, burning line 14 and confession
Water pipeline 13 is respectively positioned in the framework of bracket 5, is assembled lower plate 5-2 and two round steel 5-3, is tightened suspension bracket nut 5-4, bracket 5 with
Suspension rod 3 connects;Two brackets 5 form hanging basket shapes and simultaneously hold up burning line 14 and water supply line 13, round steel 5-3 length according to
On-site actual situations determine;
Step 5: after foundation ditch is dug, when near pipe network channel excavation to bracket 5 of moving back, groove construction side needs again
Suspension bracket nut 5-4 on bracket 5 is added into stubborn half-turn, whole bracket 5 is reached stress in advance, plays camber effect, in advance
The anti-unexpected stress of earth's surface pipeline is sunk, and causes pipeline safety hidden danger.
Construction precautions:(1), because the pipeline of protection is burning line, in the assembling process of bracket 5, weldering must not be used
Connect, so as to avoid an accident.(2) when, excavating, there should be special messenger to make an inspection tour pipeline, it is ensured that excavation mechinery is forbidden to encounter lifting support
Frame.
Embodiment seven:Illustrate present embodiment with reference to Fig. 5, present embodiment is vertical rod 2 in step 1 apart from base
The threshold value W for cheating Guan Liang 10 is 5m.Other steps are identical with embodiment six.
Embodiment eight:Illustrate present embodiment with reference to Fig. 1, present embodiment is that expansion bolt 12 is adopted in step 2
With M18 expansion bolts.Other compositions and annexation are identical with embodiment six.
Embodiment nine:Illustrate present embodiment with reference to Fig. 1, present embodiment is Guan Liang top steel plate 11 in step 2
Thickness be 20mm.Other compositions and annexation are identical with embodiment six.
Embodiment ten:Illustrate present embodiment with reference to Fig. 1, present embodiment is the caliber of burning line 14 of top
During less than lower section 13 caliber of water supply line, the space timber wedge 16 between burning line 14 and round steel 5-3 stoppers, and prevents pipeline from moving
It is dynamic.Other compositions and annexation are identical with embodiment six.
Claims (5)
1. fluted tube line guard method is excavated below a kind of interim pipeline realized using ceiling mount bracket below interim pipeline, it is described
Ceiling mount bracket includes cross bar (1), vertical rod (2), suspension rod (3), diagonal brace (4), bracket (5), connecting plate (6) and horizontal stroke below interim pipeline
Stem nut (7), vertical rod (2) and suspension rod (3) are vertically set on the both ends of cross bar (1), vertical rod (2) be located at the lower end of cross bar (1) and
Welded with cross bar (1), the upper end of suspension rod (3) is threadedly coupled through cross bar (1) and connecting plate (6) with cross bar nut (7), suspension rod
(3) lower end is detachably connected with bracket (5), and diagonal brace (4) is arranged between cross bar (1) and vertical rod (2), one end of diagonal brace (4)
It is connected with cross bar (1), the other end of diagonal brace (4) is connected with vertical rod (2), it is characterised in that:Methods described through the following steps that
Realize:
Step 1: two ceiling mount brackets are arranged in the both ends of longitudinal direction at the top of foundation ditch Guan Liang (10), on each ceiling mount bracket
Threshold value (W) of the vertical rod (2) apart from foundation ditch Guan Liang (10) is 4m~6m;
Step 2: Guan Liang top steel plate (11) is arranged between vertical rod (2) and foundation ditch Guan Liang (10), will be preced with using expansion bolt (12)
Back steel plate (11) is fixed in foundation ditch Guan Liang (10);
Step 3: vertical rod (2) is connected with cross bar (1) full weld;
Step 4: digging groove (15) below water supply line (13), lower plate (5-2) is placed in groove (15), burning line
(14) it is respectively positioned on water supply line (13) in the framework of bracket (5), assembling lower plate (5-2) and two round steel (5-3), tightens suspension bracket
Nut (5-4), bracket (5) are connected with suspension rod (3);
Step 5: after foundation ditch is dug, move back pipe network channel excavation to bracket (5) nearby when, groove construction side need to again by
Suspension bracket nut (5-4) plus stubborn half-turn on bracket (5).
2. excavate fluted tube line guard method below interim pipeline according to claim 1, it is characterised in that:The step
Threshold value (W) of the vertical rod (2) apart from foundation ditch Guan Liang (10) is 5m in one.
3. excavate fluted tube line guard method below interim pipeline according to claim 1, it is characterised in that:The step
Expansion bolt (12) uses M18 expansion bolts in two.
4. excavate fluted tube line guard method below interim pipeline according to claim 1, it is characterised in that:The step
The thickness of Guan Liang top steel plate (11) is 20mm in two.
5. excavate fluted tube line guard method below interim pipeline according to claim 1, it is characterised in that:The combustion of top
When gas pipeline (14) caliber is less than lower section water supply line (13) caliber, the space between burning line (14) and round steel (5-3) is used
Timber wedge (16) stoppers.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610251939.4A CN105782576B (en) | 2016-04-21 | 2016-04-21 | Fluted tube line guard method is excavated below interim pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610251939.4A CN105782576B (en) | 2016-04-21 | 2016-04-21 | Fluted tube line guard method is excavated below interim pipeline |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105782576A CN105782576A (en) | 2016-07-20 |
CN105782576B true CN105782576B (en) | 2018-01-16 |
Family
ID=56398178
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610251939.4A Active CN105782576B (en) | 2016-04-21 | 2016-04-21 | Fluted tube line guard method is excavated below interim pipeline |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105782576B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108988193A (en) * | 2018-08-09 | 2018-12-11 | 中铁十局集团第三建设有限公司 | A kind of safe and efficient formula electricity comb line hanger and application method |
CN111335440B (en) * | 2020-03-12 | 2021-04-20 | 郴州市晟恒工程建设有限公司 | Water supply and drainage engineering construction device and water supply and drainage engineering construction process for building construction |
CN115217122B (en) * | 2022-08-25 | 2023-08-22 | 广东城华工程咨询有限公司 | Municipal pipeline protection structure and construction method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101235649A (en) * | 2008-02-22 | 2008-08-06 | 上海市政工程设计研究总院 | Covered digging system for pit |
CN201265706Y (en) * | 2008-08-06 | 2009-07-01 | 中国原子能科学研究院 | Cable hanger of sodium-cooled fast reactor |
CN202834411U (en) * | 2012-08-27 | 2013-03-27 | 天津海德天润海上工程技术有限公司 | Suction anchor double column automatic support device for submarine pipeline suspension treatment |
CA2848441A1 (en) * | 2013-04-10 | 2014-10-10 | Tony O'brien | Hoisting apparatus and method of use |
CN104676110A (en) * | 2015-01-22 | 2015-06-03 | 中国地质大学(武汉) | On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit |
CN204533963U (en) * | 2015-04-08 | 2015-08-05 | 中铁六局集团天津铁路建设有限公司 | A kind of foundation ditch built-in pipe overhead device |
CN205504219U (en) * | 2016-04-21 | 2016-08-24 | 中铁建大桥工程局集团第四工程有限公司 | Interim pipeline below hoist and mount bracket |
-
2016
- 2016-04-21 CN CN201610251939.4A patent/CN105782576B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101235649A (en) * | 2008-02-22 | 2008-08-06 | 上海市政工程设计研究总院 | Covered digging system for pit |
CN201265706Y (en) * | 2008-08-06 | 2009-07-01 | 中国原子能科学研究院 | Cable hanger of sodium-cooled fast reactor |
CN202834411U (en) * | 2012-08-27 | 2013-03-27 | 天津海德天润海上工程技术有限公司 | Suction anchor double column automatic support device for submarine pipeline suspension treatment |
CA2848441A1 (en) * | 2013-04-10 | 2014-10-10 | Tony O'brien | Hoisting apparatus and method of use |
CN104676110A (en) * | 2015-01-22 | 2015-06-03 | 中国地质大学(武汉) | On-site overhanging protection method of high-voltage cable bailey truss under condition of excavation of foundation pit |
CN204533963U (en) * | 2015-04-08 | 2015-08-05 | 中铁六局集团天津铁路建设有限公司 | A kind of foundation ditch built-in pipe overhead device |
CN205504219U (en) * | 2016-04-21 | 2016-08-24 | 中铁建大桥工程局集团第四工程有限公司 | Interim pipeline below hoist and mount bracket |
Also Published As
Publication number | Publication date |
---|---|
CN105782576A (en) | 2016-07-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101614125B (en) | Construction method of V-level surrounding rock tunnel | |
CN108978949A (en) | The plug-in filling wall construction system of steel frame, assembled filled-in panel and construction method | |
CN105782576B (en) | Fluted tube line guard method is excavated below interim pipeline | |
CN104947681B (en) | Super large super deep basement ground pit construction method | |
CN204753628U (en) | Guider that hangs down is transferred to contrary way of doing things steel -pipe column that can have enough to meet need | |
CN214883827U (en) | Construction elevator foundation support system device that encorbelments | |
CN105756380B (en) | A kind of multilayer large-span assembled integral space steel lattice box structure construction of hydropower method | |
WO2020103351A1 (en) | Bailey support system applied to crossed protection of complicated pipe cable and construction method therefor | |
CN205504219U (en) | Interim pipeline below hoist and mount bracket | |
CN211498507U (en) | Whole reassembling type protection rack | |
CN111795212B (en) | Suspension method and suspension structure for pipeline crossing foundation pit | |
CN217518226U (en) | Turbo generator base direct-burried sleeve adjusting device | |
CN206159649U (en) | Pipeline suspends bracket in midair | |
CN210266160U (en) | Construction device for shield to pass through underground pipeline | |
CN212715876U (en) | Socket type disc buckle type steel pipe support | |
CN211547754U (en) | High slope anchor bolt support working platform | |
CN210031746U (en) | Steel casing drilling platform for bridge construction | |
CN203822340U (en) | Gate-type support frame equipment | |
CN107060093A (en) | The support system and assembling method of large-scale oblique braiding gusset plate latticed shell structure | |
CN106836242A (en) | Deep excavation cable stretching assembled operating platform | |
CN209434853U (en) | It is a kind of to move the arragement construction for changing rear electric power pipe trench | |
CN108729938B (en) | Large-size restraint rod for enhancing stability of tunnel primary support structure | |
CN218063703U (en) | Portable gas pipeline hoist and mount protection device | |
CN206467668U (en) | A kind of welded type building enclosure for suspended net shotcrete between stake | |
CN213655894U (en) | Existing underground pipeline suspension protection structure in trenchless construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |