CN105363545B - A kind of powdery paints pulverizer - Google Patents

A kind of powdery paints pulverizer Download PDF

Info

Publication number
CN105363545B
CN105363545B CN201510951202.9A CN201510951202A CN105363545B CN 105363545 B CN105363545 B CN 105363545B CN 201510951202 A CN201510951202 A CN 201510951202A CN 105363545 B CN105363545 B CN 105363545B
Authority
CN
China
Prior art keywords
plate
fixed
sub
crushing
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510951202.9A
Other languages
Chinese (zh)
Other versions
CN105363545A (en
Inventor
徐妍玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangjiang Yanghe Coating Industry Co., Ltd
Original Assignee
Jiaxing Reeyah Photoelectric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiaxing Reeyah Photoelectric Co Ltd filed Critical Jiaxing Reeyah Photoelectric Co Ltd
Priority to CN201510951202.9A priority Critical patent/CN105363545B/en
Publication of CN105363545A publication Critical patent/CN105363545A/en
Application granted granted Critical
Publication of CN105363545B publication Critical patent/CN105363545B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B02CRUSHING, PULVERISING, OR DISINTEGRATING; PREPARATORY TREATMENT OF GRAIN FOR MILLING
    • B02CCRUSHING, PULVERISING, OR DISINTEGRATING IN GENERAL; MILLING GRAIN
    • B02C21/00Disintegrating plant with or without drying of the material
    • B02C21/02Transportable disintegrating plant
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B02CRUSHING, PULVERISING, OR DISINTEGRATING; PREPARATORY TREATMENT OF GRAIN FOR MILLING
    • B02CCRUSHING, PULVERISING, OR DISINTEGRATING IN GENERAL; MILLING GRAIN
    • B02C23/00Auxiliary methods or auxiliary devices or accessories specially adapted for crushing or disintegrating not provided for in preceding groups or not specially adapted to apparatus covered by a single preceding group
    • B02C23/08Separating or sorting of material, associated with crushing or disintegrating
    • B02C23/10Separating or sorting of material, associated with crushing or disintegrating with separator arranged in discharge path of crushing or disintegrating zone
    • B02C23/12Separating or sorting of material, associated with crushing or disintegrating with separator arranged in discharge path of crushing or disintegrating zone with return of oversize material to crushing or disintegrating zone
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B07SEPARATING SOLIDS FROM SOLIDS; SORTING
    • B07BSEPARATING SOLIDS FROM SOLIDS BY SIEVING, SCREENING, SIFTING OR BY USING GAS CURRENTS; SEPARATING BY OTHER DRY METHODS APPLICABLE TO BULK MATERIAL, e.g. LOOSE ARTICLES FIT TO BE HANDLED LIKE BULK MATERIAL
    • B07B1/00Sieving, screening, sifting, or sorting solid materials using networks, gratings, grids, or the like
    • B07B1/28Moving screens not otherwise provided for, e.g. swinging, reciprocating, rocking, tilting or wobbling screens

Landscapes

  • Engineering & Computer Science (AREA)
  • Food Science & Technology (AREA)
  • Crushing And Grinding (AREA)

Abstract

The invention discloses a kind of powdery paints pulverizers, including rack, vibratory feed, feeding-distribution device, grinding device.The present invention can carry out sub-material before crushing to powder raw material, can realize the abundant crushing to powder raw material.

Description

A kind of powdery paints pulverizer
Technical field
The present invention relates to powdery paints pulverizers.
Background technology
Powdery paints is a kind of novel to be free of 100% solid powdery coating of solvent.With it is solvent-free, pollution-free, can return It receives, environmental protection, saves the energy and resource, reduces labor intensity the features such as high with coating machinery intensity.
Powdery paints has the requirement of fineness, grain size, and the raw material of some powdery paints may be that blocky or grain size is larger Therefore graininess will be mixed to form powdery paints and need to crush raw material, its fineness and grain size is allowed to reach requirement.
It is 2014.8.27 publication date 201410426811.8 applyings date is the special of 2015.1.7 to be in Chinese Patent Application No. A kind of paint pulverizer is disclosed in sharp document, including bottom is equipped with the pulverization cylinder of the first filter screen, the pulverization cylinder connection There is feed hopper, shaft is housed in the pulverization cylinder and is fixed on more crushing serrated knife, one end of the shaft in the shaft First motor is connected by machine driving;Press-powder case is housed below the pulverization cylinder, the press-powder case, which is equipped with, is equipped with the second mistake The discharge port of screen net, the press-powder case is built-in, and there are two the pressure rollers relatively rotated, are passed by gear between two pressure rollers Dynamic connection, one of pressure roller are connected with the second motor.Compared with prior art, the present invention makes the coating into pulverization cylinder by powder Broken serrated knife by the first filter screen enters press-powder case after smashing, and the pressure roller relatively rotated using two is crushed, and second Filter screen sifts out powder, and coating crushes thoroughly, and powder is thin, improves the glossiness of coating.
Reach the powder of requirement in some raw materials containing fineness and grain size, in addition may also have also in raw material and be not required to The impurity etc. wanted, the paint pulverizer of above structure, raw material all to pass through the first filter screen and the second filter screen carries out It crushes, sub-material, decontamination cannot be carried out to raw material, since all raw materials will through the step of crushing, pulverizer Load is larger, and energy consumption is more.At the same time, which is inconvenient to carry out continuous crushed work, is also unfavorable for comminuting matter Conveying.
Invention content
In order to carry out sub-material to powder raw material before crushing, it can realize that the abundant crushing to powder raw material, the present invention provide A kind of powdery paints pulverizer.
In order to achieve the above objectives, a kind of powdery paints pulverizer, including rack, vibratory feed, feeding-distribution device, crushing Device and conveying device;
The rack includes the first supporting rack, the second supporting rack and link;First supporting rack is located at the second supporting rack Left side, between the first supporting rack and the second supporting rack have space;Link is connected to the first supporting rack and the second support The upper end of frame;
The vibratory feed include vibrating transportation fixed frame, elastic device, vibration conveying mechanism, vibrating device and Magazine attachment;
The elastic device includes left elastic parts and right elastic parts;Left elastic parts is formed by two, right elasticity Component is formed by two;Left elastic parts includes lower-left seat, left spring and upper left seat, and left spring is located at lower-left seat and upper left seat Between;Right elastic parts includes bottom right seat, right spring and upper right seat, and right spring is located between bottom right seat and upper right seat, each right bullet Property component include two right springs, and lateral arrangement;
The vibration conveying mechanism includes vibrating transportation frame, vibrating transportation bottom plate, vibrating transportation top plate, muscle beam and sieve Expect device;
Vibrating transportation frame includes the 4th crossbeam and the 4th longeron;4th crossbeam includes two, and is mutually parallel;Two The left part of four crossbeams is welded with the 4th longeron;There is cavity in vibrating transportation frame;The right end of vibrating transportation frame, which has, to be opened Mouthful;The vibrating transportation bottom plate, the left end of vibrating transportation bottom plate self-excited oscillation transportation frame are welded in vibrating transportation frame Extend right up to middle part;It is located above vibrating transportation bottom plate in vibrating transportation frame and is welded with the vibrating transportation top The left end of plate, vibrating transportation top plate self-excited oscillation transportation frame extends right up to middle part;It is formed with above vibrating transportation top plate Material cavity;Be welded with more longitudinally arranged muscle beams between vibrating transportation bottom plate and vibrating transportation top plate, adjacent muscle beam it Between have gap;
The sieve material device includes fixed beam, connecting plate and cantilever beam;Fixed beam be fixed in vibrating transportation frame and Positioned at the right side of vibrating transportation bottom plate;Connecting plate is fixed on the right side of fixed beam, and in vibrating transportation frame;In connecting plate Right side be welded with the multiple cantilever beams for being mutually parallel and being laterally extended, cantilever beam is located in vibrating transportation frame, and two is adjacent outstanding It is formed with charging conduit between arm beam;It is fixed with sieve, the upper surface of the upper surface and vibrating transportation top plate of sieve on a cantilever beam Concordantly, there is sieve sieve pore, the diameter of sieve pore to be arranged according to the particle size of powdery paints;
Vibrating device is located between vibrating transportation fixed frame and vibration conveying mechanism;
Magazine attachment is fixed on vibrating transportation fixed frame;
The feeding-distribution device is fixed on the rack, and the lower section of the charging conduit positioned at vibration conveying mechanism;Point Expect that device includes sub-material shell and separatory funnel;
Sub-material shell includes sub-material front side board, sub-material back side panel, sub-material left plate and sub-material right plate;
Sub-material front side board and sub-material back side panel are arranged in parallel;For sub-material left plate from up to down towards tilted extension, sub-material is right Side plate is from up to down towards tilted extension, and relative to vertical plane, the angle of inclination of sub-material left plate is more than inclining for sub-material right plate Rake angle;Sub-material front side board, sub-material back side panel, sub-material left plate and sub-material right plate surround sub-material chamber;
It is respectively equipped with separatory funnel in the both sides of sub-material shell;Relative to vertical plane, the separatory funnel positioned at left side inclines Oblique angle is more than the inclination angle of the separatory funnel positioned at right side;Separatory funnel includes sub-material bottom plate and sub-material side plate;The sub-material of both sides Bottom plate is upwards and relative tilt extends in top and crosses to form sub-material side, and the right side of sub-material chamber is leaned on sub-material side;In sub-material bottom plate Front and rear sides are respectively welded sub-material side plate, and the both sides sub-material side plate of same separatory funnel extends internally from the top down, two sub-materials Upper end distance between side plate is more than lower end distance;Sub-material side shield is connected in the lower end of sub-material side plate;
It is located at left end in sub-material intracavitary and wind turbine is installed;
The grinding device is mounted on the space in rack and being predominantly located between the first supporting rack and the second supporting rack It is interior;
Grinding device includes loading device and disintegrating mechanism;Disintegrating mechanism is located at the top of loading device;
Disintegrating mechanism includes crushing frame, crushing frame, dynamic crushing frame, adjusting apparatus, resetting apparatus, drive system and closing piece surely Device;
It includes crushing front side board, crush back side panel and crushing right plate to crush frame;It crushes front side board, crush back side panel and powder It is formed with accommodating cavity in broken right plate;It crushes front side board and crushes back side panel and be mutually parallel, before crushing right plate is connected to crushing Side plate and the right end for crushing back side panel;
It is respectively welded outwardly extending crushing connecting plate in the bottom for crushing front side board and crushing back side panel, crushes connection Plate is connected on loading device;
It is respectively welded crushing mounting base on the lateral wall for crushing front side board and crushing back side panel;
The crushing frame of determining includes fixed frame and crushes plate surely;
Fixed frame includes fixed left plate, fixed right arc panel, fixed bottom plate, fixed top plate and fixed gusset;
Fixed bottom plate is connected to the lower end of fixed left plate and fixed right arc panel;Fixed top plate is connected to fixed left plate With the upper end of the right arc panel of fixation;It is surrounded by fixation between fixed left plate, fixed right arc panel, fixed bottom plate and fixed top plate Cavity is located between fixed left plate and fixed right arc panel in fixed cavity and is welded with polylith fixation gusset, fixed gusset Central axes by the center of circle of the right arc panel of fixation, be formed with fixed cavity between adjacent fixed gusset;
It is described to determine that crushing plate is arc-shaped, and radian is consistent with fixed right arc panel;
It is equipped with the asperities being longitudinally extended on the fixed surface for crushing plate;It is equipped with manganese steel layer on the fixed surface for crushing plate;
The dynamic crushing frame includes pivotally connected set, dynamic crushing bearing support, dynamic crushing plate and dynamic connecting seat;Pivotally connected set, dynamic powder Broken bearing support, dynamic crushing plate and dynamic connecting seat are structure as a whole;
The dynamic bearing support that crushes is connected in pivotally connected set, and it includes the first extension, the second extension, third to move and crush bearing support Extension, the 4th extension and the 5th extension;From pivotally connected set, lower section extends first extension to the left, and the second extension is from first The lower end bending of extension extends to the right, and from the bending of the lower end of the second extension, lower section extends third extension to the left, the From the lower end of third extension, bending extends four extensions to the right, the 5th extension from the lower end of the 4th extension bend to Lower left extends, and the bending angle of the 4th extension is more than the bending angle of the second extension, the bending angle of the 5th extension More than the bending angle of third extension;The dynamic lower end for crushing bearing support is connected on dynamic connecting seat;The dynamic plate that crushes is connected to pivot Between female connector and dynamic connecting seat, the dynamic plate that crushes is arc-shaped, moves and is formed with dynamic crushing cavity between crushing bearing support and dynamic crushing plate, Surely it crushes and is formed with crushing chamber between frame and dynamic crushing frame, the upper end of crushing chamber is more than lower end;
It is equipped with the asperities being longitudinally extended on moving the surface for crushing plate, move the asperities crushed on plate and crushes on plate surely Asperities shift to install, be equipped with manganese steel layer on the dynamic surface for crushing plate;
The adjusting apparatus is hinged on dynamic crush on frame;The resetting apparatus be located at it is dynamic crush frame with crush frame it Between;The dynamic frame that crushes of the drive system driving moves up and down;
Loading device be located at disintegrating mechanism left side be equipped with feeding mouth, the material through right side separatory funnel from feeding mouth into Enter into loading device, the material crushed through disintegrating mechanism also enters in loading device, and the powder material in loading device is fallen Enter onto conveying device.
The beneficial effects of the invention are as follows:Due to having space between the first supporting rack and the second supporting rack, conveniently exist Feeding-distribution device and grinding device are set at this.For elastic device, left elastic parts includes a left spring, right elasticity group Part includes two right springs, in this way, when vibrating device works, the Oscillation Amplitude of vibration conveying mechanism left end is more than shaking for right end Dynamic amplitude, continuously can be transported to right end from left end by the material on vibration conveying mechanism, prevent material in vibration conveying mechanism Interior delay.Two right spring lateral arrangements in same right elastic parts can realize that equal power supports, using same to vibration conveying mechanism One bottom right seat and upper right seat support two right springs simultaneously, can allow entire right elastic parts homogeneous deformation.In vibrating transportation top plate Top be formed with material cavity, be used for loaded material, can prevent material before vibration conveying mechanism using vibrating transportation frame Rear side and left side are slipped away.More longitudinally arranged muscle beams are welded between vibrating transportation bottom plate and vibrating transportation top plate.It is adjacent Muscle beam between have gap.Above structure allows vibration conveying mechanism to be in box-structure, compares entity structure, jigging conveyer The vibration meeting bigger of structure, is more conducive to the continuous conveying of material.Be fixed with sieve on a cantilever beam, the upper surface of sieve with shake The upper surface of dynamic conveying top plate is concordant, the material on vibrating transportation top plate can be smoothly entered on sieve, sieve has sieve The diameter in hole, sieve pore is arranged according to the particle size of powdery paints, in this way, being less than the powder of sieve diameter by sieve and grain size It falls, the particle to meeting powdery paints carries out first time screening, and incongruent material is transported in grinding device.Material passes through Charging conduit drops into sub-material intracavitary, and under the action of wind turbine, light thin material enters in the separatory funnel on right side, through sub-material Funnel exports material, and the thick material of weight drops into discharge in the separatory funnel of left end, can thus be detached to material, Useful powder materials are separated to be used.The fixed frame of above structure, due to foring fixed cavity between fixed gusset, In this way, when fixed frame is by outside extruding force, relative to entity structure, elastic deformation amount is big, and therefore, fixed frame is not easy By hard breakdown, service life is extended.In addition, since the central axes of fixed gusset are by the center of circle of the right arc panel of fixation, this Sample, when fixed frame is squeezed power, the Impact direction of fixed gusset is concentrated to circle centre position, allows the stress of fixed right arc panel More uniformly.Surely it crushes frame and dynamic crush is formed with crushing chamber between frame, cooperation crushes the structure of frame surely, allows the upper of crushing chamber End is more than lower end, is conducive to material in this way and enters in crushing chamber, while is more abundant to the crushing of material.When crushing, The dynamic power for crushing frame lower end is more than the power of upper end, using above-mentioned dynamic crushing branching bolster structure, since the 4th extension and the 5th prolongs The bending angle of extending portion is larger, in this way, allowing the load ability bigger for crushing bearing support lower end, it is not easy to allow and crush frame Elasticity and plasticity deforms, and is more conducive to crushing.The asperities being longitudinally extended are equipped on the dynamic surface for crushing plate, moves and crushes plate On asperities with surely crush plate on asperities shift to install, in this way, to material in addition to having granulitization, be also bent and cut The effect of the effect cut, crushing is more preferable.
Description of the drawings
Fig. 1 is the stereogram of powdery paints pulverizer.
Fig. 2 is the stereogram at another visual angle of powdery paints pulverizer.
Fig. 3 is the exploded view of powdery paints pulverizer.
Fig. 4 is the stereogram of rack.
Fig. 5 is the stereogram at another visual angle of rack.
Fig. 6 is the stereogram of vibratory feed.
Fig. 7 is the exploded view of vibratory feed.
Fig. 8 is the stereogram of vibrating transportation fixed frame.
Fig. 9 is the exploded view of vibrating transportation fixed frame.
Figure 10 is the assembling figure of vibrating transportation fixed frame, elastic device, vibration conveying mechanism and vibrating device.
Figure 11 is the exploded view of vibrating transportation fixed frame, elastic device, vibration conveying mechanism and vibrating device.
Figure 12 is the schematic diagram of vibration conveying mechanism and vibrating device.
Figure 13 is the schematic diagram of vibration conveying mechanism and another visual angle of vibrating device.
Figure 14 is the exploded view of vibration conveying mechanism and vibrating device.
Figure 15 is the schematic diagram of magazine attachment.
Figure 16 is the schematic diagram at the second visual angle of magazine attachment.
Figure 17 is the schematic diagram at magazine attachment third visual angle.
Figure 18 is the exploded view of magazine attachment.
Figure 19 is the stereogram of feeding-distribution device.
Figure 20 is the stereogram at another visual angle of feeding-distribution device.
Figure 21 is the sectional view of feeding-distribution device.
Figure 22 is the stereogram of grinding device.
Figure 23 is the exploded view of grinding device.
Figure 24 is loading device stereogram.
Figure 25 is the stereogram at another visual angle of loading device.
Figure 26 is the stereogram at loading device third visual angle.
Figure 27 is the stereogram of drive shaft.
Figure 28 is the schematic diagram of disintegrating mechanism internal structure.
Figure 29 is the stereogram at another visual angle of disintegrating mechanism internal structure.
Figure 30 is the assembling figure for driving fixed frame, driving snubber block and driving motor.
Figure 31 is the stereogram for driving big belt pulley.
Figure 32 is the stereogram of flywheel.
Specific implementation mode
The present invention will be described in further detail with reference to the accompanying drawings and detailed description.
As shown in Figure 1 to Figure 3, powdery paints pulverizer includes rack 1, vibratory feed 2, feeding-distribution device 3 and crushes Device 4.
As shown in Figure 4 and Figure 5, the rack 1 includes the first supporting rack 11, the second supporting rack 12 and link 13.The One supporting rack 11 is located at the left side of the second supporting rack 12, has space between the first supporting rack 11 and the second supporting rack 12;Even Connect the upper end that frame 13 is connected to the first supporting rack 11 and the second supporting rack 12.
As shown in Figure 4 and Figure 5, the first supporting rack 11 includes first crossbeam 111, the first longeron 112, the first column 113, the Longitudinal diagonal brace 117 on one the 114, first lateral diagonal brace 115 of upper longitudinal beam, first time longitudinal diagonal brace 116 and first.
First crossbeam 111 is formed by two, and is mutually parallel.The section of first crossbeam 111 includes lateral under first crossbeam Transverse part and first crossbeam vertical portion in portion, first crossbeam, first crossbeam vertical portion are located at transverse part and first under first crossbeam It is in I-shaped to allow the section of first crossbeam 111 on crossbeam between transverse part, and it is vertical to be located at first crossbeam for transverse part under first crossbeam The lower section in portion, transverse part is located at the top of first crossbeam vertical portion on first crossbeam.The bottom edge at 111 both ends of first crossbeam has Angle 1111;If chamfering 1111 is not arranged, the bottom edge at first crossbeam both ends is substantially rectangular sharp edge, in this way, working as When mobile pulverizer, be easy with human impact and be easy to hurt human body, meanwhile, if pulverizer is hit with harder substance When hitting, it is easy to damage first crossbeam, first crossbeam is caused to deform, is easy to influence the original stress performance of rack;In addition, moving When dynamic pulverizer, if being provided with chamfering 1111, guiding can be played the role of.First crossbeam 111 uses I-steel, by first When longeron 112 is welded between first crossbeam 111, the end of the first longeron 112 can be plugged into the slot of first crossbeam 111, right Positioning action is played in the connection of first longeron 112, and the weld seam area between the first longeron 112 and first crossbeam 111 increases, To improve bonding strength.
The section of first longeron 112 includes transverse part under the first longeron, transverse part and the first longeron are vertical on the first longeron Portion, the first longeron vertical portion, which is located under the first longeron, allows the cutting of the first longeron 112 between transverse part on transverse part and the first longeron Face is in I-shaped, and transverse part is located at the lower section of the first longeron vertical portion under the first longeron, and transverse part is located at first on the first longeron The top of longeron vertical portion.
First longeron 112 is formed by two, and the first longeron 112 is mutually parallel, and is installed respectively at the both ends of the first longeron 112 It is welded with the first crossbeam 111, the first longeron 112, the both ends point of the first longeron 112 are stretched out in the both ends of first crossbeam 111 It does not extend into the slot of first crossbeam 111.
First column 113 is respectively welded at the both ends of first crossbeam 111.First column 113 is I-steel.
The section of first column 113 includes among the left transverse part of the first column, the right transverse part of the first column and the first column Portion, the first column middle part allowed between the left transverse part of the first column and the right transverse part of the first column the first column 113 cut Face is in I-shaped, and the left transverse part of the first column is located at the left side of the first column middle part, and the right transverse part of the first column is located at first The right side of column middle part.
On same longitudinal direction, the is welded between 113 middle part of the first column between different first crossbeams 111 One upper longitudinal beam 114.The both ends of first upper longitudinal beam 114 are located in the slot of the first column 113, and the first upper longitudinal beam 114 is I-steel.
The first lateral diagonal brace 115 is welded between the first crossbeam 111 and the first column 113 of the same side, in the same side The first column 113 and link 13 between be welded with the lateral diagonal brace 115 of described first, in this way, first crossbeam 111, first Column 113 and the first lateral diagonal brace 115 form three-legged structure, and first crossbeam 111, the first column 113 and link 13 form three Corner structure allows the first supporting rack 11 to be less likely to occur to deform, and structural stability is good.
First time longitudinal diagonal brace 116 is welded between first longeron 112 and the first column 113 of the same end, under first Longitudinal diagonal brace 116 is I-steel, is welded on first longitudinal diagonal brace 117 between the first upper longitudinal beam 114 and link 13, first Upper longitudinal direction diagonal brace 117 is angle steel, in this way, the first supporting rack 11 is allowed to be in multiple three-legged structures, the stable structure of the first supporting rack 11 Property it is good, the main reason for design is can the heavier jigging conveyer 2, Er Qiezhen of installation quality in the top of the first supporting rack 11 Dynamic conveyer will produce frequent vibration at work, therefore, require the structural stability of the first supporting rack high.
In the present invention, first time longitudinal diagonal brace 116 uses I-steel, and longitudinal diagonal brace 117 uses angle steel on first, allows the Once the weight of longitudinal diagonal brace 116 is more than the weight of longitudinal diagonal brace 117 on first so that the decentralization of the first supporting rack allows The stability of entire rack 1 is good.
As shown in Figure 4 and Figure 5, the second supporting rack 12 includes second cross beam 121, the second longeron 122,123 and of the second column Second upper longitudinal beam 124.
Second cross beam 121 is formed by two, and is mutually parallel.The section of second cross beam 121 includes lateral under second cross beam Transverse part and second cross beam vertical portion in portion, second cross beam, second cross beam vertical portion are located at transverse part and second under second cross beam It is in I-shaped to allow the section of second cross beam 121 on crossbeam between transverse part, and it is vertical to be located at second cross beam for transverse part under second cross beam The lower section in portion, transverse part is located at the top of second cross beam vertical portion on second cross beam.The bottom edge at 121 both ends of second cross beam has Angle 1211;If chamfering 1211 is not arranged, the bottom edge at second cross beam both ends is substantially rectangular sharp edge, in this way, working as When mobile pulverizer, be easy with human impact and be easy to hurt human body, meanwhile, if pulverizer is hit with harder substance When hitting, it is easy to damage second cross beam, second cross beam is caused to deform, is easy to influence the original stress performance of rack;In addition, moving When dynamic pulverizer, if being provided with chamfering 1211, guiding can be played the role of.Second cross beam 121 uses I-steel, by second When longeron 122 is welded between second cross beam 121, the end of the second longeron 122 can be plugged into the slot of second cross beam 121, right Positioning action is played in the connection of second longeron 122, and the weld seam area between the second longeron 122 and second cross beam 121 increases, To improve bonding strength.
The section of second longeron 122 includes transverse part under the second longeron, transverse part and the second longeron are vertical on the second longeron Portion, the second longeron vertical portion, which is located under the second longeron, allows the cutting of the second longeron 122 between transverse part on transverse part and the second longeron Face is in I-shaped, and transverse part is located at the lower section of the second longeron vertical portion under the second longeron, and transverse part is located at second on the second longeron The top of longeron vertical portion.
Second longeron 122 is formed by two, and the second longeron 122 is mutually parallel, and is installed respectively at the both ends of the second longeron 122 It is welded with the second cross beam 121, the second longeron 122, the both ends point of the second longeron 122 are stretched out in the both ends of second cross beam 121 It does not extend into the slot of second cross beam 121.
Second column 123 is respectively welded at the both ends of second cross beam 121.Second column 123 is I-steel.
The section of second column 123 includes among the left transverse part of the second column, the right transverse part of the second column and the second column Portion, the second column middle part allowed between the left transverse part of the second column and the right transverse part of the second column the second column 123 cut Face is in I-shaped, and the left transverse part of the second column is located at the left side of the second column middle part, and the right transverse part of the second column is located at second The right side of column middle part.
On the longitudinal direction of inside, it is welded between 123 middle part of the second column between different second cross beams 121 Second upper longitudinal beam 124.The both ends of second upper longitudinal beam 124 are located in the slot of the second column 123, and the second upper longitudinal beam 124 is I-steel.
In the present invention, the second supporting rack 12 needs the weight carried small, therefore, is not provided to three-legged structure, can save Material.
As shown in Figure 4 and Figure 5, link 13 includes connecting cross beam 131, longitudinal beam connected 132 and connection diagonal brace 133.
Connecting cross beam 131 is formed by two, and is mutually parallel, and connecting cross beam 131 is I-steel.In two connecting cross beams 131 Between be welded with more longitudinal beam connecteds 132, longitudinal beam connected 132 is I-steel.Between connecting cross beam 131 and longitudinal beam connected 132 Four connection diagonal braces 133 are welded with positioned at the top of the first supporting rack 11, four connection diagonal braces 133 constitute prismatic.Using above-mentioned The link 13 of structure can reliably connect the first supporting rack 11 and the second supporting rack 12, in addition, the first supporting rack needs The weight to be carried is big, and connecting diagonal brace 133 by setting can be improved stability of the link at this.
Due to having space between the first supporting rack 11 and the second supporting rack 12, the convenient sub-material that is arranged at this fills Set 3 and grinding device 4.
As shown in Figure 4 and Figure 5, it is equipped with beam 14 in the upper surface middle part of connecting cross beam 131, is easily installed feeding-distribution device 3。
As shown in Figure 6 and Figure 7, the vibratory feed 2 includes vibrating transportation fixed frame 21, elastic device 22, shakes Dynamic conveying mechanism 23, vibrating device 24 and magazine attachment 25.
As shown in Figure 7 to 9, vibrating transportation fixed frame 21 includes third crossbeam 211, third longeron 212, third upper longitudinal beam 213, third diagonal brace 214, motor fixed beam 215.
Third crossbeam 211 includes two, and the section of third crossbeam 211 includes transverse part under third crossbeam, on third crossbeam Transverse part and third crossbeam vertical portion, third crossbeam vertical portion be located under third crossbeam on transverse part and third crossbeam transverse part it Between allow the section of third crossbeam 211 in I-shaped, transverse part is located at the lower section of third crossbeam vertical portion, third cross under third crossbeam Transverse part is located at the top of third crossbeam vertical portion on beam.In this way, the strength and stiffness of third crossbeam can be improved, while can improve The bending resistance of third crossbeam.
Third mounting hole 2111 is equipped on transverse part under third crossbeam.It is defeated that bolt passes through third mounting hole 2111 that will vibrate Device 2 is sent to be fixed on link 13, and positioned at the top of the first supporting rack 11.
The both ends lower edge of third crossbeam 211 has chamfering 2112.In this way, when mobile pulverizer, it is not easy to human body It hits and is easy to hurt human body, meanwhile, if pulverizer is hit with harder substance, it is not easy to be damaged to third cross Beam causes third beam deformation, it is not easy to influence the original stress performance of vibrating transportation fixed frame;In addition, in mobile pulverizer When, if being provided with chamfering 2112, guiding can be played the role of.Third crossbeam 211 uses I-steel, by third longeron 212 When being welded between third crossbeam 211, the end of third longeron 212 can be plugged into the slot of third crossbeam 211, to third longeron Positioning action is played in 212 connection, and the weld seam area between third longeron 212 and third crossbeam 211 increases, to improve Bonding strength.
As shown in Figure 7 to 9, third longeron 212 includes three, is welded respectively at the both ends of two third crossbeams and middle part It is connected to the third longeron 212.Third longeron 212 is I-steel.The end of third longeron 212 is plugged on third crossbeam 211 Slot in, positioning action, and the weld seam between third longeron 212 and third crossbeam 211 are played to the connection of third longeron 212 Area increases, to improve bonding strength.
As shown in Figure 7 to 9, the top of the third longeron 212 between two third crossbeams 211 positioned at both ends is welded with Third upper longitudinal beam 213, third upper longitudinal beam 213 are I-steel, and third upper longitudinal beam 213 is welded on transverse part on third crossbeam so that The area of welding is big, improves bonding strength.There is gap between third upper longitudinal beam 213 and third longeron 212, in this way, in third Longeron has the space deformed downwards so that longitudinal elastic deformation amount is big in third, elastic when being installed in third upper longitudinal beam Device, when installing vibration conveying mechanism on elastic device, the Oscillation Amplitude bigger of vibration conveying mechanism is more conducive to vibration Conveying mechanism conveys material.
It is being welded with third diagonal brace 214 between the third longeron of left part and the third longeron of middle part, third is oblique Support 214 is angle steel, and third diagonal brace 214 is welded between third crossbeam 211 and third longeron 212, and third diagonal brace is formed by four, Four third diagonal braces are in prismatic, in this way, the structural stability of vibrating transportation fixed frame can be improved.
Between two third crossbeams two-phase is welded between the third longeron and the third longeron of middle part of right part Mutually parallel motor fixed beam 215, motor fixed beam 215 are angle steel, and motor fixed beam 215 is held by transverse part under third crossbeam Support, in this way, bearing value of the motor fixed beam 215 to vibrating motor can be improved;Waist-shaped hole is equipped in motor fixed beam 215 2151, it is easily installed vibrating motor and finely tunes the position of vibrating motor.
As shown in Figure 6 and Figure 7, the elastic device 22 includes left elastic parts 221 and right elastic parts 222.
Left elastic parts 221 is formed by two.Left elastic parts 221 includes lower-left seat 2211, left spring 2212 and upper left Seat 2213.
As shown in fig. 7, lower-left seat 2211 includes lower-left pedestal 22111 and the lower-left being located on lower-left pedestal 22111 positioning Ring 22112 is respectively equipped with lower-left seat mounting hole 22113 on lower-left pedestal 22111 positioned at the both sides of lower-left locating ring 22112. It is formed with chamfering on four angles of lower-left pedestal 22111.Lower-left pedestal 22111 passes through across lower-left seat mounting hole 22113 Screw is mounted in third upper longitudinal beam.Lower-left locating ring 22112 is inserted into the lower end of left spring 2212.
As shown in fig. 7, upper left seat 2213 includes upper left pedestal 22131 and the upper left being located on upper left pedestal 22131 positioning Ring 22132 is respectively equipped with upper left seat mounting hole 22133 on upper left pedestal 22131 positioned at the both sides of upper left locating ring 22132. It is formed with chamfering on four angles of upper left pedestal 22131.Upper left pedestal 22131 passes through across upper left seat mounting hole 22133 Screw is installed on vibration conveying mechanism 23.Upper left locating ring 22132 is inserted into the upper end of left spring 2212.
In this configuration, preferably left spring can be determined using lower-left locating ring 22112 and upper left locating ring 22132 Position.
As shown in Figure 6 and Figure 7, balance plate 223 is welded in the third upper longitudinal beam of left end, two lower-left seats 2211 are sat It falls on balance plate 223, the screw across lower-left seat mounting hole 22113 is connected on balance plate 223.It, can using this structure To balance the elastic force of two left springs 2212, make the vibration force before and after vibrating device of substantially equal, it is not easy to vibrating device be allowed to send out After before death the phenomenon that beat, is conducive to vibrating device and is uniformly fed forward material.Subtract in addition, balance plate 223 can also play The effect of shake reduces the vibration to vibrating transportation fixed frame 21.
Right elastic parts 222 is formed by two.Right elastic parts 222 includes bottom right seat 2221, right spring 2222 and upper right Seat 2223.
As shown in fig. 7, bottom right seat 2221 includes bottom right pedestal 22211 and two bottom rights being located on bottom right pedestal 22211 Locating ring 22212, two 22212 lateral arrangements of bottom right locating ring are located at bottom right locating ring 22212 on bottom right pedestal 22211 Both sides be respectively equipped with bottom right seat mounting hole 22213.It is formed with chamfering on four angles of bottom right pedestal 22211.Bottom right pedestal 22211 across the screw of bottom right seat mounting hole 22213 by being mounted in third upper longitudinal beam.Bottom right locating ring 22212 is inserted into In the lower end of right spring 2222.
Right spring 2222 is formed by two.
As shown in fig. 7, upper right seat 2223 includes upper right pedestal 22231 and two upper rights being located on upper right pedestal 22231 Locating ring 22232, two 22232 lateral arrangements of upper right locating ring are located at upper right locating ring 22232 on upper right pedestal 22231 Both sides be respectively equipped with upper right seat mounting hole 22233.It is formed with chamfering on four angles of upper right pedestal 22231.Upper right pedestal 22231 across the screw of upper right seat mounting hole 22233 by being installed on vibration conveying mechanism 23.Upper right locating ring 22232 is inserted Enter into the upper end of right spring 2222.
In this configuration, preferably right spring can be positioned using bottom right locating ring and upper right locating ring.
It is fixed with the force bearing plate 224 being laterally extended in the third upper longitudinal beam of right end, force bearing plate is equipped on force bearing plate 224 Mounting hole 2241 passes through the screw of bottom right seat mounting hole 22213 to be connect with force bearing plate 224, under the action of force bearing plate, in right bullet Under the frequent flexible deformation of spring, bottom right seat is less likely to occur to be plastically deformed.
For elastic device 22, left elastic parts 221 includes a left spring 2212, and right elastic parts 222 includes Two right springs 2222, in this way, when vibrating device 24 works, the Oscillation Amplitude of 23 left end of vibration conveying mechanism is more than right end Material on vibration conveying mechanism 23 continuously can be transported to right end from left end, prevent material in vibrating transportation by Oscillation Amplitude It is detained in mechanism 23.Two right spring lateral arrangements in same right elastic parts, can realize vibration conveying mechanism 23 equal power branch It holds, two right springs is supported using same bottom right seat and upper right seat simultaneously, can allow entire right elastic parts homogeneous deformation.
As shown in Fig. 7, Figure 10 to Figure 14, the vibration conveying mechanism 23 includes vibrating transportation frame 231, vibrating transportation Bottom plate 232, vibrating transportation top plate 233, muscle beam 234 and sieve material device 235.
Vibrating transportation frame 231 includes the 4th crossbeam 2311 and the 4th longeron 2312.4th crossbeam 2311 include from down toward Transverse part, the 4th crossbeam vertical portion on transverse part, the 4th crossbeam vertical portion and the 4th crossbeam under upper sequentially connected 4th crossbeam It is connected under the 4th crossbeam on transverse part and the 4th crossbeam on the inside of transverse part.4th crossbeam 2311 includes two, and is mutually parallel.
It is welded with the 4th longeron 2312 in the left part of two the 4th crossbeams.4th longeron 2312 includes connecting successively from bottom to up Transverse part on transverse part, the 4th longeron vertical portion and the 4th longeron under the 4th longeron connect, the 4th longeron vertical portion are connected to Under four longerons on transverse part and the 4th longeron on the inside of transverse part.
Lug 23111 is outward extended on the outside of the 4th crossbeam, lug 23111 is located on upper right seat, allows upper right seat It is big with the contact area of vibration conveying mechanism, improve supporting stabilizer.
There is cavity in vibrating transportation frame 231.The right end of vibrating transportation frame 231 has opening.
The vibrating transportation bottom plate 232,232 self-excited oscillation of vibrating transportation bottom plate are welded in vibrating transportation frame 231 The left end of transportation frame extends right up to middle part.It is welded positioned at the top of vibrating transportation bottom plate 232 in vibrating transportation frame 231 There are the vibrating transportation top plate 233, the left end of 233 self-excited oscillation transportation frame of vibrating transportation top plate to extend right up to middle part; The top of vibrating transportation top plate 233 is formed with material cavity, is used for loaded material, material can be prevented using vibrating transportation frame 231 It slips away from the front and back side of vibration conveying mechanism and left side.It is welded between vibrating transportation bottom plate 232 and vibrating transportation top plate 233 The section of more longitudinally arranged muscle beams 234, muscle beam 234 is U-shaped, in this way, the intensity of muscle beam 234 is not interfered with not only, and energy Mitigate the weight of vibration conveying mechanism 23.There is gap between adjacent muscle beam 234.Above structure, allows the vibration conveying mechanism to be in Box-structure, compares entity structure, and the vibration meeting bigger of vibration conveying mechanism 23 is more conducive to the continuous conveying of material.
The sieve material device 235 includes fixed beam 2351, connecting plate 2352 and cantilever beam 2353.Fixed beam 2351 is fixed Right side in vibrating transportation frame 231 and positioned at vibrating transportation bottom plate;The section of fixed beam 2351 is U-shaped, can mitigate vibration The weight of conveying mechanism.Connecting plate 2352 is fixed on the right side of fixed beam 2351, and in vibrating transportation frame 231.Even The right side of fishplate bar 2352 is welded with the multiple cantilever beams 2353 for being mutually parallel and being laterally extended, and cantilever beam 2353 is located at vibrating transportation In frame 231, charging conduit 2354 is formed between two adjacent cantilever beams 2353, the section of cantilever beam 2353 is in I-shaped, can be carried High bearing strength.It is fixed with sieve on cantilever beam 2353(It is not shown), the upper surface of sieve is upper with vibrating transportation top plate 233 The material on vibrating transportation top plate 233 can be smoothly entered on sieve for flush, sieve have sieve pore, sieve pore it is straight Diameter is arranged according to the particle size of powdery paints, in this way, the powder for being less than sieve diameter by sieve and grain size is fallen, to meeting The particle of powdery paints carries out first time screening, and incongruent material is transported in grinding device.
As shown in FIG. 10 to 14, the vibrating device 24 includes vibrating motor 241, driving pulley 242, driven pulley 243, belt 244, vibration support plate 245, vibrating shaft 246, eccentric block and outer cover 247.
Vibrating motor 241 is fixed in motor fixed beam 215, due to being equipped with waist-shaped hole 2151 in motor fixed beam 215, It is easily installed vibrating motor and finely tunes the position of vibrating motor.
Driving pulley 242 is mounted on the output shaft of vibrating motor 241, and driven pulley 243 is mounted on vibrating shaft 246, Belt 244 is sleeved on driving pulley 242 and driven pulley 243.
Vibration support plate 245 is constituted by two pieces, and is mutually parallel.The upper end of vibration support plate 245 extend into the 4th crossbeam Between vibrating transportation bottom plate 232, the 4th crossbeam and vibration support plate 245 is passed through to fix vibration support plate by multiple screws 245, in this way, it is more secured to the fixation for vibrating support plate 245, service life can be improved in frequent vibration environment.
Vibrating shaft 246 is mounted on by bearing between vibration support plate 245.Eccentric block is fixed on vibrating shaft 246.Outer cover 247 cover on the outside of vibration support plate 245, play the role of protection.
When vibrating motor 241 works, the output shaft of vibrating motor 241 drives driving pulley 242 to rotate, driving pulley 242 drive driven pulley 243 to rotate by belt 244, and driven pulley 243 drives eccentric block to rotate by vibrating shaft 246, to Vibration force is generated, vibration conveying mechanism is allowed to vibrate, convenient for conveying material.Since the upper end of vibration support plate 245 extend into the 4th Between crossbeam and vibrating transportation bottom plate 232, the vibration frequency of vibration conveying mechanism 23 and the frequency one of vibrating device can be allowed in this way It causes, the rotating speed for requiring to be easier to control vibrating motor 241 according to the conveying of material.
The operation principle of vibration conveying mechanism 23 is:After material drops into material cavity, if vibrating motor 241 opens Dynamic, under the action of eccentric block and elastic device 22, vibration conveying mechanism vibration conveys material from left end to right end.
As shown in Fig. 6,7, Figure 15 to Figure 18, magazine attachment 25 includes support column 251 and hopper 252.
The section of support column 251 is in I-shaped, and there is support plate 2511, support plate 2511 to fix for the lower end of support column 251 In third upper longitudinal beam, due to being provided with support plate 2511, not only facilitate fixed bearing column 251, but also support column 251 and third The connection area of longeron is big, improves the reliability of connection.As shown in figure 18, the both sides of the upper end of support column 251 have first Inclined-plane 2512 and the second inclined-plane 2513, the first inclined-plane 2512 are located inside, and the second inclined-plane 2513 is located at outside, the first inclined-plane and Two inclined-planes upper end cross to form wedge angle, and relative to vertical plane, the oblique angle on the first inclined-plane is less than the oblique angle on the second inclined-plane.
As shown in FIG. 15 to 18, the hopper 252 includes hopper front side board 2521, hopper back side panel 2522, hopper Left plate 2523, hopper right plate 2524 and hopper bottom plate 2525.
The bottom of hopper front side board 2521 is connected on hopper bottom plate 2525, and hopper front side board 2521 is from lower end to upper end court Outside tilts, and inclined angle is 20-30 °.
The bottom of hopper back side panel 2522 is connected on hopper bottom plate 2525, and hopper back side panel 2522 is from lower end to upper end court Outside tilts, and inclined angle is 20-30 °.
The bottom of hopper left plate 2523 is connected on hopper bottom plate 2525, and hopper left plate 2523 is from lower end to upper end court Outside tilts, and inclined angle is 20-30 °.
The bottom of hopper right plate 2524 is connected on hopper bottom plate 2525, and hopper right plate 2524 extends vertically upwards. Open slot 25241 up and down is provided on hopper right plate 2524, convenient for big material thence through.
The bottom of hopper bottom plate 2525 is provided with blanking groove 25251.It is provided on the inner wall of hopper bottom plate 2525 down big up small Step 25252, the structure, when vibration conveying mechanism vibrates, the upper end of vibrating transportation frame 231 can enter in step, The amplitude that vibration conveying mechanism moves upwards can be limited using step.
Above structure, after material drops into hopper 252, in hopper front side board 2521, hopper back side panel 2522, hopper Under the guiding role of left plate 2523, material drops into vibration conveying mechanism 23, by vibration conveying mechanism by material to the right Conveying.As a result of 20-30 ° of inclination angle, in this way, material can be dropped into more smoothly on vibration conveying mechanism, due to Hopper right plate is vertically arranged, and can play the role of stopping material.
It is welded with two pieces or more of the hopper being laterally extended in the outside of hopper front side board 2521 and hopper back side panel 2522 Support plate 253, hopper support plate 253 are downwardly inclined from inside to outside, have gap between adjacent skips support plate 253.Positioned at front and back Keep out the lateral surface in corresponding hopper front side board 2521 and hopper back side panel 2522 in first inclined-plane of the support column upper end of both sides On, the second inclined-plane is kept out on uppermost hopper support plate 253, in this way, hopper 252 will not be relative to moving before and after support column Dynamic, support column 251 is good to the supporting stabilizer of hopper 252.
It is equipped with the first card slot in the inside of support column 251, snaps onto in the first card slot, carries positioned at intermediate hopper support plate Reliability and stability of the height to the bearing of hopper 252.
The rest pad 254 being welded on support column 251 is equipped between support column 251 and hopper 252.Rest pad 254 wraps Bearing plate 2541 and bearing riser 2542 are included, bearing riser 2542 is welded on bearing plate 2541, and bearing plate is welded on On support column 251, there is third inclined-plane, third inclined-plane to be supported on corresponding hopper front side board 2521 and material for the inside for supporting riser It struggles against on the lateral surface of back side panel 2522, is provided with the second card slot on bearing riser 2542, nethermost hopper support plate snaps onto In second card slot, the reliability and stability of bearing are improved.
As shown in Figures 1 to 3, the feeding-distribution device 3 is fixed in rack 1, and positioned at the charging conduit of vibration conveying mechanism Lower section.
As shown in Figure 19 to Figure 21, the feeding-distribution device 3 includes that sub-material shell 31, separatory funnel 32 and sub-material fix dress Set 33.
Sub-material shell 31 includes sub-material front side board 311, sub-material back side panel 312, sub-material left plate 313 and sub-material right plate 314。
Sub-material front side board 311 and sub-material back side panel 312 are arranged in parallel.Sub-material left plate 313 prolongs towards tilted from up to down It stretches, sub-material right plate 314 is from up to down towards tilted extension, and relative to vertical plane, the angle of inclination of sub-material left plate 313 is more than The angle of inclination of sub-material right plate 314.Sub-material front side board 311, sub-material back side panel 312, sub-material left plate 313 and sub-material right plate 314 surround sub-material chamber.
It is respectively equipped with separatory funnel 32 in the both sides of sub-material shell 31.Relative to vertical plane, it is located at the separatory funnel in left side Inclination angle be more than positioned at right side separatory funnel inclination angle.Separatory funnel 32 includes sub-material bottom plate 321 and sub-material side plate 322.The sub-material bottom plate of both sides is upwards and relative tilt extends in top and crosses to form sub-material side, and the right side of sub-material chamber is leaned on sub-material side Side;Be respectively welded sub-material side plate 322 in the front and rear sides of sub-material bottom plate, the both sides sub-material side plate of same separatory funnel on to Under extend internally, upper end between two sub-material side plates distance is more than lower end distance, is concentrated to the material fallen.In sub-material side The lower end connection sub-material side shield 3221 of plate, plays the role of backgauge.
It is respectively fixed with sub-material fixing device 33 on sub-material front side board and sub-material back side panel, makes sub-material fixing device symmetrical Be arranged in front and rear sides, in this way, the bearing that can be balanced to feeding-distribution device.The sub-material fixing device 33 includes sub-material Fixed plate 331 and the sub-material being located in sub-material fixed plate 331 fix gusset 332, and sub-material fixed plate 331 is located at beam 14 On, damping can be played the role of to feeding-distribution device by beam 14.
Be connected with sub-material guide plate 34 in the upper end of sub-material left plate 313, sub-material guide plate 34 is inclined outwardly, when material from When charging conduit is fallen, sub-material guide plate 34 can play the role of guide, and material is allowed to drop into sub-material intracavitary.
The sub-material baffle 35 upwardly extended is connected on sub-material right plate 314, when material is fallen from charging conduit, sub-material Baffle 35 plays the role of backgauge, and material is allowed to drop into sub-material intracavitary, while the material that can also prevent elsewhere enters point Expect intracavitary.
It is connected separately with grip block 36, the grip block 36 in the upper end of sub-material front side board 311 and sub-material back side panel 312 Plate is kept out including the clamping guide plate 361 for extending outwardly and upwardly extending, the clamping upwardly extended from 361 upper end of clamping guide plate 362 and from clamping keep out the clamping ear 363 that plate 362 is upwardly extended by upper right edge.The clamping guide plate 361 can be to falling Material play the role of guiding.The clamping keeps out plate 362 and plays the role of backgauge.The clamping ear 363 is clamped In the both sides of vibration conveying mechanism, has the function of front and back limit to feeding-distribution device, in addition also play the effect of backgauge.
It is located at left end in sub-material intracavitary and wind turbine is installed.
The operation principle of above-mentioned feeding-distribution device is:Material drops into sub-material intracavitary through charging conduit 2354, in the effect of wind turbine Under, light thin material enters in the separatory funnel on right side, exports material through separatory funnel, and the thick material of weight drops into Discharge, can thus detach material, useful powder materials be separated to be used in the separatory funnel in left side.
As shown in Figure 1 to Figure 3, the grinding device 4 is mounted in rack 1 and is predominantly located at the first supporting rack and second In space between supporting rack.
As shown in Figure 22 and Figure 23, grinding device 4 includes loading device 41, disintegrating mechanism 42 and stop gauge 43.
As shown in Figure 23 to Figure 26, loading device 41 includes bearing material front side board 411, bearing material back side panel 412, bearing material left plate 413 and bearing material bottom plate 414.The lower end of bearing material front side board 411, bearing material back side panel 412 and bearing material left plate 413 is both connected to bearing material On bottom plate 414.The first gusset of bearing material 410 triangular in shape is welded between bearing material front side board 411 and bearing material bottom plate 414, The first gusset of bearing material 410 triangular in shape is welded between bearing material back side panel 412 and bearing material bottom plate 414, to improve bonding strength.
Bearing material front side board 411 and bearing material back side panel 412 are arranged in parallel.The upper surface that bearing material front side board 411 keeps left is certainly It is obliquely extended to form inclined-plane downward under left-hand, upper surface horizontal extension of the bearing material front side board 411 from inclined-plane to the right, bearing material front side board 411 right side is bottom-up to be obliquely extended towards the right side.The upper surface that bearing material back side panel 412 keeps left is obliquely extended downward under left-hand Form inclined-plane, upper surface horizontal extension of the bearing material back side panel 412 from inclined-plane to the right, the right side of bearing material back side panel 412 from it is lower to On be obliquely extended towards the right side.Bearing material is welded on bearing material front side board 411 and 412 horizontal-extending upper surface of bearing material back side panel to connect Plate 415 is equipped with bearing material mounting hole 4151, for loading device to be connected to grinding device on bearing material connecting plate 415.It is holding It is welded with the second gusset of wadding 416 between material front side board 411 and bearing material connecting plate 415, is connect with bearing material in bearing material back side panel 412 The second gusset of wadding 416 is welded between plate 415, to improve bonding strength.
Bearing material left plate 413 is obliquely installed, and can play the role of guide.
There is trough 4141, the material entered in loading device to be entered through trough 4141 on bearing material bottom plate 414 In conveying device.It is respectively fixed with bearing material fixed plate 417 in the front and rear sides of trough 4141, facilitates fixed other components.
The right side of above-mentioned loading device is open ports, in this way, more materials can be allowed to drop into conveying device.
The loading device of the present invention is mounted on the lower section of disintegrating mechanism, outlet input of the coating through crushing through disintegrating mechanism Into the cavity being made of bearing material front side board, bearing material back side panel, bearing material left plate and bearing material bottom plate, concentrate to the raw material of crushing into Row is collected, and is then discharged through trough, and concentration is facilitated to convey, and is flown upward everywhere when being fallen prevented also from the raw material of crushing, is caused wave The phenomenon that taking pulverized raw material.
As shown in Fig. 1 to 3 and Figure 22,23,28 and 29, disintegrating mechanism 42 includes crushing frame 421, crushing frame 422, dynamic powder surely Broken frame, adjusting apparatus 424, resetting apparatus 425, drive system 426 and closing piece device 427.
As shown in Figure 22,23,28 and 29, it includes crushing front side board 4211, crushing back side panel 4212 and crush to crush frame 421 Right plate 4213.It crushes front side board 4211, crushing back side panel 4212 and crushes in right plate 4213 and be formed with accommodating cavity.Before crushing Side plate 4211 is mutually parallel with back side panel 4212 is crushed, and crushes right plate 4213 and is connected to crushing front side board 4211 and crushing rear side The right end of plate 4212.
It is respectively welded outwardly extending crushing connecting plate in the bottom for crushing front side board 4211 and crushing back side panel 4212 4214, it is equipped on crushing connecting plate 4214 and crushes mounting hole 42141.Bolt passes through bearing material mounting hole 4151 and crushes mounting hole 42141 are fixed to loading device on crushing frame 421.It is equipped with and is welded in the both sides of the crushing mounting hole 42141 positioned at left side The crushing reinforcing plate 4215 on connecting plate is crushed, to improve intensity.
It is respectively welded on the lateral wall for crushing front side board 4211 and crushing back side panel 4212 and crushes mounting base 4216, position Crushing mounting base in right side is less than the crushing mounting base positioned at left side, can will crush frame 421 in this way and be mounted obliquely on connection On frame 13.The crushing mounting base 4216 includes crushing mounting body 42161 and being welded on to crush in mounting body 42161 Gusset 42162 is crushed, gusset 42162 is crushed and is also welded simultaneously with corresponding crushing front side board 4211 and crushing back side panel 4212, To improve bonding strength.
As shown in Figure 28 and Figure 29, the crushing frame 422 of determining includes fixed frame 4221 and crushes plate 4222 surely.
Fixed frame 4221 includes fixed left plate 42211, fixed right arc panel 42212, fixed bottom plate 42213, fixed top Plate 42214 and fixed gusset 42215.
The upper end of fixed left plate 42211 is less than fixed left plate to the distance between right 42212 lower end of arc panel is fixed 42211 lower end is the distance between to fixed right 42212 lower end of arc panel.Fixed bottom plate 42213 is connected to fixed left plate 42211 and fixed right arc panel 42212 lower end;Fixed top plate 42214 is connected to fixed left plate 42211 and fixed right arc The upper end of plate 42212.Fixed left plate 42211, fixed right arc panel 42212, fixed bottom plate 42213 and fixed top plate 42214 Between complete have fixed cavity, be located in fixed cavity between fixed left plate 42211 and fixed right arc panel 42212 and weld There is polylith to fix gusset 42215, the central axes of fixed gusset 42215 pass through the center of circle of the right arc panel of fixation 42212, adjacent fixation Fixed cavity 42216 is formed between gusset 42215.
The fixed frame 4221 of above structure, due to foring fixed cavity between fixed gusset, in this way, fixed frame 4221 by When to outside extruding force, relative to entity structure, elastic deformation amount is big, and therefore, fixed frame 4221 is not easy rigidly to be broken It is bad, extend service life.In addition, since the central axes of fixed gusset 42215 are by the center of circle of the right arc panel of fixation 42212, In this way, when fixed frame is squeezed power, the Impact direction of fixed gusset 42215 is concentrated to circle centre position, is allowed and is fixed right arc The stress of plate is more uniform.
It is described to determine that crushing plate 4222 is arc-shaped, and radian is consistent with fixed right arc panel, allow determine crushing plate in this way 4222 are tightly attached on fixed right arc panel 42212, make the fixed load for crushing plate more uniform, in the fixed lower end for crushing plate 4222 There is blocking part 42221, blocking part 42221 to catch on the lower end of fixed right arc panel in portion, in this way, can be right using blocking part 42221 Fixed frame 4221 positions, and is also possible to prevent 4221 slide downward of fixed frame.
It is equipped with the asperities being longitudinally extended on the fixed surface for crushing plate 4222.It is equipped on the fixed surface for crushing plate 4222 Manganese steel layer, to improve wear-resisting property.
As shown in Figure 28 and Figure 29, the dynamic crushing frame includes pivotally connected set 4231, dynamic crushing bearing support 4232, dynamic crushing Plate 4233 and dynamic connecting seat 4234.Pivotally connected set 4231, dynamic bearing support 4232, dynamic crushing plate 4233 and the dynamic connecting seat 4234 of crushing are Strength and stiffness can be improved in integral structure.
The dynamic bearing support 4232 that crushes is connected in pivotally connected set 4231, and it includes the first extension to move and crush bearing support 4232 42321, the second extension 42322, third extension 42323, the 4th extension 42324 and the 5th extension 42325.First prolongs From pivotally connected set 4231, lower section extends extending portion 42321 to the left, and the second extension from the lower end of the first extension, prolong to the right by bending It stretches, from the bending of the lower end of the second extension, lower section extends third extension to the left, and the 4th extension is from the lower end of third extension Bending extends to the right, and from the bending of the lower end of the 4th extension, lower section extends the 5th extension to the left, the 4th extension it is curved Dog-ear degree is more than the bending angle of the second extension, and the bending angle of the 5th extension is more than the bending angle of third extension; The dynamic lower end for crushing bearing support 4232 is connected on dynamic connecting seat 4234.The dynamic plate 4233 that crushes is connected to pivotally connected set 4231 and dynamic company Between joint chair 4234, the dynamic plate 4233 that crushes is arc-shaped, moves and crushes 4233 upper end of plate between 4232 upper end of dynamic crushing bearing support Apart from dynamic 4233 lower end of plate that crushes is less than to the distance between 4232 lower end of crushing bearing support is moved, moves and crush bearing support 4232 and move Dynamic crushing cavity 420a is formed between crushing plate 4233, in this way, when dynamic crushing plate is squeezed power, the dynamic elasticity for crushing frame Deflection is big, it is not easy to crushing frame be allowed the phenomenon that hard breakdown occur.Surely it crushes and is formed with powder between frame 422 and dynamic crushing frame Broken chamber 420, cooperation crush the structure of frame 422 surely, allow the upper end of crushing chamber 420 to be more than lower end, are conducive to material in this way and enter In crushing chamber, at the same it is more abundant to the crushing of material.When crushing, moves and crush power of the power of frame lower end more than upper end, adopt With above-mentioned dynamic crushing branching bolster structure, since the bending angle of the 4th extension and the 5th extension is larger, in this way, allowing crushing The load ability bigger of bearing support lower end, it is not easy to allow and crush frame generation elasticity and plasticity deformation, be more conducive to crushing.
It is equipped with the asperities being longitudinally extended on the surface for moving crushing plate 4233, move the asperities crushed on plate 4233 and determines The asperities crushed on plate shift to install, in this way, to material in addition to having granulitization, the effect for being also bent and shearing crushes Effect it is more preferable.It is equipped with manganese steel layer on the dynamic surface for crushing plate 4233, to improve wear-resisting property.
The adjusting apparatus 424 includes adjusting fixed seat 4241 and being hinged on to adjust fixed seat 4241 and dynamic connecting seat Toggle link 4242 between 4234.
As shown in Figure 28 and Figure 29, resetting apparatus 425 is located at the lower section of adjusting apparatus 424.The resetting apparatus 425 wraps Include replacement and fixation seat 4251, restoring link 4252, resetting spring 4253 and reduction nut 4254.
Replacement and fixation seat 4251, which is fixed on, to be crushed between front side board and crushing back side panel.Adjustment fixed seat 4241 is fixed on multiple In the fixed seat 4251 of position.Restoring link 4252 is hinged on across replacement and fixation seat 4251 on dynamic connecting seat 4234, on the right side of crushing Plate is equipped with perforation, and the diameter of perforation is more than the diameter of restoring link 4252, and the outer end perforated of restoring link 4252 stretches out powder Broken right plate.It is connected with reduction nut 4254 in the external part of restoring link 4252.It is located on restoring link 4252 and resets admittedly Resetting spring 4253 is cased between reservation 4251 and reduction nut 4254.By adjusting reduction nut 4254, then it is adjusted and resets Stroke, with the crushing suitable for different material.
As shown in Figure 22,23,28 and 29, the drive system 426 includes driving fixed frame 4261, driving snubber block 4262, driving motor 4263, driving small pulley 4264, driving big belt wheel 4265, drive belt 4266, drive shaft 4267, bias Set and flywheel 4268.
As shown in figure 30, the U-shaped frame 42611 that driving fixed frame 4261 is mutually parallel by two forms.In two U-shaped framves Across driving snubber block 4262 has been located on 42611, has the function of damping to driving motor.Driving motor 4263 is fixed on drive On dynamic snubber block 4262.Small pulley 4264 is driven to be mounted on the output shaft of driving motor.Drive the installation driving of big belt wheel 4265 One end of axis.Belt 4266 is sleeved on driving small pulley 4264 and driving big belt wheel 4265.
As shown in figure 27, the drive shaft 4267 includes jackshaft 42671 and the connecting shaft for being located at jackshaft both ends 42672, the diameter of jackshaft is more than the diameter of connecting shaft.Connecting shaft is mounted on by bearing and bearing block and is crushed on frame 421.In There is annular groove 426711 on countershaft 42671, bulge loop is formed between two adjacent annular grooves.
The eccentric bushing is cased on annular groove, eccentric bushing protrudes bulge loop.Pivotally connected set 4231 is sleeved on eccentric bushing, this Sample forms oil groove between bulge loop and pivotally connected set 4231, is used for oil storage, plays the role of lubrication.
As shown in figure 31, driving big belt wheel 4265 includes axle sleeve 42651, outer ring 42652, belt wheel gusset 42653 and side muscle Plate 42654.Axle sleeve is equipped with the axis hole passed through for connecting shaft.It is connected with belt wheel gusset in axle sleeve 42651 and outer ring 42652 42653, one can be improved intensity, in addition can mitigate the weight of driving big belt wheel 4265.It is located in the both sides of belt wheel gusset 42653 Side gusset 42654 is welded between axle sleeve 42651 and outer ring 42652, the middle part of side gusset 42654 is recessed groove 426541。
The closing piece device 427 includes two pieces of grip blocks, and two grip blocks are clamped in connecting shaft, and two grip blocks pass through spiral shell It tethers and connects, have gap between two grip blocks, in this way, grip block can be allowed tightly to embrace in connecting shaft, be equipped in the inside of grip block Slot, the side gusset on the inside of groove are inserted in slot, can prevent driving big belt wheel from skidding relative to drive shaft in this way, are driven It is dynamic more reliable.
Flywheel 4268 is installed in another connecting shaft 42672.As shown in figure 32, flywheel 4268 includes flywheel axle sleeve 42681, flywheel outer ring 42682, flywheel gusset 42683 and flywheel side gusset 42684.Flywheel shaft puts on to be equipped with and be passed through for connecting shaft Axis hole.It is connected with flywheel gusset 42683 in flywheel axle sleeve 42681 and flywheel outer ring 42682, intensity can be improved.In flywheel muscle The both sides of plate 42683 are welded with flywheel side gusset 42684, flywheel side between flywheel axle sleeve 42681 and flywheel outer ring 42682 The middle part of gusset 42684 is recessed flywheel groove 426841.In connecting shaft closing piece device is equipped with positioned at the outside of flywheel 427, the flywheel side gusset on the inside of flywheel groove is inserted in slot, can prevent flywheel from skidding relative to drive shaft in this way, Driving is more reliable.
The operation principle of above-mentioned disintegrating mechanism 42 is:Driving motor drives driving small pulley rotation, driving small pulley to pass through Drive belt drives driving big belt wheel rotation, driving big belt wheel to drive drive shaft rotation, and drive shaft drives eccentric bushing rotation, inclined The heart moves under the action of covering crushes frame up and down motion, when dynamic crushing frame moves upwards, toggle link and the dynamic angle change crushed between frame Greatly, toggle link pushes the dynamic frame that crushes close to fixed crushings bridge joint, and at the same time material such as is extruded, rubs with the hands, grinding at multiple be crushed;It is crushed when dynamic When frame moves downward, toggle link and the dynamic angle crushed between frame become smaller, and move and crush frame under the action of reset lever, resetting spring It leaves and determines crushing frame, broken material mouth under crusher chamber is discharged at this time, as drive motor continuous rotation is crushed motor-driven powder Broken frame makees periodically crushing and discharge, realizes batch production.
As shown in figure 22, the left side for disintegrating mechanism 42 being located in loading device 41 is equipped with feeding mouth 40, is leaked through right side sub-material The material of bucket 32 is entered from feeding mouth 40 in loading device, and the material crushed through disintegrating mechanism also enters in loading device, Powder material in loading device drops into conveying device.
As shown in Figure 22 and Figure 23, the stop gauge 43 includes backgauge front side board 431, backgauge back side panel 432 and gear Expect right plate 433.Stop gauge 43 is on frame and corresponding with the feeding mouth position of powder frame mounted on crushing, and plays the work of backgauge With can reliably ensure that the material through vibration conveying mechanism drops into disintegrating mechanism.
The operation principle of powdery paints of the present invention is:Material is put into magazine attachment 25, the material in magazine attachment It dropping into vibration conveying mechanism 23, under the action of vibrating device 24, the material in vibration conveying mechanism 23 conveys to the right, when When material is transported at sieve, the powder material for meeting granular size is dropped into through sieve, charging conduit in powder device, in wind Under the action of machine, separatory funnel of the light powder material through right side enters in loading device, and incongruent powder material is through a left side The separatory funnel of side is discharged, and realizes the separation to powder material.Grinding device is entered for the material that cannot be fallen from sieve It is interior, material is crushed by grinding device, the powder material after crushing drops into loading device, and powder material is from bearing material Device exports.

Claims (8)

1. a kind of powdery paints pulverizer, it is characterised in that:Including rack, vibratory feed, feeding-distribution device and grinding device;
The rack includes the first supporting rack, the second supporting rack and link;First supporting rack is located at a left side for the second supporting rack Side has space between the first supporting rack and the second supporting rack;Link is connected to the first supporting rack and the second supporting rack Upper end;
The vibratory feed includes vibrating transportation fixed frame, elastic device, vibration conveying mechanism, vibrating device and hopper Device;
The elastic device includes left elastic parts and right elastic parts;Left elastic parts is formed by two, right elastic parts It is formed by two;Left elastic parts includes lower-left seat, left spring and upper left seat, and left spring is located between lower-left seat and upper left seat; Right elastic parts includes bottom right seat, right spring and upper right seat, and right spring is located between bottom right seat and upper right seat, each right elastic group Part includes two right springs, and lateral arrangement;
The vibration conveying mechanism includes vibrating transportation frame, vibrating transportation bottom plate, vibrating transportation top plate, muscle beam and sieve material dress It sets;
Vibrating transportation frame includes the 4th crossbeam and the 4th longeron;4th crossbeam includes two, and is mutually parallel;In two the 4th cross The left part of beam is welded with the 4th longeron;There is cavity in vibrating transportation frame;The right end of vibrating transportation frame has opening; The vibrating transportation bottom plate is welded in vibrating transportation frame, the left end of vibrating transportation bottom plate self-excited oscillation transportation frame prolongs to the right Extend to middle part;It is located above vibrating transportation bottom plate in vibrating transportation frame and is welded with the vibrating transportation top plate, vibration The left end of conveying top plate self-excited oscillation transportation frame extends right up to middle part;It is formed with material cavity above vibrating transportation top plate; More longitudinally arranged muscle beams are welded between vibrating transportation bottom plate and vibrating transportation top plate, between having between adjacent muscle beam Gap;
The sieve material device includes fixed beam, connecting plate and cantilever beam;Fixed beam is fixed in vibrating transportation frame and is located at The right side of vibrating transportation bottom plate;Connecting plate is fixed on the right side of fixed beam, and in vibrating transportation frame;On the right side of connecting plate Side is welded with the multiple cantilever beams for being mutually parallel and being laterally extended, and cantilever beam is located in vibrating transportation frame, two adjacent cantilever beams Between be formed with charging conduit;It is fixed with sieve on a cantilever beam, the upper surface of sieve is concordant with the upper surface of vibrating transportation top plate, There is sieve sieve pore, the diameter of sieve pore to be arranged according to the particle size of powdery paints;
Vibrating device is located between vibrating transportation fixed frame and vibration conveying mechanism;
Magazine attachment is fixed on vibrating transportation fixed frame;
The feeding-distribution device is fixed on the rack, and the lower section of the charging conduit positioned at vibration conveying mechanism;The sub-material dress It sets including sub-material shell and separatory funnel;
Sub-material shell includes sub-material front side board, sub-material back side panel, sub-material left plate and sub-material right plate;
Sub-material front side board and sub-material back side panel are arranged in parallel;Sub-material left plate is from up to down towards tilted extension, sub-material right plate From up to down towards tilted extension, relative to vertical plane, the angle of inclination of sub-material left plate is more than the inclination angle of sub-material right plate Degree;Sub-material front side board, sub-material back side panel, sub-material left plate and sub-material right plate surround sub-material chamber;
It is respectively equipped with separatory funnel in the both sides of sub-material shell;Relative to vertical plane, it is located at the inclination angle of the separatory funnel in left side More than the inclination angle of the separatory funnel positioned at right side;Separatory funnel includes sub-material bottom plate and sub-material side plate;The sub-material bottom plate of both sides Upwards and relative tilt extends in top and crosses to form sub-material side, and the right side of sub-material chamber is leaned on sub-material side;Before and after sub-material bottom plate Both sides are respectively welded sub-material side plate, and the both sides sub-material side plate of same separatory funnel extends internally from the top down, two sub-material side plates Between upper end distance be more than lower end distance;Sub-material side shield is connected in the lower end of sub-material side plate;
It is located at left end in sub-material intracavitary and wind turbine is installed;
The grinding device is mounted in rack and in the space being predominantly located between the first supporting rack and the second supporting rack;
Grinding device includes loading device and disintegrating mechanism;Disintegrating mechanism is located at the top of loading device;
Disintegrating mechanism includes crushing frame, crushing frame, dynamic crushing frame, adjusting apparatus, resetting apparatus, drive system and closing piece dress surely It sets;
It includes crushing front side board, crush back side panel and crushing right plate to crush frame;Front side board is crushed, back side panel is crushed and crushes right Accommodating cavity is formed in side plate;It crushes front side board and crushes back side panel and be mutually parallel, crush right plate and be connected to crushing front side board With the right end for crushing back side panel;
It is respectively welded outwardly extending crushing connecting plate in the bottom for crushing front side board and crushing back side panel, connecting plate is crushed and connects It is connected on loading device;
It is respectively welded crushing mounting base on the lateral wall for crushing front side board and crushing back side panel;
The crushing frame of determining includes fixed frame and crushes plate surely;
Fixed frame includes fixed left plate, fixed right arc panel, fixed bottom plate, fixed top plate and fixed gusset;
Fixed bottom plate is connected to the lower end of fixed left plate and fixed right arc panel;Fixation top plate is connected to fixed left plate and consolidates The upper end of fixed right arc panel;It is surrounded by lock chamber between fixed left plate, fixed right arc panel, fixed bottom plate and fixed top plate Body is located between fixed left plate and fixed right arc panel in fixed cavity and is welded with polylith fixation gusset, fixed gusset Central axes are formed with fixed cavity by the center of circle of the right arc panel of fixation between adjacent fixed gusset;
It is described to determine that crushing plate is arc-shaped, and radian is consistent with fixed right arc panel;
It is equipped with the asperities being longitudinally extended on the fixed surface for crushing plate;It is equipped with manganese steel layer on the fixed surface for crushing plate;
The dynamic crushing frame includes pivotally connected set, dynamic crushing bearing support, dynamic crushing plate and dynamic connecting seat;Pivotally connected set, dynamic crushing branch Bolster, dynamic crushing plate and dynamic connecting seat are structure as a whole;
The dynamic bearing support that crushes is connected in pivotally connected set, is moved crushing bearing support and is extended including the first extension, the second extension, third Portion, the 4th extension and the 5th extension;From pivotally connected set, lower section extends first extension to the left, and the second extension extends from first The lower end bending in portion extends to the right, and from the bending of the lower end of the second extension, lower section extends third extension to the left, and the 4th prolongs From the lower end of third extension, bending extends extending portion to the right, and the 5th extension is bent to left down from the lower end of the 4th extension Fang Yanshen, the bending angle of the 4th extension are more than the bending angle of the second extension, and the bending angle of the 5th extension is more than The bending angle of third extension;The dynamic lower end for crushing bearing support is connected on dynamic connecting seat;The dynamic plate that crushes is connected to pivotally connected set Between dynamic connecting seat, the dynamic plate that crushes is arc-shaped, moves and is formed with dynamic crushing cavity between crushing bearing support and dynamic crushing plate, determines powder Crushing chamber is formed between broken frame and dynamic crushing frame, the upper end of crushing chamber is more than lower end;
Be equipped with the asperities being longitudinally extended on the dynamic surface for crushing plate, move crush the asperities on plate with it is recessed on crushing plate surely Burr shifts to install, and manganese steel layer is equipped on the dynamic surface for crushing plate;
The adjusting apparatus is hinged on dynamic crush on frame;The resetting apparatus is located at dynamic crush between frame and crushing frame;Institute The dynamic frame that crushes of drive system driving stated moves up and down;
The left side for being located at disintegrating mechanism in loading device is equipped with feeding mouth, and the material through right side separatory funnel is entered from feeding mouth In loading device, the material crushed through disintegrating mechanism also enters in loading device, and the powder material in loading device drops into In conveying device.
2. powdery paints pulverizer according to claim 1, it is characterised in that:Vibrating transportation fixed frame includes third cross Beam, third longeron, third upper longitudinal beam, third diagonal brace and motor fixed beam;Third crossbeam includes two, and the section of third crossbeam is wrapped Include transverse part under third crossbeam, transverse part and third crossbeam vertical portion on third crossbeam, third crossbeam vertical portion is located at third cross Allow the section of third crossbeam in I-shaped under beam on transverse part and third crossbeam between transverse part, transverse part is located under third crossbeam The lower section of third crossbeam vertical portion, transverse part is located at the top of third crossbeam vertical portion on third crossbeam;It is horizontal under third crossbeam It is equipped with third mounting hole to portion;Bolt passes through third mounting hole that vibratory feed is fixed on link, and positioned at the The top of one supporting rack;The both ends lower edge of third crossbeam has chamfering;Third longeron includes three, the two of two third crossbeams End and middle part are respectively welded the third longeron;Third longeron is I-steel;The end of third longeron is plugged on In the slot of three crossbeams;Between two third crossbeams third upper longitudinal beam, third are welded with above the third longeron at both ends Upper longitudinal beam is I-steel, and third upper longitudinal beam is welded on transverse part on third crossbeam;Positioned at left part third longeron with it is intermediate Third diagonal brace is welded between the third longeron in portion, third diagonal brace is angle steel, and it is vertical with third that third diagonal brace is welded on third crossbeam Between beam, third diagonal brace is formed by four, and four third diagonal braces are in prismatic;It is located at the third of right part between two third crossbeams The two motor fixed beams being mutually parallel are welded between longeron and the third longeron of middle part.
3. powdery paints pulverizer according to claim 2, it is characterised in that:Have between third upper longitudinal beam and third longeron Gap;Motor fixed beam is angle steel, and motor fixed beam is by transverse part support under third crossbeam;Waist type is equipped in motor fixed beam Hole.
4. powdery paints pulverizer according to claim 1, it is characterised in that:Lower-left seat includes lower-left pedestal and is located at a left side Lower-left locating ring on lower base is respectively equipped with lower-left seat mounting hole on the pedestal of lower-left positioned at the both sides of lower-left locating ring;It is left Lower base across the screw of lower-left seat mounting hole by being mounted in third upper longitudinal beam;Lower-left locating ring is inserted under left spring In end;Upper left seat includes upper left pedestal and the upper left locating ring being located on the pedestal of upper left, and upper left is located on the pedestal of upper left and is positioned The both sides of ring are respectively equipped with upper left seat mounting hole;Upper left pedestal across the screw of upper left seat mounting hole by being installed to vibrating transportation In mechanism;Upper left locating ring is inserted into the upper end of left spring;Bottom right seat include bottom right pedestal and be located on the pedestal of bottom right two A bottom right locating ring, two bottom right locating ring lateral arrangements, the both sides positioned at bottom right locating ring on the pedestal of bottom right are respectively equipped with Bottom right seat mounting hole;Bottom right pedestal across the screw of bottom right seat mounting hole by being mounted in third upper longitudinal beam;Bottom right locating ring It is inserted into the lower end of right spring;Upper right seat includes upper right pedestal and two upper right locating rings being located on upper right pedestal, two Upper right locating ring lateral arrangement, the both sides positioned at upper right locating ring on upper right pedestal are respectively equipped with upper right seat mounting hole;Upper right Pedestal across the screw of upper right seat mounting hole by being installed on vibration conveying mechanism;Upper right locating ring is inserted into the upper of right spring In end.
5. powdery paints pulverizer according to claim 4, it is characterised in that:It is welded on vibrating transportation fixed frame flat Weigh plate, and two lower-left seats are located on balance plate, and the screw across lower-left seat mounting hole is connected on balance plate.
6. powdery paints pulverizer according to claim 4, it is characterised in that:It is outward extended on the outside of the 4th crossbeam Lug, lug are located on upper right seat;The section of muscle beam is U-shaped;The section of fixed beam is U-shaped.
7. powdery paints pulverizer according to claim 1, it is characterised in that:The vibrating device includes vibration horse It reaches, driving pulley, driven pulley, belt, vibrate support plate, vibrating shaft and eccentric block;It is solid that vibrating motor is fixed on vibrating transportation Determine on frame;Driving pulley is mounted on the output shaft of vibrating motor, and driven pulley is mounted on vibrating shaft, and belt sleeve is in main belt On wheel and driven pulley;Vibration support plate is constituted by two pieces, and is mutually parallel;Vibration support plate is fixed on vibrating transportation frame On;Vibrating shaft is mounted on by bearing between vibration support plate;Eccentric block is fixed on vibrating shaft.
8. powdery paints pulverizer according to claim 1, it is characterised in that:On sub-material front side board and sub-material back side panel It is respectively fixed with sub-material fixing device, the sub-material fixing device includes sub-material fixed plate and point that is located in sub-material fixed plate The fixed gusset of material, sub-material fixed plate are located on the beam in rack;Sub-material is connected in the upper end of sub-material left plate to be oriented to Plate, sub-material guide plate are inclined outwardly;The sub-material baffle upwardly extended is connected on sub-material right plate;In sub-material front side board and divide The upper end of material back side panel is connected separately with grip block, and the grip block includes the clamping guiding for extending outwardly and upwardly extending Plate, the clamping upwardly extended from clamping guide plate upper end keep out plate and keep out the clamping that plate is upwardly extended by upper right edge from clamping Ear.
CN201510951202.9A 2015-12-19 2015-12-19 A kind of powdery paints pulverizer Active CN105363545B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510951202.9A CN105363545B (en) 2015-12-19 2015-12-19 A kind of powdery paints pulverizer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510951202.9A CN105363545B (en) 2015-12-19 2015-12-19 A kind of powdery paints pulverizer

Publications (2)

Publication Number Publication Date
CN105363545A CN105363545A (en) 2016-03-02
CN105363545B true CN105363545B (en) 2018-09-21

Family

ID=55366458

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510951202.9A Active CN105363545B (en) 2015-12-19 2015-12-19 A kind of powdery paints pulverizer

Country Status (1)

Country Link
CN (1) CN105363545B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110328007A (en) * 2019-07-30 2019-10-15 全凤兰 A kind of engineering stone screening and grinding equipment
CN111408433A (en) * 2020-03-31 2020-07-14 马鞍山元辰网络科技有限公司 Conveying and smashing device used in earthwork project
CN115400837A (en) * 2022-09-19 2022-11-29 金陵科技学院 Construction waste treatment device
CN115957878B (en) * 2023-03-15 2023-05-16 山东渠风食品科技有限公司 Real-time monitoring device and method for wheat gluten production

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1588249A (en) * 1977-07-13 1981-04-23 Kawasaki Heavy Ind Ltd Jaw plate structure for jaw crushers
EP0773065A1 (en) * 1995-11-10 1997-05-14 Nakayama Iron Works, Ltd. Swing type crusher
CN102303379A (en) * 2011-07-07 2012-01-04 常熟市中联光电新材料有限责任公司 Vibration screening mechanism for plastic granulator
CN203209099U (en) * 2013-04-09 2013-09-25 攀枝花市钛联投资有限公司 Schreyerite jaw crusher
CN203281333U (en) * 2013-05-16 2013-11-13 洛阳宇航重工机械有限公司 Environment-friendly and energy-saving jaw crusher
CN104624285A (en) * 2015-02-16 2015-05-20 浙江浙矿重工股份有限公司 Stone jaw crusher
CN204416355U (en) * 2014-12-12 2015-06-24 郑州一帆机械设备有限公司 A kind of vibrating feeder

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1588249A (en) * 1977-07-13 1981-04-23 Kawasaki Heavy Ind Ltd Jaw plate structure for jaw crushers
EP0773065A1 (en) * 1995-11-10 1997-05-14 Nakayama Iron Works, Ltd. Swing type crusher
CN102303379A (en) * 2011-07-07 2012-01-04 常熟市中联光电新材料有限责任公司 Vibration screening mechanism for plastic granulator
CN203209099U (en) * 2013-04-09 2013-09-25 攀枝花市钛联投资有限公司 Schreyerite jaw crusher
CN203281333U (en) * 2013-05-16 2013-11-13 洛阳宇航重工机械有限公司 Environment-friendly and energy-saving jaw crusher
CN204416355U (en) * 2014-12-12 2015-06-24 郑州一帆机械设备有限公司 A kind of vibrating feeder
CN104624285A (en) * 2015-02-16 2015-05-20 浙江浙矿重工股份有限公司 Stone jaw crusher

Also Published As

Publication number Publication date
CN105363545A (en) 2016-03-02

Similar Documents

Publication Publication Date Title
CN105363517B (en) A kind of powdery paints pulverizer
CN105363545B (en) A kind of powdery paints pulverizer
CN105396776B (en) Dynamic separation sieve
CN105903677A (en) Movable double-screen combined grain cleaner
CN210079638U (en) Colliery is breaker for mining site with screening function
CN206315859U (en) In-line arrangement grinds screening machine
CN205199701U (en) Powder coating rubbing crusher jigging conveyer
CN105344454B (en) A kind of powdery paints pulverizer vibratory feed
CN105327731B (en) A kind of powdery paints pulverizer reducing mechanism
CN105363544B (en) Powdery paints pulverizer vibration conveying equipment
CN105381835B (en) A kind of powdery paints pulverizer disintegrating mechanism
CN211217462U (en) Vibrating screening machine
WO2021090725A1 (en) Horizontal type grain hulling device
CN210700346U (en) Waste residue grading and crushing equipment with vibration screening device
CN114345486A (en) Multifunctional straw pulverizer
KR101571956B1 (en) Method for the production of milled grain products and system
CN105583022A (en) Movable grinding frame device of powder coating grinding machine
CN208976042U (en) One kind removing mud feeder
CN205199704U (en) Powder coating rubbing crusher conveying with vibration structure
CN207430436U (en) A kind of circulating materials crusher
CN206121896U (en) Portable combination breaker
CN105344456B (en) A kind of powdery paints pulverizer vibration conveying equipment
CN2391685Y (en) Vertical vibration shocking crusher
CN109663733A (en) A kind of grading plant returning to material for graphite
CN217568902U (en) Crushing and screening machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20180326

Address after: 330114 Jiangxi city of Nanchang province Xinjian County Lehua Zhen Lao Wu Cun Xia Fang Village No. 107

Applicant after: Liu Meixiang

Address before: 1 Guangzhou, Huadu District, Guangdong, No. three East Avenue, building 168, building 510800

Applicant before: Xu Yanling

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20180821

Address after: 314011 Mei Xiu Lu, Wang Dian Town, Xiuzhou District, Jiaxing, Zhejiang, 350

Applicant after: Jiaxing reeyah photoelectric Co Ltd

Address before: 330114 No. 107, Lao Fang village, Lao Hua Village, Xinjian County, Nanchang, Jiangxi

Applicant before: Liu Meixiang

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200707

Address after: 529500 Gaoxin 1st Road, zhangang (Fugang) science and Technology Park, Yangjiang high tech Zone, Yangjiang City, Guangdong Province

Patentee after: Yangjiang Yanghe Coating Industry Co., Ltd

Address before: 314011 Mei Xiu Lu, Wang Dian Town, Xiuzhou District, Jiaxing, Zhejiang, 350

Patentee before: SUNYA OPTOELECTRONIC Co.,Ltd.

TR01 Transfer of patent right