CN106545168A - Infilled wall tie bar connection construction method - Google Patents

Infilled wall tie bar connection construction method Download PDF

Info

Publication number
CN106545168A
CN106545168A CN201510592175.0A CN201510592175A CN106545168A CN 106545168 A CN106545168 A CN 106545168A CN 201510592175 A CN201510592175 A CN 201510592175A CN 106545168 A CN106545168 A CN 106545168A
Authority
CN
China
Prior art keywords
construction method
bar
infilled wall
reserved
silk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510592175.0A
Other languages
Chinese (zh)
Inventor
刘乐
邢占清
黄华
黄辉
童鹤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201510592175.0A priority Critical patent/CN106545168A/en
Publication of CN106545168A publication Critical patent/CN106545168A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to coagulation civil engineering, more particularly to the construction method of infilled wall tie bar.A kind of infilled wall tie bar connection construction method, first, makes and a screw shell matched with steel tie;Then, the processing before casting concrete is reserved in the reinforcing bar in concrete, exposed parts cover the silk of length 30mm~50mm on die head threading machine, then, the reinforcement installation of silk will be packaged in specified location, 100mm is exposed in template only, finally, with the screw shell by remaining 100mm exposed parts reinforcing bar and the bar connecting to be reserved in masonry after form removal.The present invention installs simple, can reduce xoncrete structure form removal difficulty, can guarantee that tension rib intensity again.

Description

Infilled wall tie bar connection construction method
Technical field
The present invention relates to coagulation civil engineering, more particularly to the construction method of infilled wall tie bar.
Background technology
Filling wall needs horizontal reinforcing bar when building by laying bricks or stones(Tension rib)It is connected with the xoncrete structure for having completed.If by protruded length 1000mm before concreting(Level interval 500mm)Tension rib be reserved in xoncrete structure, then can be very difficult during form removal.After the method for generally adopting at present is form removal, before building a wall, the steel planting on xoncrete structure.Although it is easy so to construct, the intensity of bar planting it is difficult to ensure that, and have certain destruction to structure.
The content of the invention
It is contemplated that overcoming the defect of prior art, there is provided a kind of infilled wall tie bar connection construction method.The present invention installs simple, can reduce xoncrete structure form removal difficulty, can guarantee that tension rib intensity again.
In order to solve above-mentioned technical problem, what the present invention was realized in:A kind of infilled wall tie bar connection construction method, first, makes and a screw shell matched with steel tie;Then, the processing before casting concrete is reserved in the reinforcing bar in concrete, exposed parts cover the silk of length 30mm~50mm on die head threading machine, then, the reinforcement installation of silk will be packaged in specified location, 100mm is exposed in template only, finally, with the screw shell by remaining 100mm exposed parts reinforcing bar and the bar connecting to be reserved in masonry after form removal.
The construction method bar planting intensity of the present invention can be sufficiently ensured, and will not destroy structure, while form removal is easy.
Description of the drawings
Below, with reference to accompanying drawing, the present invention is further illustrated:
Fig. 1 is the schematic diagram of the present invention.
Specific embodiment
As shown in figure 1, a kind of infilled wall tie bar connection construction method, first, makes and a screw shell 1 matched with steel tie;Then, the processing before casting concrete is reserved in the reinforcing bar 2 in concrete, exposed parts cover the silk of length 30mm~50mm on die head threading machine, then, the reinforcement installation of silk will be packaged in specified location, one section reinforcing bar 3 about 100mm is exposed in template only, finally, with the screw shell by remaining 100mm exposed parts reinforcing bar 3 and the bar connecting to be reserved in masonry 4 after form removal.

Claims (1)

1. a kind of infilled wall tie bar connection construction method, it is characterised in that first, make and one and steel tie matching screw shell;Then, the processing before casting concrete is reserved in the reinforcing bar in concrete, exposed parts cover the silk of length 30mm~50mm on die head threading machine, then, the reinforcement installation of silk will be packaged in specified location, one section is exposed in template only, finally, with the screw shell by remaining that section of exposed parts reinforcing bar and the bar connecting to be reserved in masonry after form removal.
CN201510592175.0A 2015-09-17 2015-09-17 Infilled wall tie bar connection construction method Pending CN106545168A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510592175.0A CN106545168A (en) 2015-09-17 2015-09-17 Infilled wall tie bar connection construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510592175.0A CN106545168A (en) 2015-09-17 2015-09-17 Infilled wall tie bar connection construction method

Publications (1)

Publication Number Publication Date
CN106545168A true CN106545168A (en) 2017-03-29

Family

ID=58361875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510592175.0A Pending CN106545168A (en) 2015-09-17 2015-09-17 Infilled wall tie bar connection construction method

Country Status (1)

Country Link
CN (1) CN106545168A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109306773A (en) * 2017-07-28 2019-02-05 中国二十冶集团有限公司 A kind of wall tie bar inspection localization method
CN113187221A (en) * 2021-04-21 2021-07-30 上海宝冶集团南京建筑有限公司 Reservation method of tie bar of aluminum alloy template

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU712389B2 (en) * 1995-11-15 1999-11-04 Daniel Charles Underwood Concrete joint and method
WO2004111363A1 (en) * 2003-06-13 2004-12-23 Onesteel Reinforcing Pty Ltd A coupler
CN101575844A (en) * 2009-06-05 2009-11-11 中国葛洲坝集团股份有限公司 Accurate contraposition connection method of horizontally embedded reinforcing steel bars
CH704181A2 (en) * 2010-12-01 2012-06-15 Bossard & Staerkle Ag Connecting element for installation between base- or cover plate and cantilever plate, has end surfaces approximately aligned with lateral exterior surfaces of isolation body in inserted condition
CN102852229A (en) * 2012-09-27 2013-01-02 安徽建工集团有限公司 After-embedding mechanical cold connection wall body drawknot rib construction member and installation method
CN203846679U (en) * 2014-05-22 2014-09-24 青岛一建集团有限公司 Tie bar of embedded sleeve of infilled wall

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU712389B2 (en) * 1995-11-15 1999-11-04 Daniel Charles Underwood Concrete joint and method
WO2004111363A1 (en) * 2003-06-13 2004-12-23 Onesteel Reinforcing Pty Ltd A coupler
CN101575844A (en) * 2009-06-05 2009-11-11 中国葛洲坝集团股份有限公司 Accurate contraposition connection method of horizontally embedded reinforcing steel bars
CH704181A2 (en) * 2010-12-01 2012-06-15 Bossard & Staerkle Ag Connecting element for installation between base- or cover plate and cantilever plate, has end surfaces approximately aligned with lateral exterior surfaces of isolation body in inserted condition
CN102852229A (en) * 2012-09-27 2013-01-02 安徽建工集团有限公司 After-embedding mechanical cold connection wall body drawknot rib construction member and installation method
CN203846679U (en) * 2014-05-22 2014-09-24 青岛一建集团有限公司 Tie bar of embedded sleeve of infilled wall

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109306773A (en) * 2017-07-28 2019-02-05 中国二十冶集团有限公司 A kind of wall tie bar inspection localization method
CN113187221A (en) * 2021-04-21 2021-07-30 上海宝冶集团南京建筑有限公司 Reservation method of tie bar of aluminum alloy template

Similar Documents

Publication Publication Date Title
CN103485537A (en) Construction method and structure of embedded reinforcement of super high-rise horizontal secondary structure
CN104963431A (en) Corner structural column construction method
CN106545168A (en) Infilled wall tie bar connection construction method
CN106638307A (en) Deeply-buried anchorage device
CN105040743A (en) Detachable support replacing method for underground structure post-cast strip and structure
CN106284428A (en) A kind of concrete column method for supporting of building structure post-cast strip
CN102660956B (en) Concrete moulding bed structure and pouring method
CN211923107U (en) Formwork-supporting-free structure of constructional column in wall
CN206071601U (en) The device that a kind of prevention tunnel double-lining vault comes to nothing
CN106381883B (en) Bar Seepage method through walls
CN105569092B (en) Underground pipe gallery deformation joint water-stopping belt transmission rod position integrated template construction method
CN105604339A (en) Secondary structure column reinforcing method
CN203977884U (en) A kind of steel reinforcement protective sleeve pipe
CN207376661U (en) A kind of plugging structure of poured band of outer wall of basement
CN203429798U (en) Embedded bar structure for horizontal secondary structure of super high-rise
CN201835524U (en) Pouring device for concrete beam with top embedded part
CN204001696U (en) The mould of building cob
CN203755682U (en) Secondary pouring form board constructing structure for small opening of concrete structure floor slab
CN103485527B (en) A kind of wall-connecting piece and using method thereof
CN104775831A (en) Tunnel secondary lining inverted arch and arch wall combined part short-free side wall arcing construction method
CN206233381U (en) A kind of structure roof discharge jacket pipe reserved opening blocks system
CN205776796U (en) A kind of U-shaped building built-in part
CN103726648A (en) Cast-in-situ lightweight aggregate concrete filler wall slip-form construction template system and construction method
CN104533085A (en) Detachable sealing-up screw
CN105421775B (en) A kind of lintel construction method of brick mix structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170329

WD01 Invention patent application deemed withdrawn after publication