CN104947655A - Construction technology and equipment for cement mixing pile - Google Patents

Construction technology and equipment for cement mixing pile Download PDF

Info

Publication number
CN104947655A
CN104947655A CN201510243370.2A CN201510243370A CN104947655A CN 104947655 A CN104947655 A CN 104947655A CN 201510243370 A CN201510243370 A CN 201510243370A CN 104947655 A CN104947655 A CN 104947655A
Authority
CN
China
Prior art keywords
stirring
cement
pile
head
entity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510243370.2A
Other languages
Chinese (zh)
Inventor
高沃辉
林镇周
彭孝雄
蔡天机
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Ltd Of Energy Source In China Construction Group Guangdong Electric Power Engineering Bureau
Original Assignee
Co Ltd Of Energy Source In China Construction Group Guangdong Electric Power Engineering Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Of Energy Source In China Construction Group Guangdong Electric Power Engineering Bureau filed Critical Co Ltd Of Energy Source In China Construction Group Guangdong Electric Power Engineering Bureau
Priority to CN201510243370.2A priority Critical patent/CN104947655A/en
Publication of CN104947655A publication Critical patent/CN104947655A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a construction technology and equipment for a cement mixing pile. The construction technology comprises the steps that when the hollow pile section is constructed, clear water is ejected from a grout ejecting opening, the clear water is also ejected by the grout ejecting opening in the first sinking process of the solid pile section, a mixing head is lifted and sunk for many times in the lifting process of the solid pile section, and cement grout is ejected from the grout ejecting opening. According to the construction technology for the cement mixing pile, the cement is distributed in the solid pile section uniformly, and the cement grout is combined with soil body in the solid pile section, so that the pile forming quality of the solid pile section is guaranteed, waste of the cement grout is avoided, and follow-up digging work of the hollow pile section is convenient.

Description

A kind of cement mixing pile constructing process and equipment
Technical field
The present invention relates to the construction technology of cement mixing pile, and the equipment that construction cement mixing pile is used.
Background technology
Adopting cement mixing pile to carry out basement process is coastal area, Pearl River Delta, method for processing foundation that Yangtze River Delta Area soft foundation is conventional.At present, the job site of cement mixing pile only arranges a set of cement grout induction system, in cement mixing pile in construction process, cement grout induction system from agitator from land subsidence to completing in single pile work progress, omnidistance whitewashing.Due to the existence of the ground bottom pressure at mouth spray place, overhead darker, ground bottom pressure is larger, therefore along with the sinking of agitator, the spray pressure difference of slurry delivery system will be more and more less, causes from ground, and more down the whitewashing amount of unit length pile cutoff is fewer, whitewashing amount is fewer, and its pile quality is also poorer.Thus, the cement mixing pile that above-mentioned construction method is formed, it is best at the empty pile cutoff pile quality of the top, and the pile quality of entity pile cutoff is poor on the contrary.There is following defect in the construction technology of above-mentioned cement mixing pile: 1, part cement grout is injected in empty stake soil layer, and cause entity pile cutoff whitewashing quantity not sufficient, pile quality is poor; Meanwhile, the cement grout be injected in sky pile cutoff also result in waste.2, be injected in cement grout and the soil consolidation of empty stake soil layer, change the physical property of empty stake soil layer, increase the intensity of empty stake soil layer, thus increase the difficulty of follow-up soil layer excavation.
Summary of the invention
The present invention is intended to overcome above-mentioned prior art defect, provides a kind of cement mixing pile constructing process and the construction equipment that can ensure entity pile cutoff pile quality.
A kind of cement mixing pile constructing process of the present invention, comprises the step of following order:
A, empty pile cutoff construction sequence
Stirring-head is bottom land subsidence to empty pile cutoff, and in this process, limit is stirred, mouth spray limit spray clear water;
B, entity section construction sequence
Stirring-head continues by sinking, and is sunk until close to bottom entity pile cutoff by entity pile cutoff top, and this process limit is stirred mouth spray and become spray clear water;
Stirring-head stops certain hour, while stirring spraying cement slurries in entity pile cutoff bottom;
Upper and lower repeated multiple times lifting and sinking stirring-head in entity pile cutoff, until stirring-head is finally positioned at the top of entity pile cutoff, mouth spray limit spraying cement slurries are stirred on limit in the process;
C, stirring-head extract step
Carry stirring-head on being continued by entity pile cutoff top, be promoted to ground through empty pile cutoff, spray clear water while stirring in the process.
Cement mixing pile construction method of the present invention, it is in empty pile cutoff work progress, mouth spray sprays clear water and not jet cement slurries, stirring-head is extracted in step, be similarly through empty pile cutoff and spray clear water but not cement grout, thus, it both can soften soil layer, be convenient to soil layer disturbance, make the smooth sinking of agitation pile and extract, the waste of cement grout can be avoided again; Meanwhile, almost do not have cement grout, there is not the situation of cement grout and soil consolidation, can not increase the intensity of empty pile cutoff in the empty pile cutoff after its pile, in contrary construction, the water of ejection can also reduce the soil layer intensity of empty pile cutoff, is more conducive to the excavation of follow-up soil layer.And, in the work progress of entity section, have employed sinking watching water spray first, put forward the mode with sinking watching spraying cement slurries while stirring on follow-up, start bottom its cement grout entity pile cutoff to spray, the overflow of cement grout when can avoid stirring-head is carried, prevent cement grout overflow to empty pile cutoff, the utilization rate of further raising cement grout, avoids waste, also better prevents cement and soil consolidation in sky pile cutoff simultaneously.In addition, stirring-head, when arriving entity pile cutoff bottom first, keeps bottom position spraying cement slurries a period of time while stirring, well can also ensure that the pile quality of entity pile cutoff bottom, make the bottom pile crown of entity pile cutoff have higher intensity, thus the bearing capacity of composite foundation can be improved.In addition, cement mixing pile construction method of the present invention, its cement grout course of injection is within the scope of entity pile cutoff all the time, there is not the waste of cement grout, effectively improve the utilization rate of cement grout, meanwhile, in its entity pile cutoff work progress, stirring-head is first through spraying water while stirring, softened stake position soil layer, reduced the pressure reduction that entity pile cutoff is upper and lower, the pressure differential change that entity pile cutoff upper-lower position is whitewashed is less, whitewashing evenly, overall pile quality is also better.
Cement mixing pile construction equipment of the present invention, comprise slush pump, cement paste liquid pool and clear water reserviors, cement paste liquid pool and clear water reserviors are respectively by respective pipeline communication slush pump inlet duct, be communicated with valve slush pump inlet duct being respectively arranged with and controlling pipeline opening and closing separately at cement paste liquid pool and clear water reserviors, slurries delivery side of pump is then connected to a machine by pipeline.
Cement mixing pile construction equipment of the present invention, its slush pump respectively by different pipeline communication cement paste liquid pools and clear water reserviors; By controlling the opening and closing of each pipeline valve, can respectively to stake machine conveying slurries and clear water.When the empty pile cutoff of cement mixing pile of constructing, the valve on the valve on clear water reserviors pipeline, closedown cement paste liquid pool pipeline can be opened, in stake machine, supply clear water by slush pump; And when constructing entity pile cutoff, first can control clear water reserviors pipeline opens, cement paste liquid pool closedown of pipeline, until the stirring-head of stake machine is close to bottom entity pile cutoff, the opening and closing situation of switch valve, makes clear water reserviors closedown of pipeline, and cement paste liquid pool pipeline is opened.The mouth spray arriving stirring-head from valve due to cement grout needs regular hour T1, therefore should control the switching time of valve to arrive previous time T1 bottom entity pile cutoff at stirring-head, when stirring-head can be made like this to arrive bottom entity pile cutoff, mouth spray switches to jet cement slurries just.In entity pile cutoff work progress afterwards, promote up and down at stirring-head and in the subsequent process that sinks, keep cement grout pipeline to open, and clear water slurry pipe line closed; Until the complete front time T2 of entity pile cutoff construction, switch valve opening and closing situation, time T2 is after valve open-close state switches, clear water flows to the time of mouth spray from valve, complete in the construction of entity pile cutoff like this, upper body stirring-head is through empty pile cutoff, and stirring-head is in the process through empty pile cutoff, and mouth spray can spray clear water.Visible, described cement mixing pile construction equipment, its slush pump is optionally to stake machine conveying clear water or cement grout, by the demand that well can adapt to cement mixing pile constructing process of the present invention on conveying opportunity and time controlling clear water and cement grout, complete the construction of cement mixing pile very easily.
Accompanying drawing explanation
Fig. 1 is cement mixing pile constructing process step schematic diagram of the present invention.
Fig. 2 is that the present invention narrates cement mixing pile construction equipment schematic diagram.
Detailed description of the invention
As shown in Figure 1, Figure 2, a kind of construction equipment of cement mixing pile, comprise slush pump 1, cement paste liquid pool 2 and clear water reserviors 3, cement paste liquid pool and clear water reserviors are respectively by respective pipeline communication slush pump inlet duct 6, be communicated with the valve 4,5 slush pump inlet duct being respectively arranged with and controlling pipeline opening and closing separately at cement paste liquid pool and clear water reserviors, slurries delivery side of pump is then connected to a machine by pipeline.
By selecting the opening and closing of valve 4, valve 5, controlled slurrying liquid pump 1 is communicated with cement paste liquid pool 2 or is communicated with clear water reserviors 3, thus carries different liquid to stake machine, meets the needs of cement mixing pile driving construction.
When valve 4 open, valve 5 close time, inlet duct 6 and cement paste liquid pool 2 conducting of slush pump, start slush pump, can to stake machine conveying cement grout.
When valve 4 close, valve 5 open time, inlet duct 6 and clear water reserviors 3 conducting of slush pump, start slush pump, can to stake machine conveying clear water.
In the inlet duct of slush pump, flowmeter 7 can be installed, the injection rate of cement grout can be monitored and measure by flowmeter, thus control the construction of cement mixing pile better.
Can setting pressure table 8 at the outlet conduit of slush pump, in order to monitor spray pressure.
As follows with above-mentioned construction equipment construction cement mixing pile:
Open valve 5, valve-off 4, start slush pump, by clarified water pump to the mouth spray of stake machine; Stirring-head from land subsidence until bottom empty pile cutoff 10, spray water while stirring; Stirring-head continues to sink, and is sunk until bottom entity pile cutoff by entity pile cutoff 20 top, and this process mouth spray is sprayed water; Close to bottom entity stake for the previous period, be good with 30 seconds, switch valve, opens valve 4, valve-off 5, and when stirring-head is arrived bottom entity stake, mouth spray sprays cement grout just; Stirring-head stays for some time in bottom, while stirring spraying cement glue, and cement grout is combined with soil layer; Then, above carry stirring-head, spraying cement slurries while stirring in the process of upper body; Until on mention entity pile cutoff top, then sink agitation pile again, maintains spraying cement slurries while stirring, until again sink to bottom; And then on mention entity pile cutoff top, spraying cement slurries while stirring; Outreaching for the previous period, switch valve, opening valve 5, valve-off 4, when making stirring-head rise to entity pile cutoff top, mouth spray starts to spray clear water just; Afterwards, stirring-head is carried in continuation, through empty pile cutoff, above carry in process and spray clear water while stirring, until propose from empty pile cutoff top.

Claims (5)

1. a cement mixing pile constructing process, is characterized in that: the step comprising following order:
A, empty pile cutoff construction sequence
Stirring-head is bottom land subsidence to empty pile cutoff, and in this process, limit is stirred, mouth spray limit spray clear water;
B, entity section construction sequence
Stirring-head continues by sinking, and is sunk until close to bottom entity pile cutoff by entity pile cutoff top, and this process limit is stirred mouth spray and become spray clear water;
Stirring-head stops certain hour, while stirring spraying cement slurries in entity pile cutoff bottom;
Upper and lower repeated multiple times lifting and sinking stirring-head in entity pile cutoff, until stirring-head is finally positioned at the top of entity pile cutoff, mouth spray limit spraying cement slurries are stirred on limit in the process;
C, stirring-head extract step
Carry stirring-head on being continued by entity pile cutoff top, be promoted to ground through empty pile cutoff, spray clear water while stirring in the process.
2. a cement mixing pile construction equipment, it is characterized in that: comprise slush pump, cement paste liquid pool and clear water reserviors, cement paste liquid pool and clear water reserviors are respectively by respective pipeline communication slush pump inlet duct, be communicated with valve slush pump inlet duct being respectively arranged with and controlling pipeline opening and closing separately at cement paste liquid pool and clear water reserviors, slurries delivery side of pump is then connected to a machine by pipeline.
3. cement mixing pile construction equipment according to claim 2, is characterized in that: be provided with flowmeter in the inlet duct of slush pump.
4. cement mixing pile construction equipment according to claim 2, is characterized in that: be provided with pressure meter at the outlet conduit of slush pump.
5. use the cement mixing pile construction equipment described in claim 2 to carry out the technique of cement mixing pile driving construction, it is characterized in that: comprise the steps:
By switch valve, control clear water reserviors and be communicated with slush pump inlet duct, startup slush pump, by clarified water pump to the mouth spray of stake machine; Stirring-head from land subsidence until bottom empty pile cutoff, spray water while stirring; Stirring-head continues to sink, and is sunk until bottom entity pile cutoff by entity pile cutoff top, and this process mouth spray is sprayed water; Close to bottom entity stake for the previous period, switch valve, makes cement paste liquid pool be communicated with slush pump inlet duct, and when stirring-head is arrived bottom entity stake, mouth spray sprays cement grout just; Stirring-head stays for some time in bottom, while stirring spraying cement glue, and cement grout is combined with soil layer; Then, above carry stirring-head, spraying cement slurries while stirring in the process of upper body; Until on mention entity pile cutoff top, then sink agitation pile again, maintains spraying cement slurries while stirring, until again sink to bottom; And then on mention entity pile cutoff top, spraying cement slurries while stirring; Outreaching for the previous period, switch valve again, clear water reserviors are communicated with slush pump inlet duct, and when making stirring-head rise to entity pile cutoff top, mouth spray starts to spray clear water just; Afterwards, stirring-head is carried in continuation, through empty pile cutoff, above carry in process and spray clear water while stirring, until propose from empty pile cutoff top.
CN201510243370.2A 2015-05-14 2015-05-14 Construction technology and equipment for cement mixing pile Pending CN104947655A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510243370.2A CN104947655A (en) 2015-05-14 2015-05-14 Construction technology and equipment for cement mixing pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510243370.2A CN104947655A (en) 2015-05-14 2015-05-14 Construction technology and equipment for cement mixing pile

Publications (1)

Publication Number Publication Date
CN104947655A true CN104947655A (en) 2015-09-30

Family

ID=54162677

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510243370.2A Pending CN104947655A (en) 2015-05-14 2015-05-14 Construction technology and equipment for cement mixing pile

Country Status (1)

Country Link
CN (1) CN104947655A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106368214A (en) * 2016-11-17 2017-02-01 安徽理工大学 Pile forming operation method for protection barrel type cement soil mixing pile
CN107939296A (en) * 2017-12-26 2018-04-20 上海广大基础工程有限公司 A kind of changeable drilling tool of mouth spray

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002371550A (en) * 2001-06-18 2002-12-26 Asahi Kasei Corp Construction method of soil cement composite precast pile
CN101886385A (en) * 2010-07-28 2010-11-17 何世鸣 Construction process of long-auger jet-grouting mixing curtain pile
CN102322058A (en) * 2011-06-17 2012-01-18 北京荣创科宏岩土工程有限公司 Construction process and equipment for downhole impacting high-pressure jet grouting pile
CN102505683A (en) * 2011-11-11 2012-06-20 刘松玉 Drilling tool for two-way soil-cement mixed pile
CN103422497A (en) * 2013-08-21 2013-12-04 国家电网公司 Method for reinforcing soft soil foundation by using cement-soil mixing pile
CN104452752A (en) * 2014-11-27 2015-03-25 河南黄河勘测设计研究院 Construction method for cement mixing pile in high-dense hardening clay layer
CN204690737U (en) * 2015-05-14 2015-10-07 中国能源建设集团广东电力工程局有限公司 A kind of cement mixing pile construction equipment

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002371550A (en) * 2001-06-18 2002-12-26 Asahi Kasei Corp Construction method of soil cement composite precast pile
CN101886385A (en) * 2010-07-28 2010-11-17 何世鸣 Construction process of long-auger jet-grouting mixing curtain pile
CN102322058A (en) * 2011-06-17 2012-01-18 北京荣创科宏岩土工程有限公司 Construction process and equipment for downhole impacting high-pressure jet grouting pile
CN102505683A (en) * 2011-11-11 2012-06-20 刘松玉 Drilling tool for two-way soil-cement mixed pile
CN103422497A (en) * 2013-08-21 2013-12-04 国家电网公司 Method for reinforcing soft soil foundation by using cement-soil mixing pile
CN104452752A (en) * 2014-11-27 2015-03-25 河南黄河勘测设计研究院 Construction method for cement mixing pile in high-dense hardening clay layer
CN204690737U (en) * 2015-05-14 2015-10-07 中国能源建设集团广东电力工程局有限公司 A kind of cement mixing pile construction equipment

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
康两源: "有关湿法施工水泥深层搅拌桩设计及施工中的若干问题", 《中华民居》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106368214A (en) * 2016-11-17 2017-02-01 安徽理工大学 Pile forming operation method for protection barrel type cement soil mixing pile
CN106368214B (en) * 2016-11-17 2019-07-26 安徽理工大学 A kind of casing formula cement mixing method at pile operation method
CN107939296A (en) * 2017-12-26 2018-04-20 上海广大基础工程有限公司 A kind of changeable drilling tool of mouth spray
CN107939296B (en) * 2017-12-26 2023-08-04 上海广大基础工程有限公司 Drilling tool with switchable spraying opening

Similar Documents

Publication Publication Date Title
CN102155241B (en) Karst grouting reinforcement water-stop constructing method
CN103924584B (en) The construction method of bored pile
CN107130633A (en) A kind of steel tube concrete clay model bag stake is combined soil-baffling structure construction technology
CN104947655A (en) Construction technology and equipment for cement mixing pile
CN103806433A (en) Foundation backfill reinforcement method
CN206835817U (en) A kind of practical rainer
CN109736302A (en) High-pressure rotary jet grouting pile Grouting Pipe plugging structure
CN104563129B (en) A kind of pile body is provided with the Double-row-piles Structure that adds the stake of core horizontal jet grouting
CN111364532A (en) Existing pile foundation reinforcing method based on slurry control
CN204690737U (en) A kind of cement mixing pile construction equipment
CN110153904B (en) Abrasive hydraulic punching system and method capable of continuously adding sand
CN110094169B (en) Threaded pile drill rod for reinforcing local sludge layer and pile forming method thereof
CN202672132U (en) Reinforcing structure for basement backfilling
CN112252349A (en) Sinking construction method without drainage for open caisson
CN204040155U (en) Two-way water-saving toilet
CN205387702U (en) Shutoff fluid bowl or channelling structure in underground continuous wall work progress
CN207672587U (en) A kind of bedrock surface subsurface pressure water burst dredges structure
CN207619995U (en) A kind of material for diaphragm wall of Cofferdam construction high-pressure rotary jet grouting pile equipment
CN115030147A (en) Mixing pile up-down guniting conversion mechanism and construction method
CN109496803A (en) A kind of small-sized garden Intelligent rainwater irrigation system
CN108396728A (en) Constructing device and construction method for the multi-functional pile pile that the islands Tian Haizhu can drain
CN206396771U (en) Building basement ground construction conserves discharge structure
CN103114601A (en) Cut-off method of rapid-hardening high-spray grouting of strong leakage stratum and device thereof
CN201202106Y (en) Inserting plate special for water power
CN104500108A (en) Tunnel foundation water return point processing method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150930