CN105735133A - Pier sinking and floating construction method - Google Patents

Pier sinking and floating construction method Download PDF

Info

Publication number
CN105735133A
CN105735133A CN201610151959.4A CN201610151959A CN105735133A CN 105735133 A CN105735133 A CN 105735133A CN 201610151959 A CN201610151959 A CN 201610151959A CN 105735133 A CN105735133 A CN 105735133A
Authority
CN
China
Prior art keywords
bridge pier
pier
sink
cushion cap
basis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610151959.4A
Other languages
Chinese (zh)
Inventor
王燏斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610151959.4A priority Critical patent/CN105735133A/en
Publication of CN105735133A publication Critical patent/CN105735133A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a pier sinking and floating construction method which comprises a method A or a method B. The method A includes the following steps that firstly, pier columns 3-1 and a bearing platform 2 are manufactured in a factory; secondly, the bottoms of the pier columns 3-1 are hinged to the bearing platform 2; thirdly, water is injected into the bearing platform 2, so that the bearing platform 2 sinks, and the pier columns 3-1 are erected; and fourthly, all the pier columns 3-1 are connected to form a pier 3. The method has the beneficial effects that the pier 3 (or the pier columns 3-1) and the bearing platform 2 are manufactured in the factory and transported to a construction water area in a floating manner so as to be subjected to pose adjustment, assembly and construction. A construction period can be shortened, the labor intensity is relieved, the construction quality is guaranteed, and the method can adapt to foundation construction in a deeper water area.

Description

Bridge pier sink-float construction method
Technical field
The present invention relates to a kind of bridge pier sink-float construction method, belong to technical field of bridge construction.
Background technology
Existing Bridge Pier Construction, bridge pier cast on-site therefore long construction period, labor intensity are big, construction quality is difficult to ensure that and it is shallower to adapt to construction waters.
Summary of the invention
What the present invention proposed is a kind of bridge pier sink-float construction method, and its purpose is intended to the defect overcoming prior art to exist, and makes bridge pier (or pier stud) and cushion cap at workshop, is utilized waterpower to be adjusted attitude by transportation by driving to construction waters, assembles and construct.
Technical scheme: bridge pier sink-float construction method, has A method or B method, and wherein A method comprises the steps:
1) pier stud 3-1 completes at workshop with cushion cap 2;
2) hinged with cushion cap 2 bottom pier stud 3-1;
3) cushion cap 2 water filling is sunk, and pier stud 3-1 holds up;
4) each pier stud 3-1 connects formation bridge pier 3.
B method comprises the steps:
1) bridge pier 3 completes at workshop;
2) bridge pier 3 is transported to waters of constructing;
3) bridge pier 3 is holded up;
4), after bridge pier 3 and basis 4 link into an integrated entity, basis 4 enters the soil body.
Advantages of the present invention: bridge pier 3(or pier stud 3-1) all completing at workshop with cushion cap 2, utilize waterpower to be adjusted attitude by transportation by driving to construction waters, assemble and construct, construction period can be shortened, reduce labor intensity, it is ensured that construction quality and adapt to the foundation construction of more deepwater field.
Accompanying drawing explanation
Fig. 1 is embodiment 1 overall schematic.
Fig. 2 is that in embodiment 1, pier stud 3-1 and cushion cap 2 are transported to waters schematic diagram of constructing.
Fig. 3 is schematic diagram hinged with cushion cap 2 bottom pier stud 3-1 in embodiment 1.
Fig. 4 is that in embodiment 1, pier stud 3-1 holds up schematic diagram 1.
Fig. 5 is that in embodiment 1, pier stud 3-1 holds up schematic diagram 2.
Fig. 6 is that in embodiment 1, pier stud 3-1 connects formation bridge pier 3 schematic diagram 1.
Fig. 7 is that in embodiment 1, pier stud 3-1 connects formation bridge pier 3 schematic diagram 2.
Fig. 8 is that in embodiment 1, pier stud 3-1 connects formation bridge pier 3 schematic diagram 3.
Fig. 9 is that in embodiment 2, bridge pier 3 is transported to waters schematic diagram of constructing.
Figure 10 is that in embodiment 2, schematic diagram 1 holded up by bridge pier 3.
Figure 11 is that in embodiment 2, schematic diagram 2 holded up by bridge pier 3.
Figure 12 is that in embodiment 2, schematic diagram 3 holded up by bridge pier 3.
Figure 13 is that in embodiment 2, bridge pier 3 and well foundation 1 are integrally connected schematic diagram.
Figure 14 is bridge pier 3 and well foundation 1 overall press-in schematic diagram in embodiment 2.
Figure 15 is that in embodiment 3, schematic diagram holded up by bridge pier 3.
Figure 16 is bridge pier 3 overall press-in schematic diagram in embodiment 3.
In figure 1 is well foundation;2 is cushion cap;3 is bridge pier;3-1 is pier stud;4 is basis.
Detailed description of the invention
Bridge pier sink-float construction method, has A method or B method, and wherein A method comprises the steps:
1) pier stud 3-1 completes at workshop with cushion cap 2;
2) hinged with cushion cap 2 bottom pier stud 3-1;
3) cushion cap 2 water filling is sunk, and pier stud 3-1 holds up;
4) each pier stud 3-1 connects formation bridge pier 3.
B method comprises the steps:
1) bridge pier 3 completes at workshop;
2) bridge pier 3 is transported to waters of constructing;
3) bridge pier 3 is holded up;
4), after bridge pier 3 and basis 4 link into an integrated entity, basis 4 enters the soil body.
Pier stud 3-1 and cushion cap 2 in described A method realize sink-float by water filling and draining.
Pier stud 3-1 in described A method and cushion cap 2 transportation by driving are to waters of constructing.
Step 2 in described A method) hinged with cushion cap 2 bottom pier stud 3-1: by water filling in bottom cushion cap 2 and pier stud 3-1 or to extracardiac pumping, with or adjust cushion cap 2 and pier stud 3-1 by the equipment such as lifting and be hinged at the water surface position at place, make bottom pier stud 3-1 hinged with cushion cap 2.
Step 3) cushion cap 2 water filling in described A method is sunk, and pier stud 3-1 holds up: make cushion cap 2 sink by water filling in cushion cap 2, and buoyancy makes pier stud 3-1 hold up.
Step 4) each pier stud 3-1 in described A method connects formation bridge pier 3: be integrally connected by each pier stud 3-1 by modes such as welding and/or bolt-connections, forms bridge pier 3.
Bridge pier 3 in described B method realizes sink-float by water filling and draining.
Bridge pier 3 transportation by driving in described B method is to waters of constructing.
In described bridge pier 3, the passage leading to cushion cap 2 is set.
After step 4) bridge pier 3 and basic 4 in described B method links into an integrated entity, basis 4 enters the soil bodys: bridge pier 3 and basis 4 are linked into an integrated entity by the guider on bridge pier 3, makes basic 4 to be only capable of turning round around himself axis, and then basis 4 enters the soil bodys.
After step 4) bridge pier 3 and basic 4 in described B method links into an integrated entity, basis 4 enters the soil bodys: after bridge pier 3 and basic 4 being linked into an integrated entity by modes such as welding and/or bolt-connections, and basis 4 enters the soil bodys.
Pier stud 3-1 in described B method bridge pier 3 is basis 4.
Basis 4 in described B method is well foundation 1.
Further describe technical scheme below in conjunction with the accompanying drawings:
Embodiment 1
Bridge pier sink-float construction method A method comprises the steps:
1) pier stud 3-1 completes at workshop with cushion cap 2, by the mode such as transportation by driving, shipping to waters of constructing, as shown in Figure 2;
2) as it is shown on figure 3, by water filling in bottom cushion cap 2 and pier stud 3-1 or to extracardiac pumping, and or adjust cushion cap 2 and pier stud 3-1 by equipment such as liftings and be hinged the position located at the water surface, make bottom pier stud 3-1 hinged with cushion cap 2;
3) as shown in Figure 4, Figure 5, making it sink by water filling in cushion cap 2, buoyancy makes pier stud 3-1 gradually hold up around hinged central rotation;
4) as Figure 6-Figure 8, by modes such as welding and/or bolt-connections, each pier stud 3-1 is integrally connected, forms bridge pier 3.
Embodiment 2
Bridge pier sink-float construction method B method comprises the steps:
1) bridge pier 3 completes at workshop;
2) as it is shown in figure 9, bridge pier 3 is transported to waters of constructing by the mode such as transportation by driving, shipping;
3) as shown in Figure 10-Figure 12, by water filling in bottom bridge pier 3, and or make pier stud 3 hold up by equipment such as liftings;
4) as shown in Figure 13, Figure 14, after bridge pier 3 and well foundation 1 link into an integrated entity, well foundation 1 is pressed into the soil body.
Embodiment 3
Pier stud 3-1 is that the bridge pier sink-float construction method B method of well foundation 1 comprises the steps:
1) bridge pier 3 completes at workshop;
2) by the mode such as transportation by driving, shipping, bridge pier 3 is transported to waters of constructing;
3) as shown in figure 15, by bridge pier 3 bottom water injection, and or make bridge pier 3 hold up by equipment such as liftings;
4) as shown in figure 16, by water-pumping/draining, the bottom i.e. well foundation 1 of bridge pier 3 is made to be pressed into the soil body.

Claims (13)

1. bridge pier sink-float construction method, is characterized in that having A method or B method, and wherein A method comprises the steps:
1) pier stud (3-1) completes at workshop with cushion cap (2);
2) pier stud (3-1) bottom is hinged with cushion cap (2);
3) cushion cap (2) water filling is sunk, and pier stud (3-1) is holded up;
4) each pier stud (3-1) connects formation bridge pier (3);
B method comprises the steps:
1) bridge pier (3) completes at workshop;
2) bridge pier (3) is transported to waters of constructing;
3) bridge pier (3) is holded up;
4), after bridge pier (3) and basis (4) link into an integrated entity, basis (4) enters the soil body.
Bridge pier the most according to claim 1 sink-float construction method, it is characterised in that pier stud (3-1) and cushion cap (2) in described A method realize sink-float by water filling and draining.
Bridge pier the most according to claim 2 sink-float construction method, it is characterised in that pier stud (3-1) in described A method and cushion cap (2) transportation by driving are to waters of constructing.
Bridge pier the most according to claim 1 sink-float construction method, it is characterized in that the step 2 in described A method) pier stud (3-1) bottom is hinged with cushion cap (2): by water filling in bottom cushion cap (2) and pier stud (3-1) or to extracardiac pumping, with or adjust cushion cap (2) and pier stud (3-1) by the equipment such as lifting and be hinged at the water surface position at place, make bottom pier stud (3-1) hinged with cushion cap (2).
Bridge pier the most according to claim 1 sink-float construction method, it is characterized in that step 3) cushion cap (2) water filling in described A method is sunk, pier stud (3-1) is holded up: make cushion cap (2) sink by water filling in cushion cap (2), and buoyancy makes pier stud (3-1) hold up.
Bridge pier the most according to claim 1 sink-float construction method, it is characterized in that each pier stud of the step 4) (3-1) in described A method connects and form bridge pier (3): by modes such as welding and/or bolt-connections, each pier stud (3-1) is integrally connected, forms bridge pier (3).
Bridge pier the most according to claim 1 sink-float construction method, it is characterised in that the bridge pier (3) in described B method realizes sink-float by water filling and draining.
Bridge pier the most according to claim 7 sink-float construction method, it is characterised in that bridge pier (3) transportation by driving in described B method is to waters of constructing.
Bridge pier the most according to claim 1 sink-float construction method, it is characterised in that the passage leading to cushion cap (2) is set in described bridge pier (3).
Bridge pier the most according to claim 1 sink-float construction method, after it is characterized in that the step 4) bridge pier (3) in described B method and basis (4) link into an integrated entity, basis (4) enters the soil body: bridge pier (3) and basis (4) are linked into an integrated entity by the guider on bridge pier (3), making basis (4) be only capable of around himself axis to turn round, then basis (4) enters the soil body.
11. bridge pier according to claim 1 sink-float construction methods, after it is characterized in that the step 4) bridge pier (3) in described B method and basis (4) link into an integrated entity, basis (4) enters the soil body: after bridge pier (3) and basis (4) being linked into an integrated entity by modes such as welding and/or bolt-connections, basis (4) enters the soil body.
12. bridge pier according to claim 1 sink-float construction methods, it is characterised in that the pier stud (3-1) in described B method bridge pier (3) is basis (4).
13. according to the bridge pier sink-float construction method described in claim 1 and claim 12, it is characterised in that the basis (4) in described B method is well foundation (1).
CN201610151959.4A 2016-03-17 2016-03-17 Pier sinking and floating construction method Pending CN105735133A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610151959.4A CN105735133A (en) 2016-03-17 2016-03-17 Pier sinking and floating construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610151959.4A CN105735133A (en) 2016-03-17 2016-03-17 Pier sinking and floating construction method

Publications (1)

Publication Number Publication Date
CN105735133A true CN105735133A (en) 2016-07-06

Family

ID=56251237

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610151959.4A Pending CN105735133A (en) 2016-03-17 2016-03-17 Pier sinking and floating construction method

Country Status (1)

Country Link
CN (1) CN105735133A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476201A (en) * 2017-09-26 2017-12-15 孟凡星 Bridge pier installs equipment in a kind of water
CN108221708A (en) * 2018-01-04 2018-06-29 嘉兴学院 A kind of mobile Temporary Piers for bridge incremental launching construction
CN108330837A (en) * 2018-02-05 2018-07-27 石家庄铁道大学 Set up the construction method of girder steel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2470822A1 (en) * 1979-11-30 1981-06-12 Sofresid Offshore platform for petroleum drilling etc. - where hinged tower can be towed in horizontal position, but automatically assumes vertical position when tower base is sunk by ballast
JP2004162426A (en) * 2002-11-14 2004-06-10 Ishikawajima Harima Heavy Ind Co Ltd Foundation cell, cell foundation structure, and construction method for cell foundation structure
JP2005036468A (en) * 2003-07-18 2005-02-10 Sumitomo Mitsui Construction Co Ltd Bridge construction method
CN1742158A (en) * 2003-03-27 2006-03-01 赫里斯托斯·帕帕耶奥尔尤 Floating solar chimney
CN201224866Y (en) * 2008-10-08 2009-04-22 中交第二航务工程勘察设计院有限公司 Floating pier steel bridge approach floating type elevating system
CN105386408A (en) * 2015-11-02 2016-03-09 中交第二航务工程局有限公司 Deep-water bridge pile foundation construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2470822A1 (en) * 1979-11-30 1981-06-12 Sofresid Offshore platform for petroleum drilling etc. - where hinged tower can be towed in horizontal position, but automatically assumes vertical position when tower base is sunk by ballast
JP2004162426A (en) * 2002-11-14 2004-06-10 Ishikawajima Harima Heavy Ind Co Ltd Foundation cell, cell foundation structure, and construction method for cell foundation structure
CN1742158A (en) * 2003-03-27 2006-03-01 赫里斯托斯·帕帕耶奥尔尤 Floating solar chimney
JP2005036468A (en) * 2003-07-18 2005-02-10 Sumitomo Mitsui Construction Co Ltd Bridge construction method
CN201224866Y (en) * 2008-10-08 2009-04-22 中交第二航务工程勘察设计院有限公司 Floating pier steel bridge approach floating type elevating system
CN105386408A (en) * 2015-11-02 2016-03-09 中交第二航务工程局有限公司 Deep-water bridge pile foundation construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476201A (en) * 2017-09-26 2017-12-15 孟凡星 Bridge pier installs equipment in a kind of water
CN107476201B (en) * 2017-09-26 2019-03-01 万智彬 Bridge pier installs equipment in a kind of water
CN108221708A (en) * 2018-01-04 2018-06-29 嘉兴学院 A kind of mobile Temporary Piers for bridge incremental launching construction
CN108221708B (en) * 2018-01-04 2019-08-13 嘉兴学院 A kind of mobile Temporary Piers for bridge incremental launching construction
CN108330837A (en) * 2018-02-05 2018-07-27 石家庄铁道大学 Set up the construction method of girder steel
CN108330837B (en) * 2018-02-05 2019-11-05 石家庄铁道大学 Set up the construction method of girder steel

Similar Documents

Publication Publication Date Title
CN103228909B (en) For the method installing offshore tower
CN104067960B (en) Anti-stormy wave cultivation net cage system in the open ocean that can assemble on the spot on the water and reef dish
CN104040075B (en) A kind of method for installing offshore tower
CN105735133A (en) Pier sinking and floating construction method
CN101845820B (en) Sinking-assistant construction method for sinking sunk well
CN204551518U (en) The wide shallow bucket negative pressure stake combination foundation of major diameter
CN102782218A (en) Multi-purpose ocean platform, and production and installation method thereof
JP2015507111A (en) Method for installing foundation on the seabed and the above seabed foundation
KR20140051531A (en) Structure of offshore structure, manufacturing and constructing method thereof
GB2507248A (en) Conical transition piece between the tower and jacket of a wind turbine
CN103031853B (en) Seabed oil storage system
CN104018443B (en) A kind of Detachable multifunctional road pile
CN206219974U (en) The assembled attachment structure of prefabricated bent cap and prefabricated stand column
CN104476055B (en) A kind of spud leg manufacture method of meter of font stay tube
CN205189011U (en) Well cover
CN204370462U (en) Open-cut station water drainage of deep foundation pit system
CN104221968B (en) A kind of fish reef structure being suitable for neritic area octopus cultivation
CN109112950A (en) Floating body case bridge pier type mortise and tenon beam connects marine rail-road bridge
CN104153366B (en) The method of a kind of marine high wind wave high strength naked rock steel pipe pile foundation
CN104554644A (en) Water surface floating body platform
CN105332387A (en) Large transmission tower suction type barrel-shaped foundation structure and construction method
WO2010115933A3 (en) Method for erecting an offshore station and offshore station
EP2840185B1 (en) Support construction
CN204510256U (en) The steel cylinder-shaped foundation structure of offshore wind turbine
CN203768936U (en) Concrete bearing platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160706

RJ01 Rejection of invention patent application after publication