CN105672137B - A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar - Google Patents

A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar Download PDF

Info

Publication number
CN105672137B
CN105672137B CN201610163800.4A CN201610163800A CN105672137B CN 105672137 B CN105672137 B CN 105672137B CN 201610163800 A CN201610163800 A CN 201610163800A CN 105672137 B CN105672137 B CN 105672137B
Authority
CN
China
Prior art keywords
steel reinforcement
framework
pier shaft
reinforcing
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610163800.4A
Other languages
Chinese (zh)
Other versions
CN105672137A (en
Inventor
闫立忠
李金宝
庞希海
任红专
郭照辉
王宏金
钟高洁
胡晓军
曹建球
张广平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 8 Co Ltd
Original Assignee
Sinohydro Bureau 8 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 8 Co Ltd filed Critical Sinohydro Bureau 8 Co Ltd
Priority to CN201610163800.4A priority Critical patent/CN105672137B/en
Publication of CN105672137A publication Critical patent/CN105672137A/en
Application granted granted Critical
Publication of CN105672137B publication Critical patent/CN105672137B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar, construction method includes step, S1:Set up stent;S2:Make framework of steel reinforcement;S3:Installing bottom layer framework of steel reinforcement;S4:Upper strata framework of steel reinforcement is installed;S5:Pier shaft reinforcing bar is installed, which has pier shaft reinforcing bar accurate positioning, and locating speed is fast;The overall stability of pier shaft steel reinforcement cage is good, is not susceptible to vertical position and deviates and overall distortion;The advantages that improving model sheetinstallat quality and formwork erection speed;Framework of steel reinforcement includes two semicircle spacer bars and two cross reinforcings, two cross reinforcings parallel arrangement, described two semicircle spacer bars are divided into cross reinforcing both ends, welded respectively with a cross reinforcing at the both ends of each semicircle spacer bar, the framework of steel reinforcement has the advantages that simple in structure, assembling speed is fast, improves the overall stability of pier shaft steel reinforcement cage.

Description

A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar
Technical field
The present invention relates to pier construction method and device, more particularly to a kind of construction method and reinforcing bar of bridge pier pier shaft reinforcing bar Skeleton.
Background technology
With the fast development of Chinese economy, also there is the unprecedented booming impetus in the high-speed railway cause in China.Car The continuous improvement of speed proposes the construction quality of railroad bridge the requirement of higher, and the effect of bridge pier shaft is to transmit release bridge The load that beam superstructure is born, is the important component of bridge structure, therefore to pier construction design and construction quality No doubt also there is the requirement of higher.It is accurate install and fix pier shaft reinforcing bar be ensure bridge pier shaft concrete cover effective thickness and Improve the key point of pier construction quality.
At present, the construction method of the installation single welding of binding method generally use for pier shaft reinforcing bar, before construction first Bowl buckle stent is set up, pier shaft reinforcing bar and pier shaft embedded bar are then subjected to single welding, to the end of pier shaft reinforcing bar all welding Formed afterwards and pier shaft steel reinforcement cage and lay pier shaft steel reinforcement cage internal stiffeners, subsequently according to by pier shaft bottom progressively up suitable Sequence, exterior stirrup, pier shaft steel are finally bound by single pier shaft reinforcing bar again according to drawing requirement uniform welding on internal stiffeners Pier cap reinforcing bar is embedded in pier shaft design position according to drawing requirement after muscle construction.The construction method is deposited in use It is specific as follows clearly disadvantageous:
(1)Location difficulty and position inaccurate when pier shaft embedded bar is constructed, can influence pier shaft reinforcing bar installation progress and Installation quality.
(2)After removing working bowl buckle stent, pier shaft reinforcing bar not enough can cause deviation vertical position because of overall stiffness, Overall twisted phenomena even can occur, pier shaft reinforcing bar integrally distorts the quality and progress that can influence pier shaft formwork erection, concrete protective The effective thickness of layer can not also be guaranteed.
(3)For higher pier shaft, pier shaft reinforcing bar can be needed because influencing installation speed and alignment quality without supporting stress point Lacing wire is set up along pier shaft steel reinforcement cage surrounding to be fixed, and its stablizing effect is bad.
The content of the invention
The technical problem to be solved in the present invention is overcome the deficiencies of the prior art and provide a kind of pier shaft reinforcing bar locating speed Hurry up, quality it is good, it is ensured that the effective thickness of concrete cover, pier shaft steel reinforcement cage overall stability is good, without departing from vertical position, no The construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar integrally distorted occurs.
In order to solve the above technical problems, the present invention uses following technical scheme:A kind of construction method of bridge pier pier shaft reinforcing bar, Comprise the following steps,
S1:Set up stent:Set up fixed platform of the stent as framework of steel reinforcement;
S2:Make framework of steel reinforcement:Framework of steel reinforcement is made according to the shape and size of pier shaft steel reinforcement cage cross section;
S3:Installing bottom layer framework of steel reinforcement:Some control points for the positioning of pier shaft steel reinforcement cage are released in measurement, according to control point Bottom layer of the reinforcing steel skeleton is positioned, is then fixed on bottom layer of the reinforcing steel skeleton on the reinforcing bar of concrete foundation top surface;
S4:Upper strata framework of steel reinforcement is installed:Multistory reinforced skeleton is fixedly mounted along the short transverse of the stent, and ensures more Layer framework of steel reinforcement aligns with bottom layer of the reinforcing steel skeleton;
S5:Pier shaft reinforcing bar is installed:Pier shaft reinforcing bar is circumferentially placed along the framework of steel reinforcement, and by pier shaft reinforcing bar and reinforcing bar Frame is fixedly connected to form pier shaft steel reinforcement cage.
Further as above-mentioned technical proposal is improved:
The step S4 include it is following step by step:
S4.1:Top layer framework of steel reinforcement is installed:Some control points on bottom layer of the reinforcing steel skeleton are led to top layer using weight line Framework of steel reinforcement, realizes the positioning of top layer framework of steel reinforcement, and then top layer muscle sample rack is fixed on the stent;
S4.2:Intermediate layer framework of steel reinforcement is installed:Will be each on bottom layer of the reinforcing steel skeleton and top layer framework of steel reinforcement using connecting rope Control point connects one to one, and the positioning of intermediate layer framework of steel reinforcement is realized by the connecting rope, then by intermediate layer reinforcing bar Frame is fixed on the stent.
Step S6 is further included after step S5:Bridging is installed between adjacent two layers framework of steel reinforcement.
A kind of framework of steel reinforcement of construction method for above-mentioned bridge pier pier shaft reinforcing bar, the framework of steel reinforcement include two semicircles Shape spacer bar and two cross reinforcings, two cross reinforcings parallel arrangement, described two semicircle spacer bars Cross reinforcing both ends are divided into, the both ends of each semicircle spacer bar are welded with a cross reinforcing respectively.
Further as above-mentioned technical proposal is improved:
The framework of steel reinforcement further includes first longitudinal direction reinforcing rib and second longitudinal direction reinforcing rib, the first longitudinal direction reinforcing rib with Semicircle spacer bar both ends welding, the second longitudinal direction reinforcing rib are welded between two cross reinforcings, and described the More radial reinforcing ribs are welded between one waling and the semicircle spacer bar.
Compared with prior art, the advantage of the invention is that:The construction method of the present invention, which first measures, releases some control points, And location and installation bottom layer of the reinforcing steel skeleton, then some top bars skeletons are installed on stent and ensure top bars skeleton and bottom Layer framework of steel reinforcement alignment, circumferential direction placement, fixed pier shaft reinforcing bar finally along framework of steel reinforcement, pier shaft reinforcing bar accurate positioning, Locating speed is fast;Set framework of steel reinforcement also to strengthen the overall stiffness of pier shaft steel reinforcement cage, improve pier shaft steel reinforcement cage monolithic stability Property, it can prevent to deviate and entirety distorts, it is ensured that the effective thickness of concrete cover, is conducive to the quick peace of pier body formwork Dress.
Further, bridging is set between neighbouring two layers of framework of steel reinforcement, can further lifts pier shaft steel reinforcement cage Overall stiffness.
The framework of steel reinforcement of the present invention, it is simple in structure, easy to assembly, contribute to quick, the accurate positionin of pier shaft reinforcing bar, improve The overall stiffness of pier shaft steel reinforcement cage, ensures the overall stability of pier shaft steel reinforcement cage.
Brief description of the drawings
Fig. 1 is the flow chart of the construction method of bridge pier pier shaft reinforcing bar of the present invention.
Fig. 2 is the dimensional structure diagram for completing the pier shaft steel reinforcement cage after constructing.
Fig. 3 is the side structure schematic view for completing the pier shaft steel reinforcement cage after constructing.
Fig. 4 is the structure diagram of framework of steel reinforcement of the present invention.
Each label represents in figure:1st, concrete foundation;2nd, framework of steel reinforcement;21st, semicircle spacer bar;22nd, laterally strengthen Muscle;23rd, first longitudinal direction reinforcing rib;24th, second longitudinal direction reinforcing rib;25th, radial reinforcing rib;3rd, pier shaft reinforcing bar;4th, bridging.
Embodiment
The present invention is described in further details below with reference to Figure of description and specific embodiment.
As shown in Figure 1, the construction method of the bridge pier pier shaft reinforcing bar of the present embodiment, comprises the following steps,
S1:Set up stent:Fixed platform of the stent as framework of steel reinforcement 2 is set up, 1 structure type of stent is normal for engineering field Double-row steel pipe stent, the specification of single-layer bracket is 1.0x1.5x1.8m;
S2:Make framework of steel reinforcement 2:Framework of steel reinforcement 2 is made according to the shape and size of pier shaft steel reinforcement cage cross section;
S3:Installing bottom layer framework of steel reinforcement 2:Some control points for the positioning of pier shaft steel reinforcement cage are released in measurement, according to control Bottom layer of the reinforcing steel skeleton 2, is then fixed on the reinforcing bar of 1 top surface of concrete foundation, the present embodiment by point location bottom layer of the reinforcing steel skeleton 2 In, the quantity at control point is six, be respectively two semicircle spacer bars 21 midpoint and two endpoints, the tool at each control point Body position is obtained according to construction site technical staff's measurement;
S4:Upper strata framework of steel reinforcement 2 is installed:Multistory reinforced skeleton 2 is fixedly mounted along the short transverse of stent, and ensures multilayer Framework of steel reinforcement 2 aligns with bottom layer of the reinforcing steel skeleton 2;
S5:Pier shaft reinforcing bar 3 is installed:Pier shaft reinforcing bar 3 is placed along framework of steel reinforcement 2 is circumferential, and by pier shaft reinforcing bar 3 and reinforcing bar Frame 2 is fixedly connected to form pier shaft steel reinforcement cage.
Complete pier shaft reinforcement cage structure such as Fig. 2 after construction and as shown in figure 3, the construction method pier shaft reinforcing bar 3 positions standard Really, locating speed is fast;Set framework of steel reinforcement 2 also to strengthen the overall stiffness of pier shaft steel reinforcement cage, improve pier shaft steel reinforcement cage entirety Stability, can prevent to deviate and entirety distorts, it is ensured that the effective thickness of concrete cover, is conducive to the fast of pier body formwork Speed installation.
In the present embodiment, step S4 include it is following step by step:
S4.1:Top layer framework of steel reinforcement 2 is installed:Some control points on bottom layer of the reinforcing steel skeleton 2 are led to top using weight line Layer framework of steel reinforcement 2, realizes the positioning of top layer framework of steel reinforcement 2, then top layer muscle sample rack 2 is fixed on stent;
S4.2:Intermediate layer framework of steel reinforcement 2 is installed:Using connecting rope by bottom layer of the reinforcing steel skeleton 2 and top layer framework of steel reinforcement 2 Each control point connects one to one, and the positioning of intermediate layer framework of steel reinforcement 2 is realized by connecting rope, then by intermediate layer framework of steel reinforcement 2 are fixed on stent, which can quickly and reliably complete the positioning and installation of top bars skeleton 2, it is ensured that top bars Skeleton 2 aligns with bottom layer of the reinforcing steel skeleton 2, so as to ensure that pier shaft reinforcing bar does not deviate.
In the present embodiment, step S6 is further included after step S5:Bridging 4 is installed between adjacent two layers framework of steel reinforcement 2, It can further improve the overall stiffness of pier shaft steel reinforcement cage.
As shown in figure 4, the framework of steel reinforcement 2 of the present embodiment includes two semicircle spacer bars 21 and two cross reinforcings 22, two cross reinforcings 22 are arranged in parallel, and two semicircle spacer bars 21 are divided into 22 both ends of cross reinforcing, each semicircle The both ends of shape spacer bar 21 are welded with a cross reinforcing 22 respectively, the framework of steel reinforcement 2 of kidney ellipsoid are formed, along kidney ellipsoid Pier shaft reinforcing bar 3 is placed in the inner side of framework of steel reinforcement 2, and for pier shaft reinforcing bar 3 with framework of steel reinforcement 2 using being welded to connect, 2 structure of framework of steel reinforcement is simple It is single, easy to assembly, contribute to quick, the accurate positionin of pier shaft reinforcing bar 3, improve the overall stiffness of pier shaft steel reinforcement cage, ensure pier The overall stability of body steel reinforcement cage.
In the present embodiment, framework of steel reinforcement 2 further includes first longitudinal direction reinforcing rib 23 and second longitudinal direction reinforcing rib 24, first longitudinal direction Reinforcing rib 23 is welded with semicircle 21 both ends of spacer bar, second longitudinal direction reinforcing rib 24 be welded in two cross reinforcings 22 it Between, it is welded with more radial reinforcing ribs 25 between first longitudinal direction reinforcing rib 23 and semicircle spacer bar 21.
Scissors is welded between the first longitudinal direction reinforcing rib 23 and second longitudinal direction reinforcing rib 24 of upper and lower two layers of framework of steel reinforcement 2 Support 4, improves the overall stiffness of pier shaft steel reinforcement cage, and in the present embodiment, bridging 4 is the support of C25 shear for cutting steel bar.
Although the present invention is disclosed above with preferred embodiment, but is not limited to the present invention.It is any to be familiar with ability The technical staff in domain, in the case where not departing from technical solution of the present invention scope, all using the technology contents pair of the disclosure above Technical solution of the present invention makes many possible changes and modifications, or is revised as the equivalent embodiment of equivalent variations.Therefore, it is every Without departing from the content of technical solution of the present invention, according to the technology of the present invention essence to any simple modification made for any of the above embodiments, Equivalent variations and modification, should all fall in the range of technical solution of the present invention protection.

Claims (5)

  1. A kind of 1. construction method of bridge pier pier shaft reinforcing bar, it is characterised in that:Comprise the following steps,
    S1:Set up stent:Stent is set up as framework of steel reinforcement(2)Fixed platform;
    S2:Make framework of steel reinforcement(2):More reinforcement weldings are fabricated to steel according to the shape and size of pier shaft steel reinforcement cage cross section Tendons skeleton(2);
    S3:Installing bottom layer framework of steel reinforcement(2):Some control points for the positioning of pier shaft steel reinforcement cage are released in measurement, according to control point Position bottom layer of the reinforcing steel skeleton(2), then by bottom layer of the reinforcing steel skeleton(2)It is fixed on concrete foundation(1)On the reinforcing bar of top surface;
    S4:Upper strata framework of steel reinforcement is installed(2):Multistory reinforced skeleton is fixedly mounted along the short transverse of the stent(2), and ensure Multistory reinforced skeleton(2)With bottom layer of the reinforcing steel skeleton(2)Alignment;
    S5:Pier shaft reinforcing bar is installed(3):Along the framework of steel reinforcement(2)It is circumferential to place pier shaft reinforcing bar(3), and by pier shaft reinforcing bar(3) With framework of steel reinforcement(2)It is fixedly connected to form pier shaft steel reinforcement cage.
  2. 2. the construction method of bridge pier pier shaft reinforcing bar according to claim 1, it is characterised in that:The step S4 includes following Step by step:
    S4.1:Top layer framework of steel reinforcement is installed(2):Using weight line bottom layer of the reinforcing steel skeleton(2)On some control points lead to top Layer framework of steel reinforcement(2), realize top layer framework of steel reinforcement(2)Positioning, then by top layer framework of steel reinforcement(2)It is fixed on the stent On;
    S4.2:Intermediate layer framework of steel reinforcement is installed(2):Using connecting rope by bottom layer of the reinforcing steel skeleton(2)With top layer framework of steel reinforcement(2)On Each control point connect one to one, intermediate layer framework of steel reinforcement is realized by the connecting rope(2)Positioning, then by intermediate layer Framework of steel reinforcement(2)It is fixed on the stent.
  3. 3. the construction method of bridge pier pier shaft reinforcing bar according to claim 1 or 2, it is characterised in that:Also wrapped after step S5 Include step S6:In adjacent two layers framework of steel reinforcement(2)Between bridging is installed(4).
  4. 4. a kind of framework of steel reinforcement of the construction method of bridge pier pier shaft reinforcing bar for any one of claims 1 to 3, it is special Sign is:Including two semicircle spacer bars(21)With two cross reinforcings(22), two cross reinforcings(22) Parallel arrangement, described two semicircle spacer bars(21)It is divided into cross reinforcing(22)Both ends, each semicircle spacer bar (21)Both ends respectively with a cross reinforcing(22)Welding.
  5. 5. framework of steel reinforcement according to claim 4, it is characterised in that:The framework of steel reinforcement(2)First longitudinal direction is further included to add Strengthening tendons(23)With second longitudinal direction reinforcing rib(24), the first longitudinal direction reinforcing rib(23)With the semicircle spacer bar(21)Two End welding, the second longitudinal direction reinforcing rib(24)It is welded in two cross reinforcings(22)Between, the first longitudinal direction reinforcing rib (23)With the semicircle spacer bar(21)Between be welded with more radial reinforcing ribs(25).
CN201610163800.4A 2016-03-22 2016-03-22 A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar Active CN105672137B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610163800.4A CN105672137B (en) 2016-03-22 2016-03-22 A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610163800.4A CN105672137B (en) 2016-03-22 2016-03-22 A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar

Publications (2)

Publication Number Publication Date
CN105672137A CN105672137A (en) 2016-06-15
CN105672137B true CN105672137B (en) 2018-04-13

Family

ID=56311331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610163800.4A Active CN105672137B (en) 2016-03-22 2016-03-22 A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar

Country Status (1)

Country Link
CN (1) CN105672137B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109322248A (en) * 2018-10-12 2019-02-12 中铁隧道集团二处有限公司 A kind of Bridge Piers bar reinforcement positioning device and installation method
CN113668387A (en) * 2021-07-08 2021-11-19 中交路桥建设有限公司 Modularized construction method for pier body reinforcing steel bars

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003239455A (en) * 2002-02-18 2003-08-27 Kyushu Univ Concrete support
CN101929249A (en) * 2010-08-10 2010-12-29 中铁一局集团有限公司 Double line stream-line type round end entity pier cap steel bar overall binding construction method
CN203420229U (en) * 2013-09-05 2014-02-05 中铁上海工程局有限公司 Positioner for reinforcement framework of round-ended solid pier body
CN104404883A (en) * 2014-11-19 2015-03-11 中交四航局第三工程有限公司 Inner working platform for rapid construction of bridge pier and construction method using inner working platform
CN204266115U (en) * 2014-12-03 2015-04-15 中铁上海工程局有限公司 Round end type entity pier shaft clad steel muscle colligation auxiliary positioning mould
CN105220619A (en) * 2015-10-12 2016-01-06 中铁城建集团第二工程有限公司 A kind of method of quick manufacture two-wire nose circle solid pier

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003239455A (en) * 2002-02-18 2003-08-27 Kyushu Univ Concrete support
CN101929249A (en) * 2010-08-10 2010-12-29 中铁一局集团有限公司 Double line stream-line type round end entity pier cap steel bar overall binding construction method
CN203420229U (en) * 2013-09-05 2014-02-05 中铁上海工程局有限公司 Positioner for reinforcement framework of round-ended solid pier body
CN104404883A (en) * 2014-11-19 2015-03-11 中交四航局第三工程有限公司 Inner working platform for rapid construction of bridge pier and construction method using inner working platform
CN204266115U (en) * 2014-12-03 2015-04-15 中铁上海工程局有限公司 Round end type entity pier shaft clad steel muscle colligation auxiliary positioning mould
CN105220619A (en) * 2015-10-12 2016-01-06 中铁城建集团第二工程有限公司 A kind of method of quick manufacture two-wire nose circle solid pier

Also Published As

Publication number Publication date
CN105672137A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN106088780B (en) The cast-in-place concrete pylon and its construction method of pre-made void reinforcement bar truss mould plate
CN108505433B (en) Pier structure and construction method thereof
CN108049305A (en) The splicing construction and joining method of a kind of precast pier and prefabricated cushion cap
CN108149825B (en) A kind of connection type and construction method for the prefabricated board of assembled architecture, prefabricated board and beam
CN102877407B (en) Concrete continuous box girder of corrugated steel web for curved bridge
CN105672137B (en) A kind of construction method and framework of steel reinforcement of bridge pier pier shaft reinforcing bar
CN105970803B (en) Shear-resistant energy dissipation device of assembled pier and construction method
CN102979042B (en) Bridge pier connecting device for bridge lifting process and construction method for bridge pier connecting device
CN103410090B (en) A kind of suspension rod anchoring structure of active enforcement concrete bowstring arch bridge and construction method thereof
CN208586511U (en) A kind of soap-free emulsion polymeization post-tensioned prestressing assembled pier connection structure
CN102777050B (en) Assembly type jig frame for longspan pipe truss roof girder
CN103924676B (en) Prestressing force connects beams of concrete concrete-filled circular steel tube column node
CN108824211A (en) A kind of bridge pier foundation in construction duration method in the river of bridge
CN109267489B (en) Construction method for cable-stayed bridge cable tower anchoring area
CN205501803U (en) Framework of steel reinforcement of pier pier shaft reinforcing bar
CN110847022A (en) Multi-support steel pipe concrete single-column pier with concrete cover beam
CN215669083U (en) T roof beam cross slab reinforced structure
CN103924682A (en) Circular concrete-filled steel tubular column node of unbonded pre-stressing connecting concrete beam
CN209602942U (en) A kind of compound seismic reinforcing structure of V-type bridge pier
CN103924677B (en) Prestressing without bondn is connected beams of concrete square steel tube concrete column combination node with regular reinforcement
CN203097109U (en) Pre-tensioning pre-stressing superposed secondary beam prefabricated component
CN206570674U (en) Assembled pretensioned prestressing corrugated steel web plate composite box girder
CN110331656A (en) A kind of soap-free emulsion polymeization post-tensioned prestressing assembled pier connection structure and its construction method
CN214328490U (en) Prefabricated pier adopting ultra-high performance concrete in complex stress area
CN202705885U (en) Welding-free support node for continuous beam bridge made of concrete-filled steel tube

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Yan Lizhong

Inventor after: Zhang Guangping

Inventor after: Li Jinbao

Inventor after: Pang Xihai

Inventor after: Ren Hongzhuan

Inventor after: Guo Zhaohui

Inventor after: Wang Hongjin

Inventor after: Zhong Gaojie

Inventor after: Hu Xiaojun

Inventor after: Cao Jianqiu

Inventor before: Li Jinbao

Inventor before: Ren Hongzhuan

Inventor before: Guo Zhaohui

Inventor before: Wang Hongjin

Inventor before: Zhong Gaojie

Inventor before: Hu Xiaojun

Inventor before: Cao Jianqiu

Inventor before: He Lei

Inventor before: Wang Yong

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant