CN101235649A - Covered digging system for pit - Google Patents
Covered digging system for pit Download PDFInfo
- Publication number
- CN101235649A CN101235649A CNA200810033821XA CN200810033821A CN101235649A CN 101235649 A CN101235649 A CN 101235649A CN A200810033821X A CNA200810033821X A CN A200810033821XA CN 200810033821 A CN200810033821 A CN 200810033821A CN 101235649 A CN101235649 A CN 101235649A
- Authority
- CN
- China
- Prior art keywords
- cover plate
- foundation pit
- crossbeam
- links
- cover board
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Foundations (AREA)
Abstract
The invention relates to a cover and cut foundation pit system, which is characterized in that an erect column pile is arranged in the foundation pit, the erect column pile is connected with a cover board column, a steel longitudinal beam and a horizontal beam are arranged on the lower portion of a ground cover board, the cover board column is connected with the horizontal beam and the steel longitudinal beam, and a curb wall is connected with the ground cover board through a concrete-top ring beam. When in use, the ground cover board of the invention adopts the standardized product which can be repeatedly used, which can avoid from generating waste project when the traditional top-down method adopts the cast-in-situ structure, thereby being more environment-friendly and economical. The erect column pile in the foundation pit can be simultaneously used as a foundation pit supporting component and a ground cover board supporting component, which can simultaneously support the load such as foundation pit supporting and the like and ground traffic or construction load, and the construction is more convenient. Simultaneously, pipeline is hanged in the foundation pit, which is convenient for repair, can save project cost, and reduces the affect of the foundation pit construction to environment.
Description
Technical field:
The present invention relates to the technical field of foundation ditch, specifically a kind of covered digging system for pit.
Background technology:
The road surface cover plate need be set at present in advance to solve social traffic, conduit wiring suspension and not have contradiction such as construction plant in some foundation pit constructions on foundation ditch, foundation pit construction carries out under cover plate, promptly so-called cap excavation method foundation pit construction.At present general domestic traditional lid excavation construction is that level and the vertical support member with member such as support, column in the foundation ditch and road surface cover plate system is provided with respectively, and the cover plate that is adopted also is generally forms such as cast-in-situ reinforced concrete slab or steel subgrade case.This traditional cap excavation method structural system exists shortcomings such as structural element is many, abandoned project is many, the cover plate result of use is not good, construction costs height, and traditional cap excavation method adopts structures such as military Bian Liang sometimes, produce bigger noise thereon when vehicle travels, be not suitable for the city proper and use.Japan is more advanced at the cap excavation method technical elements, Japannish cap excavation method foundation ditch all adopts the steel road surface cover plate that can reuse, but have the column of road structure in the foundation ditch and the situation that the support post branch is arranged in the structural system of Japonica type cap excavation method, so this cap excavation method structural system exists construction inconvenience, the too high shortcoming of construction costs.
Summary of the invention:
The object of the present invention is to provide a kind of improved covered digging system for pit, it can overcome structural system existence construction inconvenience, the too high some shortcomings of construction costs that the prior art middle cover digs.
To achieve these goals, technical scheme of the present invention is: a kind of covered digging system for pit, it mainly comprises the enclosure wall of foundation ditch, foundation ditch both sides and is located at the road surface cover plate of foundation ditch top, it is characterized in that: be provided with stand column pile in the foundation ditch, stand column pile links to each other with the cover plate beam, the below of road surface cover plate is provided with the steel longitudinal and cross beam, and the cover plate column links to each other with crossbeam or steel longeron, links to each other by the concrete top beam between enclosure wall and the road surface cover plate.
Road surface of the present invention cover plate adopts the approved product that can reuse during use, thereby more environmental protection is more economical to produce abandoned project in the time of can avoiding traditional cap excavation method to adopt cast-in-place structural, stand column pile in the foundation ditch is double as foundation ditch supporting member and road surface cover plate supporting member simultaneously, can bear load and traffic above-ground or working load such as foundation ditch support simultaneously, it is comparatively convenient to construct, and hangs pipeline simultaneously in foundation ditch, and easy access, can save engineering cost, reduce the influence of foundation pit construction environment.
Description of drawings:
Fig. 1 is the structural representation of cover plate cross section of the present invention
Fig. 2 is the structural representation of foundation ditch cross section of the present invention
Fig. 3 is the structural representation of one embodiment of the invention
The specific embodiment:
The invention will be further described below in conjunction with drawings and Examples.
The present invention mainly comprises the enclosure wall 2 of column 1 in foundation ditch, the foundation ditch, foundation ditch both sides and is located at the road surface cover plate 3 of enclosure wall top, its difference with the prior art is: be provided with stand column pile 4 in the foundation ditch, stand column pile links to each other with the cover plate column, the vertical fulcrum of double as foundation ditch horizontal support, stand column pile also can be used as the anti-floating stake of structure, the below of road surface cover plate is provided with steel longeron 5 and crossbeam 6, and the cover plate column links to each other with crossbeam or steel longeron, links to each other by concrete top beam 7 between enclosure wall and the road surface cover plate.The cover plate column links to each other with crossbeam, links to each other by the steel longeron between crossbeam and the road surface cover plate, and the top of crossbeam is provided with pipeline 8.The road surface cover plate links to each other with crossbeam, and the cover plate column links to each other with the steel longeron, and the steel longeron links to each other with crossbeam, and the crossbeam below is provided with hangs pipeline 9.Crossbeam adopts reinforced concrete beam or girder steel to make, and can make girder and also can make secondary beam, and the steel longeron of road surface cover plate adopts section steel beam, and steel longeron or crossbeam spacing satisfy road surface cover plate modulus requirement.
In force, the present invention is that a kind of novel lid digs the foundation ditch system, comprise road surface cover plate system and support system in the system, and the structure of two kinds of systems united two into one, the excavation of foundation pit support system still adopts domestic common inner supporting body to be, the vertical supporting member of road surface cover plate system (being cover plate column and stand column pile) combines with the interim column (being column and stand column pile) of interior support, this spline structure returns to be built the rear column stake and promptly becomes profile steel concrete column, can effectively reduce the stand column pile size or increase the stand column pile safety stock, the first road of foundation ditch supports and combines with the horizontal supporting system (being crossbeam) of road surface cover plate system, and the double as pipeline is hung primary structure member simultaneously.The road surface cover plate adopts the approved product that can reuse, thereby more environmental protection is more economical to produce abandoned project in the time of can avoiding traditional cap excavation method to adopt cast-in-place structural, think ratio with Japan's lid digging structure and tradition lid digging structure, because stand column pile is double as foundation ditch supporting member and road surface cover plate supporting member simultaneously, thereby it is more economical, construction also is convenient in the minimizing of foundation ditch inner member during construction, has accelerated speed of application, protects environment better thereby reduce foundation pit deformation; The present invention can solve the pipeline in-situ conservation and hang problem, thereby can reduce relocation of services quantity, minimizing engineering land used, thereby can save engineering cost significantly.And can apply to the foundation ditch of inner supporting bodies such as subway foundation pit, building foundation pit system widely, lid digs along doing and lid digs contrary doing all and is suitable for.
Claims (4)
1, a kind of covered digging system for pit, it mainly comprises the enclosure wall of foundation ditch, foundation ditch both sides and is located at the road surface cover plate of enclosure wall top, it is characterized in that: be provided with stand column pile in the foundation ditch, stand column pile links to each other with the cover plate column, the below of road surface cover plate is provided with the steel longitudinal and cross beam, the cover plate column links to each other with crossbeam or steel longeron, links to each other by the concrete top beam between enclosure wall and the road surface cover plate.
2, a kind of covered digging system for pit according to claim 1, it is characterized in that: the cover plate column links to each other with crossbeam, links to each other by the steel longeron between crossbeam and the road surface cover plate, and the top of crossbeam is provided with pipeline.
3, a kind of covered digging system for pit according to claim 1, it is characterized in that: the road surface cover plate links to each other with crossbeam, and the cover plate column links to each other with the steel longeron, and the steel longeron links to each other with crossbeam, and the crossbeam below is provided with pipeline and hangs.
4, a kind of covered digging system for pit according to claim 1 is characterized in that: crossbeam adopts reinforced concrete beam or girder steel to make.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA200810033821XA CN101235649A (en) | 2008-02-22 | 2008-02-22 | Covered digging system for pit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNA200810033821XA CN101235649A (en) | 2008-02-22 | 2008-02-22 | Covered digging system for pit |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101235649A true CN101235649A (en) | 2008-08-06 |
Family
ID=39919531
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNA200810033821XA Pending CN101235649A (en) | 2008-02-22 | 2008-02-22 | Covered digging system for pit |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101235649A (en) |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102505706A (en) * | 2011-09-30 | 2012-06-20 | 北京市政建设集团有限责任公司 | Method for building subway station |
CN102877539A (en) * | 2012-09-26 | 2013-01-16 | 中国建筑第二工程局有限公司 | Profile steel suspension type sewage pipe line changing structure and construction method thereof |
CN102926403A (en) * | 2012-11-15 | 2013-02-13 | 中国建筑第八工程局有限公司 | Roof construction method by cover-excavation method |
CN104372799A (en) * | 2014-11-26 | 2015-02-25 | 江苏鸿基科技有限公司 | Rigid unearthing platform foundation pit inner support structure and construction method |
CN105604091A (en) * | 2016-02-04 | 2016-05-25 | 石家庄铁道大学 | Construction method of cover-excavation-method covering system |
CN105780809A (en) * | 2016-03-24 | 2016-07-20 | 上海市机械施工集团有限公司 | Multifunctional immersion equipment and construction method thereof |
CN105782576A (en) * | 2016-04-21 | 2016-07-20 | 中铁建大桥工程局集团第四工程有限公司 | Temporary pipeline lower hoisting bracket and trench excavating pipeline protection method |
CN105951839A (en) * | 2016-05-31 | 2016-09-21 | 中铁第四勘察设计院集团有限公司 | Method for treatment and cover-and-cut of temporary stand columns by using expansion reinforcing bands |
CN105951844A (en) * | 2016-06-21 | 2016-09-21 | 中铁第四勘察设计院集团有限公司 | Roof node structure adopting cover-excavation method and construction method of roof node structure |
CN106522079A (en) * | 2016-11-15 | 2017-03-22 | 中国建筑第八工程局有限公司 | Prefabricated assembled combination concrete trestle system and construction method thereof |
CN109914480A (en) * | 2019-04-15 | 2019-06-21 | 贵州理工学院 | A kind of structural system for solving underground structure and conflicting with municipal pipeline |
CN110230730A (en) * | 2019-05-20 | 2019-09-13 | 中国二冶集团有限公司 | The construction method reinforced for pipeline |
CN110453687A (en) * | 2019-07-31 | 2019-11-15 | 南京林业大学 | A kind of Metro station excavation excavates the protection structure and construction method of pipeline |
CN112982435A (en) * | 2021-02-26 | 2021-06-18 | 闫芳林 | Supporting construction is built to building engineering project foundation ditch |
-
2008
- 2008-02-22 CN CNA200810033821XA patent/CN101235649A/en active Pending
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102505706A (en) * | 2011-09-30 | 2012-06-20 | 北京市政建设集团有限责任公司 | Method for building subway station |
CN102877539A (en) * | 2012-09-26 | 2013-01-16 | 中国建筑第二工程局有限公司 | Profile steel suspension type sewage pipe line changing structure and construction method thereof |
CN102877539B (en) * | 2012-09-26 | 2013-12-11 | 中国建筑第二工程局有限公司 | Profile steel suspension type sewage pipe line changing structure and construction method thereof |
CN102926403A (en) * | 2012-11-15 | 2013-02-13 | 中国建筑第八工程局有限公司 | Roof construction method by cover-excavation method |
CN102926403B (en) * | 2012-11-15 | 2015-07-08 | 中国建筑第八工程局有限公司 | Roof construction method by cover-excavation method |
CN104372799A (en) * | 2014-11-26 | 2015-02-25 | 江苏鸿基科技有限公司 | Rigid unearthing platform foundation pit inner support structure and construction method |
CN105604091A (en) * | 2016-02-04 | 2016-05-25 | 石家庄铁道大学 | Construction method of cover-excavation-method covering system |
CN105604091B (en) * | 2016-02-04 | 2017-08-29 | 石家庄铁道大学 | A kind of cap excavation method cover system construction method |
CN105780809A (en) * | 2016-03-24 | 2016-07-20 | 上海市机械施工集团有限公司 | Multifunctional immersion equipment and construction method thereof |
CN105782576A (en) * | 2016-04-21 | 2016-07-20 | 中铁建大桥工程局集团第四工程有限公司 | Temporary pipeline lower hoisting bracket and trench excavating pipeline protection method |
CN105782576B (en) * | 2016-04-21 | 2018-01-16 | 中铁建大桥工程局集团第四工程有限公司 | Fluted tube line guard method is excavated below interim pipeline |
CN105951839A (en) * | 2016-05-31 | 2016-09-21 | 中铁第四勘察设计院集团有限公司 | Method for treatment and cover-and-cut of temporary stand columns by using expansion reinforcing bands |
CN105951839B (en) * | 2016-05-31 | 2018-03-20 | 中铁第四勘察设计院集团有限公司 | A kind of method that the interim column of lid digging is handled using expansion reinforcing band |
CN105951844A (en) * | 2016-06-21 | 2016-09-21 | 中铁第四勘察设计院集团有限公司 | Roof node structure adopting cover-excavation method and construction method of roof node structure |
CN105951844B (en) * | 2016-06-21 | 2018-04-03 | 中铁第四勘察设计院集团有限公司 | A kind of cap excavation method top plate node structure and its construction method |
CN106522079A (en) * | 2016-11-15 | 2017-03-22 | 中国建筑第八工程局有限公司 | Prefabricated assembled combination concrete trestle system and construction method thereof |
CN106522079B (en) * | 2016-11-15 | 2019-02-26 | 中国建筑第八工程局有限公司 | The prefabricated assembled combination concrete trestle system of one kind and its construction method |
CN109914480A (en) * | 2019-04-15 | 2019-06-21 | 贵州理工学院 | A kind of structural system for solving underground structure and conflicting with municipal pipeline |
CN110230730A (en) * | 2019-05-20 | 2019-09-13 | 中国二冶集团有限公司 | The construction method reinforced for pipeline |
CN110453687A (en) * | 2019-07-31 | 2019-11-15 | 南京林业大学 | A kind of Metro station excavation excavates the protection structure and construction method of pipeline |
CN110453687B (en) * | 2019-07-31 | 2024-03-19 | 南京林业大学 | Protection structure of subway station foundation pit excavation pipeline and construction method |
CN112982435A (en) * | 2021-02-26 | 2021-06-18 | 闫芳林 | Supporting construction is built to building engineering project foundation ditch |
CN112982435B (en) * | 2021-02-26 | 2022-06-03 | 山东高速岩土工程有限公司 | Supporting construction is built to building engineering project foundation ditch |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101235649A (en) | Covered digging system for pit | |
CN102127974B (en) | Design and construction method of additional cellar under existing building | |
CN204662499U (en) | Concrete of basement exterior wall, waterproof, fertile groove integrated construction structure | |
CN105089670B (en) | Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel | |
CN105972313B (en) | One kind is across base pit engineering conduit wiring suspension method and overhung construction | |
CN102561384A (en) | Steel hoop truss type elevated pile cap tower crane foundation construction method and structure | |
CN103866693A (en) | Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge | |
CN211922740U (en) | Subway anti-floating system combined with peripheral underground space development | |
CN101498133B (en) | Method and supporting construction for enlarging basement top-down method earth excavation space | |
CN105256836A (en) | Construction method for fast restoring road traffic in construction of underground project | |
CN206128077U (en) | Dark excavation supporting's interior bearing structure | |
CN201169781Y (en) | Cap digging pit structure | |
CN204510989U (en) | Multistage concrete towers cylinder integral structure | |
CN203782544U (en) | Combined bracket for river-crossing section of elevated bridge | |
CN207062955U (en) | The foundation pit supporting construction that a kind of thick long stake is combined with thin stub | |
CN105735196B (en) | A kind of frame bucket dock structure and its manufacturing method | |
CN110616714B (en) | Novel enclosure construction method for existing underground structure deepening | |
CN204570718U (en) | A kind of raft foundation with fluid pipeline path | |
CN205188982U (en) | Removable system of strutting of rectangle work well | |
CN201554033U (en) | Tower crane foundation for deep foundation ditch | |
CN204509922U (en) | Underpasses structure | |
CN103711132A (en) | Cylindrical reinforcing steel bar connecting method and connecting structure in reverse building method | |
CN102912858A (en) | Support adapting to non-uniform settlement of foundation and implementation method for support | |
CN207567786U (en) | A kind of upper pipe working well supporting construction | |
CN207700026U (en) | Space steel mesh arch bridge hyperboloid subtracts vibration-isolating system arrangement |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20080806 |