CN105604339B - Secondary structure constructs column reinforcing method - Google Patents

Secondary structure constructs column reinforcing method Download PDF

Info

Publication number
CN105604339B
CN105604339B CN201510982012.3A CN201510982012A CN105604339B CN 105604339 B CN105604339 B CN 105604339B CN 201510982012 A CN201510982012 A CN 201510982012A CN 105604339 B CN105604339 B CN 105604339B
Authority
CN
China
Prior art keywords
column
post
constructional column
nut
constructional
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510982012.3A
Other languages
Chinese (zh)
Other versions
CN105604339A (en
Inventor
柴旭光
张大鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201510982012.3A priority Critical patent/CN105604339B/en
Publication of CN105604339A publication Critical patent/CN105604339A/en
Application granted granted Critical
Publication of CN105604339B publication Critical patent/CN105604339B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention discloses a kind of secondary structure to construct column reinforcing method, including step:Play constructional column center line, absolute altitude control line;Colligation constructional column post muscle;Screw arbor with nut at both-ends and the horizontal tension rib of wall are welded;T-shaped spacer bar, control construction column section, axial location are welded in the constructional column cage bar position of 5cm eminences on away from constructional column post root;About 5mm pastes wide sponge strip on the outside of constructional column post skin;Installation constitution column template;Installation constitution post tie;Construct column template correction, reinforce;Pour into a mould post concrete;Form removal, the Screw arbor with nut at both-ends stretched out is cut off along constructional column surface, and to the Screw arbor with nut at both-ends head antirust treatment after cut-out.The horizontal tension rib of wall and the welding of constructional column wall-punching pair-pulling threaded spindle, screw combinations butterfly are captivated the steel pipe of construction column end wood reinforcement back cord by the present invention, and providing construction column end using the pulling force of horizontal bar reinforces required horizontal restraint, and stability is higher;Masonry structure is avoided to cause wall integrity and the disadvantage of compression strength step-down because of the punching of constructional column formwork.

Description

Secondary structure constructs column reinforcing method
Technical field
The present invention relates to building construction, secondary structure construction field, and in particular to a kind of secondary structure constructional column reinforcing side Method.
Background technology
In current building trade, masonry structure needs to add constructional column to strengthen masonry globality, the template of constructional column Reinforce mainly using the punching sleeve-penetrating combination wood stupefied on masonry structure and the conventional practice of steel pipe reinforcing template.Its shortcoming be Punching can destroy the globality and compression strength of masonry structure on masonry wall, the stability of wall be reduced, to follow-up plastering process Cause the mass defects such as hollowing, crackle.
The documents 1 of Application No. 201420504673.6 disclose a kind of construction column template building block, directly with construction Column template building block pours mould as constructional column, and constructional column can be constructed simultaneously with wall, without formwork, but needs to customize and builds Block, cost improve, and do not consider each department building block level of production difference and work progress in damage to building block mould and Transport loss.The documents 2 of Application No. 200920217311.8 disclose a kind of constructional column sleeve bolt formwork system, adopt With being embedded in from top to bottom in the horizontal mortar joint of horse tooth trough both sides and length and the PVC sleeve pipes of constructional column masonry consistency of thickness, Split bolt is worn in PVC sleeve pipes and realizes that construction is easy to control to the drawknot of constructional column, saves construction cost, save fee of material and Labour, but due to the requirement principle that specification must not punch to masonry wall, therefore take masonry wall sleeve-penetrating drawknot no longer feasible, The program do not consider in mortar joint bury sleeve pipe violate in specification to mortar joint control requirement, with sleeve pipe to masonry rigidity, intensity, Globality, masonry adverse effect attractive in appearance.
The content of the invention
The technical problem to be solved in the present invention is, for existing Constructional Col-umn Construction above shortcomings, there is provided one kind two Secondary structure constructs column reinforcing method, and fundamentally solving the problems, such as that constructional column formwork is reinforced must punch on masonry structure, Avoid the drawbacks of masonry structure causes wall integrity and compression strength step-down because constructional column formwork punches.
The present invention is that technical scheme is used by solving above-mentioned technical problem:
A kind of secondary structure constructs column reinforcing method, comprises the following steps:
1)Play constructional column center line, absolute altitude control line;
2)Mast axis, absolute altitude control point pilot measurement to post side, colligation constructional column post muscle will be constructed;
3)Screw arbor with nut at both-ends and the horizontal tension rib of wall are welded;
4)According to constructional column center line, the constructional column cage bar position welding of 4 ~ 6cm eminences is T-shaped fixed on away from constructional column post root Position reinforcing bar, to control construction column cross-section size and axial location(Position-limiting action);
5)5mm pastes wide sponge strip on the outside of constructional column post skin, to ensure that lower mouth and seam are tight;
6)Installation constitution column template, construction column template include the support of post inner cross type and post surrounding exterior sheathing;
7)Installation constitution post tie, wherein styletable captivate wood reinforcement with the screw combinations butterfly welded with horizontal bar and carried on the back Stupefied steel pipe carries out formwork reinforcement;
8)Construct column template correction, reinforce;
9)Pour into a mould post concrete;
10)Form removal when post intensity to be constructed reaches design strength, 8 ~ 12mm depths are picked out in pre-buried Screw arbor with nut at both-ends cut-off part Pit, the Screw arbor with nut at both-ends stretched out is cut off along constructional column surface, and to the Screw arbor with nut at both-ends head antirust treatment after cut-out.
By such scheme, the step 5)Middle sponge strip width is 18 ~ 22mm.
By such scheme, the step 6)Specifically include:First mounting post inner cross type support, back mounting pole surrounding external mold Plate, the punching corresponding Screw arbor with nut at both-ends extended position being welded with horizontal tension rib during dispensing;Construct column template and press logical organ timbering installation, Both sides column template is first installed, draws each column template among logical line installation after calibrated, reinforcing again.
By such scheme, the step 7)Middle tie is buckled including flitch back cord, steel pipe and anti-skidding butterfly, and installation process is specific For:50mm × 100mm flitch back cord is followed closely on construction column template, spacing 100mm is outer with two along vertical flitch back cord direction Footpath 48mm wall thickness 3.5mm steel pipe and the anti-skidding butterfly of twice are buckled on Screw arbor with nut at both-ends and tighten fixation, tie vertical interval be 300 ~ 500mm。
By such scheme, the step 8)Specifically include:First by the correction of construction mast axis, both sides column template has been reinforced, Then column template among logical line correction is hung up, column template timing must assure that four sides on the same line, perpendicularity deviation, axle Line deviation, adjacent two surface difference of height, surface smoothness and cross-sectional internal size are controlled in job specfication tolerance scope It is interior.
By such scheme, the step 10)Middle Screw arbor with nut at both-ends head antirust treatment is specially floating with cement mortar.
Compared with conventional construction method, beneficial effects of the present invention:
1st, directly the horizontal tension rib of wall and constructional column wall-punching pair-pulling threaded spindle are welded, then with the screw combinations butterfly button The steel pipe of construction column end wood reinforcement back cord is pinned, the level needed for construction column end reinforcing is provided using the pulling force of horizontal bar Constraint, fundamentally solve the problems, such as constructional column formwork reinforce must be punched on masonry structure, avoid masonry structure because The drawbacks of punching of constructional column formwork causes wall integrity and compression strength step-down, make masonry globality and compression strength higher, Construction is more simple and efficient;
2nd, template construct, installation carry out operation by the quality requirement of plain form, and shuttering supporting uses flitch back cord group Steel pipe is closed with the reinforcement system of screw rod drawknot, compared with traditional masonry wall sleeve-penetrating drawknot method, simple and easy, the technique is on the spot Materials, the exposed direct cutting process of screw rod, it is higher to compare the construction method template strength of other building block moulds, more economical.
Brief description of the drawings
Fig. 1 is the reinforcing schematic diagram that secondary structure of the present invention constructs column reinforcing method;
Fig. 2 is that the horizontal tension rib of wall of the present invention coordinates welded structure schematic diagram with Screw arbor with nut at both-ends;
In figure, the horizontal tension rib of 1- walls, 2- Screw arbor with nut at both-ends, 3- flitch back cords.
Embodiment
Technical solution of the present invention is described in detail with reference to the accompanying drawings and examples.
Shown in 1 ~ Fig. 2 of reference picture, secondary structure of the present invention constructs column reinforcing method, comprises the following steps:
1)Before column template is sealed, post root top layer laitance is first cut, and is rinsed well with water, plays constructional column center line, absolute altitude Control line;
2)Mast axis, absolute altitude control point pilot measurement to post side, colligation constructional column post muscle will be constructed;
3)The tension rib 1 horizontal with wall of Screw arbor with nut at both-ends 2 is welded(10d single weldings;5d weldings by both sides, d are the horizontal drawknot of wall The diameter of muscle 1);
4)According to constructional column center line, T-shaped positioning is welded at the constructional column cage bar position of 5cm eminences on away from constructional column post root Reinforcing bar, to control construction column cross-section size and axial location(Position-limiting action);
5)About 5mm pastes the wide sponge strips of 20mm on the outside of constructional column post skin, to ensure that lower mouth and seam are tight;
6)Installation constitution column template:The support of first mounting post inner cross type, back mounting pole surrounding exterior sheathing, punching pair during dispensing The extended position of Screw arbor with nut at both-ends 2 that should be welded with horizontal tension rib;Construct column template and press logical organ timbering installation, two side column moulds are first installed Plate, each column template among logical line installation is drawn after calibrated, reinforcing again;
7)Installation constitution post tie:Tie is buckled including flitch back cord 3, steel pipe and anti-skidding butterfly, is followed closely on construction column template 50mm × 100mm flitch back cord 3, spacing about 100mm, along the vertical direction of flitch back cord 3 with two steel pipes of φ 48 × 3.5(Outside Footpath 48mm wall thickness 3.5mm)And the anti-skidding butterfly of twice is buckled on Screw arbor with nut at both-ends 2 and tightens fixation, tie vertical interval be 300 ~ 500mm;
8)Construct column template correction, reinforce:First by the correction of construction mast axis, both sides column template has been reinforced, has then been hung up Column template among logical line correction, column template timing must assure that four sides on the same line, perpendicularity deviation, misalignment of axe, Adjacent two surface difference of height, surface smoothness and cross-sectional internal size are controlled in the range of job specfication tolerance;
9)Pour into a mould post concrete;
10)Form removal when post intensity to be constructed reaches design strength, the recessed of 10mm depths is picked out in the pre-buried cut-off part of Screw arbor with nut at both-ends 2 Hole, the Screw arbor with nut at both-ends 2 stretched out is cut off along constructional column surface, it is floating with cement mortar(Screw head antirust treatment).
Obviously, above-described embodiment is only intended to clearly illustrate example of the present invention, and is not to the present invention The restriction of embodiment.For those of ordinary skill in the field, spirit under this invention is extended out aobvious and easy Among the change or variation seen are still in protection scope of the present invention.

Claims (6)

1. secondary structure constructs column reinforcing method, it is characterised in that comprises the following steps:
1)Play constructional column center line, absolute altitude control line;
2)Mast axis, absolute altitude control point pilot measurement to post side, colligation constructional column post muscle will be constructed;
3)Screw arbor with nut at both-ends and the horizontal tension rib of wall are welded;
4)According to constructional column center line, T-shaped positioning steel is welded at the constructional column cage bar position of 4 ~ 6cm eminences on away from constructional column post root Muscle, to control construction column cross-section size and axial location;
5)5mm pastes wide sponge strip on the outside of constructional column post skin, to ensure that lower mouth and seam are tight;
6)Installation constitution column template, construction column template include the support of post inner cross type and post surrounding exterior sheathing;
7)Installation constitution post tie, wherein styletable captivate wood reinforcement back cord with the screw combinations butterfly welded with horizontal bar Steel pipe carries out formwork reinforcement;
8)Construct column template correction, reinforce;
9)Pour into a mould post concrete;
10)Form removal when post intensity to be constructed reaches design strength, the deep pits of 8 ~ 12mm are picked out in pre-buried Screw arbor with nut at both-ends cut-off part, The Screw arbor with nut at both-ends stretched out along the cut-out of constructional column surface, and to the Screw arbor with nut at both-ends head antirust treatment after cut-out.
2. secondary structure according to claim 1 constructs column reinforcing method, it is characterised in that the step 5)Middle sponge strip Width is 18 ~ 22mm.
3. secondary structure according to claim 1 constructs column reinforcing method, it is characterised in that the step 6)Specific bag Include:The support of first mounting post inner cross type, back mounting pole surrounding exterior sheathing, punching is corresponding during dispensing is welded with horizontal tension rib Screw arbor with nut at both-ends extended position;Construction column template is pressed logical organ timbering and installed, and first installs both sides column template, is drawn again after calibrated, reinforcing logical Each column template among line installation.
4. secondary structure according to claim 1 constructs column reinforcing method, it is characterised in that the step 7)Middle tie bag Include flitch back cord, steel pipe and anti-skidding butterfly to buckle, installation process is specially:50mm × 100mm flitch is followed closely on construction column template Back cord, spacing 100mm, along vertical flitch back cord direction with two external diameter 48mm wall thickness 3.5mm steel pipe and the anti-skidding butterfly of twice It is buckled on Screw arbor with nut at both-ends and tightens fixation, tie vertical interval is 300 ~ 500mm.
5. secondary structure according to claim 1 constructs column reinforcing method, it is characterised in that the step 8)Specific bag Include:First by the correction of construction mast axis, both sides column template has been reinforced, has then hung up column template among logical line correction, column template school Timing must assure that four sides on the same line, perpendicularity deviation, misalignment of axe, adjacent two surface difference of height, surface smoothness And cross-sectional internal size is controlled in the range of job specfication tolerance.
6. secondary structure according to claim 1 constructs column reinforcing method, it is characterised in that the step 10)In to draw Screw head antirust treatment is specially floating with cement mortar.
CN201510982012.3A 2015-12-22 2015-12-22 Secondary structure constructs column reinforcing method Active CN105604339B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510982012.3A CN105604339B (en) 2015-12-22 2015-12-22 Secondary structure constructs column reinforcing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510982012.3A CN105604339B (en) 2015-12-22 2015-12-22 Secondary structure constructs column reinforcing method

Publications (2)

Publication Number Publication Date
CN105604339A CN105604339A (en) 2016-05-25
CN105604339B true CN105604339B (en) 2017-12-15

Family

ID=55984637

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510982012.3A Active CN105604339B (en) 2015-12-22 2015-12-22 Secondary structure constructs column reinforcing method

Country Status (1)

Country Link
CN (1) CN105604339B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178216B (en) * 2016-11-10 2019-04-02 叶香菲 Big height brick-concrete composite buildings reinforcing construction
CN107299701B (en) * 2017-07-31 2019-07-23 武汉一冶建筑安装工程有限责任公司 Fill wall construction column one-time-concreting construction method
CN113982261A (en) * 2021-09-27 2022-01-28 中国一冶集团有限公司 Constructional column compensation type combined aluminum mould and formwork supporting construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008163646A (en) * 2006-12-28 2008-07-17 Taisei Corp Method and structure for reinforcing existing column
CN201627279U (en) * 2009-12-24 2010-11-10 青岛海川建设集团有限公司 Fixing device for masonry structure
CN104295003A (en) * 2014-09-26 2015-01-21 中建七局第二建筑有限公司 Structural column construction method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7337591B2 (en) * 2001-11-28 2008-03-04 Inteplast Group, Ltd. Building construction system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008163646A (en) * 2006-12-28 2008-07-17 Taisei Corp Method and structure for reinforcing existing column
CN201627279U (en) * 2009-12-24 2010-11-10 青岛海川建设集团有限公司 Fixing device for masonry structure
CN104295003A (en) * 2014-09-26 2015-01-21 中建七局第二建筑有限公司 Structural column construction method

Also Published As

Publication number Publication date
CN105604339A (en) 2016-05-25

Similar Documents

Publication Publication Date Title
CN102121310B (en) Double column constructional template for large-section ultrahigh steel reinforced clear water concrete and construction method thereof
CN105604339B (en) Secondary structure constructs column reinforcing method
CN103556819B (en) A kind of construction method of reserved constructional column hole on beam slab
CN204645268U (en) A kind of infilled wall tie bar built-in fitting
CN107083804B (en) A kind of wall structure column joint bar construction method
CN104712086B (en) Assembled type concrete hollow composite floor slab and manufacturing method thereof
CN106760502A (en) Shear wall end cylinder construction method
CN109676748A (en) A kind of production method of the concrete prefabricated frame of distribution box
CN113216252A (en) Expansion joint reinforcing device and method for multi-section continuous casting of underground pipe gallery
CN106930523A (en) A kind of concrete structure catch pit detachable template reinforcement technique
CN106284789B (en) Construction technology for controlling cast-in-situ floor Forming Quality
CN105484421A (en) Ring beam formwork bricks and building secondary structure filler wall ring beam construction method
CN208502075U (en) A kind of constructional column upper reinforcement connection pre-embedded device
CN202509764U (en) Template bracing structure for constructional column
CN107288341A (en) A kind of reserving hole building mortion and construction method
CN207469596U (en) A kind of beam column outer rim is exempted to tear concrete mold open
CN203866972U (en) Embedded component for filler wall tie bars
CN103352568A (en) Method for building constructional column on foundation pad
CN207673351U (en) A kind of tunnel lining trolley end mould
CN203755682U (en) Secondary pouring form board constructing structure for small opening of concrete structure floor slab
CN102926544A (en) Method for constructing wall pulling steel bars in frame column and structure thereof
CN106545168A (en) Infilled wall tie bar connection construction method
CN103104099A (en) Method for constructing wall pulling steel bars in frame column and structure thereof
CN208918280U (en) A kind of mortar leakage prevention item preventing concrete wall column root spillage
CN203034790U (en) Basic prefabricated concrete formwork for basement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant