CN105088979A - Demolition blasting method for large bridge - Google Patents
Demolition blasting method for large bridge Download PDFInfo
- Publication number
- CN105088979A CN105088979A CN201510554777.7A CN201510554777A CN105088979A CN 105088979 A CN105088979 A CN 105088979A CN 201510554777 A CN201510554777 A CN 201510554777A CN 105088979 A CN105088979 A CN 105088979A
- Authority
- CN
- China
- Prior art keywords
- bridge
- corridor
- bridge floor
- equipment
- personnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Working Measures On Existing Buildindgs (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention relates to a demolition method for a bridge, in particular to a demolition blasting method for a large bridge, and belongs to the technical field of bridge engineering application. The method comprises the following steps that firstly, an opening is formed in a bridge floor; secondly, a crawling ladder is erected; thirdly, a scaffold is erected; fourthly, a hanging basket is arranged; fifthly, a corridor and rails are erected; sixthly, drilling and powder charging are carried out; seventhly, demolition blasting is carried out; eighthly, detached objects are treated. The method has the advantages of being small in workload, high in efficiency, safe, reliable and the like.
Description
Technical field
The present invention relates to a kind of bridging toughening method, particularly relate to a kind of large bridge blasting demolishing method, belong to bridge engineering applied technical field.
Background technology
As everyone knows, contrary with newly building bridge on the principle of temporal sequence removing bridge, i.e. bridge floor accessory structure → basic unit's concrete and bridge deck pavement → column bridge deck → spandrel column → arch rib → abutment and attached → dismounting thing process.Current bridging toughening usually adopts manually directly to remove or set up support and removes, and no matter adopt which kind of mode above-mentioned to remove, it all exists the shortcomings such as workload is large, efficiency is low, danger is high.Especially large bridge, dismounting need be carried out in the air at height, if adopt artificial directly dismounting, its operation easier is larger, and danger is higher.
Summary of the invention
In order to overcome above technical problem, the object of the present invention is to provide a kind of high efficiency, safe and reliable large bridge blasting demolishing method.
The present invention is achieved through the following technical solutions: a kind of large bridge blasting demolishing method, comprises the following steps:
The first, bridge floor opening: the bridge floor above bridge pier or column breaks bridge floor and form the opening passed through for personnel, equipment;
The second, set up cat ladder: set up cat ladder at bridge floor opening part, facilitate the current of personnel and equipment;
Three, set up scaffold: bridge pier place sets up scaffold by land, for personnel up and down, handling equipment, borehole charge, installation protection, lay corridor;
Four, arrange hanging basket: above bridge floor opening part, arrange hanging basket, hanging basket adopts elevator lifting, convenient from bridge floor opening part shipment personnel, equipment, carries out that brill is quick-fried, construction of prevention work;
Five, set up corridor, railing: set up corridor at the arch rib place of bridge, facilitate the current and equipment carrying of workman, set up railing on both sides, corridor;
Six, boring, powder charge;
Seven, demolition blasting;
Eight, thing process is removed.
Compared with prior art, the invention has the beneficial effects as follows:
The present invention adopts demolition blasting large bridge, and it has, and workload is little, efficiency advantages of higher; And the present invention is that large bridge demolition blasting constructor provides a set of safe construction plateform system, the method easy construction, the simple and reliable property of system architecture is good, available protecting constructor can avoid falling accident, and execution conditions easily can be provided for a series of constructions such as the boring of constructor, powder charge, blockings, extremely meet the actual demand of demolition blasting safety and efficiency aspect; To sum up, specific works amount of the present invention is little, the advantages such as efficiency is high, safe and reliable.
Detailed description of the invention
Below by specific embodiment, the invention will be further described, but claimed scope is not limited to content described in the present embodiment.
A kind of large bridge blasting demolishing method, comprises the following steps:
The first, bridge floor opening: the bridge floor above bridge pier or column adopts quartering hammer construct and break multiple length × wide bridge floor opening for 1.0m × 2.0m;
The second, set up cat ladder: set up cat ladder at bridge floor opening part, facilitate the current of personnel and equipment;
Cat ladder adopts steel-pipe welding to form, upper and lower steel pipe spacing 0.4m, wide is 0.5m, the length of several cat ladder is determined according to the spatial altitude of installed position, it can be 6m, 4m, 2m etc., be placed in bridge floor opening part below each bridge floor opening after cat ladder completes, the upper and lower and equipment carrying for convenience of personnel, it is to have constant slope that the cat ladder at column place is laid;
Three, set up scaffold: bridge pier place sets up scaffold by land, for personnel up and down, handling equipment, borehole charge, installation protection, lay corridor;
The adjacent land bridge pier of scaffold is set up, it adopts fastener type to assemble, following requirement should be followed: 1. extend to both sides from a bight and hand over circle to set up when setting up, first locate and set up vertical rod successively, vertical rod is connected with bar of sweeping the floor in length and breadth, the height of bar of sweeping the floor must not be greater than 300mm, then first step size cross bar is set up, after correcting vertical and level thereupon, the junction button of each bar is tightened, and set up as required, 2. bridging is established at scaffold two ends, bridging and ground angle are 45 °, also increasing by 2 ~ 4 therebetween detains node for the vertical rod of two ends rotary buckle and scaffold or leger fastening, 3. the deviation of vertical rod should not be greater than frame high 1/300, and control its absolute deviation values simultaneously and should not be greater than 75mm, the spreading position of 4. going up sheer pole should be staggeredly arranged in different vertical rod advances, / 3rd of an advance is not more than with close distance, the horizontal departure of same row's leger is not more than 1/250 of this sheet scaffold total length, and be not more than 50mm, the leger of adjacent step frame should be staggeredly arranged in the inboard of vertical rod and outside, to reduce vertical rod eccentric force situation, 5. scaffold set up middle vertical rod, horizon bar, little tringle, an application right angle button fastener that links for wall connecting rod connects, the extended spot of vertical rod will stagger mutually in asynchronous distance, at connecting rod, leger, the connecting end portion of little cross bar should stretch out fastener 20mm ~ 30mm,
Four, arrange hanging basket: above bridge floor opening part, arrange hanging basket, hanging basket adopts elevator lifting, convenient from bridge floor opening part shipment personnel, equipment, carries out that brill is quick-fried, construction of prevention work;
At bridge floor overthe openings wire rope hoist for promoting hanging basket, hanging basket and hoist engine is connected with steel cable, hanging basket can be put down to bridge pier place for construction, personnel equipment can pass in and out hanging basket after promoting hanging basket to bridge floor place with hoist engine, after hanging basket installation, namely available hanging basket carries out holing and charging as mobile work platform, and use hoist engine adjustment construction location, hanging basket can be multiple;
Five, set up corridor, railing: set up corridor at the arch rib place of bridge, facilitate the current and equipment carrying of workman, set up railing on both sides, corridor;
Corridor and railing all adopt steel pipe manufacture, be mainly used in the construction at bridge arch, arch rib place, railing is except the security protection for also can be used for cat ladder except corridor, railing mainly adopts welding, the mode of tying up is fixed on cat ladder, a corridor is all established at every bar bridge arch place, horizontal corridor is also set simultaneously and connects longitudinal corridor formation network type passage, convenient current and fixing.
Six, boring, powder charge;
Position boring suitable below bridge pier, column and bridge floor, and powder charge;
Seven, demolition blasting;
Carry out the protection of surrounding environment safety, explosion is carried out to bridge;
Eight, thing process is removed;
Dismounting thing after explosion is processed.
Claims (1)
1. a large bridge blasting demolishing method, is characterized in that: comprise the following steps:
The first, bridge floor opening: the bridge floor above bridge pier or column breaks bridge floor and form the opening passed through for personnel, equipment;
The second, set up cat ladder: set up cat ladder at bridge floor opening part, facilitate the current of personnel and equipment;
Three, set up scaffold: bridge pier place sets up scaffold by land, for personnel up and down, handling equipment, borehole charge, installation protection, lay corridor;
Four, arrange hanging basket: above bridge floor opening part, arrange hanging basket, hanging basket adopts elevator lifting, convenient from bridge floor opening part shipment personnel, equipment, carries out that brill is quick-fried, construction of prevention work;
Five, set up corridor, railing: set up corridor at the arch rib place of bridge, facilitate the current and equipment carrying of workman, set up railing on both sides, corridor;
Six, boring, powder charge;
Seven, demolition blasting;
Eight, thing process is removed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510554777.7A CN105088979B (en) | 2015-09-04 | 2015-09-04 | Demolition blasting method for large bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510554777.7A CN105088979B (en) | 2015-09-04 | 2015-09-04 | Demolition blasting method for large bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105088979A true CN105088979A (en) | 2015-11-25 |
CN105088979B CN105088979B (en) | 2017-03-22 |
Family
ID=54570239
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510554777.7A Active CN105088979B (en) | 2015-09-04 | 2015-09-04 | Demolition blasting method for large bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105088979B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105648931A (en) * | 2015-12-31 | 2016-06-08 | 中铁二局集团有限公司 | Blasting method of separated type overpass |
CN107328322A (en) * | 2017-06-30 | 2017-11-07 | 中国建筑第七工程局有限公司 | Cable-stayed type truss bridge blasting method is held under one kind |
CN107858941A (en) * | 2017-11-16 | 2018-03-30 | 南京交通工程有限公司 | A kind of hydraulic pressure demolition removes Prestressed Continuous Box Beam bridge construction technique |
CN111648260A (en) * | 2020-04-27 | 2020-09-11 | 北京诺和兴建设工程有限公司 | Construction process for bridge demolition |
CN115058989A (en) * | 2022-07-06 | 2022-09-16 | 中国十七冶集团有限公司 | Construction method for rapidly dismounting single-column-pier single-box-chamber box girder bridge |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005179924A (en) * | 2003-12-16 | 2005-07-07 | Sumitomo Mitsui Construction Co Ltd | Method for blowing up and demolishing reinforced concrete structure |
JP4201633B2 (en) * | 2003-03-28 | 2008-12-24 | 三井住友建設株式会社 | Blasting and dismantling method of reinforced concrete structure |
CN102839610A (en) * | 2012-09-17 | 2012-12-26 | 贵州新联***工程有限公司 | Demolition blasting method for prestress concrete cantilever trussed arch bridge |
CN203593968U (en) * | 2013-11-30 | 2014-05-14 | 中铁二十局集团有限公司 | Steel tube bamboo row frame for shallow hole blasting excavation bridge foundation bit construction |
CN104775367A (en) * | 2015-02-07 | 2015-07-15 | 河南理工大学 | Method for blasting demolition of bridge in urban area by controlling stepping-type sequential collapse |
-
2015
- 2015-09-04 CN CN201510554777.7A patent/CN105088979B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4201633B2 (en) * | 2003-03-28 | 2008-12-24 | 三井住友建設株式会社 | Blasting and dismantling method of reinforced concrete structure |
JP2005179924A (en) * | 2003-12-16 | 2005-07-07 | Sumitomo Mitsui Construction Co Ltd | Method for blowing up and demolishing reinforced concrete structure |
CN102839610A (en) * | 2012-09-17 | 2012-12-26 | 贵州新联***工程有限公司 | Demolition blasting method for prestress concrete cantilever trussed arch bridge |
CN203593968U (en) * | 2013-11-30 | 2014-05-14 | 中铁二十局集团有限公司 | Steel tube bamboo row frame for shallow hole blasting excavation bridge foundation bit construction |
CN104775367A (en) * | 2015-02-07 | 2015-07-15 | 河南理工大学 | Method for blasting demolition of bridge in urban area by controlling stepping-type sequential collapse |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105648931A (en) * | 2015-12-31 | 2016-06-08 | 中铁二局集团有限公司 | Blasting method of separated type overpass |
CN107328322A (en) * | 2017-06-30 | 2017-11-07 | 中国建筑第七工程局有限公司 | Cable-stayed type truss bridge blasting method is held under one kind |
CN107328322B (en) * | 2017-06-30 | 2018-09-21 | 中国建筑第七工程局有限公司 | Cable-stayed type truss bridge blasting method is held under one kind |
CN107858941A (en) * | 2017-11-16 | 2018-03-30 | 南京交通工程有限公司 | A kind of hydraulic pressure demolition removes Prestressed Continuous Box Beam bridge construction technique |
CN111648260A (en) * | 2020-04-27 | 2020-09-11 | 北京诺和兴建设工程有限公司 | Construction process for bridge demolition |
CN115058989A (en) * | 2022-07-06 | 2022-09-16 | 中国十七冶集团有限公司 | Construction method for rapidly dismounting single-column-pier single-box-chamber box girder bridge |
Also Published As
Publication number | Publication date |
---|---|
CN105088979B (en) | 2017-03-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105088979A (en) | Demolition blasting method for large bridge | |
CN202324571U (en) | Overhanging type double-row scaffold | |
CN101775896B (en) | Rigid suspended scaffold for installing pipeline of steel roof equipment | |
CN103993735A (en) | Support system of roof inclined beam and slab cantilever structure and construction method of support system | |
CN105298099A (en) | Modular suspension type steel tube fastener scaffold operating platform and erecting method thereof | |
US9556624B1 (en) | Scaffold system | |
CA2909214C (en) | Truss girder for a weather protection roof as well as weather protection roof with several truss girders | |
CN205654060U (en) | Scalable high altitude construction passageway | |
CN105908960A (en) | Construction rack for construction of high and large space | |
CN104153586B (en) | A kind of suspension cable hangs the construction method of mounting purlines | |
CN103362297B (en) | A kind of attached lift scaffold constructure scheme | |
CN105350760B (en) | A kind of construction method of suspending scaffold | |
CN104278828A (en) | Concrete chimney demolition operating platform | |
CN201635377U (en) | Rigid suspended type scaffold provided with large-span steel roof equipment pipeline | |
CN211623284U (en) | Movable hanging ladder for steel structure building | |
CN109653484B (en) | Roofing superelevation faces external hanging flower basket mounting structure of empty curtain engineering | |
CN115306137A (en) | Operation platform structure for mounting suspended ceiling at bottom of overhead corridor and construction method thereof | |
CN211775606U (en) | Regularization assembled that can have enough to meet need climbs frame and goes up people's passageway | |
CN104818856B (en) | Mounting method of roof thin-wall Z-shaped purline | |
CN111663758A (en) | Suspended scaffold and construction method | |
CN203701567U (en) | Steel pipe scaffold provided with safety facility | |
CN107217912A (en) | It is a kind of to be used for the superelevation physical isolation construction method of neighbouring high ferro Business Line construction | |
CN111764623A (en) | Lower hanging construction platform module of high-altitude large-cantilever steel roof truss and construction method | |
CN106703418A (en) | Mobile safety set hanging method for large-span net shell structure roof installation | |
CN215402670U (en) | Assembled tower crane temporary pedestrian passageway |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 550002, 14 floor, Fu Zhong commercial building, No. 102 Xinhua Road, Nanming District, Guiyang, Guizhou. Patentee after: Poly Xinlian Blasting Engineering Group Co., Ltd. Address before: 550002, 14 floor, Fu Zhong commercial building, No. 102 Xinhua Road, Nanming District, Guiyang, Guizhou. Patentee before: Guizhou Xinlian Blasting Engineering Group Co., Ltd. |