CN105019655A - Pouring construction method of concrete beams - Google Patents

Pouring construction method of concrete beams Download PDF

Info

Publication number
CN105019655A
CN105019655A CN201510462011.6A CN201510462011A CN105019655A CN 105019655 A CN105019655 A CN 105019655A CN 201510462011 A CN201510462011 A CN 201510462011A CN 105019655 A CN105019655 A CN 105019655A
Authority
CN
China
Prior art keywords
steel
steel plate
shaped steel
work template
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510462011.6A
Other languages
Chinese (zh)
Other versions
CN105019655B (en
Inventor
杨龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201510462011.6A priority Critical patent/CN105019655B/en
Publication of CN105019655A publication Critical patent/CN105019655A/en
Application granted granted Critical
Publication of CN105019655B publication Critical patent/CN105019655B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a pouring construction method of concrete beams. Construction is conducted through a U-shaped steel-structure formwork. The method includes the following steps of S1, manufacturing the U-shaped steel-structure formwork, and hanging the U-shaped steel-structure formwork through steel corbels; S2, anchoring reinforcing steel bars of the concrete beams at a support in the U-shaped steel-structure formwork; S3, pouring concrete on a bottom steel plate of the U-shaped steel-structure formwork to complete pouring of the concrete bottom plate; S4, pouring concrete on two side steel plates of the U-shaped steel-structure formwork to complete pouring of the concrete beams; S5, pouring concrete on a plurality of upper H-shaped steel beams of the U-shaped steel-structure formwork to complete pouring of a concrete top plate. A reinforcement cage can be rolled on the ground in advance, the concrete beams can be directly formed in the formwork through pouring after the steel-structure formwork is hung, and therefore the construction quality can be effectively ensured, no scaffold needs to be erected any more, the construction period can be shortened, and good economic benefits are achieved.

Description

A kind of construction method of concreting beam
Technical field
The present invention relates to technical field of civil engineering, be specifically related to a kind of construction method adopting U-shaped steel work template concreting beam.
Background technology
Building of current concrete beam generally all needs erecting scaffold, and when especially building high-altitude long-span concrete beam, setting up of scaffold needs the at substantial time.
Summary of the invention
The object of the present invention is to provide a kind of construction method of concreting beam, the rolling of reinforcing cage can be completed in advance on the ground, after steel work template completes lifting, can directly at the inner directly concreting beam of template, effectively can not only ensure construction quality, nor need erecting scaffold again, can the construction period be shortened, there is good economic benefit.
In order to achieve the above object, the present invention is achieved through the following technical solutions: a kind of construction method of concreting beam, and adopt U-shaped steel work template to construct, this U-shaped steel work template comprises, end steel plate and two blocks of side steel plates, steel plate of the described end and two blocks of side steel plates are spliced into U-shaped mutually; Some lower H profile steel beams, the length direction along steel plate of the described end is disposed on the top of steel plate of the described end, and the web of described lower H profile steel beam is mutually vertical with steel plate of the described end; Some upper H profile steel beams, correspondence is arranged on the top of described lower H profile steel beam, and the upper flange of described upper H profile steel beam is connected with two blocks of side steel plates respectively by two blocks of top steel plates, and the web of described upper H profile steel beam is mutually vertical with steel plate of the described end; Steel corbel, is connected with steel plate of the described end, it is characterized in that, this construction method comprises following steps:
S1, complete described U-shaped steel work template, and completed the lifting of U-shaped steel work template by steel corbel;
S2, in U-shaped steel work template, to complete in concrete beam reinforcing bar in the anchoring at bearing place;
S3, on the end steel plate of U-shaped steel work template concreting, complete building of concrete floor;
S4, on two blocks of side steel plates of U-shaped steel work template concreting, complete building of concrete beam;
S5, on some of U-shaped steel work template concreting on H profile steel beam, complete building of concrete roof.
Two side steel plates in described U-shaped steel work template are respectively arranged with several transverse stiffeners, several described transverse stiffeners along described side steel plate length direction interval arrange, and described transverse stiffener two ends are connected with end steel plate with described top steel plate respectively.
Also comprise several bearing diagonals in described U-shaped steel work template, between the transverse stiffener being arranged on both sides, described bearing diagonal and described transverse stiffener removably connect.
In described U-shaped steel work template, bearing diagonal is X-shaped.
Transverse stiffener in described U-shaped steel work template is provided with several waist muscle holes, the end that described transverse stiffener is connected with steel plate of the described end is provided with muscle hole at the bottom of beam, and the end that described transverse stiffener is connected with described top steel plate is provided with back muscle hole.
The web of described lower H profile steel beam is provided with several slab muscle holes.
Several pegs are also comprised in described U-shaped steel work template, be separately positioned on steel plate of the described end, on the upper flange of upper H profile steel beam and on two side steel plates, wherein, on steel plate of the described end, peg one end is connected with steel plate of the described end, the other end points to described upper H profile steel beam, peg on the upper flange of described upper H profile steel beam is connected with the upper flange of described upper H profile steel beam, the other end deviates from steel plate of the described end, peg on the steel plate of described side, one end is connected with described side steel plate, and the other end points to the side steel plate of offside.
In described step S1, the step making U-shaped steel work template comprises:
According to size and the reinforcing bar configuration of the stressing conditions determination concrete beam of concrete beam;
According to the size of the size of concrete beam and deadweight, working load determination U-shaped steel work template;
According to position and the size at muscle hole and back muscle hole at the bottom of waist muscle hole, beam on the arrangement of reinforcement determination transverse stiffener of concrete beam, and the position at lower H profile steel beam upper plate reinforcing bar hole and size.
Comprise in described step S2:
At waist muscle hole, waist muscle is installed;
Muscle at the bottom of the mounting rail of muscle hole at the bottom of beam;
At back muscle hole, back muscle is installed;
At slab muscle hole installing plate reinforcing bar.
Reinforcing bar is completed in concrete beam in the anchoring at bearing place by the mode of reinforcing bar connector or bar planting in described step S2.
The construction method of a kind of concreting beam of the present invention compared with prior art has the following advantages: adopt U-shaped steel work template, because U-shaped steel work template is provided with bearing diagonal and transverse stiffener, ensure the stability requirement of U-shaped steel work template in whole work progress; Because U-shaped steel work template is provided with muscle hole at the bottom of waist muscle hole, beam and back muscle hole, facilitate anchor bar; Because U-shaped steel work template is provided with peg, as shear key, make concrete be easy to U-shaped steel work template and combine; Owing to being provided with steel corbel, be convenient to lifting U-shaped steel work template.
Accompanying drawing explanation
Fig. 1 is a kind of sectional view of U-shaped steel work template;
Fig. 2 is the construction method of a kind of concreting beam of the present invention, the schematic diagram of concreting base plate;
Fig. 3 is the schematic diagram of concreting crossbeam;
Fig. 4 is the schematic diagram of concreting top board.
Detailed description of the invention
Below in conjunction with accompanying drawing, by describing a preferably specific embodiment in detail, the present invention is further elaborated.
As shown in Figure 1, a kind of U-shaped steel work template, for concreting beam, is particularly useful for the construction of large span, work high above the ground concrete hollow case beam, this U-shaped steel work template comprises: end steel plate 10 and two blocks of side steel plates 20, and steel plate of the described end 10 and two blocks of side steel plates 20 are spliced into U-shaped mutually; Some lower H profile steel beams 30, the length direction along steel plate of the described end 10 is disposed on the top of steel plate of the described end 10, and the web 31 of described lower H profile steel beam 30 is mutually vertical with steel plate of the described end 10; Some upper H profile steel beams 40, correspondence is arranged on the top of described lower H profile steel beam 30, the upper flange 41 of described upper H profile steel beam 40 is connected with two blocks of side steel plates 20 respectively by two blocks of top steel plates 50, and the web 42 of described upper H profile steel beam 40 is mutually vertical with steel plate of the described end 10.
In the present embodiment, preferably, U-shaped steel work template also comprises steel corbel 60, is connected with steel plate of the described end 10, for lifting described U-shaped steel work template.
In the present embodiment, preferably, two described side steel plates 20 are respectively arranged with several transverse stiffeners 70, transverse stiffener 70 must be arranged according to span and stressing conditions, several described transverse stiffeners 70 along described side steel plate 20 length direction interval arrange, and described transverse stiffener 70 two ends are connected with end steel plate 10 with described top steel plate 50 respectively.
In other embodiment, U-shaped steel work template also comprises several bearing diagonals 80, bearing diagonal 80 must be arranged according to span and stressing conditions, for ensureing the stability requirement of U-shaped steel work template in whole work progress, between the transverse stiffener 70 being arranged on both sides, preferably, described bearing diagonal 80 removably connects with described transverse stiffener 70, so that bearing diagonal 80 is disassembled after construction, preferably, described bearing diagonal 80 is in X-shaped, and other forms of bearing diagonal 80 can meet stability requirement and also can.
In the present embodiment, preferably, described transverse stiffener 70 is provided with several waist muscle holes 71, the end that described transverse stiffener 70 is connected with steel plate of the described end 10 is provided with muscle hole 72 at the bottom of beam, and the end that described transverse stiffener 70 is connected with described top steel plate 50 is provided with back muscle hole 73.
In the present embodiment, preferably, the web 31 of described lower H profile steel beam 30 is provided with several slab muscle holes 32.
In other embodiment, U-shaped steel work template also comprises a dry peg, be separately positioned on steel plate of the described end 10, on the upper flange 41 of upper H profile steel beam 40 and on two side steel plates 20, wherein, peg 91 one end on steel plate of the described end 10 is connected with steel plate of the described end 10, the other end points to described upper H profile steel beam 40, peg 92 on the upper flange 41 of described upper H profile steel beam 40 is connected with the upper flange 41 of described upper H profile steel beam 40, the other end deviates from steel plate of the described end 10, peg 93 on described side steel plate 20, one end is connected with described side steel plate 20, the other end points to the side steel plate 20 of offside.
For above-mentioned U-shaped steel work template, also disclose a kind of construction method adopting the concreting beam of above-mentioned U-shaped steel work template in the present embodiment, shown in composition graphs 2 to Fig. 4, comprise following steps:
S1, complete described U-shaped steel work template, and completed the lifting of U-shaped steel work template by steel corbel.
According to size and the reinforcing bar configuration of the stressing conditions determination concrete beam of concrete beam;
According to the size of the size of concrete beam and deadweight, working load determination U-shaped steel work template;
According to position and the size at muscle hole and back muscle hole at the bottom of waist muscle hole, beam on the arrangement of reinforcement determination transverse stiffener of concrete beam, and the position at lower H profile steel beam upper plate reinforcing bar hole and size, the diameter of opening holes should about 5mm larger than the diameter of reinforcing bar to be rolled.
S2, in U-shaped steel work template, to complete in concrete beam reinforcing bar in the anchoring at bearing place.
Complete reinforcing bar in concrete beam by the mode of reinforcing bar connector or bar planting and, in the anchoring at bearing place, namely at waist muscle hole, waist muscle is installed; Muscle at the bottom of the mounting rail of muscle hole at the bottom of beam; At back muscle hole, back muscle is installed; At slab muscle hole installing plate reinforcing bar.
S3, on the end steel plate of U-shaped steel work template concreting, complete building of concrete floor 200, as shown in Figure 2.
S4, on two blocks of side steel plates of U-shaped steel work template concreting, complete building of concrete beam 300, as shown in Figure 3.
S5, on some of U-shaped steel work template concreting on H profile steel beam, complete building of concrete roof 400, as shown in Figure 4.
Although content of the present invention has done detailed introduction by above preferred embodiment, will be appreciated that above-mentioned description should not be considered to limitation of the present invention.After those skilled in the art have read foregoing, for multiple amendment of the present invention and substitute will be all apparent.Therefore, protection scope of the present invention should be limited to the appended claims.

Claims (10)

1. a construction method for concreting beam, adopt U-shaped steel work template to construct, this U-shaped steel work template comprises, end steel plate and two blocks of side steel plates, and steel plate of the described end and two blocks of side steel plates are spliced into U-shaped mutually; Some lower H profile steel beams, the length direction along steel plate of the described end is disposed on the top of steel plate of the described end, and the web of described lower H profile steel beam is mutually vertical with steel plate of the described end; Some upper H profile steel beams, correspondence is arranged on the top of described lower H profile steel beam, and the upper flange of described upper H profile steel beam is connected with two blocks of side steel plates respectively by two blocks of top steel plates, and the web of described upper H profile steel beam is mutually vertical with steel plate of the described end; Steel corbel, is connected with steel plate of the described end, it is characterized in that, this construction method comprises following steps:
S1, complete described U-shaped steel work template, and completed the lifting of U-shaped steel work template by steel corbel;
S2, in U-shaped steel work template, to complete in concrete beam reinforcing bar in the anchoring at bearing place;
S3, on the end steel plate of U-shaped steel work template concreting, complete building of concrete floor;
S4, on two blocks of side steel plates of U-shaped steel work template concreting, complete building of concrete beam;
S5, on some of U-shaped steel work template concreting on H profile steel beam, complete building of concrete roof.
2. construction method as claimed in claim 1, it is characterized in that, two side steel plates in described U-shaped steel work template are respectively arranged with several transverse stiffeners, several described transverse stiffeners along described side steel plate length direction interval arrange, and described transverse stiffener two ends are connected with end steel plate with described top steel plate respectively.
3. construction method as claimed in claim 2, is characterized in that, also comprise several bearing diagonals in described U-shaped steel work template, and between the transverse stiffener being arranged on both sides, described bearing diagonal and described transverse stiffener removably connect.
4. construction method as claimed in claim 3, it is characterized in that, in described U-shaped steel work template, bearing diagonal is X-shaped.
5. construction method as claimed in claim 2, it is characterized in that, transverse stiffener in described U-shaped steel work template is provided with several waist muscle holes, the end that described transverse stiffener is connected with steel plate of the described end is provided with muscle hole at the bottom of beam, and the end that described transverse stiffener is connected with described top steel plate is provided with back muscle hole.
6. construction method as claimed in claim 5, it is characterized in that, the web of described lower H profile steel beam is provided with several slab muscle holes.
7. construction method as claimed in claim 1, it is characterized in that, several pegs are also comprised in described U-shaped steel work template, be separately positioned on steel plate of the described end, on the upper flange of upper H profile steel beam and on two side steel plates, wherein, on steel plate of the described end, peg one end is connected with steel plate of the described end, the other end points to described upper H profile steel beam, peg on the upper flange of described upper H profile steel beam is connected with the upper flange of described upper H profile steel beam, the other end deviates from steel plate of the described end, peg on the steel plate of described side, one end is connected with described side steel plate, the other end points to the side steel plate of offside.
8. construction method as claimed in claim 6, is characterized in that, in described step S1, the step making U-shaped steel work template comprises:
According to size and the reinforcing bar configuration of the stressing conditions determination concrete beam of concrete beam;
According to the size of the size of concrete beam and deadweight, working load determination U-shaped steel work template;
According to position and the size at muscle hole and back muscle hole at the bottom of waist muscle hole, beam on the arrangement of reinforcement determination transverse stiffener of concrete beam, and the position at lower H profile steel beam upper plate reinforcing bar hole and size.
9. construction method as claimed in claim 6, is characterized in that, comprise in described step S2:
At waist muscle hole, waist muscle is installed;
Muscle at the bottom of the mounting rail of muscle hole at the bottom of beam;
At back muscle hole, back muscle is installed;
At slab muscle hole installing plate reinforcing bar.
10. construction method as claimed in claim 6, is characterized in that, to complete in concrete beam reinforcing bar in the anchoring at bearing place in described step S2 by the mode of reinforcing bar connector or bar planting.
CN201510462011.6A 2015-07-31 2015-07-31 A kind of construction method of casting concrete beam Active CN105019655B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510462011.6A CN105019655B (en) 2015-07-31 2015-07-31 A kind of construction method of casting concrete beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510462011.6A CN105019655B (en) 2015-07-31 2015-07-31 A kind of construction method of casting concrete beam

Publications (2)

Publication Number Publication Date
CN105019655A true CN105019655A (en) 2015-11-04
CN105019655B CN105019655B (en) 2017-06-20

Family

ID=54409921

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510462011.6A Active CN105019655B (en) 2015-07-31 2015-07-31 A kind of construction method of casting concrete beam

Country Status (1)

Country Link
CN (1) CN105019655B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106639319A (en) * 2017-01-16 2017-05-10 中冶建工集团有限公司 Rotten root prevention construction method for shear walls, columns and other concrete vertical structures

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06278117A (en) * 1993-03-29 1994-10-04 Nkk Corp Concrete form
KR20090108281A (en) * 2008-04-11 2009-10-15 금호산업 주식회사 Fence structure
KR100946768B1 (en) * 2009-03-24 2010-03-11 우경건설 주식회사 Plane curved steel form for prestressed concrete girder it's possible to adjust and this method of fabrication
CN103206081A (en) * 2013-04-15 2013-07-17 清华大学建筑设计研究院有限公司 Sandwich formwork fixing device and sandwich formwork construction method
CN104153599A (en) * 2014-08-26 2014-11-19 中铁八局集团建筑工程有限公司 System of section steel concrete beam structure without section steel column support and bracket for construction of section steel concrete beam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06278117A (en) * 1993-03-29 1994-10-04 Nkk Corp Concrete form
KR20090108281A (en) * 2008-04-11 2009-10-15 금호산업 주식회사 Fence structure
KR100946768B1 (en) * 2009-03-24 2010-03-11 우경건설 주식회사 Plane curved steel form for prestressed concrete girder it's possible to adjust and this method of fabrication
CN103206081A (en) * 2013-04-15 2013-07-17 清华大学建筑设计研究院有限公司 Sandwich formwork fixing device and sandwich formwork construction method
CN104153599A (en) * 2014-08-26 2014-11-19 中铁八局集团建筑工程有限公司 System of section steel concrete beam structure without section steel column support and bracket for construction of section steel concrete beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106639319A (en) * 2017-01-16 2017-05-10 中冶建工集团有限公司 Rotten root prevention construction method for shear walls, columns and other concrete vertical structures

Also Published As

Publication number Publication date
CN105019655B (en) 2017-06-20

Similar Documents

Publication Publication Date Title
CN103774749A (en) Large-span prestressed concrete F plate frame structure system
US20100170194A1 (en) Girders for reinforcing concrete and method for connecting them to pillars in order to provide continuity from bay to bay
CN105133830A (en) Formwork reinforcing system replacing wood with steel and construction technology thereof in external wall construction
CN110512719B (en) Construction method of large-span interval corridor high-altitude formwork steel platform for high-rise residence
CN102587648A (en) Gate-type steel pipe and fastener-type steel pipe fabricated formwork support device and construction method
CN104746892A (en) Supporting beam wall demolition device and supporting beam wall demolition construction method
CN112196107A (en) Prefabricated assembled type steel reinforced concrete primary and secondary beam connecting joint
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN202509765U (en) Overhung platform template
CN114134820A (en) Formwork support and construction method for I-shaped composite beam cast-in-place bridge deck
CN110748063B (en) Assembled steel bar truss floor support plate with support
CN209941913U (en) Assembled frame construction housing construction
CN210032128U (en) Dry construction connecting structure of corner post and beam for fabricated frame structure building
CN204876557U (en) U -shaped steel construction template
CN105019655A (en) Pouring construction method of concrete beams
CN105019646A (en) U-shaped steel-structure formwork
CN102587649B (en) Template profiled bar supporting system of high and large cantilever structure
CN213653761U (en) Prefabricated assembled type steel reinforced concrete primary and secondary beam connecting joint
CN212317480U (en) Multi-story high-rise assembled steel structure non-composite floor slab supporting system
CN210507094U (en) Cable tower lower beam embedded steel bar supporting system
CN210370010U (en) Truss-like boot foot for lattice support
CN208830725U (en) A kind of wall single side formwork bracket
CN209082534U (en) Hanging operating platform sets up device in a kind of more piece open caisson
CN107060175B (en) Inner keel and outer formwork assembly floor structure
CN111546486A (en) Manufacturing and production process of diagonal rib shear wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant