CN105625447A - 一种软土地区地下结构堵漏施工方法 - Google Patents

一种软土地区地下结构堵漏施工方法 Download PDF

Info

Publication number
CN105625447A
CN105625447A CN201410827310.0A CN201410827310A CN105625447A CN 105625447 A CN105625447 A CN 105625447A CN 201410827310 A CN201410827310 A CN 201410827310A CN 105625447 A CN105625447 A CN 105625447A
Authority
CN
China
Prior art keywords
crack
hole
underground structure
construction method
gap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410827310.0A
Other languages
English (en)
Inventor
曲永昊
纪尊众
杨绍普
周冠男
窦洪羽
任宏茂
何敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201410827310.0A priority Critical patent/CN105625447A/zh
Publication of CN105625447A publication Critical patent/CN105625447A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

一种软土地区地下结构堵漏施工方法,其特征在于:所述的软土地区地下结构堵漏施工方法,采用高渗透改性环氧树脂,油溶性与水溶性聚氨酯的混合液,打孔埋设长短针头,短针头先注射聚氨酯,长针头后注射高渗透改性环氧树脂方法。渗漏的部位,采用油溶性聚氨酯与水溶性聚氨酯2~1:1的配比。长、短针头打孔时,浅孔点与裂缝应间隔5~8cm进行成孔;深孔点与裂缝间隔8~10cm斜向成孔;钻孔点布置间距:深、浅孔相间进行,沿裂缝两边梅花型交错布置;裂缝断开、分岔部位加密。钻孔倾角:孔与裂缝断面成45-75°交叉布置,所钻孔与裂缝相交,深孔穿过裂缝。本发明的优点:施工简便,对软土地区地下结构渗漏水堵漏效果良好。

Description

一种软土地区地下结构堵漏施工方法
技术领域
本发明涉及地下结构施工领域,特别涉及了一种软土地区地下结构堵漏施工方法。
背景技术
随着城市地下空间的不断开发利用,地下主体结构的渗漏水现象普遍存在,对工程的施工质量及后期的投入使用都有较大的影响。以往在结构堵漏施工中常采用聚氨酯或聚氨酯结合改性环氧树脂的方法,虽堵漏速度快、见效快,但易造成结构砼损坏、耐久性差、复漏现象严重且对结构补强作用差,费用昂贵。
经对现有技术的文献检索,尚未有采用油溶性与水溶性聚氨酯的混合液、高渗透改性环氧树脂结合使用,打孔埋设长短针头,短针头先注射聚氨酯,长针头后注射高渗透改性环氧树脂的堵漏方法。
发明内容
本发明的目的是为了针对软土地区地下结构渗漏水治理的难点,为了较好地治理地下结构的渗漏,保证主体结构的施工质量及投入使用,提出了堵漏效果较好,费用较低的施工方法,特提供了一种软土地区地下结构堵漏施工方法。
本发明提供了一种软土地区地下结构堵漏施工方法,其特征在于:所述的软土地区地下结构堵漏施工方法,采用高渗透改性环氧树脂,油溶性与水溶性聚氨酯的混合液,打孔埋设长短针头,短针头先注射聚氨酯,长针头后注射高渗透改性环氧树脂方法,达到堵漏的效果。
渗漏的部位,采用油溶性聚氨酯与水溶性聚氨酯2~1:1的配比。
长、短针头打孔时,浅孔点与裂缝应间隔5~8cm进行成孔,孔深10~15cm;深孔点与裂缝间隔8~10cm斜向成孔,孔深20~25cm;
钻孔点布置间距:深、浅孔相间进行,在20~30cm之间,沿裂缝两边梅花型交错布置;裂缝断开、分岔部位加密。
钻孔倾角:孔与裂缝断面成45-75°交叉布置,所钻孔与裂缝相交,深孔穿过裂缝。
所述的堵漏方法中的针头埋设时,要先进行清孔处理,用毛刷将孔内的泥巴清理干净,然后安装止水针头,止水针头分为10cm、20cm两种。
所述的堵漏方法中灌注浆液应该从结构立面由下向上进行,首先选择浅孔针头灌注聚氨酯混合液,当浆液从裂缝处冒出时应立即停止,在第一次浅针头注完聚氨酯后间隔两个小时,在埋设的长针头进行高渗透环氧树脂堵漏材料的灌注。
本发明的优点:
本发明所述的软土地区地下结构堵漏施工方法,施工简便,对软土地区地下结构渗漏水堵漏效果良好。
附图说明
下面结合附图及实施方式对本发明作进一步详细的说明:
图1是本发明专利针头埋设示意图。
图2是本发明工序流程图。
具体实施方式
实施例1
本实施例提供了一种软土地区地下结构堵漏施工方法,其特征在于:所述的软土地区地下结构堵漏施工方法,采用高渗透改性环氧树脂,油溶性与水溶性聚氨酯的混合液,打孔埋设长短针头,短针头先注射聚氨酯,长针头后注射高渗透改性环氧树脂方法,达到堵漏的效果。
渗漏的部位,采用油溶性聚氨酯与水溶性聚氨酯2:1的配比。
长、短针头打孔时,浅孔点与裂缝应间隔5cm进行成孔,孔深10cm;深孔点与裂缝间隔8cm斜向成孔,孔深20cm;
钻孔点布置间距:深、浅孔相间进行,在20cm之间,沿裂缝两边梅花型交错布置;裂缝断开、分岔部位加密。
钻孔倾角:孔与裂缝断面成45°交叉布置,所钻孔与裂缝相交,深孔穿过裂缝。
所述的堵漏方法中的针头埋设时,要先进行清孔处理,用毛刷将孔内的泥巴清理干净,然后安装止水针头,止水针头分为10cm、20cm两种。
所述的堵漏方法中灌注浆液应该从结构立面由下向上进行,首先选择浅孔针头灌注聚氨酯混合液,当浆液从裂缝处冒出时应立即停止,在第一次浅针头注完聚氨酯后间隔两个小时,在埋设的长针头进行高渗透环氧树脂堵漏材料的灌注。
实施例2
本实施例提供了一种软土地区地下结构堵漏施工方法,其特征在于:所述的软土地区地下结构堵漏施工方法,采用高渗透改性环氧树脂,油溶性与水溶性聚氨酯的混合液,打孔埋设长短针头,短针头先注射聚氨酯,长针头后注射高渗透改性环氧树脂方法,达到堵漏的效果。
渗漏的部位,采用油溶性聚氨酯与水溶性聚氨酯2:1的配比。
长、短针头打孔时,浅孔点与裂缝应间隔5~8cm进行成孔,孔深12cm;深孔点与裂缝间隔9cm斜向成孔,孔深25cm;
钻孔点布置间距:深、浅孔相间进行,在20~30cm之间,沿裂缝两边梅花型交错布置;裂缝断开、分岔部位加密。
钻孔倾角:孔与裂缝断面成60°交叉布置,所钻孔与裂缝相交,深孔穿过裂缝。
所述的堵漏方法中的针头埋设时,要先进行清孔处理,用毛刷将孔内的泥巴清理干净,然后安装止水针头,止水针头分为10cm、20cm两种。
所述的堵漏方法中灌注浆液应该从结构立面由下向上进行,首先选择浅孔针头灌注聚氨酯混合液,当浆液从裂缝处冒出时应立即停止,在第一次浅针头注完聚氨酯后间隔两个小时,在埋设的长针头进行高渗透环氧树脂堵漏材料的灌注。
实施例3
本实施例提供了一种软土地区地下结构堵漏施工方法,其特征在于:所述的软土地区地下结构堵漏施工方法,采用高渗透改性环氧树脂,油溶性与水溶性聚氨酯的混合液,打孔埋设长短针头,短针头先注射聚氨酯,长针头后注射高渗透改性环氧树脂方法,达到堵漏的效果。
渗漏的部位,采用油溶性聚氨酯与水溶性聚氨酯1:1的配比。
长、短针头打孔时,浅孔点与裂缝应间隔8cm进行成孔,孔深15cm;深孔点与裂缝间隔10cm斜向成孔,孔深25cm;
钻孔点布置间距:深、浅孔相间进行,在30cm距离,沿裂缝两边梅花型交错布置;裂缝断开、分岔部位加密。
钻孔倾角:孔与裂缝断面成75°交叉布置,所钻孔与裂缝相交,深孔穿过裂缝。
所述的堵漏方法中的针头埋设时,要先进行清孔处理,用毛刷将孔内的泥巴清理干净,然后安装止水针头,止水针头分为10cm、20cm两种。
所述的堵漏方法中灌注浆液应该从结构立面由下向上进行,首先选择浅孔针头灌注聚氨酯混合液,当浆液从裂缝处冒出时应立即停止,在第一次浅针头注完聚氨酯后间隔两个小时,在埋设的长针头进行高渗透环氧树脂堵漏材料的灌注。

Claims (4)

1.一种软土地区地下结构堵漏施工方法,其特征在于:所述的软土地区地下结构堵漏施工方法,采用高渗透改性环氧树脂,油溶性与水溶性聚氨酯的混合液,打孔埋设长短针头,短针头先注射聚氨酯,长针头后注射高渗透改性环氧树脂方法。
2.按照权利要求1所述的软土地区地下结构堵漏施工方法,其特征在于:渗漏的部位,采用油溶性聚氨酯与水溶性聚氨酯2~1:1的配比。
3.按照权利要求1所述的软土地区地下结构堵漏施工方法,其特征在于:长、短针头打孔时,浅孔点与裂缝应间隔5~8cm进行成孔,孔深10~15cm;深孔点与裂缝间隔8~10cm斜向成孔,孔深20~25cm;
钻孔点布置间距:深、浅孔相间进行,在20~30cm之间,沿裂缝两边梅花型交错布置;裂缝断开、分岔部位加密。
钻孔倾角:孔与裂缝断面成45-75°交叉布置,所钻孔与裂缝相交,深孔穿过裂缝。
4.按照权利要求1所述的软土地区地下结构堵漏施工方法,其特征在于:所述的堵漏方法中的针头埋设时,要先进行清孔处理,用毛刷将孔内的泥巴清理干净,然后安装止水针头,止水针头分为10cm、20cm两种。
CN201410827310.0A 2014-12-26 2014-12-26 一种软土地区地下结构堵漏施工方法 Pending CN105625447A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410827310.0A CN105625447A (zh) 2014-12-26 2014-12-26 一种软土地区地下结构堵漏施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410827310.0A CN105625447A (zh) 2014-12-26 2014-12-26 一种软土地区地下结构堵漏施工方法

Publications (1)

Publication Number Publication Date
CN105625447A true CN105625447A (zh) 2016-06-01

Family

ID=56040757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410827310.0A Pending CN105625447A (zh) 2014-12-26 2014-12-26 一种软土地区地下结构堵漏施工方法

Country Status (1)

Country Link
CN (1) CN105625447A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442862A (zh) * 2015-11-19 2016-03-30 江苏鼎达建筑新技术有限公司 一种混凝土裂缝渗漏水堵漏加固修复方法
CN108517899A (zh) * 2018-05-28 2018-09-11 深圳市工勘岩土集团有限公司 深基坑地下连续墙渗漏钻孔埋嘴高压灌浆堵漏处理方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4859064B2 (ja) * 2007-10-22 2012-01-18 首都高速道路株式会社 土木工事用シール工法
CN103174112A (zh) * 2013-03-28 2013-06-26 葛洲坝集团试验检测有限公司 一种贯穿性混凝土裂缝的灌浆方法
CN103643657A (zh) * 2013-12-24 2014-03-19 中国水电十一局郑州科研设计有限公司 应用于水电站大坝渗漏水处理的深孔化学灌浆施工方法
CN103898873A (zh) * 2014-03-25 2014-07-02 安徽水安建设集团股份有限公司 高水头下竖井施工缝渗水堵漏施工方法
CN104234090A (zh) * 2014-09-04 2014-12-24 江苏南通三建集团有限公司 一种治理混凝土底板、墙体裂缝渗水的方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4859064B2 (ja) * 2007-10-22 2012-01-18 首都高速道路株式会社 土木工事用シール工法
CN103174112A (zh) * 2013-03-28 2013-06-26 葛洲坝集团试验检测有限公司 一种贯穿性混凝土裂缝的灌浆方法
CN103643657A (zh) * 2013-12-24 2014-03-19 中国水电十一局郑州科研设计有限公司 应用于水电站大坝渗漏水处理的深孔化学灌浆施工方法
CN103898873A (zh) * 2014-03-25 2014-07-02 安徽水安建设集团股份有限公司 高水头下竖井施工缝渗水堵漏施工方法
CN104234090A (zh) * 2014-09-04 2014-12-24 江苏南通三建集团有限公司 一种治理混凝土底板、墙体裂缝渗水的方法

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442862A (zh) * 2015-11-19 2016-03-30 江苏鼎达建筑新技术有限公司 一种混凝土裂缝渗漏水堵漏加固修复方法
CN105442862B (zh) * 2015-11-19 2018-02-27 江苏鼎达建筑新技术有限公司 一种混凝土裂缝渗漏水堵漏加固修复方法
CN108517899A (zh) * 2018-05-28 2018-09-11 深圳市工勘岩土集团有限公司 深基坑地下连续墙渗漏钻孔埋嘴高压灌浆堵漏处理方法

Similar Documents

Publication Publication Date Title
CN101575983B (zh) 煤矿井下定向压裂增透消突方法及压裂增透消突装置
CN108729897B (zh) 一种二氧化碳–滑溜水间歇式混合压裂设计方法
CN108661617A (zh) 一种增加高温地层人工缝网复杂程度的压裂方法
CN110295901A (zh) 一种地浸采矿方法及***
ATE528484T1 (de) Verfahren und system zur behandlung einer unterirdischen formation mittels umleitung
CN104612130B (zh) 一种隧道底部隐伏溶洞注浆处治方法
WO2014088701A3 (en) Stabilized fluids in well treatment
CN105332681A (zh) 干热岩热储层的热刺激与化学刺激联合工艺
RU2737618C1 (ru) Способ водоудержания для ускорения самовосстановления рудничных трещин посредством химического размягчения карбонатита
CN106703011A (zh) 含水卵石层和饱和砂岩地层咬合桩施工方法
CN104314569A (zh) 一种深部孔隙卤水及低品位固体钾矿的开采方法
CN108915690B (zh) 竖井含水层掘进中预防竖井井壁涌水的新方法
CN105625447A (zh) 一种软土地区地下结构堵漏施工方法
CN204551447U (zh) 淤泥质土水泥搅拌桩钻机钻头
CN105064377B (zh) 一种组合式基坑支护桩结构
RU2010137055A (ru) Способ разработки залежей нефти в карбонатных коллекторах с водонефтяными зонами
CN106013155A (zh) 一种填造覆盖层、注浆固结处理钻孔漏浆的方法
CN103696730B (zh) 钻孔施工漏浆堵漏方法
RU2597305C1 (ru) Способ разработки нефтяной залежи в карбонатных коллекторах
CN109914390A (zh) 一种用于咬合式排桩施工冷缝的注浆结构及施工方法
CN111550250A (zh) 一种立井井筒过富水煤层段安全掘进防治水保护方法
CN105350544A (zh) 用于含有块石区域的止水帷幕及其施工方法
RU2509878C1 (ru) Способ разработки нефтяной оторочки в сложнопостроенном карбонатном коллекторе
RU2513962C1 (ru) Способ разработки нефтяной залежи
CN105781580A (zh) 隧洞裂缝修补的方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160601

RJ01 Rejection of invention patent application after publication