CN105019653B - Prefabricated assembled concrete underflow pumping plant construction method - Google Patents

Prefabricated assembled concrete underflow pumping plant construction method Download PDF

Info

Publication number
CN105019653B
CN105019653B CN201410172217.0A CN201410172217A CN105019653B CN 105019653 B CN105019653 B CN 105019653B CN 201410172217 A CN201410172217 A CN 201410172217A CN 105019653 B CN105019653 B CN 105019653B
Authority
CN
China
Prior art keywords
pumping plant
construction
underflow
concrete
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410172217.0A
Other languages
Chinese (zh)
Other versions
CN105019653A (en
Inventor
曹岳
魏楠
董世祎
刘成林
刘培文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201410172217.0A priority Critical patent/CN105019653B/en
Publication of CN105019653A publication Critical patent/CN105019653A/en
Application granted granted Critical
Publication of CN105019653B publication Critical patent/CN105019653B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention relates to metallurgical mine project underflow construction of pumping station.A kind of prefabricated assembled concrete underflow pumping plant construction method, including precast concrete wall panel is made in factory process, built-in fitting and suspension hook that design is specified are buried in concrete;After excavation of foundation pit is finished at the scene, the first layer of pouring construction underflow pumping plant reinforced concrete circular raft foundation reserves the enough joint bars and spacer bar of vertical extension according to design drawing;Prefabricated concrete panel is installed into formation tubular wall in place;The grouting material of foaming and intumescing after high-pressure slip-casting is used to carry out the closure Anti-seeping technology of edge joint position between wallboard;The second layer of pouring construction underflow pumping plant circle raft foundation;After the circular raft foundation construction of underflow pumping plant is finished, the pouring construction that scaffold carries out pumping plant top rebars concrete circular top plate is set up;Underflow construction of pumping station carries out the backfilling of earthwork construction of pumping plant periphery after finishing, and is backfilling and compacted.The present invention can shorten construction period, reduce cost.

Description

Prefabricated assembled concrete underflow pumping plant construction method
Technical field
The present invention relates to metallurgical mine project underflow construction of pumping station, more particularly to a kind of prefabricated assembled concrete structure bottom Flow pumping plant.
Background technology
Large-scale concentration basin is the visual plant in metallurgical mine project, and its main structure body is generally comprised:Underflow pumping plant, outlet Vestibule and the part of concentration basin pond body three.And underflow pumping plant generally uses monolithic reinforced concrete structure, it is necessary to which a large amount of scenes are applied Workman person carries out reinforcing bar colligation, formwork and concreting and maintenance work.Especially large-scale concentration basin, underflow pumping plant it is mixed Solidifying soil quantities is big, and long construction period, cost is higher.
To the west of exemplified by Australia's SINO IRON iron ore project ore dressing area 90m diameter console mode Tailing thickenings pond, Tailing thickening pond is set Count diameter 90m(2), the design of former underflow pumping plant is using rectangle monolithic reinforced concrete structure(Long 67m × wide by 10.5 ~ 31, 41m × high 11.7m), back-plane design thickness be 2.0m, side wall design thickness be 1.0m ~ 1.5m, top plate design thickness be 0.7m ~ 2.5m, deck-molding 1.4m ~ 3.2m, 2 underflow pumping plant reinforced concrete construction total amounts are 2.35 ten thousand m3, quantities is extremely great.In advance Meter is about 7 ~ 9 months in Australia construction period.According to the local labour cost in Australia expensive actual conditions extremely, if according to steel The design and construction technology of tendon concrete structure, only 2 2.35 ten thousand m3The underflow construction of pumping station total cost of cast-in-place concrete structure Will be more than 65,000,000 Australian Dollars.
The content of the invention
Present invention seek to address that there is provided a kind of prefabricated assembled concrete underflow pumping plant construction method for above mentioned problem.This hair It is bright to greatly shorten construction period, and reduce cost.
In order to solve the above-mentioned technical problem, a kind of prefabricated assembled concrete underflow pumping plant construction method, including following step Suddenly:
Step one, precast concrete wall panel is made in factory process according to design drawing, design is buried in concrete The built-in fitting and suspension hook specified;Prefabricated panel presentation quality, appearance and size, protective layer thickness and compression strength are intended to meet design It is required that, and the prefabricated panel that making is finished is transported to erecting bed;
Step 2, at the scene by excavation of foundation pit, after excavation of foundation pit is finished, pouring construction underflow pumping plant reinforced concrete circular The first layer of raft foundation, the enough joint bars and spacer bar of vertical extension are reserved according to design drawing;
Step 3, installs in place, using connection structure using hanging device by the prefabricated underflow pumping plant concrete panel of burst Part carries out the splicing connection between wallboard, forms tubular wall;Strict control installation accuracy, it is ensured that prefabricated panel and circular raft plate base Combined between plinth tight;After prefabricated panel is all installed, the grouting material of foaming and intumescing after high-pressure slip-casting is used between wallboard Carry out the closure Anti-seeping technology of edge joint position;
Step 4, confirms that prefabricated panel is respectively mounted in place accurate, after connection sealing is tight, pouring construction underflow pumping plant is circular The second layer of raft foundation;
Step 5, after the circular raft foundation construction of wait underflow pumping plant is finished, sets up scaffold and carries out pumping plant top rebars The pouring construction of concrete circular top plate, concrete roof must reach removes lower support template and corresponding again after design strength Scaffold;
Step 6, underflow construction of pumping station carries out the backfilling of earthwork construction of pumping plant periphery after finishing, tubular is surrounded during backfill operation Wall is symmetrically synchronously backfilling and compacted, it is ensured that tubular wall uniform force, it is ensured that integrally-built stability.
Described prefabricated assembled concrete underflow pumping plant construction method, the connecting elements of the prefabricated panel includes two Part, one is the built-in fitting for being embedded in precast concrete wall panel top edge, and semi-enclosed can and one are welded into by steel plate Steel-pipe welding is constituted;Another is the connector of two blocks of wallboards, is made up of one block of steel plate with two steel-pipe weldings;Adjacent two pieces of walls After plate lifting is in place, in the sleeve that two steel pipes are inserted in two neighboring wallboard top edge built-in fitting, that is, completes connection and install.
Present invention optimizes the structure type of underflow pumping plant, by taking the SINO projects as an example, set to all in underflow pumping plant It is standby to be arranged, the position of pump is laid out again on the premise of satisfaction uses functional requirement, around central tube arrangement Equipment, reduces unnecessary space waste, and compact layout is changed into underflow pumping plant directly by cast-in-situ steel reinforced concrete rectangular configuration Footpath 16.9m, the prefabricated assembled concrete tubular construction highly for 8.44m, wherein bottom plate thickness 1.1m~1.45m, wall are thick 0.4m, top plate thickness 0.47m~1.0m.Bottom plate and top plate are monolithic reinforced concrete structure, and wall is by 17 prefabricated assembled steel Tendon concrete structure is constituted.Wallboard lower edge reserves positioning hole, is accurately positioned when being easily installed;Wallboard top edge is pre-buried and top The reinforcing bar of connection and Heave Here, facilitate lifting operation.By the present invention in that replacing cast-in-place mixed with prefabricated assembled concrete structure Xtah Crude Clay structure form, is greatly reduced the construction volume of field cast-in-place concrete, can shift to an earlier date prefabricated in processing factory's progress structure Make, both shorten the construction period, site operation intensity can be reduced again, construction costs is significantly reduced, while environmental pollution is reduced, Meet the development trend of energy-conserving and environment-protective.
Embodiment
Below, with specific implementation method, the present invention is further illustrated:A kind of prefabricated assembled concrete of the present invention Underflow pumping plant construction method
(1) the thick bottom plates of underflow pump chamber 1.1m~1.45m are poured in two times.First layer first pours the thick bottom plates of 0.5m, and pre-buried Diameter 24mm wallboard spacer bars, can install to wallboard and carry out precise positioning, facilitate wallboard lifting construction.
(2) 17 precast concrete wall panels, monolithic prefabricated panel weight about 24t are installed.Using connecting elements by wallboard Edge links together.
(3) after wallboard is all installed, the bottom plate that second layer residual thickness is 0.6m~0.95m is poured.Such a design With construction method can ensure precast concrete wall panel combined with cast-in-place concrete bottom plate tightly, reasonable stress, it is ensured that pump chamber wall Body lower end obtains enough horizontal supporting forces to bear the lateral pressure outside wall.
(4) after bottom pouring construction is finished, watertight grouting drain process is carried out to prefabricated panel seam crossing.What this project was used It is a kind of grouting material of foaming and intumescing after high-pressure slip-casting, is first blocked wall seam both sides with template, then using fills Equipment is starched by grouting material high pressure injection wall body seam.Construction finishes rear preventing water leakage and worked well.
(5) set up full hall scaffold, formwork and cast-in-situ steel reinforced concrete pump chamber top plate, top thickness be 470mm ~ 1000mm, one-piece casting weight about 420t, height are about 7m, and scaffold building must assure that safety.
The connecting elements of the prefabricated panel includes two parts, and one is embedded in precast concrete wall panel top edge Built-in fitting, semi-enclosed 243mm*105mm*50mm can and DN80*125 steel pipe are welded into by the thick steel plates of 10mm It is welded to form;Another is the connector of two blocks of wallboards, by one piece of 456mm*100mm*32mm steel plate and two DN65*100 Steel-pipe welding composition.
After adjacent two blocks of wallboards lifting is in place, two DN65*100 of connector steel pipe is inserted on two neighboring wallboard In the sleeve of edge built-in fitting, that is, complete connection and install.Such a design and installation is easily and fast.
After whole prefabricated panels are installed, connecting elements is cast in by the roof support with reinforced concrete of branch module and cast-in-situ pump chamber In concrete roof, it is ensured that connecting elements will not loose or dislocation.

Claims (2)

1. a kind of prefabricated assembled concrete underflow pumping plant construction method, it is characterised in that comprise the following steps:
Step one, precast concrete wall panel is made in factory process according to design drawing, design is buried in concrete and is specified Built-in fitting and suspension hook;Prefabricated panel presentation quality, appearance and size, protective layer thickness and compression strength are intended to meet to design and wanted Ask, and the prefabricated panel that making is finished is transported to erecting bed;
Step 2, at the scene by excavation of foundation pit, after excavation of foundation pit is finished, pouring construction underflow pumping plant reinforced concrete circular raft plate The first layer on basis, the enough joint bars and spacer bar of vertical extension are reserved according to design drawing;
Step 3, is installed in place by the prefabricated underflow pumping plant concrete panel of burst using hanging device, is entered using connecting elements Splicing connection between row wallboard, forms tubular wall;Strict control installation accuracy, it is ensured that prefabricated panel and circular raft foundation it Between combine it is tight;After prefabricated panel is all installed, the grouting material of foaming and intumescing after high-pressure slip-casting is used to carry out between wallboard The closure Anti-seeping technology of edge joint position;
Step 4, confirms that prefabricated panel is respectively mounted in place accurate, after connection sealing is tight, pouring construction underflow pumping plant circle raft plate The second layer on basis;
Step 5, after the circular raft foundation construction of wait underflow pumping plant is finished, sets up scaffold and carries out pumping plant top rebars coagulation The pouring construction of native circular top plate, concrete roof must reach removes lower support template and corresponding pin again after design strength Hand cradle;
Step 6, underflow construction of pumping station carries out the backfilling of earthwork construction of pumping plant periphery after finishing, tubular wall is surrounded during backfill operation It is symmetrical to be synchronously backfilling and compacted, it is ensured that tubular wall uniform force, it is ensured that integrally-built stability.
2. prefabricated assembled concrete underflow pumping plant construction method according to claim 1, it is characterised in that described prefabricated The connecting elements of wallboard includes two parts, and one is the built-in fitting for being embedded in precast concrete wall panel top edge, is welded by steel plate It is connected into semi-enclosed can and a steel-pipe welding is constituted;Another is the connector of two blocks of wallboards, by one block of steel plate and two Steel-pipe welding is constituted;After adjacent two blocks of wallboards lifting is in place, two steel pipes are inserted in two neighboring wallboard top edge built-in fitting In sleeve, that is, complete connection and install.
CN201410172217.0A 2014-04-28 2014-04-28 Prefabricated assembled concrete underflow pumping plant construction method Active CN105019653B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410172217.0A CN105019653B (en) 2014-04-28 2014-04-28 Prefabricated assembled concrete underflow pumping plant construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410172217.0A CN105019653B (en) 2014-04-28 2014-04-28 Prefabricated assembled concrete underflow pumping plant construction method

Publications (2)

Publication Number Publication Date
CN105019653A CN105019653A (en) 2015-11-04
CN105019653B true CN105019653B (en) 2017-08-25

Family

ID=54409919

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410172217.0A Active CN105019653B (en) 2014-04-28 2014-04-28 Prefabricated assembled concrete underflow pumping plant construction method

Country Status (1)

Country Link
CN (1) CN105019653B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106258555A (en) * 2016-07-28 2017-01-04 龙信建设集团有限公司 Prefabricated assembled greening flower pond construction method for hanging
CN114941341A (en) * 2022-05-26 2022-08-26 安徽民升井架制造有限公司 Install elevator assembled basis and metal foundation groove additional

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3622227A1 (en) * 1986-06-10 1987-12-17 Frei & Egger Ag Process for producing a structure, in particular a container, and apparatus for this purpose
JP2004276976A (en) * 2003-03-17 2004-10-07 Ishii Iron Works Co Ltd Lining structure of concrete-made storage tank, and work execution method therefor
CN201458940U (en) * 2009-03-31 2010-05-12 中国市政工程华北设计研究总院 Muddy water discharge high-efficient concentration tank
CN101967834A (en) * 2009-07-28 2011-02-09 鞍钢集团矿业公司 Pulp concentration pool underground base structure with anti-floating function

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3622227A1 (en) * 1986-06-10 1987-12-17 Frei & Egger Ag Process for producing a structure, in particular a container, and apparatus for this purpose
JP2004276976A (en) * 2003-03-17 2004-10-07 Ishii Iron Works Co Ltd Lining structure of concrete-made storage tank, and work execution method therefor
CN201458940U (en) * 2009-03-31 2010-05-12 中国市政工程华北设计研究总院 Muddy water discharge high-efficient concentration tank
CN101967834A (en) * 2009-07-28 2011-02-09 鞍钢集团矿业公司 Pulp concentration pool underground base structure with anti-floating function

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
大直径浓缩池模板及混凝土施工工艺;袁保珍;《煤炭工程》;20050930(第9期);第32-33页 *

Also Published As

Publication number Publication date
CN105019653A (en) 2015-11-04

Similar Documents

Publication Publication Date Title
CN105178357B (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN108505805B (en) Large cast-in-situ water pool with expansion reinforcing belt for crack control and construction method thereof
CN104060629B (en) The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN106759462B (en) A kind of prefabricated piping lane and its construction method suitable for narrow construction site
CN106854873A (en) A kind of engineering method and garage parking in precast spliced sinking type garage parking
CN109537851A (en) A kind of method for prefabricating of assembled pipe well
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN106638940A (en) Fabricated high-rise residence precast concrete component construction method
CN108149706A (en) A kind of cast-in-place hidden girder and the prefabricated assembled pipe gallery and its construction method of superimposed sheet splicing
CN104452812A (en) Construction method of basement outer wall
CN206625428U (en) Floor closed system is poured after a kind of pipe well
CN102653946A (en) Waterproof construction method for setting rubber waterstop at bottom of reinforced concrete raft foundation
CN203924116U (en) Portable side wall formwork jumbo
CN103410173A (en) Construction method for vertical post pouring belt plugging of underground structural outer wall
CN106869548A (en) A kind of newel framework assembled underground parking structural system and construction method
CN105350581A (en) Advanced sealing structure for basement top slab settlement post-cast strips
CN104295003A (en) Structural column construction method
CN110424455A (en) The underground confined space is without fertile slot structure side wall big steel form plate system and construction method
CN210263131U (en) Assembled is from stagnant water underground pipe gallery structure
CN105019653B (en) Prefabricated assembled concrete underflow pumping plant construction method
CN203049630U (en) Building foundation slab waterproof system
CN207944339U (en) A kind of prefabricated superposed type anti-collision wall for urban viaduct
CN103866982B (en) A kind of petal art framework construction method
CN210768793U (en) Two-lining construction system at intersection of main tunnel and double-layer construction transverse channel
CN109680722B (en) Construction method for directly reserving external building access port on basement outer wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant